P. M. Paul v. Union of India

Case / Petition Number:
Civil Appeal No. 2632 of 1987
Neutral Citation:1989 SCR 1

Case Synopsis & Summary

This case concerns a two-phase construction contract (Phase I: due 9 June 1980; Phase II: due 9 November 1980) and disputes over site handover, delays, and price escalation. The appellant contractor claimed the site was not handed over as agreed and alleged obstruction, while the Union of India argued apparent abstraction or abandonment by the contractor. The contract provided for arbitration under Clause 70; the disputes were referred to arbitration and an arbitrator (a former judge appointed by this Court) conducted hearings, weighed evidence, and issued a reasoned award. The arbitrator found delay on the respondent’s part and allowed 20% escalation on the claim for the extended period, a decision based on the evidence of inflationary cost increases and the delay’s impact. The respondent challenged the award as beyond the arbitrator’s jurisdiction and argued that no escalation clause existed to support such an award and that the arbitrator adjudicated matters outside the reference. The Supreme Court reaffirmed the core arbitration principle: an award can only be set aside under s.30 if the arbitrator misconducted himself or the proceedings, and adjudicating on matters outside the subject-matter constitutes legal misconduct. It upheld that escalation-related findings were within the arbitrator’s remit, and directed the award to be made a decree of the Court with specified costs and remuneration, disposing of the Civil Miscellaneous Petition accordingly.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Sabyasachi Mukharji
  • S. Ranganathan
Judgment Date
1989-01-16
Court Decision / Holding
The Court held that the award can be set aside only for misconduct under Section 30, and adjudicating on matters outside the subject matter constitutes legal misconduct. It found the arbitrator’s escalation findings within the scope of the dispute and upheld the award, ordering that it be made the decree of the Court. The respondent was directed to pay Rs. 17,500 as arbitrator’s remuneration and Rs. 10,000 as advocates’ fees and costs. The arbitrator’s total remuneration of Rs. 75,000 was noted, with Rs. 50,000 already deposited; the remaining balance (Rs. 25,000) was to be divided equally between the claimant and the respondent and remitted to the arbitrator within two weeks under Section 14. The Civil Miscellaneous Petition was disposed of in terms of the award.
Final Disposition
The Civil Miscellaneous Petition is disposed of; the arbitration award is made the decree of the Court with specified costs and remuneration and the parties to comply with the directions.

Parties to the Case

Appellants / Petitioners

  • P. M. Paul

Respondents

  • Union of India

Legal Representation & Advocates

Counsels for Petitioners

  • • Mrs. Baby Krishnan

Counsels for Respondents

  • • A. K. Srivastava
  • • C. V. Rao

Provisions of Law Cited

Arbitration Act, 1940 – Sections 14, 17, 30, 33-ASection 5 of the Arbitration ActSection 12 of the Arbitration ActSection 14 of the Arbitration Act, 1940

Legal Doctrines & Maxims

  • A tribunal's award can be set aside under Section 30 only if the arbitrator has misconducted himself or the proceedings.
  • Adjudicating upon a matter not the subject-matter of adjudication amounts to legal misconduct by the arbitrator.
  • Escalation is a normal incident arising out of delay and inflation in performing contracts; such considerations may fall within the arbitrator’s remit when causally connected to delay.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contended that the contract’s Clause 70 provided for arbitration and that the arbitrator’s award of escalation was within his jurisdiction as it related to the consequences of delay in completing the contract. The appellant argued the award was reasoned and within the scope of the disputes referred, and that the absence of a specific escalation clause did not automatically render such a finding outside the contract. The contractor asserted that the extension of time and damages were properly within the arbitrator’s remit and that the award should stand.

Contentions of Respondents

The Union of India argued that the arbitrator exceeded his jurisdiction by granting escalation absent an escalation clause and by addressing matters not within the reference. It contended that the arbitrator’s determination of delay and price escalation was not within the contract terms and thus a legal misconduct under Section 30. It challenged the findings as beyond the subject-matter of adjudication and urged that the award be set aside or limited.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,989 words•~14 min read

In The Court Record

P. M. Paul v. Union of India

P.M. PAUL A _v._ UNION OF INDIA JANUARY 16, 1989 -)'., [SABYASACHI MUKHARJI AND S, RANGANATHAN, JJ.] B _Arbitration_ _Act_ _1940:_ _Sections_ _14, 17,_ _30_ _and_ _33-Award-_ _Setting aside_ _of-Whether_ _arbitrator_ _has_ _misconducted himself or_ _proceedings-Adjudicating upon matter not subject matter of adjudica-_ _tion-Legal misconduct._ -{ The appellant, a contractor entered into a contract with the respondent for the construction of a building. The contract consisted of two phases. The date of commencement of both the phases was March 10, 1979, the date of completion of Phase I was June 9, 1980 and that of Phase II was November 9, 1980. Dispute arose about the handing over of the site. The appellant's case was that the site was not handed over as stipulated and consequently the work could not either be commenced or completed as stipulated. The respondent asserted that the appellant had X abandoned the work and committed a breach of contract. This was negated by the appellant. As the contract provided for settlement of disputes by an arbitrator, the appellant filed a suit for the appointment of an arbitrator. ## _/ l_ The matter came up in appeal to this Court, and one of its former Judges was appointed as an arbitrator. The Arbitrator entered upon the reference, examined the documents, heard the parties, considered the evidence, and made an award after inspecting the sites. The respondent aggrieved by the award filed a petition and contested the same. It was contended that the arbitrator had travelled beyond his jurisdiction in awarding a sum of Rs.2 lakhs as escalation cost and charges in respect of claim I. c D E F G H ·,/ Disposing of the Civil Miscellaneous Petition the Court, HELD: I. It is well-settled that an award can only be set aside under section 30 of the Arbitration Act, if the Arbitrator has misconducted himself or the proceeding. [ 121 C-D I 115 A B c D 116 SUPREME COURT REPORTS [1989] 1 S.C.R. 2. Adjudicating upon a matter which is not the subject-matter of -t adjudication, is a legal misconduct for the Arbitrator. [ 121D I 3. Escalation is a normal ineident arising out of gap of time in this inflationary age in performing any contract. [12IF] In the instant case, the dispute that was referred to the arbitrator _:¥-_ was, as to who was responsible for the delay, what are the repercussions of the delay in completion of the building, and how to apportion the consequences of the responsibility. Aller discussing the evidence and the submission of the parties to the contract, the arbitrator, found ihat it was evident that there was escalation and, therefore, he came to the conclusion that it was reasonable to allow 20% of the compensation under claim I, he accordingly allowed the same. This was a matter which was within the jurisdiction of the arbitrator, and the arbitrator had not misconducted himself in awarding the amount as he has done. [121D-E, G-H; 122A] 4. Once it was found that the arbitrator had jurisdiction to find that there was delay in execution of the contract due to the conduct of the respondent, the respondent was liable for the consequences of the delay, namely, increase in prices. [122C-DJ CIVIL APPELLATE JURISDICTION:: Civil Miscellaneous )(. E ·Petition No. 26519 of 1988. F IN Civil Appeal No. 2632 of 1987. ' From the Judgment and Order dated 10.6.1985 of the Kerala,\ High Courtin W.P. No. 210 of 1985 in O.P. No. 897 of 1984. . \ Mrs. Baby Krishnan for the Appellant. A.K. Srivastava and C. V.S. Rao for the Respondent. G The Judgment of the Court was delivered by SABY ASACHI MUKHARJI, J. This is an application for )<' making the award dated 17th February, 1988 passed by Mr V. Khalid, a former Judge of this Court, in a dispute referred to hini by thiS Court's order dated 6th October, 1987, final and to give consequenH tial directions thereupon. ' P.M. PAUL _v._ U.0.1. [MUKHARJI, J.) 117 On 7th April, 1979 there was a contract for construction of the building in question. The contract consisted of two phases. The date of commencement of both the phases was 10th March, 1979: the date of completion of phase-I was 9th .June, 1980 and for phase-II 9th November, 1980. The dispute arose about the handing over of the site. According to the appellant, the site was not handed over to him as agreed upon and therefore, the work could not either _be_ commenced or completed as stipulated. He, therefore, accused the respondent of obstructionist tactics also. According to the respondent, however, the claims put forward by the appellant were imaginary excuses to gain time and that he put forward various demands for extension of time and for payment of compensation to which he was not entitled. A c Clause 70 of the general conditions of the contract provided for settlement of disputes by arbitration. The appellan.t resorted to this clause and addressed a letter dated 13th September, 1980 to the Chief Engineer, South West Zone, Cochin, informing him that if the said disputes were not settled to his satisfaction within 15 days from the date of receipt of the notice, he would be taking appropriate steps to D refer the disputes to arbitration in accordance with the said clause. This request of the appellant was turned down by the Chief Engineer, as according to him, work was in progress and the question of grant ~- ing reasonable extension of time was under examination. Dissatisfied with this, the appellant took the mattet to the Engineer-in-Chief by his letter dated 14th October, 1980 calling upon him to appoint an E Engineer Officer as the sole arbitrator to adjudicate upon the disputes between the parties. This request was not acceded to. The relationship between the parties becaine strained. ' _,_ The respondent asserted that the appellant had abandoned the _}_ work and committed breach of contract. Thereafter, the appellant vi de F a notice dated 4th October, 1982 called upon the Engineer-in-Chief to appoint an Engineer Officer as the sole arbitrator. After further correspondence, the Engineer-in-Chief by his letter dated 9.6.1983 appointed one Mr. K.C.S. Rao, Chief Engineer, Poona Zone, as the arbitrator in respect of the disputes. Mr Rao, it is asserted, entered into reference. The appellant asserted that Mr Rao was incompetent to G _-{_ function as arbitrator for it was he who had terminated the contract when he was officiating as the Chief Engineer of Sought West Zone. Aggrieved by this appointment, he filed a suit in the Court of ... Subordinate Judge, Cochin, seeking leave to revoke the authority of the appointed arbitrator under section 5 of _the_ Arbitration Act. H A B c D 118 SUPREME COURT REPORTS [1989] 1 S.C.R. (hereinafter referred to as 'the Act'), and for appointment of another person as arbitrator under section 12 of the Act. It is not necessary to set out the various stages of litigation thereafter. Ultimately, the matter came to this Court and by an order passed by this Court on 25th August, 1987 in Civil Appeal No. 2632/87, it was observed as follows; "Having regard to the facts and circumstances of the case, .we are of the opinion that all the disputes mentioned in the Paper Book be arbitrated by a former retired Judge of this Court. We accordingly appoint _Mr. Justice_ v. _Khalid_ (Retd.) a former Judge of this Court, as the Arbitrator. The Arbitrator will decide his remuneration as he thinks fit and the parties will pay the same in equal shares. The parties will also bear the costs and charges of holding the proceedings including the remuneration and other assis· tance of Stenographers etc. Counce! for both the parties have no objection to the aforesaid order. The learned Arbitrator will enter into reference within a fortnight from the receipt of the copy of the order and will make the award within four months thereafter. Costs of the parties in the Arbitration proceedings will abide by the decision of the **Arbitrator".** \~ ·.:f-. "\-· _I_ The arbitrator entered upon the reference, examined the docuE ments, heard the parties and considered the evidence. He made his award after inspecting the sites on 20th December, 1987 and 21st January, 1988. The claims of the appellants contractor were as follows: "1. On account of losses caused due to increase in prices of materials and cost of labour and transport during the F extended period of contract from 9.6.80 work for under phase I and from 9 .11.80 for work under phase II. 5,47,612.15 2. On Account of work done under the contract including fully executed and partly executed items at the origiG nally agreed rates and for the cost of materials lying at site and taken over by the Department as well as for the value of machinery, tools and plants lying over the site and taken over by Department. 7,27,095.01 3. On account of losses caused due to added and infructuH ous expenditure on overheads, establishments, and P.M. PAUL _v._ U.0.1. IMUKHARJI, J.) li9 - _j-_ supervision during the extended period of contract upto 3.12.81, the date of termination, 1,28,864.00 4. On account of losses caused by way of gains prevented due to unlawful repudiation of the contract by the Department and the consequent termination of the con-t'. tract by the contractor. 1,04,424.58 5. (a) Release of Bank Guarantee for Rs.1,25.000 (Bank Guarantee No. G/19/80 dated 28.4.80 issued by the State Bank of India, Willingdon Island, Conchin-3). (b) Refund of the retention amounts recovered by the Department from the Running Account Bills. Amount not **indicated** 6. Interest on all the amounts due and payable. @18% PA from 9.12.81 till **actual date** **of payment** **or realisation''.** The claims on behalf of the respondent, were as under: "1. Excess cost which had to be borne by the Department i9,16,198.82 on account of the defaults of the contractor and subsequent cancellation of the contract after adjusting other amounts due from the contractor under this contract. ## _./ I_ 2. Cost of reference to Arbitration 7,000.00" The arbitrator by his award asked the respondent to pay the following: A B c D E F "(a) On claim No. I, a sum of Rs.2,00,216.18 with interest at 10% from 9.12.1981 till the date of this Award. (b) On claim No. II, a sum of Rs.2,47,269.69 with interest at 10% from 9.12.1981 till the date of this Award. G (c) Claim No. III-Disallowed. (d) Claim No. IV-Disallowed. (e) On claim No. V(a), the respondent is directed to H A _B_ c D E F G H 120 SUPREME COURT REPORTS. [1989] 1 S.C.R. refund the Bank Guarantee sum of Rs.1,25,000 to the Cliamant with interest at 10% from the date of the encashment till the date of this Award. II. The remuneration of the Arbitrator is Rs.75,000. Rs.50,000 has already been deposited. The claimant and the Respondent are directed to· remit the balance equally (Rs.12,5000 each) to the Arbitrator to his Madras address by Account payee Draft within two weeks of receipt of the notice under Section 14 of the Arbitration Act, 1940. III. The respondent is directed to pay to the Claimant by way of cost Rs.17,500 towards Arbitrator's remuneration and Rs.10,000 towards Advocates' fees and cost. IV. The respondent is directed to suffer their cost. V. The counter claims preferred by the Respondent against the Claimant are disallowed." A petition was filed on behalf of the respondent, wherein it was stated as follows: "Regarding petitioner's claim No. 1, in the absence of any escalation clause, it is not permissible to the Arbitrator to grant any escalation price as sought by the petitioner. On the other hand, if the .work is not completed within the ~pecifiet! time, he has got right to ask for extension of time. Failure to grant extension of time, the contractor can claim difference of prices. That is not the case here. Extension of time l!(llS granted and the Arbitrator after considering the contentions put-forth before him has granted 20% of the escalation price which is not in accordance with the terms of the contract. Though the term of the cotract envisages that the entire site should be handed over in-time for completion of the work entrusted to him as referred to above in civil works before starting of the work, the contrator is required to put up some preliminary work like construction of temporary store sheds, temporary office which requires sometime and within that time if the other area or the site is not handed over the contractor has got grievances to complain against the Department. Further, by not handing over the· site how much damage or loss is sustained has not been P.M. PAUL _v._ U.0.1. [MUKHARJI, J.) 121 apprised off. Therefore, it is submitted that Claim No. 1 of A the Contractor should have been considered as outside the scope of the contract and hence the arbitrator has exceeded his jurisdiction." Mr Ashok Srivastava, counsel appearing for the Union of India, submitted before us that this is a reasoned award and the learned arbitrator had granted a sum of Rs.2 lakhs as escalation charges and costs. Mr Srivastava tried to urge that the right to get escalation charges and costs in the absence of escalation clause was not a matter referred to the arbitrator. In other words, it was urged that the arbitrator had travelled beyond his jurisdiction in awarding the escalation cost and charges. It is difficult to accept this objection for reason more than one. B c It is well-settled that an award can only be set aside under section 30 of the Act, which enjoins that an award of an arbitrator/umpire can be set aside, _inter alia,_ if he has misconducted himself or the proceed ing. Adjudicating upon a matter which is not the subject-matter of _D_ adjudication, is a legal misconduct for the arbitrator. The dispute that was referred to the arbitrator was, as to who is responsible for the delay, what are the repercussions of the delay .in completion of the l~ building and how to apportion the consequences of the responsibility. ### _}_ ( In the objections filed on behalf of t)le respondent, it has been stated that if the work was not completed within the stipulated time the party E has got a right for extention of time. On failure to grant extension of time, it has been asserted, the contractor can claim difference in prices. In the instant case, it is assert~d that the extension of time was granted ·and the arbitrator has granted 20% of the escalation cost. Escalation is a normal incident arising out of gap of time in this infla- F tionary age in performing any contract. The arbitrator has held that there was delay, and he has further referred to this aspect in his award. The arbitrator has noted that Claim I related to the losses caused due to increase in prices of materials and cost of labour and transport during the extended period of contract from 9.5.1980 for the work under phase I, and from 9.11.80 for the work under phase II. The total G amount shown was Rs.5,47,618.50. After discussing the evidence and the submissions the arbitrator found that it was evident that there was escalation and, therefore, he came to the conclusion that it was reasonable to allow 20% of the compensation under Claim I, he has accordingly allowed the same. This was a matter which was within the jurisdiction of the arbitrator and, hence, the arbitrator had not mis- H 122 SUPREME COURT REPORTS 11989] 1 S.C.R. A conducted himself in awarding the amount as he has done. It was submitted that if the contract work was not completed within the stipulated time which it appears, was not done then the contractor has got a right to ask for extension of time, and he could claim difference in price. This is precisely what he has done and has B obtained a portion of the claim in the award. It was submitted on behalf of the Union of India that failure to complete the contract was not the case. Hence, there was no substance in the objections raised. Furthermore, in the objections raised, it must be within the time provided for the application under section 30 i.e., 30 days during which the objection was not specifically taken, we are of the opinion that # I behalf of the Union of India that failure to complete the contract was not the case. Hence, there was no substance in the objections raised. Furthermore, in the objections raised, it must be within the time provided for the application under section 30 i.e., 30 days during which the objection was not specifically taken, we are of the opinion that c [there ][is no substance in this objection sought to be raised in opposition ] ### llio •w.m. °""' ;, WU"""" lli• U. """•W "" j•ri- m \ find that there was delay in execution of the contract due to the con- I # r duct of the respondent, the respondent was liable for the consequences of the delay, namely, increase in prices. Therefore, the arbitrator had D [jurisdiction to go into this question. He has gone into that question ] and lias awarded as he did. Claim I is not outside the purview of the contract. It arises as an incident of the contract and the arbitrator had jurisdiction. In that _,. view of the matter the objections raised against the award, cannot be E [sustained. No other objection was urged before us. The award, there-] fore, must be made the rule of the Court and there will be a decree in terms of the award, and the respondent is directed to pay Rs.17,500 as the arbitrator's remuneration and Rs.10,000 as advocates' fees and costs. ###### The Civil Miscellaneous Petition is disposed of accordingly.,.\ F N.V.K. Petition disposed of.
End of Judgment Record
Browse All Supreme Court of India (1989) Decisions
1989-12-22

LAXMI NARAYAN NAYAK v. RAMRATAN CHATURVEDI AND ORS.

This appeal concerns an election petition challenging the Madhya Pradesh Vidhan Sabha election from Niwadi constituency (No. 34) held in early 1985. The appellant, Laxmi Narayan Nayak, alleged that the first respondent, Ramratan Chaturvedi, engaged in corrupt practices under Sections 123(2), 123(3) and 123(3A) of the Representation of the People Act, 1951. The Madhya Pradesh High Court dismissed the petition for lack of substantiation, and Nayak challenged that decision in this Supreme Court appeal. The Court concentrates on three issues: (i) whether the nomination paper of Pratap Singh (11th respondent) was improperly rejected; (ii) whether the respondent held a meeting on 28 February 1985 at Niwadi and promised a silver shield to electors, constituting corrupt practice under Section 123(1); and (iii) whether government servants and a police officer accompanied the respondent to persuade electors and whether money was distributed. The Court reiterates that election petitions are quasi-criminal and require strict proof, including a clear element of bargaining in bribery, with reliability and corroboration of oral evidence. It critically analyzes the evidence: the nomination issue is resolved in the petitioner's favour by the High Court’s reasoning, while the alleged bribery and use of government officers fail due to inconsistencies and lack of corroboration. Ultimately, the Supreme Court upholds the High Court’s decision and dismisses the appeal with costs.

1989-09-19

Aphali Pharmaceuticals Ltd. v. State of Maharashtra & Ors.

Aphali Pharmaceuticals Ltd., an Ayurvedic medicine manufacturer, challenged excise-duty liability on the product Ashvagandharist, which contains self-generated alcohol but is not a beverage. Initially treated as exempt under item 2(i) of the 1955 Act’s Schedule (renumbered as item 3(i) after the 1961 Amendment) because it was an Ayurvedic preparation containing self-generated alcohol not capable of being consumed as an ordinary alcoholic beverage. The 1962 Finance Act introduced Explanation I to the Schedule, defining “patent and proprietary” medicines by reference to the Drugs Act, 1940, with retrospective effect. A Maharashtra circular (31 May 1962) directed treating such preparations as falling under item 1 (patent or proprietary medicines) rather than item 3, and excise duties were subsequently levied and paid under protest. The appellant filed suit; the Civil Judge decreed in its favor, the High Court reversed, and this Court allowed the appeal. The Court held that Explanation I did not amend or override the Schedule’s categories, and the circular could not override the enactment; the Schedule and the Act, read with the Rules (Rules 64-66) and the Drugs Act, determine taxability. The Supreme Court restored the Civil Judge’s decree, holding the appellant was not liable under the amended schedule as interpreted. The parties were to bear their own costs.

1989-07-13

Sundarjas Kanyalal BhatiJa & Ors. v. Collector, Thane, Maharashtra & Ors.

This matter concerns judicial review of Government action under Section 3 of the Bombay Provincial Municipal Corporations Act, 1949, in the context of proposing the formation of the Kalyan Municipal Corporation by merging Kalyan, Ambarnath, Domoivali, and Ulhasnagar. Objections poured in, including from Ulhasnagar’s Sindhi community which sought to preserve its identity via the All India Sindhi Panchayat Federation. The Government undertook a draft notification under Section 3(3) and later issued a final notification excluding Ulhasnagar under Section 3(2). The Bombay High Court held that excluding Ulhasnagar while keeping contiguous areas in the proposed Corporation was arbitrary and irrational, and it directed the Government to reconsider the proposal under Section 3(3), inviting hearing for petitioners and Federation. The appellants contended that the formation of a corporation is a legislative function, thus subject to no general rules of natural justice, and that the State had complied with statutory requirements. The Supreme Court, in a Division Bench, reversed the High Court, emphasizing that judicial review aims at predictability and certainty of law, and that the procedure for forming a Corporation under Section 3 is a legislative act not bound by ordinary hearing requirements unless expressly prescribed. It criticized the High Court’s approach and held that the Government’s action was within the scheme of law, while affirming the need for proper procedure and respecting the decorum of judicial process.

1989-08-08

ATUL MATHUR v. ATUL KALRA

This appeal from the Bombay criminal proceedings concerns Section 630 of the Companies Act, where a company sought to recover possession of a flat occupied by a former employee after resignation. The leave-and-licence agreement for the flat was executed on behalf of Jenson and Nicholson (India) Ltd by the first respondent, who served as Divisional Sales Manager, under a power of attorney. The first respondent filed a civil suit asserting he was the licencee, while the company paid deposits and continued to pay licence fees. After resignation, the respondent did not vacate, was convicted under Section 630 by the Additional Chief Metropolitan Magistrate, and the conviction was upheld by the Sessions Court. The Bombay High Court, via Article 227 converted to Section 482 Cr.P.C., reversed the judgments, holding that two letters by a junior employee, Exs. 3 and 4, and the existence of a civil suit created a bona fide dispute that should be resolved in civil court rather than a criminal proceeding. The Supreme Court allowed the appeal, holding that Section 630 aims to provide speedy relief to the company, that the complaint was properly filed, and that the two letters did not establish a bona fide dispute. The Court restored the lower court judgments and granted the respondent time to vacate.