P. M. Muneer v State of Kerala and Others
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- Anu Sivaramman
- Judgment Date
- 2019-12-03
- Court Decision / Holding
- The writ petition is ordered accordingly. The court directs the Government to consider the petitioner’s claim for Ext.P3 benefits with reference to the reports placed by the Chief Engineer (Exts.P6 and P10) and to grant the petitioner an opportunity of hearing. The Government shall take an informed decision in accordance with law, after hearing the petitioner, and pass appropriate orders within three months from the date of receipt of a copy of the judgment, considering the treatment afforded to similarly situated contractors under extant Government orders (including GO dated 27.10.2011).
- Final Disposition
- The writ petition is ordered accordingly.
Parties to the Case
Appellants / Petitioners
- P. M. Muneer
Respondents
- State of Kerala represented by the Secretary to Government, Fisheries & Ports (B) Department, Government Secretariat, Thiruvananthapuram
- The Superintending Engineer Harbour Engineering (North Circle), Kozhikode
- The Executive Engineer Harbour Engineering (North Circle), Kozhikode
- The Chief Engineer Harbour Engineering Department, Thiruvananthapuram
- The Secretary Finance Department, Govt. of Kerala
Legal Representation & Advocates
Counsels for Petitioners
- • K. L. Varghese (Sr.)
- • Ranjith Varghese
- • Rahul Varghese
- • Smt. Santha Varghese
Counsels for Respondents
- • Shri. Ron Bastian (Government Pleader)
Case Synopsis & Summary
This writ petition challenges the termination of the petitioner’s contract for the Fishery Harbour Project at Ponnani and seeks the benefit of Ext.P3, which provides revised rates in respect of cement and steel for works not completed due to factors beyond the contractor’s fault. The petitioner, an A-class registered contractor of the Kerala Public Works Department, was awarded the Quay on Pile and Slab, Auction Hall and Reclamation works under Ext.P1 (22.10.2005) on the basis of the 1999 schedule of rates. Escalating costs of materials led to non-completion, and Ext.P3 circular was issued to permit revised rates for such cases. Termination at risk and cost was effected by Ext.P4, which the petitioner challenged in earlier petitions. Following ministerial discussions, Ext.P5 revoked the termination and directed completion with a fine of Rs. 45,000 and a deadline of 31.12.2008. The petitioner resumed work but floods on 17–18.10.2008 damaged a portion of the progress; Ext.P6 records the situation, and Ext.P7 certifies completion on 31.08.2009. The petitioner contends that, despite completion, the 2008 SOR-based revised rates were not granted. The State defends Ext.P5’s conditions. The petitioner cites B. Anas Babu v. Union of India (2018 (1) KLT 437) and an unreported decision (WP(C).No.6982 of 2011) to argue for extension of Ext.P3 benefits and judicial consideration. The High Court directs a hearing and an informed decision within three months, considering Ext.P6 evidence and other identically situated cases.
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioner argues that the termination at risk and cost was not due to a fault of the contractor and that Ext.P3, allowing revised rates for works affected by the surge in cement and steel prices, should be extended to his balance work. He asserts that floods and natural calamities (17–18.10.2008) caused substantial disruption, and the government’s subsequent actions, including Ext.P5 and Ext.P6, justify granting the revised rates without tender excess as per the 2008 Schedule of Rates, subject to an due process and hearing. The petitioner seeks a mandamus directing respondents to grant Ext.P3 benefits and complete the balance work accordingly within legal boundaries. respondents:The respondents contend that Ext.P5 set conditions including completion by 31.12.2008 and that revised rates without tender excess are contingent on the Finance Department’s concurrence. They maintain that since the balance work was not completed within the specified time, the revised rates cannot be granted and the termination was valid subject to applicable rules and financial approvals.
Contentions of Respondents
The respondents rely on Ext.P5 and the prerequisites therein for revision of rates and completion timelines; they emphasize that any extension or revision must be backed by financial concurrence and proper due process. They contend that the floods and subsequent damages were taken into account in the factual assessment but advance the position that the final entitlement to revised rates is dependent on government sanction and completion within the prescribed deadline.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| B. Anas Babu and Ors. v Union of India and Ors. | 2018 (1) KLT 437 | Positive | The judgment relies on this decision to argue that escalations in cement and steel costs and non-fault circumstances can justify interim relief or extensions in rate revisions, aligning with the petitioner’s treatment of Ext.P3. |
| WP(C).No.6982 of 2011 (unreported) | Unreported (WP(C).No.6982 of 2011) | Positive | Cited as an additional authority supporting similar outcomes in extending benefits or revisiting termination-related consequences in the wake of non-fault scenarios and material escalation. |
Diagnostic Tool
Does this judgment govern your specific facts?
Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against P. M. Muneer v State of Kerala and Others and instantly map out authorities that support, challenge, or govern your position.
Extracted Judgment Text
Exact text extracted from official judgment records.