Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1993Division BenchAppeal allowed; High Court order set aside; Tri...

Orissa State Electricity Board v. Orissa Tiles Limited

Case / Petition Number:
Civil Appeal No. 1496 of 1993
Neutral Citation:1993 SCC (2) 860

Case Synopsis & Summary

This is a civil appeal in which the Orissa State Electricity Board (the appellant) challenges a decision of the Orissa High Court partly allowing the respondent’s appeal. The dispute concerns the liability of a consumer (Orissa Tiles Limited) to pay minimum charges after disconnection for non-payment of electricity dues. The appellant had executed an electricity-supply agreement on 5 March 1965, valid until 5 March 1970, requiring minimum charges in any event. Supply was disconnected on 30 April 1968 for non-payment, and the Board claimed minimum charges for the period from 1 May 1968 to 5 March 1970 in addition to charges for energy consumed up to 30 April 1968. The Trial Court decreed the suit, but the High Court allowed it only up to the date of disconnection, holding that no energy was availed post-disconnection, and thus minimum charges could not be payable. The Board contended that, following Bihar State Electricity Board v. Mis Green Rubber Industries (1990) 1 SCC 731, the minimum charges could be payable post-disconnection under clause 13 of the agreement. The Supreme Court allowed the appeal, restoring the Trial Court’s decree for the post-disconnection period, and struck down the High Court’s partial allowance. The decision clarifies that minimum charges may be due irrespective of continued energy usage after disconnection, relying on the Green Rubber Industries precedent.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • B. P. Jeevan Reddy
  • N. Venkatachala
Judgment Date
1993-03-31
Court Decision / Holding
Appeal allowed. The High Court’s order is set aside. The Trial Court’s decree is restored in full (including post-disconnection minimum charges). No costs.
Final Disposition
Appeal allowed; High Court order set aside; Trial Court decree restored; No costs

Parties to the Case

Appellants / Petitioners

  • Orissa State Electricity Board

Respondents

  • Orissa Tiles Limited

Legal Representation & Advocates

Counsels for Petitioners

  • • Raj Kumar Mehta

Provisions of Law Cited

Indian Electricity Act, 1910

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that, following Bihar State Electricity Board v. Mis Green Rubber Industries (1990) 1 SCC 731, the consumer is liable to pay minimum charges for the post-disconnection period. Clause 13 of the agreement obliges payment of minimum charges in any event, irrespective of whether energy is consumed after disconnection.

Contentions of Respondents

The respondent contends that since no energy was used after disconnection, it should not be liable to pay minimum charges for the post-disconnection period.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Bihar State Electricity Board, Patna & Ors. v. Mis Green Rubber Industries and Ors.(1990) 1 S.C.C. 731PositiveThe Court relied on this decision to hold that minimum charges can be due for the period after disconnection, as clause 13 of the agreement imposes minimum charges regardless of actual energy use.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,259 words•~6 min read

In The Court Record

Orissa State Electricity Board v. Orissa Tiles Limited

~ A ORISSA .STATE ELECTRICITY BOARD _v._ ORISSA TILES LIMITED MARCH 31, 1993 B [B.P. JEEVAN REDDY AND N. VENKATACHALA, JJ.] _Indian Electricity Act, 1910:_ - _Agreement between Electricity Board and Consumer-Provision for_ c _minimum charges-Default in payment of electricity charges-Disconnectio11 of supply-Liability of consumer to pay minimum charges for period subsequent to date of disconnection of supply-Consumer held liable to pay minimum charg"' for period subsequent to disconnection._ ~ D The respondent-industry entered into an agreement with the appel!ant-Board for snpply of electricity on Sth March, 1965. Under the agreement, which was valid for five years i.e. upto Sth March 1970, consumer **was obliged to pay certain minimum charges in any event. However, on** 30th April, 1968 supply of electricity to respondent was disconnected for non-payment of electricity charges. Since the respondent also failed to pay E the minimum charges for the period subsequent to the date of disconneclion, the Electricity Board filed a suit for the amount due on account of the electricity consumed upto April 30, 1968 and for the minimum charges from May 1, 1968 to March S, 1970. The Trial Court decreed the suit. ,.,l - F The respondent preferred an appeal before the High Court which sustained the Trial Court's decree only for the period upto the date of disconnection but disallowed the claim for the period subsequent to th• date of disconnection on the ground that since -the respondent did not avail of any energy whatsoever during the period subsequent to the disconnection it was not liable to pay the minimum charges for that perioo. G _;J.,_ In appeal to this Court it was contended on behalf of the Electricity _**·"'7**_[.. ] Board that in view of the judgment of this Court in the case of _Bilzar State Electricity Board, Patna a11d Ors._ v. _Mis Green Rubber Industries a11d Ors.,_ (1990] I S.C.C. 731 the respondent was liable to pay the minimum charges H for the period subsequent to disconnection. 860 _·r-_ 861 ~ ORISSA S.E.B. _v._ ORISSA TILES [REDDY, J.] Allowing the appeal dnd setting aside the order of the High Court, this Court, ~ > HELD: Clause (13) of the agreement between the parties does oblige the consumer to pay a certain minimum charges in any event. The judgment and decree of the Trial Court is restored. [862 E, 863 DJ B _Bihar State Electricity Board, Patna & Ors._ v. _Mis Green Rubber Industries and Ors.,_ (1990] 1 S.C.C. 731, relied on. ·--( CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1496 of 1993. From the Judgment and Order dated 20.2.1985 of the Orissa High Court in First Appeal No.139 of 1974 c Raj Kumar Mehta for the Appellant. The Judgment of the Court was delivered by D B.P. JEEVAN REDDY, J. Heard the counsel for the appellant. None appears for the respondent though served. Leave granted . _.J-.._ This appeal by the Orissa State Electricity Board is preferred against E the judgment of the Orissa High Court allowing partly an appeal preferred by the respondent. The dispute pertains to the liability of the consumer (respondent in this appeal) to pay the minimum charges during the period subsequent to the date of disconnection of supply of energy to him for the non-payment of electricity dues. F ... +'r The respondent is an industry. It entered into an agreement with the ' appellant for supply of electricity on .March 5, 1965. The agreement was valid for a period of five years. He started availing of the energy with effect from July 31, 1965. The supply of his industry was disconnected on April 30, 1968 for non-payment of electricity charges. Since the consumer also G failed to pay the minimum charges for the period subsequent to the date of <iisconnection, the Board filed a suit for the amount due on account of the electricity consumed between April 1, 1968 and April 30, 1968 and for the minimum charges for the period May 1, 1968 to March 5, 1970. (It may be remembered that the agreement between parties was valid upto March 5, 1970). The Trial Court decreed the suit as prayed for along with interest H [1993) 2 S.C.R. ## 862 ## SUPREME COURT REPORTS - A of 6% per annum on the amount decreed from the date of suit till the date of decree and also future interest at the same rate till full satisfaction. On appeal, the High Court sustained the decree of the Trial Court only for the period upto the date of c(isconnection (April 30, 1968) but disallowed the claim for the period subsequent to the date of disconnection. The reason- - _B_[ing ][of ][the High Court ][is ][that inasmuch ][as ][the supply ][was ][disconnected and ] the respondent-consumer did not avail of any energy whatsoever during the period subsequent to the disconnection, it is not liable to pay the minimum charges. - In this appeal, it is contended by the learned counsel for the appelC !ant that the question arising herein is concluded in favour of the Board by the decision of this Court in _Bihar State Electricity Board, Patna and Ors._ v. _Mis Green Rubber lndusiries and Ors.,_ [1990) 1 S.C.C. 731. On a perusal of the judgment, we find that that was also a case w~ere the claim _inter alia_ pertained to the period subsequent to the date of disconnection till the expiry of the agreement. In that case too, minimum charges were claimed D by the Board even for the period during which the supply remained disconnected and no energy whatsoever was availed of by the consumer. We also find that clause (4) of the agreement considered in the said decision and clauses (6) and (13) of the agreement concerned herein are substantially same. Clause (13) of the agreement between the parties hereto E does oblige the consumer to pay a certain minimum charges in any event. The clause reads as follows: _';r-_ A- · · ## _"Clause 13:_ F G The consumer shall (subject to the provisions hereinafter contained) pay to the Engineer for the power demand and electrical energy supplied under this Agreement, the charges to be ascertained as mentioned below viz. (Government resolution on tariff to be inserted here) _LARGE INDUSTRIES:_ For demand of 1'.?5 K.V.A. and above for supply at 11 K.V. at - (i) Rs.5.50 paise per K.V.A. per month plus H (ii) Rs.0.08 paise per K.W.H. per month subject to an overall maximum rate of Rs.0.09 paise per K.W .H. and 863 ORISSA S.E.B. _v._ ORISSA TILES [REDDY, J.] - - without prejudice to payment of minimum charge of 75 per cent of the contract demand at the above rate of Rs.5.50 paise per K.V.A. per month and subject further to absolute minimum payment on 125 K. V .A. in the first part of the tariff. For less than 250 K.V.A the demand may be metered in K.W. and charged for at Rs.6.00 per K.W. per month. Besides the charges for K. W.H. consumed at the rate specified above. For supply at M.T; less than 11 K.V.A and M.T. less that 11 K.V.A. and M.T. the above rate will be increased by 10%." A B c The reasons for such a stipulation and its justifiability are duly and fully explained by this Court in the aforesaid decision. It is not necessary for us to reiterate the same. The appeal is accordingly allowed. The Judgment of the High Court D **is set aside. The judgn1ent and decree of the Trial Court is restoi"ed. NO costs.** T.N.A. Appeal allowed. . _-f.._ _.I_
End of Judgment Record
Browse All Supreme Court of India (1993) Decisions
1993-04-22

Commissioner of Income Tax, Madras v. G.R. Karthikeyan

This Supreme Court judgment concerns whether prize money totaling Rs. 22,000 won by G.R. Karthikeyan in the All India Highway Motor Rally could be treated as income under the Income Tax Act, 1961. The Madras High Court had held that the prize money was not income under Sec. 2(24)(ix) since the rally was not a race and the input terms of Sec. 10(3) were not satisfied, viewing the receipt as casual and non-taxable. The Tribunal had similarly decided the money did not constitute income. The Supreme Court reversed, holding that the expression ‘income’ is an inclusive term, and that prize money arising from a rally involving skill and endurance falls within the ambit of income under Sec. 2(24). The Court rejected the High Court’s view that the sub-clauses of Sec. 2(24) are exhaustive and emphasized that income can arise even if a receipt does not fit any sub-clause, provided it possesses the nature of income. It also held that casual receipts can be income under Sec. 10(3) if they exceed Rs. 1,000 in aggregate. The decision discusses the broad constitutional and statutory understanding of ‘income,’ citing multiple authorities to illustrate that the word should be given its widest sense. The appeal was allowed, with the question answered in the Revenue’s favor.

1993-09-08

Satyanarain Bajoria and Anr. v. Ramnarain Tibrewal and Anr.

Satyanarain Bajoria and another (the judgment-debtors) challenged an order setting aside a sale in a money execution case arising from a 1964 decree for Rs. 8,256.05 on a Rs. 4,000 loan. After initial payments, the decree-holder pursued further sums, and land belonging to the judgment-debtor was sold at auction in 1978 for Rs. 1,500, bought by the decree-holder himself. The executing court had set aside the sale due to material irregularities and allegations of fraud; the lower appellate court reversed, holding the application under Order 21 Rule 90 CPC barred by time and that notices had, in fact, been served as per order sheets. The Supreme Court reversed the lower appellate court, holding that notice under Order 21 Rule 22 CPC was mandatory for proceedings after more than two years; that orders under Rule 90 are independent proceedings requiring actual proof of service; and that the conduct of the decree-holder demonstrated deliberate ignorance of the execution proceedings. It found that the sale was conducted fraudulently and without proper notice, causing substantial injustice to the judgment-debtor, and restored the executing court’s order setting aside the sale, with costs to the appellants. The decision underscores the centrality of service, due process, and safeguards in Order 21 proceedings.

1993-11-26

M. JANARDHAN v. STATE

This Supreme Court appeal arises out of a dispute concerning retrospective regularisation and inter se seniority of Health Inspectors in the Andhra Pradesh Public Health Subordinate Service (APPHSS). The background spans 1958–1962 when Appellants were appointed as Health Inspectors on a temporary basis, and 1961–1969 when Respondents 4–121 were temporarily promoted from feeder cadres. In 1964, Special Rules for APPHSS were framed under the proviso to Article 309, retrospectively effective from 1.11.1956, requiring three years of feeder service for promotion to Health Inspector. In 1968 PSC selected candidates for permanent appointments; while both sides were selected, Respondents 4–121 were ranked above the Appellants. Later, the State regularised some temporary promotees retroactively (April 1977) under Rule 37(e). Thereafter, the State attempted to regularise direct recruits retrospectively (memo 46/ Hl/84-11, 22.2.1985) and issued G.O. Ms. No. 105, Health (2.2.1989) arranging zone-wise regularisation and fixing inter se seniority, subject to pending SLP in this Court. The Tribunal dismissed petitions challenging these actions. This Court held that Rule 37(e) permits retrospective regularisation of temporary promotees from an anterior date, though the record did not show such regularisation occurred for Respondents 4–121 as required by the Rules; it also upheld retrospective regularisation of direct recruits under Rule 23(a) and 37(e) and approved the Government’s final seniority arrangement. The appeal is allowed with no costs, and inter se seniority is fixed accordingly.

1993-02-05

Rama Kant Pandey v Union of India

This case concerns Rama Kant Pandey challenging two Representation of the People Amendments enacted in 1992 via Ordinances 1 and 2, which amended sections 52 and 30 of the Representation of the People Act, 1951. The petitioner contends that the amendments violate Articles 14, 19 and 21 by discriminating between candidates tied to recognised political parties and others; modifying the countermanding of elections and shortening the period for poll. The Court, however, held that the right to vote or stand for election is not a fundamental or civil right but a statutory right; and that the constitutional framework recognises the party system and cabinet government as essential to a functioning democracy. It noted that Parliament’s reforms aim to curb disruption of elections amid terrorism and increased independent candidates; the Electoral Reforms Committee recommended these changes; the amendments were subsequently incorporated into statute. The Court concluded there is no constitutional invalidity in distinguishing party-sponsored candidates and in reducing the window from 20 to 14 days as a reasonable measure in the changed security scenario. It dismissed the petition with costs, endorsing the government’s view that the amendments were necessary to ensure the integrity and smooth conduct of elections. The decision underscores the role of political parties in a democratic system and the permissible limits of electoral rights.