High Court of KeralaKerala High Court · 2009Single JudgeOriginal Petition is disposed of as above.

OP.No. 7047 of 2001 (L) - The MANGING DIRECTOR, PERIA PEAK ESTATE PVT. LTD, PERIA POST, MANANDAVADY, WYNAD. v. KERALA STATE ELECTRICITY BORD AND OTHERS

Case / Petition Number:
OP.No.7047 of 2001(L)

Case Synopsis & Summary

The petitioner, Managing Director of Peria Peak Estate Pvt. Ltd., a tea factory at Mananthavady, challenged a power bill raised after an Anti Power Theft Squad inspection on 16/9/2000. The meter was found to record only about one-third of actual consumption due to an internal CT connection fault causing reverse running in one phase and an unauthorised additional load of 44 kW beyond the authorised load of 130 kW. Based on the inspection report (Ext. P2), the Board reassessed consumption from 12/1997 and levied triple the fixed charge plus proportionate current charges, producing a bill of Rs. 8,04,741 (Ext. P3). The petitioner challenged Ext. P3 before the Appellate Authority, which dismissed the appeal (8/2/2001). The issues centered on whether reassessment could be limited to six months under Regulation 42(d) and Section 26(6) of the Indian Electricity Act, and whether prior judgments (Belwal Spinning Mills Ltd. v. UPSB, AIR 1997 SC 2793; O.P. No. 191/98; Nirmala Metal Industries v. K.S.E.B., 2006 (3) KLT 465) applied. The respondents argued the six-month limit applies where there is a six-month window due to the meter fault, and reassessment from 12/1997 was justified by the sudden drop after inspection. The Kerala High Court ultimately quashed Ext. P3 and P4, directing the Board to recalculate arrears and issue a fresh bill within two months, with adjustments for any deposits.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Harun-ul-Rashid
Judgment Date
2009-02-18
Court Decision / Holding
Ext.P3 and Ext.P4 are quashed. The respondents are directed to re-work the arrears and issue a fresh bill to the petitioner within two months from the date of receipt of a copy of the judgment, with adjustment for any amount already deposited under the interim order.
Final Disposition
Original Petition is disposed of as above.

Parties to the Case

Appellants / Petitioners

  • THE MANGING DIRECTOR, PERIA PEAK ESTATE PVT. LTD, PERIA POST, MANANDAVADY, WYNAD.

Respondents

  • KERALA STATE ELECTRICITY BOARD, represented by Secretary, Thiruvananthapuram
  • DEPUTY CHIEF ENGINEER, ANTI POWER THEFT SQUAD, KSEB, Thiruvananthapuram
  • ASSISTANT EXECUTIVE ENGINEER, ELECTRICAL MAJOR SECTION, MANANDAVADY

Legal Representation & Advocates

Counsels for Petitioners

  • • MR.P.V.JYOTHI PRASAD

Counsels for Respondents

  • • MR.C.K.KARUNAKARAN, SC FOR KSEB FOR R1 TO R3

Provisions of Law Cited

Section 26(6) of the Indian Electricity ActRegulation 42(d) of the Conditions of Supply of Electrical Energy

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that Regulation 42(d) permits reassessment for six months; extending reassessment from 12/1997 to beyond six months results in an impermissible liability. He relies on Belwal Spinning Mills Ltd. v. U.P. State Electricity Board (AIR 1997 SC 2793) and the unreported O.P. No. 191/98 and the Division Bench decision in Nirmala Metal Industries v. K.S.E.B. (2006 (3) KLT 465) to argue that arrears must be limited to six months prior to detection. It is asserted that there was no fraud or malpractice by the consumer; the meter under-recording arose from an internal meter connection fault (Y-phase reversed). The petitioner seeks quashing of Ext. P3 and P4 and recalculation of arrears with adjustments to deposits.

Contentions of Respondents

The Board defends that the CT connection reversal and unauthorised 44 kW load justify reassessment from 12/1997, especially given a marked drop in recorded consumption post-inspection. Section 26(6) is applicable in cases of faulty meters causing under-recording, but the period of arrears may extend as per the facts; the Appellate Authority’s reasoning is backed by case law, and the Board is entitled to recover arrears for the period from 12/1997 onward. The reliance on Belwal Spinning Mills, O.P. No. 191/98, and Nirmala Metal Industries is to support the six-month limitation under 26(6) where appropriate, but the Board argues the instant case falls under that regime as established by precedent.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Belwal Spinning Mills Ltd. v. U.P. State Electricity BoardAIR 1997 SC 2793PositiveCited to support that Section 26(6) applies when there is meter fault causing under-recording, limiting arrears to six months prior to detection.
O.P.No.191/98O.P.No.191/98PositiveUnreported decision cited as endorsing the six-month limitation under Section 26(6) in similar circumstances.
Nirmala Metal Industries v. K.S.E.B.2006 (3) KLT 465PositiveDivision Bench decision endorsing the six-month limit under Section 26(6) in analogous cases.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,221 words•~6 min read

In The Court Record

OP.No. 7047 of 2001 (L) - The MANGING DIRECTOR, PERIA PEAK ESTATE PVT. LTD, PERIA POST, MANANDAVADY, WYNAD. v. KERALA STATE ELECTRICITY BORD AND OTHERS

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE HARUN-UL-RASHID** **WEDNESDAY, THE 18TH FEBRUARY 2009 / 29TH MAGHA 1930** **OP.No. 7047 of 2001(L)** **-------------------------------** **PETITIONER(S):** **----------------------** **THE MANGING DIRECTOR, PERIA PEAK ESTATE PVT. LTD, PERIA POST, MANANDAVADY, WYNAD.** **BY ADV. MR.P.V.JYOTHI PRASAD** **RESPONDENT(S):** **-------------------------** ## **1. KERALA STATE ELECTRICITY BORD, REPRESENTED BY SECRETRY, THIRUVANANTHAPURAM.** **2. DEPUTY CHIEF ENGINEER, ANTI POWER THEFT SQUAD, KERALA STATE ELECTRICITY BOARD, THIRUVANANTHAPURAM.** **3. ASSISTANT EXECUTIVE ENGINEER, ELECTRICAL MAJOR SECTION, MANANDAVADY.** **ADV. MR.C.K.KARUNAKARAN, SC FOR KSEB FOR R1 TO R3** **THIS ORIGINAL PETITION HAVING BEEN FINALLY HEARD ON 18/02/2009,THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** ## **OP.No. 7047 of 2001(L)** ## **APPENDIX** **PETITIONER'S EXHIBITS:** **EXT.P1: COPY OF THE ELECTRICITY BILLS PERTAINING TO AUGUST, SEPTEMBER AND OCTOBER 2000.** **EXT.P2: COPY OF THE ORDER OF THE 3RD RESPONDENT DATED 06/11/2000.** **EXT.P3: COPY OF THE INVOICE SHOWING THE AMOUNT OF Rs.8,04,741/- DATED 06/11/2000.** **EXT.P4: COPY OF THE ORDER OF THE 2ND RESPONDNT DATED 08/02/2001.** **RESPONDENT'S EXHIBITS: NIL** ## **//TRUE COPY//** **P.S. TO JUDGE** **Rs/** **HARUN-UL-RASHID,J. --------------------------O.P.NO.7047 OF 2001 ---------------------------DATED THIS THE 18TH DAY OF FEBRUARY, 2009** ## **JUDGMENT** Petitioner is the Managing Director of a tea factory at Mananthavady and is the consumer of electrical energy for the said factory. On 16/9/2000 the Anti Power Theft Squad conducted a site inspection and detected that the power meter is recording only 1/3[rd] of the actual power drawn from the mains due to wrong electrical connection of CT meters resulted in reverse running in one phase and the existence of unauthorised additional load of 44 KW over and above the authorised load of 130 KW. On the basis of the inspection report, which is produced as Ext.P2, the consumer was re-assessed with effect from 12/97 for partial recording and 3 times rate on fixed charge and proportionate current charge was charged for unauthorised additional load (UAL). Ext.P3 is the bill in which the grand total shows Rs.8,04,741/- out of that fixed charge is Rs.27,720/-. Petitioner challenged Ext.P3 bill in an **-2-** ## O.P.No.7047/2001 appeal filed before the Appellate Authority. The Appellate Authority by proceedings dated 8/2/2001 dismissed the appeal. 2. The learned counsel for the petitioner raised all the contentions placed before the Appellate Authority. According to the learned counsel, Regulation 42(d) of the Conditions of Supply of Electrical Energy provides for re-assessment for six months and there is no reason for adopting the period from 12/97, a total period of 32 months. The learned counsel also brought to this Court's attention the decision of the Supreme Court in **Belwal Spinning Mills Ltd. v. U.P. State Electricity Board (AIR 1997 SC 2793),** the unreported decision of the learned Single Judge of this Court dated 23/11/2005 in O.P.No.191/98 and the decision of the Division Bench of this Court in **Nirmala Metal Industries v. K.S.E.B. (2006 (3) KLT 465).** Learned counsel submitted that re-assessment has to be done based on the aforesaid decisions and it has to be limited to six months. 3. The learned Standing Counsel for the K.S.E. Board contended that CT connection in Y phase was reversed and there **-3-** ## O.P.No.7047/2001 was unauthorised additional load of 44 KW during inspection. The period of re-assessment is taken as 12/97, as there was sudden drop in recorded consumption from the said date. The recorded consumption for 10/97 was 21098 Kwh, 11/97 was 23020 KWh and 12/97 was 8782 KWh, which is approximately 1/3 of earlier consumption. It is also brought to this Court's attention the recorded consumption subsequent to the site inspection conducted by the Anti Power Theft Squad. It shows that the recorded consumption for the month of November, 2000 is 30,280 and for the month of December, 2000, is 36,962 kwh. The Appellate Authority did not accept the contention of the appellant that Section 26(6) is applicable and therefore the maximum amount that can be realised is only for a period of six months prior to the date of inspection. The Appellate Authority held that Section 26(6) is applicable only in case of faulty meters where the reassessment is done based on approximation or overcharging. In such cases Section 26(6) will attract and the period has to be limited to six months. According to the **-4-** ## O.P.No.7047/2001 Appellate Authority, in the instant case, it is entirely different and that similar issue has been settled by the judgment of the Apex Court and the High Court. In the judgment in O.P.No.191/98 referred to above, it was stated that on inspection, it was found that there was some defect in the electric connections inside the meter consequent to which the meter was recording only 1/3 of the actual energy consumed. In that case a bill for short assessment for consumption of electrical energy for the period stated therein was issued demanding charges for the balance 2/3 energy as payable by the petitioner therein. 4. This Court relying on the decision reported in Belwal Spinning Mills's case (1997 SC 2793) discussed the issue and observed that there is absolutely no allegation of fraud or malpractice on the part of the consumer, that the reduced recording was caused due to the wrong connection inside the meter. The meter recorded on l/3 of the actual consumption. The facts of the said case and the facts of the present case are more or less similar. In this case also the the consumer has not done any mal- **-5-** ## O.P.No.7047/2001 practice or fraud for the purpose of showing reduced consumption of energy. Since the Y phase connection is reversed, 1/3 of the actual consumption was recorded. In the Supreme Court case also, there was a defective connection whereby the original meter was registering only 76.6% less than the actual use. The Court held that Section 26(6) of the Indian Electricity Act is attracted and therefore, the right of the K.S.E. Board to demand arrears is limited to a period of past six months. In this case also applying Section 26(6) of the Indian Electricity Act, the matter has to be referred to the Chief Electrical Inspector, as in the said case. It was held that the K.S.E. Board is entitled to demand arrears only for a period of past six months for the reason that the recorded consumption is 1/3 of the actual consumption. 5. Ext.P3 bill was issued for realisation of the amount for the loss caused to the Board for the reason that Y phase connection is reversed and for unauthorised additional load to the extent of 44 KWh under Regulation 42(d) of the Conditions of **-6-** ## O.P.No.7047/2001 Supply of Electrical Energy. The petitioner is liable to pay the amounts assessed by the Board for unauthorised additional load of 44 Kwh in addition to the demand for payment of arrears for the past six months from the date of detection. Respondents are entitled to demand only the amount as stated above. 6. In the result, Exts.P3 and P4 are quashed. There will be a direction to the respondents to re-work the arrears and issue a fresh bill to the petitioner within a period of two months from the date of receipt of a copy of this judgment. The amount already deposited in compliance of the interim order passed by this Court shall be adjusted. Original Petition is disposed of as above. **HARUN-UL-RASHID, Judge.** **kcv.**
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.