Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Single JudgeDismissed

OP.No. 35824 of 2002 (M)

Case / Petition Number:
O.P.No. 35824 of 2002
Neutral Citation:.

Case Synopsis & Summary

OP No. 35824 of 2002 (M) is a Kerala High Court matter by Mohammed HaneeFa Kapoor, a Gulf Automobiles proprietor, challenging electricity charges raised by KSEB after May 2000. An inspection in May 2000 revealed that after May 2000 no bills were issued for consumption, and that on transition from slab to spot billing an appropriate adjustment was not made. Four bills were issued for two consumer numbers, including charges for unauthorised load. The petitioner argued that he had been paying all bills promptly and correctly, and that any delay in billing was the Board’s fault; even if true, liability should not be imposed in a heavy lump sum. The Board contended that no bills were issued from May 2000 to July 2002, and that delay cannot excuse non-payment; it also noted petitioner’s admission of unauthorised load and the validity of penal charges. The Executive Engineer’s Ext.P13 order upheld three categories of charges: (i) energy actually consumed but belatedly billed; (ii) energy billed belatedly for the spot period; and (iii) penalties for unauthorised load. The court relied on W.A. No. 2076/2004 and Kusumam Hotels (P) Ltd. v. State Electricity Board to hold that delay does not extinguish liability; the Board may rectify mistakes and demand payment. The petition was dismissed, but instalment options were allowed and notices for recovery were directed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • S. Siri Jagan
Judgment Date
2009-04-02
Court Decision / Holding
The petition is dismissed. The court upholds the bills as in order (including the energy bills and unauthorised load charges) and directs the Assistant Executive Engineer to recover the amounts with instalment facilities as specified. The court also notes prior judicial decisions supporting the Board’s rectification of mistakes and the ongoing liability to pay electricity charges.
Final Disposition
Dismissed

Parties to the Case

Appellants / Petitioners

  • Mohammed HaneeFa Kapoor

Respondents

  • The Assistant Executive Engineer, Electrical Major Section, Kerala State Electricity Board, Perinthalmanna
  • The Executive Engineer, Electrical Division, Kerala State Electricity Board, Perinthalmanna
  • Kerala State Electricity Board, represented by its Secretary, Vydyuthi Bhavan, Thiruvananthapuram

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. K.M. Sathyanatha Menon
  • • Adv.

Counsels for Respondents

  • • Sri. C.K. Karunakaran, SC for KSEB for R1-3

Provisions of Law Cited

Section 56(2) of Electricity Act, 2003Section 61 of Electricity ActSection 6 of the General Clauses Act, 1897

Legal Doctrines & Maxims

  • Public interest shall not suffer in view of the mistake committed by the Board.
  • Law of limitation will not apply since the default is a continuing one.
  • The liability to pay electricity charges is a statutory liability.
  • Board shall have power of rectifying the mistake and bills issued after rectifying the mistake have to be honoured.
  • Continuing liability principle under General Clauses Act, Section 6.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that he has paid all bills promptly and correctly and that the Board’s negligence in delaying or failing to issue bills cannot justify demanding large sums at once. He asserts that even if there was an error by the Board, it cannot unjustly penalize him with a huge liability, and that penal charges for unauthorised load are not justified without proper notice or due process. He also relies on prior court directives (O.P. 20752/02) to challenge the present demands.

Contentions of Respondents

The Board argues that from May 2000 to July 2002 no bills were issued, and delay cannot excuse payment; it emphasizes petitioner’s admission of unauthorised load and asserts that penal charges are valid. It relies on the reviewing order Ext.P13, and cites W.A. 2076/2004 and Kusumam Hotels to demonstrate that the liability for electricity charges persists despite missteps and that the Board may rectify mistakes and demand payment.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Kusumam Hotels (P) Ltd. v. State Electricity Board & OthersCDJ 2008 SC 1056; AIR 2008 SC 2796; 2008 (2) KHC 792PositiveUsed to establish that liability for electricity charges continues and that bills arising from earlier periods can be enforced, even where there was delay in issuing bills.
Southern Petrochemical Industries Co. Ltd. v. Electricity Inspector and E.T.I.O. And Ors.2007 5 SCC 447PositiveCited to reinforce the general principle of liability continuation and the effect of statutory provisions on billing and payment.
W.A.No.2076/2004W.A. No. 2076/2004PositiveQuoting a holding that public interest cannot suffer due to Board mistakes and that bills after rectification must be honoured; limitation does not apply for continuing defaults.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,937 words•~9 min read

In The Court Record

OP.No. 35824 of 2002 (M)

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE S.SIRI JAGAN THURSDAY, THE 2ND APRIL 2009 / 12TH CHAITHRA 1931 OP.No. 35824 of 2002(M) ----------------------- PETITIONER(S): --------------- MOHAMMED HANEEFA KAPOOR, PROPRIETOR, GULF AUTOMOBILES, TIRUKADU, MALAPPURAM DISTRICT. BY ADV. SRI.K.M.SATHYANATHA MENON RESPONDENT(S): --------------- 1. THE ASSISTANT EXECUTIVE ENGINEER, ELECTRICAL MAJOR SECTION, KERALA STATE ELECTRICITY BOARD, PERINTHALMANNA. 2. THE EXECUTIVE ENGINEER, ELECTRICAL DIVISION, KERALA STATE ELECTARICITY BOARD, PERINTHALMANNA. 3. KERALA STATE ELECTRICITY BOARD, REP. BY ITS SECRETARY, VYDYUTHI BHAVAN, THIRUVANANTHAPURAM. ADV. SRI.C.K.KARUNAKARAN, SC FOR KSEB FOR R1-3 THIS ORIGINAL PETITION HAVING BEEN FINALLY HEARD ON 02/04/2009, THE COURT ON 02/04/2009 DELIVERED THE FOLLOWING: ## O.P.No. 35824/02. ## APPENDIX ## PETITIONER(S)' EXHIBITS - P1. COPY OF THE APPLICATION DTD.9.7.02. P2. COPY OF THE BILL DTD.8.7.02. P3. COPY OF THE NOTICE DTD.9.7.02. P4. COPY OF THE NOTICE DTD.9.7.02. P5. COPY OF THE ADDITIONAL BILL DTD.8.7.02. P6. COPY OF THE NOTICE DTD.15.7.02. P7. COPY OF THE BILL DTD.15.7.02. P8. COPY OF THE BILL DTD.15.7.02. P9. COPY OF THE LAWYER NOTICE DTD.18.7.02. P10. COPY OF THE APPEAL BEFORE R2 DTD.18.7.02. - P11. COPY OF THE RECEIPT DTD.15.7.02. - P12. COPY OF THE JUDGMENT IN O.P.NO.20752/02 OF THIS COURT. P13. COPY OF THE ORDER DTD.6.11.02 BY R2. - P14. COPY OF THE ORDER DTD.12.11.02. RESPONDENT(S)' EXHIBITS: - R1A. COPY OF THE LETTER DTD.15.7.02. - B. COPY OF THE SITE MAHAZAR DTD.9.7.02. - C. COPY OF THE -DO- DTD.9.7.02. Sdk+ ///True copy/// P.A. to Judge S.SIRI JAGAN, J. ================== ## O.P.No. 35824 of 2002 ================== Dated this the 2[nd] day of April, 2009 ## J U D G M E N T The petitioner is a consumer of electricity from the KSEB. The petitioner is running an industry. In his industrial premises he had two connections; one bearing consumer No.15007 and the other bearing consumer No.14873. An inspection was conducted in the petitioner's premises in May, 2000. The squad detected that after May, 2000, no bills were raised against the petitioner for consumption of electricity and the petitioner was not paying electricity charges also. It was also found that on change over from slab system to spot billing system in May, 2000, appropriate adjustment invoice was not issued for the consumption of energy in excess of what has been paid for as per the slab system. In the above circumstances, four bills were issued to the petitioner in respect of the two consumer numbers. It was also found that the petitioner had used unauthorized connected load for which, bills for an amount of Rs.47,381/- in respect of consumer No.15007 and an amount of Rs.4543/- in respect of consumer No.14873 were issued to the petitioner. The petitioner contested the above said bills on the ground that he is not liable to pay those amounts. The petitioner earlier approached this Court by filing O.P.No. 20752/2002, in which, by judgment dated 24.7.2002, this Court directed the 2 o.p.35824/02 Executive Engineer, Electrical Division, Perinthalmanna, to consider the appeal filed by the petitioner. Pursuant thereto, the petitioner was heard and the appeal was disposed of, by Ext.P13 order, confirming the demand as per the bills. Ext.P13 is under challenge in this original petition. 2. As before the Executive Engineer, in this original petition also the contention of the petitioner is that he is not liable to pay those amounts because he had all along been paying all bills issued to him promptly and correctly. He would raise an alternate contention that it is because of the negligence of the officers of the Board that the bills were not raised. Even if it is true, the petitioner cannot be made liable to pay such huge amount all on a sudden, which would be unjust and unreasonable is the contention raised by the petitioner. 3. The counsel for the Electricity Board would strongly dispute the contentions of the petitioner. The counsel would contend that from May, 2000 onwards till July, 2002, no bills were issued to the petitioner. According to the counsel, even if it is on account of the negligence on the part of the officers of the Board, that cannot give any undue advantage to the petitioner and he cannot take a contention that because the bills were not issued in time, he will not pay that amount. The counsel also points out that the petitioner himself admitted before this Court in the original petition that he had 3 o.p.35824/02 unauthorized additional load which has been recorded in the judgment of the High Court. Therefore, according to the counsel for the Board, the realisation of penal charges for unauthorized additional load is also perfectly valid and proper. The counsel also points out that this Court has in W.A.No.2076/2004 held that even if there was delay in issue of bills, that cannot give raise to a right in the consumer not to pay for the electricity charges. 4. I have considered the rival contentions in detail. 5. The contentions of both parties have been elaborately discussed by the Executive Engineer in Ext.P13 order. He ultimately held thus: “On verification of the evidences given by both parties as above and after verifying the records, I have come to the following conclusions: - I. The cut off Reading Bill No:16941 dated 8.7.2002 issued based on the reading taken during 5/2000 towards energy consumed over and above that covered by provisional Invoice Card is in order. The petitioner consumer has to pay the bill amount of Rs.34,869/- No penal charges or penalty is imposed on the above amount and it covers only the cost of energy enjoyed by the petitioner consumer from date of connection to 5/2000 but not billed in time due to over sight. - II. The bill No: 821481 dated 8.7.2002 for Rs.1,23,726/- issued to the petitioner consumer towards actual energy used for the spot bill period from 5/2000 to 7/2002, but not billed due to over sight, is in order and the consumer has to pay the amount. The above amount does not include any penal charges or interest but the cost of energy as per tariff applicable at the time of consumption. - III. There is no evidence of receiving any application for granting additional load from the consumer on 9.7.2002. The bill for cut off reading and bill for spot bill period for consumer No:15007 is seen issued on 8.7.2002. The consumer premises was inspected on 9.7.2002 and unauthorised additional load detected as below: The 4 o.p.35824/02 petitioner consumer has accepted before the Hon'ble High Court that he has unauthorised additional load as is evident from the Judgment of the Hon'ble Court. Unauthorised Additional Load. - Consumer No:15007 9 KW Consumer No.14873 - 2 KW. The consumer has to pay the additional bill as per Rules in force. - IV. The argument of the counsel for petitioner consumer that the previous period bills are to be limited for a period of six months does not hold good. Six months limiting is applicable only to meter faulty cases and in correct meter reading. Here the meter is working properly and the meter accuracy is not disputed. Considering all the above aspects, I hereby order the following: - I. The bills issued No.:16941 dated 8.7.2002 for Rs.34,869/- is in order. The Asst. Executive Engineer will take action to realise the amount deducting Rs.3549/- already remitted by the consumer. The petitioner consumer can pay the amount in Lump Sum without interest. If he desires to pay in instalments, 9 instalments may be allowed with interest. - II. The bill No.:821481 dated 8.7.2002 for Rs.1,23,726 is in order. The Asst. Executive Engineer will take action to realise the balance amount after deducting Rs.12,396/- remitted by the consumer as Ist instalment and Rs.50,000/- remitted by the consumer as per direction of the Hon'ble High Court. The consumer can pay the amount in Lump Sum without interest or opt to avail instalment facility with interest. The consumer may be allowed 5 instalments if desired so. - III. The Asst. Executive Engineer, Electrical Sub Division, Perinthalmanna will take action to recover the following bill amounts towards unauthorised additional load. - 1) Consumer No.15007 (Bill 75474/8.7.2002 Rs.47381/2) Consumer No.14873 (Bill 168831/16.7.2002 Rs. 4543/- The consumer can pay the amount in lump sum without interest or avail ten instalment facility for bill No.75474 dated 8.7.2002 for Rs.47381/- and two instalments for Bill No:16883/16.7.2002 for Rs.4543/- - IV. The Asst. Executive Engineer, Electrical Sub Division, 5 o.p.35824/02 Perinthalmanna will arrange to issue Notice to the petitioner consumer as per rules, intimating the balance amount to be paid against each bill, mentioning instalment facility as above with due date for each instalment. ## In the decision in W.A.No.2076/2004, it has been held thus: “5..... Public interest shall not suffer in view of the mistake committed by the Board. Board shall have power of rectifying the mistake and bills issued after rectifying the mistake have to be honoured. Law of limitation will not apply since the default is a continuing one and the amount due to the Board was not claimed in time due to the negligence of the Board. Consumer is liable to pay the said amount on rectification of the mistake....” ## The Supreme Court has, in the decision in _**Kusumam Hotels (P) Ltd.**_ ## _**v. State Electricity Board & Others**_ [CDJ 2008 SC 1056], which is also reported in AIR 2008 SC 2796 and 2008 (2) KHC 792, held thus: “Whereas the bills are issued only in respect of the dues arising in terms of the law as was applicable prior to the coming into force of 2003 Act. Sub-section (2) of Section 56 shall apply after the said Act came into force. The Board could have even framed a tariff in terms of the provisions appended to Section 61 of the Act. Appellants incurred liability to pay the bill. The liability to pay electricity charges is a statutory liability. The Act provides for its consequences. Unless, therefore, the 2003 Act specifically introduced, the bar of limitation as regards the liability of the consumer incurred prior to coming into force of the said Act. In our opinion, having regard to Section 6 of the General Clauses Act, the liability continues [See Southern Petrochemical Industries Co. Ltd. v. Electricity Inspector and E.T.I.O. And Ors. [(2007 5 SCC 447].” Therefore, it is settled law that simply because there was delay on the part of the officers of the Board in issuing bills for consumption of energy, the consumer cannot escape from the liability to pay charges for the electricity consumed by him. In this case, although the petitioner would repeatedly contend that he had paid all bills he received, the petitioner has not been able to produce even a single bill 6 o.p.35824/02 and any evidence to show that he had paid any electricity charges subsequent to May, 2000 till July 2004. That being so, I am unable to countenance the contention of the petitioner that because of the fault of the officers of the KSEB in not issuing bills, he is not liable to pay the amounts demanded. 6. As far as the penal charges for additional unauthorised load is concerned, the petitioner himself admitted before this Court that the petitioner had used unauthorised additional load. That being so, he cannot escape from the liability to pay penal charges for the same. In the above circumstances, I do not find any merit in this original petition and accordingly, the same is dismissed. Sd/sdk+ S.SIRI JAGAN, JUDGE ///True copy/// P.A. to Judge o.p.35824/02 7 S.SIRI JAGAN, J. ================== O.P.No. 35824 of 2002-M ================== J U D G M E N T 2[nd] April, 2009
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.