Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Single JudgeDismissed

O.P. No. 6769/2003 (E)

Case / Petition Number:
6769/2003-E

Case Synopsis & Summary

This original petition, in the Kerala High Court, centers on the Forest (Conservation) Act, 1980 and the alleged right of the petitioner to draw water from the Periyar River through reserve forest land for irrigation of about 70 acres along the river. The petitioner and added petitioners rely on Exts. P1 and P2 (1964/1954 agreements, renewed in 1989) which permitted a pump house and channels through forest land for irrigation, subject to conditions that the Government wields ultimate control and the lessee may be required to surrender the land without compensation. The petition contends that the petitioner has operated under these agreements for decades and that Exts. P6 (6.2.2003) and P7 (30.12.2002)—the Central Government’s denial of renewal and a directive to stop forwarding proposals under Section 2 of the Act—violate the Act and the contractual arrangement. The respondents counter that Section 2(iii) requires Central permission for diverting forest land and that the Central Government, after careful consideration, refused renewal in the interest of forest conservation, and that Ext. P7 reflects reasoned consideration with an effective ban on private proposals. The court ultimately held that the petition fails and dismissed it, though permitting time to arrange alternative irrigation arrangements.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K. Surendra Mohan
Judgment Date
2009-02-20
Court Decision / Holding
Writ petition dismissed. Time granted up to June 2009 to arrange alternative irrigation methods. No costs.
Final Disposition
Dismissed

Parties to the Case

Appellants / Petitioners

  • Joseph Kurian
  • Annamma Kurian
  • Joseph Kurian (S/O Late Joseph Kurian)
  • Sebastian Kurian
  • Alex Kurian

Respondents

  • Union of India, rep by Secretary to Govt., Ministry of Environment and Forests, New Delhi
  • State of Kerala, rep by Secretary to Govt., Forests and Wildlife Department, Secretariat, Thiruvananthapuram
  • Deputy Conservator of Forests (C), Ministry of Environment & Forests, Government of India, Regional Office, Kendriya Sadan, Bangalore
  • Principal Chief Conservator of Forests, Forest Headquarters, Vazuthacaud, Thiruvananthapuram
  • Asst. Conservator of Forest, Nature Study Centre, Kalady, Malayattoor

Legal Representation & Advocates

Counsels for Petitioners

  • • V.P. Seemandini, Senior Advocate
  • • M.S. Unnikrishnan

Counsels for Respondents

  • • P. Parameswaran Nair, Asst.Solicitor General
  • • John Varghese, Assistant Solicitor General
  • • Sandesh Raj, Government Pleader

Provisions of Law Cited

Forest (Conservation) Act, 1980 - Section 2Forest (Conservation) Act, 1980 - Section 2(iii)Constitution of India - Article 226

Legal Doctrines & Maxims

  • Jurisdiction under Article 226 cannot be invoked for purely contractual disputes.
  • Section 2 of the Forest (Conservation) Act, 1980 confers overriding powers on the Central Government.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners challenge Ext.P6 (6.2.2003) directing surrender and Ext.P7 (30.12.2002) denying renewal and forbidding forwarding proposals under Section 2 of the Forest (Conservation) Act. They argue that Exts.P1 and P2 contemplated a contractual arrangement permitting water extraction via a pump house and channels within Reserve Forest lands for irrigation, creating vested rights and ongoing use. They contend the blanket ban on forwarding private proposals under Section 2 is unjustified and contrary to the Act, and that denial of renewal, without considering Ext.P8 representation, deprives them of a lawful entitlement.

Contentions of Respondents

Respondents contend that the petitioner’s use of forest land requires Central approval under Section 2(iii) of the Act; Ext.P7 shows careful consideration and Central Government denial in the interest of forest conservation. They emphasize the contractual terms in Exts.P1 and P2, including the Government’s control and surrender clause, and argue that renewal could only be granted with Central approval. They assert that the petitioner’s long-standing use since 1989 is without legal sanction, and the Central Government’s action is well within the Act’s framework, citing Ambica Quarry Works to support the power to renew/deny leases in consonance with conservation objectives.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Ambica Quarry Works v. State of Gujarat and othersAIR 1987 SC 1073PositiveCited by the Government Pleader to support the power of the Central Government to grant or refuse renewal under the FCA, recognizing the Act’s conservation objectives.
State of Kerala v. Moosa Haji1984 KLT 494 (F.B)Mentioned OnlyCited by counsel to discuss the scope of the Central Act in permitting deforestation with prior approval; court references it but does not rely on it to constrain the central government’s powers in the present case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,730 words•~13 min read

In The Court Record

O.P. No. 6769/2003 (E)

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE K.SURENDRA MOHAN** **FRIDAY, THE 20TH FEBRUARY 2009 / 1ST PHALGUNA 1930** ## **OP.No. 6769 of 2003(E)** ## **---------------------------------PETITIONER(S):** **------------------------JOSEPH KURIAN, KANNAMPUZHA HOUSE, MALAYATTOOR P.O., ERNAKULAM DISTRICT.( D I E D)** ## ***ADDL.PETITIONERS 2 TO 6 ARE IMPLEADED:** - **P2. ANNAMMA KURIAN, W/O.LATE JOSEPH KURIAN, KANNAMPUZHA HOUSE, MALAYATTOOR.** - **P3. JOSEPH KURIAN, S/O.LATE JOSEPH KURIAN,..DO.....** - **P4. SEBASTIAN KURIAN, ....DO...DO.....** - **P5. ALEX KURIAN, ............. DO...DO......** - ***ADDL.PETITIONERS 2 TO 5 ARE IMPLEADED AS PER ORDER DTD. 17/10/2008 IN I.A.NO.12609/08.** ## **BY SMT.V.P.SEEMANDINI, SENIOR ADVOCATE, MR.M.S.UNNIKRISHNAN.** ## **RESPONDENT(S):** - **---------------------------** **1. UNION OF INDIA, REP.BY ITS SECRETARY TO GOVT., MINISTRY OF ENVIORNMENT AND FOREST, NEW DELHI.** **2. STATE OF KERALA, REP.BY THE SECRETARY TO GOVT.FOREST, WILD LIFE DEPARTMENT, SECRETARIAT, TRIVANDRUM.** **3. DEPUTY CONSERVATOR OR FOREST (C), MINISTRY OF ENVIORNMENT & FOREST, GOVERNMENT OF INDIA, REGIONAL OFFICE, KENDRIYA SADAN, 4TH FLOOR, E & T WINGS, 17 MAIN ROAD, 2ND BLOCK, KARAMANGOLA, BANGALORE.** _Kss_ **..2/-** **...2....** ## **O.P.NO.6769/2003 E** **4. PRINCIPAL CHIEF CONSERVATOR OF FORESTS, FOREST HEADQUARTERS, VAZHUTHACAUD. TRIVANDRUM.** **5. ASST.CONSERVATOR OF FOREST, NATURE STUDY CENTRE, KALADY, MALAYATTOOR.** **R1 TO R3 BY ADV.MR.P.PARAMESWARAN NAIR,ASST.SOLICITOR GENERAL MR.JOHN VARGHESE, ASSISTANT SOLICITOR GENERAL R5 BY GOVERNMENT PLEADER MR. SANDESH RAJ** **THIS ORIGINAL PETITION HAVING BEEN FINALLY HEARD ON 20/02/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** _Kss_ ## **ORDER ON C.M.P.NO.11819/2003 IN O.P.NO.6769/2003E** ## **DISMISSED** ## **20/02/2009** ## **SD/- K.SURENDRA MOHAN, JUDGE** ## **APPENDIX** ## **PETITIONER'S EXHIBITS:** **EXT.P1: COPY OF THE AGREEMENT DTD. 9/07/1954 BETWEEN THE PETITIONER AN GOVT. OF TRAVANCORE.** - **EXT.P2: COPY OF THE RENEWAL DEED DTD. 31/05/1989 FOR THE FURTHER PERIOD OF 10 YEARS.** - **EXT.P3: COPY OF THE ROUGH SKETCH SHOWING THE LIE OF THE PROPERTY.** - **EXT.P4: COPY OF THE REPRESENTATION DTD. 10/07/1998 SUBMITTED BEFORE THE 4TH RESPONDENT.** - **EXT.P5: COPY OF THE LETTER DTD. 1/02/2001 SUBMITTED BEFORE THE 4TH RESPONDENT.** - **EXT.P6: COPY OF THE NOTICE NO.NSC 69/98 DTD. 6/02/2003.** - **EXT.P7: COPY OF THE LETTER DTD. 30/12/2002 GIVEN TO THE PETITIONER BY THE 4TH RESPONDENT.** - **EXT.P8: COPY OF THE PETITION DTD. 15/02/2003 SUBMITTED BY THE PETITIONER BEFORE THE 4TH RESPONDENT.** ## **RESPONDENT'S EXHIBITS: N I L** **/TRUE COPY/** **P.S.TO JUDGE** _Kss_ **K. SURENDRA MOHAN, J ------------------------------------------------------------** **O.P. NO:6769 OF 2003-E ----------------------------------------------------------Dated this the 20[th] February,2009.** ## **JUDGMENT** Substantial questions of grave import concerning protection of forests, arise for determination in the above writ petition. The petitioner has approached this Court seeking the issue of a Writ of Certiorari, quashing Ext.P6 proceedings of the fifth respondent and Ext.P7 letter of the third respondent, as violative of the provisions of the Forest (Conservation) Act, 1980, hereinafter referred to as the 'Act'. As per the impugned proceedings, the petitioner has been declined permission to irrigate his plantation by taking water from the Periyar river through the Reserve Forest Land. 2. According to the petitioner, he along with his brothers are the owners of 70 acres of land comprised in survey Nos: 426/1-2, 407/1, 407/2, 429 and 430 (re-survey Nos: 104/4, 103/3, 114/7, 97/4, 97/7, 112/8 and block No: 23) of Malayattoor Village. The property lies along the northern side of Periyar river and is separated by a strip of forest land of about 150 mtrs width (Arattukadavu tea plantation reserve). For the purpose of irrigating the said property the petitioner was taking water from the river O.P.No: 6769/2003 2 through the forest land. As per Ext.P1 agreement dated 9.7.1954 entered into between the petitioner and the then Government of Travancore-Cochin, the petitioner was permitted to take water through the forest land by cutting channels through the forest. The agreement was subsequently renewed by Ext.P2 up to the year 1999. According to the petitioner, he has put up a pump house, has cut water channels through the Reserve Forest and has been taking water to his property for irrigation purposes, ever since. A rough sketch Ext.P3 produced by the petitioner shows the location of the property, the pump house and the channels. 3. On 10.7.1998 the petitioner approached the fourth respondent, the Principal Chief Conservator of Forests, for a further extension of the lease, since the lease was to expire on 31.3.1999. The petitioner was informed that further extension of the lease could be given only with the prior permission of the third respondent, the Deputy Conservator of Forests, Ministry of Environment and Forests, Government of India and, therefore, he waited. Subsequently, the petitioner received Ext.P6 communication dated 6.2.2003 directing him to make alternative arrangements for the irrigation of his land and to surrender vacant possession of the land in his possession to the forest department 3 O.P.No: 6769/2003 before 28.2.2003. Ext.P6 was issued in view of the proceedings of the third respondent dated 30.12.2002 refusing to give permission for extension of the lease, that was sought for by the petitioner. The said proceedings, addressed to the Principal Secretary, Government of Kerala, Forests and Wild Life Department, is Ext.P7. Ext.P7 contains a further direction not to forward proposals catering to the individuals' interests for approval under Section 2 of the Act in future. The petitioner filed the above writ petition challenging Exts.P6 and P7 contending that they were violative of the provisions of the Act. The complete ban of even forwarding of proposals for consideration under Section 2 of the Act is attacked as absolutely uncalled for. 4. During the pendency of the Original Petition the petitioner died and his legal representatives have been brought on record as additional petitioners 2 to 6. However, for the sake of convenience reference is made herein only to the original petitioner who was on the party array, at the time of filing of the Original Petition. 5. The Original Petition is contested by the respondents. Separate counter affidavits have been filed on behalf of respondents 1 to 3 and the 5[th] respondent justifying the impugned proceedings. According to the respondents, as per Ext.P1 O.P.No: 6769/2003 4 agreement the petitioner was permitted to construct a pump house and to cut two channels inside the Reserve Forest for the irrigation of his property. As per condition No:5 of the said agreement it is made clear that the permission does not confer any right on the petitioner in respect of the forest land. As per Section 2(iii) of the Act, no State Government or other authority is permitted except with the prior approval of the Central Government to pass any order directing that any forest land or portion thereof may be assigned by way of lease or otherwise to any private person or to any authority, corporation, agency or any other organisation not owned, managed or controlled by Government. Accordingly the proposal of the petitioner was placed before the Central Government but, permission was not granted by the Central Government. It is contended on behalf of respondents 1 to 3 that the proposal forwarded by the State Government for diversion of forest land for non-forestry purpose in favour of the petitioner was throughly scrutinised by the Ministry of Environment and Forests. According to the counter affidavit, after considering all the relevant facts, the Ministry came to the conclusion that utilisation of forest land by the petitioner from 31.5.1989 onwards is without any legal sanction. According to them, the utilisation of the forest land upto 1989 O.P.No: 6769/2003 5 itself was illegal and violative of the provisions of the Act. Therefore, they sought for dismissal of the Original Petition. 6. I have heard the counsel for the petitioner Mr. M.S.Unnikrishnan and the Govt. Pleader appearing on behalf of the respondents. 7. It is to be noted at the very outset that the petitioner has no right to get any portion of the Reserve Forest Land either by way of a fresh lease or by way of renewal of the earlier lease. It is trite that, in the absence of any right that enjoys the protection of law, the petitioner cannot invoke the jurisdiction of this Court under Art.226 of the Constitution. 8. Further, the issue in the present case is essentially contractual in nature. It is a settled proposition of law that the jurisdiction of this Court under Art.226 of the Constitution is not available to settle contractual disputes. 9. Apart from the above, the lease agreements Exts.P1 and P2 show that they were granted for a specific purpose, on the express condition that the petitioner shall not raise any claim of easement in respect of the forest land. The condition was accepted by the petitioner and he was utilising the land subject to the said condition, which is contained in clause 5 of Ext.P1. It is further O.P.No: 6769/2003 6 stipulated in clause 11 of Ext.P2 as follows:- “The Government shall have the full control over the land on which the pump house is created and through which the channel is opened and the lessee shall surrender the area covered by the pump house and channel is and when required by the Government without claiming any compensation, after dissantling the structures, is any, at his own cost and risk. The right will be terminated is so required by the Department and the lessee can not claim any compensation for the same.” Therefore, the petitioner has also agreed to surrender the land covered by the pump house and channel as and when demanded by the Government without claiming any compensation. In view of the above clause in the agreement, the petitioner cannot claim any right in respect of the land covered by the agreement. Nor can he claim any right to get the lease renewed. 10. After the coming into force of the Forest (Conservation) Act, 1980, renewal of the lease Ext.P2 could be granted by the State Government only with the prior approval of the Central Government. It is in the above circumstances that the proposal for renewal of lease was forwarded to the Central Government. It has been stated in Ext.P7 that “after careful consideration of the proposal of the State Government, I am directed to convey Central Government's inability to approve the proposal in the interest of O.P.No: 6769/2003 7 Conservation of Forests.” Therefore the proposal for renewal of lease submitted by the petitioner has been rejected after careful consideration, on the ground of conservation of forests. No material has been produced by the petitioner to show that the decision of the Central Government was motivated by any extraneous consideration or interest. Therefore, it cannot be said that Ext.P7 has been issued without considering the proposal of the petitioner or without application of mind. 11. Further, as noticed above the petitioner does not have a right to get the lease renewed in his favour since it is an admitted fact that the land is forest land covered by the Act. The counsel for the petitioner has placed reliance on the decision reported in **State of Kerala v. Moosa Haji** {1984 KLT 494 (F.B)} . According to the counsel it has been laid down in paragraph 22 of the said decision that even as regards deforestation, there is no prohibition in the Central Act. All that it says is that, before passing an order permitting use of forest land for non-forest purposes, the State Government should get the prior approval of the Centre. The Central Act is thus not designed to ban all deforestation, but only to permit it in an orderly manner, with such controls as the Central Government may seek to enforce. The decision relied on by the O.P.No: 6769/2003 8 counsel for the petitioner does not place any fetters on the power of the Central Government to grant or refuse permission to carry on any activity with respect to forest land. In this case also what has been done by the Central Government is only to refuse permission, for valid reasons, remaining well within the ambit of the power conferred on it by the Act. Counsel for the petitioner further submitted that the proceedings, Ext.P7 have gone to the extent of banning even consideration of future proposals for utilisation of forest land by private individuals. The same is contended to be absolutely without authority. For the said reason it is contended that the order requires to be set aside and a direction to consider Ext.P8 representation should be issued by this Court. 12. I do not think that the said statement in Ext.P7 affects the rights of the petitioner in any way. The said statement has been made after considering and rejecting the proposal for renewal forwarded by the State Government with respect to the petitioner's agreement. The proceedings show that there has been application of mind. It is further contended that respondent No:4 has issued Ext.P7 on the mistaken impression that the proposal of the petitioner was to erect a pump house and to construct irrigation channels through forest land whereas, the pump house and O.P.No: 6769/2003 9 channels have been in existence in the forest land from the date of Ext.P1 onwards. The above contention is raised relying on the subject portion of Ext.P7. Since the request of the petitioner has been considered properly in the body of Ext.P7, the said error in the description of the subject in Ext.P7 does not affect the validity of the said proceedings. As already noticed, Ext.P7 mentions in its body that the proposal of the petitioner has been considered in detail and there is no material or evidence available, to discredit the said statement. 13. Conservation and preservation of the environment has long ceased to be the luxury of the developed nations and has become an imperative obligation of all, for preserving the humanity. The planet earth is in peril and the environmental depredation can be reversed only by positive efforts, concerted action and carefully planned initiatives implemented with determination. It is a realization of this grave situation that has led to the enactment of the Forest (Conservation) Act, 1980. The legislature has in its wisdom decided that conservation was too important a matter to be left to the localised decision making of the respective states and has entrusted the Central Government with the said duty. The duty has to be approached in the National and Global perspective. O.P.No: 6769/2003 10 Section 2 of the Act confers over-riding powers on the Central Government in supersession of all other enactments, to implement the policy of conservation of forests. Forests constitute the invaluable wealth not only of our Nation but the entire humanity, which are to be preserved not only for the present generation but also for the future generations and for posterity. For realising the above objective it is open to the Central Government to even ban all activities of private persons inside the forests. Therefore, the prohibition contained in Ext.P7 is well within the powers of the Central Government under the Act. 14. The learned Govt. Pleader relied on the decision of the Supreme Court in **Ambica Quarry Works v. State of Gujarat and others** (AIR 1987 SC 1073) and submittd that the Government had the power to grant or refuse the renewal of a lease under the Act. In the said case, the State Government rejected an application for renewal of a mining lease and the rejection was sustained on the ground that the same was in conformity with the purpose of the Forest (Conservation) Act, 1980. The above decision applies on all fours to the present case also. 15. The counsel for the petitioner submitted that by virtue of the order of stay granted by this Court he had been using the water O.P.No: 6769/2003 11 from the river Periyar for his irrigation purposes during the pendency of this Original Petition. He therefore prays for some time to make alternative arrangements. The Govt. Pleader has no objection in a reasonable time being granted. In the above circumstances considering his long occupation, time is granted to the petitioner till June 2009 to make alternative arrangements for irrigating his land. 16. As already noticed, the petitioner has not been able to show that Exts.P6 and P7 suffer from any infirmity or that the said proceedings are ultravires the powers of the Central Government under the Act. In view of the above the writ petition fails and is dismissed with the above directions. No costs. ## K. SURENDRA MOHAN Judge jj O.P.No: 6769/2003 12 K. SURENDA MOHAN, J. **-------------------------------O.P.NO: 6769 OF 2003-E --------------------------------** ## **JUDGMENT** Dated: 20[th] Feburary, 2009.
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.