Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Division BenchAppeal allowed in part

Omana Amma v. The State of Kerala

Case / Petition Number:
LAA No. 208 of 2009

Case Synopsis & Summary

This Land Acquisition Reference under section 18 of the Land Acquisition Act, 1894 concerns the claimant-turned appellant Omana Amma and co-claimant Goury Sadanam challenging the award of compensation by the Land Acquisition Officer for land acquired for a railway project (LA A 167/2001). The possession of the property is alleged to have been taken on 30-08-1990, before the Section 4(1) notification was issued (07-07-1991). The appellant sought statutory interest on the amount remaining unpaid from the date of possession at 9% for one year and 15% thereafter under sections 28 and 34, and asserted interest on the solatium component of the award. The respondent-State contended that pre-notification possession cannot attract interest under Section 28/34; reliance was placed on R.L. Jain v. A.D.A. and Melath Chathukutty Nair. The court recognizes the earlier line but ultimately follows Sundar v. Union of India (Constitution Bench), holding that interest on solatium is payable and that the pre-notification period is not eligible for such interest. The bench clarifies that possession may arise through a private arrangement but that the reference court's task is to determine the correct total compensation, including interest on unpaid balance. The judgment awards Rs.70,030.10 as interest on the balance and confirms interest on solatium, with the caveat that no pre-4(1) interest is payable. Costs follow the result.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Pius C. KuriaKose
  • C.K. Abdul Rehim
Judgment Date
2009-03-11
Court Decision / Holding
The appeal is allowed in part: (1) the appellant is entitled to interest on the solatium; (2) there is no entitlement to interest for the period prior to the notification under section 4(1); (3) the appellant is entitled to Rs.70,030.10 as interest on the compensation remaining payable; costs to both sides.
Final Disposition
Appeal allowed in part

Parties to the Case

Appellants / Petitioners

  • Omana Amma
  • Goury Sadanam, Perumon, Kollam District

Respondents

  • The State of Kerala, represented by the District Collector, Kollam, Kollam - 691 013

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. B. Suresh Kumar

Counsels for Respondents

  • • Sri P.K. Babu

Provisions of Law Cited

Land Acquisition Act, 1894Section 18Section 28Section 34Section 4(1)Section 16Section 17(1)Section 23(2)Section 23(1-A)

Legal Doctrines & Maxims

  • Possession must be under Sec 16 or Sec 17(1) for interest under Sec 28/34; possession otherwise is de hors the Act
  • Constitution Bench Sundar v. Union of India holds entitlement to interest on solatium
  • A reference under Sec 18 is used to determine the correct compensation including interest; LA Officer's award is an offer; the court may settle disputes on interest as part of compensation

Submissions & Arguments

Contentions of Appellants / Petitioners

Appellants contend that possession of the acquired land, taken on 30-08-1990, before the section 4(1) notification of 07-07-1991, should attract statutory interest on the unpaid compensation from the date of possession at 9% for a year and 15% thereafter under sections 28 and 34. They seek interest on the unpaid balance and on the solatium in line with Sundar v. Union of India (Constitution Bench). They challenge the Subordinate Judge’s view that disputes relating to interest lie outside Section 18; they argue that Section 18 requires the Court to determine the correct total compensation, including interest on delay, solatium, and any installments due.

Contentions of Respondents

The respondent State contends that interest under sections 28/34 cannot be awarded for the pre-notification possession captured on 30-08-1990; relying on RL Jain v. A.D.A. and Melath Chathukutty Nair, the State submits that possession prior to 4(1) is outside the Act. It concedes that interest on the unpaid balance from 19-08-1992 to 20-01-1993, and thereafter, may be payable, and that the L.A. Officer’s award should be adjusted for installments; the main dispute centers on the timing and scope of interest with reference to pre-notification possession.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
R.L. Jain v. A.D.A.AIR 2004 SC 1904DistinguishedConstitution Bench Sundar v. Union of India overruled the pre-notification interest principle of RL Jain; current judgment distinguishes RL Jain.
Sundar v. Union of India2001(3) KLT 489PositiveConstitution Bench held entitlement to interest on solatium; followed by the present judgment.
Special Tahsildar (LA) v. Melath Chathukutty Nair2002(1) KLT 700Mentioned OnlyCited as authority following RL Jain; current decision contextualizes Sundar over RL Jain.
Yadav Rao P. Pathdev v. State of Maharashtra1996(1) KLT 452OverruledSundar's Constitution Bench overrules the proposition that solatium interest is prohibited pre-notification.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,937 words•~9 min read

In The Court Record

Omana Amma v. The State of Kerala

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE PIUS C.KURIAKOSE & THE HONOURABLE MR. JUSTICE C.K.ABDUL REHIM WEDNESDAY, THE 11TH MARCH 2009 / 20TH PHALGUNA 1930 LA.App..No. 208 of 2009() ------------------------LAR.167/2001 of ADDL.SUB COURT,KOLLAM .................... APPELLANT(S): CLAIMANT ---------------------- OMANA AMMA, GOURY SADANAM, PERUMON, KOLLAM DISTRICT. BY ADV. SRI.B.SURESH KUMAR RESPONDENT(S): RESPONDENT ------------------------- THE STATE OF KERALA, REPRESENTED BY THE DISTRICT COLLECTOR, KOLLAM, KOLLAM - 691 013. SR.GOVERNMENT PLEADER SRI.P.K.BABU THIS LAND ACQUISITION APPEAL HAVING COME UP FOR ADMISSION ON 11/03/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## **PIUS C. KURIAKOSE &C.K.ABDUL REHIM, JJ.** ----------------------------------------------- LAA. No. 208 OF 2009 ----------------------------------------------Dated this the 11th day of March, 2009 ## **J U D G M E N T** ## **Pius C.Kuriakose, J.** The claimant in a reference under section 18 of the Land Acquisition Act, 1894 is the appellant. The ground which is prominently raised in the memorandum of appeal is that possession of the acquired property was taken as early as on 30-8-1990 and hence the reference court should have granted statutory interest at the rate admissible under section 28 for a period of one year from 30-8-1990 at the rate of 9% per annum and thereafter at the rate of 15% per annum. The grievance of the appellant is that the L.A. Officer has awarded interest under section 28 of the Land Acquisition Act only for the period subsequent to 7-7-1991, the date on which the relevant notification under section 4 (1) was published. The further ground which is raised in the memorandum of appeal is that the compensation due under the award of the L.A. Officer was paid in installments only, LAA. N0. 208 of 2009 -2- i.e., advance of Rs.1,07,500/- was paid on 19-8-1992 and the balance of Rs.1,20,000/- was paid on 20-1-1993 and that interest on the amount which remained unpaid has not been paid. 2. We have heard the submissions of Sri.B.Suresh Kumar, learned counsel for the appellant and those of Sri.P.K.Babu, learned Senior Govt. Pleader for the respondent who took notice when the appeal came up for admission. Drawing our attention to the judgment of the Supreme Court in R.L.Jain v. A.D.A., (AIR 2004 SC 1904) and the judgment of a Division Bench of this Court in Sp. Tahsildar (LA) v. Melath Chathukutty Nair, (2002(1) KLT 700) it was submitted by the learned Senior Govt. Pleader that the appellant cannot aspire for getting interest at the rates admissible under section 28 during the period from the date of taking possession till the date of promulgation of section 4(1) notification. As regards the claim for interest LAA. N0. 208 of 2009 -3- on the award amount which admittedly remained unpaid it was fairly conceded by the learned Senior Govt. Pleader that the appellant may be entitled for interest on the amount which remained as balance payable on 19-8-1992 till 20-1-1993 when a further amount of Rs.1,20,000/- was paid and on the further balance till its actual payment. 3. The learned counsel for the appellant was unable to meet the argument of the learned senior Govt. Pleader regarding the appellant's eligibility for interest for the period anterior to the date of publication of the notification under section 4(1)based as the same was on judgment of the Supreme Court and the judgment of this Court. Mr.Suresh Kumar however, submitted that the learned Subordinate Judge erred in his view regarding the appellant's eligibility for payment of interest on the solatium component of the compensation. He would submit that the learned Subordinate Judge did not become inclined to award the LAA. N0. 208 of 2009 -4- interest which was statutorily payable on the unpaid portion of the determined compensation on an erroneous view that such disputes are outside the purview of section 18 of the Land Acquisition Act, 1894 as amended by Act 68 of 1984which enable the Land Acquisition Court and the Land Acquisition Officer respectively to pay interest on the compensation during the first year from date of taking possession at the rate of 9% per annum and thereafter at the rate of 15% per annum. 4. It has been very clearly held by the Supreme Court in R.L.Jain's case (supra) that in order that interest at the above rate is paid to a party, his property should have been taken possession of pursuant to a notification under section 4(1) of the L.A. Act. In other words, the taking over of possession should be in land acquisition proceedings. It is held that any possession taken prior to the issuance of the notification under section 4(1) is de hors the Act. Their LAA. N0. 208 of 2009 -5- Lordships held that taking over of possession for the purpose of the provisos to both sections 28 and 34 has to be either under section 16 of the Land Acquisition Act or under section 17(1), of that Act. Any taking over of possession otherwise than under section 16 or section 17(1) will not be recognised for payment of interest under section 28 or 34 as the case may be. The above view of the Supreme Court was followed by a Division Bench of this Court in Special Tahsildar (LA) v. Melath Chathukutty Nair, (2002)(1) KLT 700. In the instant case, the property of the appellant was taken over on 30-8-1990 and the notification under section 4(1) was published only 7-7-1991. It is clear that possession was taken over neither under section 16 nor under section 17(1). Appellant does not have a case that he was illegally dispossessed of his property on 30-8-1990 without his consent. It is obvious that the property was taken over on the basis of some private arrangement LAA. N0. 208 of 2009 -6- between the appellant and the Railway (the requisitioning authority or the Government) which cannot be countenanced for the purpose of awarding interest under section 28 or section 34. The ground raised in the appeal as regards payment of interest for the period prior to the date of section 4(1) notification has to be turned down. 5. At the same time, we notice that the learned Subordinate Judge has taken the view that the solatium component of the compensation to which the appellant is entitled under the court award will not carry interest under section 28. Learned Subordinate Judge has in this context relied on the judgment of the Supreme Court in Yadav Rao P.Pathdev v. State of Maharashtra, (1996(1) KLT 452). We are afraid that the learned Subordinate Judge did not notice the judgment of the Constitution Bench of the Supreme Court in Sunder v. Union of India (2001(3) KLT 489) whereby it is declared that claimant will be entitled for LAA. N0. 208 of 2009 -7- interest on solatium also. Yadav Rao P.Pathdev's case relied on by the learned Subordinate Judge no longer holds the field. We follow the judgment of the Constitution Bench in Sundar's case and declare that the appellant is entitled for interest on the solatium component of the compensation also. 6. It is clear to our mind that the appellant is entitled to amounts of Rs.15,515.32 and Rs.54,514.78 towards interest at the statutory rates on the compensation which remained as payable after adjusting the part payments made towards the award amount. The above total amount of Rs.70,030.10 is not awarded to the appellant by the learned Subordinate Judge taking the view that in a reference under section 18 the court is not competent to examine complaints regarding non-payment of statutory interest admissible under sections 28 and 34. This is what the learned Subordinate Judge has stated in his judgment LAA. N0. 208 of 2009 -8- on the above context: “This court is not sitting in appeal over the award passed by the L.A. Officer to re-fix the interest awarded by him. The reference is made to this court with regard to the measurement of land, the amount of compensation and with respect to the persons to whom it is payable or the apportionment of the compensation among the interested persons. There is no reference to correct the mistakes if any committed by the L.A. Officer. For that the claimant has to move before the Land Acquisition Officer himself.” The reference leading to the impugned judgment was admittedly a reference under section 18 of the Land Acquisition Act. The above reference was facilitated/ initiated by the appellant himself being not satisfied with the award of compensation by the L.A. Officer. Section 18 of the Land Acquisition Act to the extent necessary is quoted below: “ **18. Reference to Court.--** (1) Any person interested who has not accepted the award may, by written application to the Collector, require that the matter be referred by the Collector for the determination of the Court, whether his objection be to the measurement of the land, the amount of the compensation, the persons to whom it is payable, or the apportionment of the LAA. N0. 208 of 2009 -9- compensation among the persons interested.” It is trite that award passed by the Land Acquisition Officer is only an offer which the awardee may accept or not accept. The awardee who does not accept the offer seeks reference under section 18 and once valid request for reference is made the awarding officer is bound to refer the matter to the court and the court determines the correct compensation payable for the acquired property and settles other objection if any taken by the party within the contemplation of section 18 taking into account the various matters enumerated under section 23 and ignoring the matters enumerated under section 24. The learned Subordinate Judge may be technically correct in saying that the reference court does not sit in appeal over the award of the L.A. Officer. But the reference court is to determine the correct compensation payable for the acquired property as an original authority on the basis of the materials which LAA. N0. 208 of 2009 -10- comes on record before the court. Compensation would take in all its components like market value, solatium under section 23(2) and additional amount under section 23(1-A). In a broader sense, statutory interest which was payable by the L.A. Officer under section 34 and is payable by the court under section 28 will also be part of the total compensation payable to the owners. In other words, any dispute regarding the correct amount payable to the awardee towards interest will have to be settled by the court while determining the correct compensation payable to the claimant before the court. The learned Subordinate Judge's view that within the contours of section 18 disputes regarding interest cannot be settled by him is erroneous. 7. It was fairly conceded by the learned Government Pleader that a total amount of Rs.70,030.10 is payable to the appellant as claimed by him in Ext.A1 statement filed before the reference court towards interest on the LAA. N0. 208 of 2009 -11- compensation which remained unpaid. 6. The result of the above discussion is that the appeal will stand allowed to the following extent: 1. It is declared that the appellant is entitled for - interest on the solatium to which he is eligible. 2. It is also declared that the appellant is not entitled for any interest during the period prior to the issuance of the notification under section 4(1). 2. It is ordered that the appellant is entitled to a further amount of Rs.70,030.10 towards interest on the compensation which remained as payable by the awarding officer. The parties are directed to suffer their respective costs. ## **(PIUS C.KURIAKOSE, JUDGE)** ## **(C.K. ABDUL RAHIM, JUDGE.)** ksv/-
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.