Supreme Court of IndiaSupreme Court · 2021Division BenchAppeals dismissed and pending amounts to be pai...

NTPC LTD. v. M/S. DECONAR SERVICES PVT. LTD.

Case / Petition Number:
Civil Appeal No. 6483 of 2014; Civil Appeal No. 6484 of 2014
Neutral Citation:[2021] 4 S.C.R. 467

Case Synopsis & Summary

NTPC Ltd. v. Deconar Services Pvt. Ltd. concerns arbitration awards under the Arbitration Act, 1940, and the standard for challenging an arbitral award. The respondent contractor participated in tenders for two contracts: (i) 100 units of A and B type quarters, and (ii) 68 units of B, C and D type quarters. After negotiations, both contracts were awarded to the respondent on the basis of a 16% rebate if both works were completed concurrently. Delays in handing over sites by the appellant (NTPC) led to disputes over the rebate, escalation charges, and the overall compensation under the awards. The Arbitrator granted substantial sums to the respondent across both contracts and allowed certain escalations, while the appellant sought to overturn these findings. The Delhi High Court (Single Judge and Division Bench) dismissed objections to the awards, observing that courts do not sit in appeal over arbitral decisions and will only interfere upon perversity, legal error, or misconduct by the arbitrator. The Supreme Court reaffirmed this doctrine, noting that where two reasonable interpretations exist, interference is improper. Regarding the rebate, the Court found the arbitrator’s interpretation of a conditional rebate permissible; regarding escalation, it recognized a permissible construction of the contract and upheld the award. The appeals were dismissed, with a direction to pay pending amounts within six months.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • N. V. Ramana
  • Surya Kant
  • Aniruddha Bose
Judgment Date
2021-03-04
Court Decision / Holding
Civil Appeals dismissed. The appellant is directed to pay the pending amounts to the respondent within 6 months from the date of this judgment.
Final Disposition
Appeals dismissed and pending amounts to be paid within six months

Parties to the Case

Appellants / Petitioners

  • NTPC Ltd.

Respondents

  • M/S. Deconar Services Pvt. Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • Puneet Taneja
  • • Manmohan Singh
  • • Ms. Laxmi

Counsels for Respondents

  • • R. Gowrishankar
  • • S. Rajappa

Provisions of Law Cited

Arbitration Act, 1940; Sections 30, 33, 39

Legal Doctrines & Maxims

  • Court does not sit in appeal over arbitrator's award
  • If two views are possible on a matter of law, the court should not interfere
  • Error apparent on the face of the record
  • Perverse award or misconduct by arbitrator is required to interfere

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that the 16% rebate was not conditioned on simultaneous completion and pointed to the contract’s firm price/price-escalation terms as barring any escalation; they contended that the rebate should not be construed as conditioned and urged interference with the award on that ground.

Contentions of Respondents

The respondents contended that courts have a narrow remit in arbitral matters and should not reweigh evidence; the arbitrator’s interpretation of the rebate and the escalation clause was a permissible view supported by contract and conduct evidence; therefore, the awards should stand.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (14)

Case NameCitationTreatmentExplanation
Kwality Manufacturing Corporation v. Central Warehousing Corporation(2009) 5 SCC 142PositiveCited for the principle that interference in arbitral awards is limited and not a reappraisal of merits.
Arosan Enterprises Ltd. v. Union of India(1999) 9 SCC 449PositiveSupports the rule that two views on a contract may exist and the court should not substitute its view for the arbitrator's.
State of U.P. v. Allied Constructions(2003) 7 SCC 396PositiveCited as authority for the limited scope of court interference in arbitral awards.
Ravindra Kumar Gupta and Company v. Union of India(2010) 1 SCC 409PositiveRelied on for principles related to interference standards.
Oswal Woollen Mills Limited v. Oswal Agro Mills Limited(2018) 16 SCC 219PositiveCited regarding arbitration award review standards and evidence-based construction.
Assam State Electricity Board v. Buildworth Private Limited(2017) 8 SCC 146PositiveSupports upholding escalation decisions based on contract construction.
New India Civil Erectors (P) Ltd. v. Oil & Natural Gas Corporation(1997) 11 SCC 75DistinguishedGrounds claimed by the appellant distinguish from the present case where escalation was allowed.
State of Orissa v. Sudhakar Das (Dead) by Lrs(2000) 3 SCC 27Partly Overruled / LimitedLimited applicability to the present case; context-dependent.
General Manager, Northern Railway v. Sarvesh Chopra(2002) 4 SCC 45DistinguishedContractual clauses distinguished from the present case’s circumstances.
Arosan Enterprises Ltd. v. Union of India(1999) 2 Suppl. SCR 621PositiveCited for reliance on non-reappraisal of evidence and permissible alternate views.
Northern Railway v. Sarvesh Chopra(2002) 4 SCC 45DistinguishedQuoted to show contexts where escalation issues depend on contract construction.
New India Civil Erectors (P) Ltd. v. Oil & Natural Gas Corporation(1997) 11 SCC 75DistinguishedSeparately construed inapplicability to present facts.
State of Orissa v. Sudhakar Das (Dead) by Lrs(2000) 3 SCC 27Partly Overruled / LimitedCited for contextual applicability rather than direct authority.
General Manager, Northern Railway v. Sarvesh Chopra(2002) 4 SCC 45DistinguishedDifference in contract terms leads to non-application of that ruling.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,520 words•~21 min read

In The Court Record

NTPC LTD. v. M/S. DECONAR SERVICES PVT. LTD.

467 [2021] 4 S.C.R. 467 ## NTPC LTD. A v. ## M/S. DECONAR SERVICES PVT. LTD. (Civil Appeal No. 6483 of 2014) ## MARCH 04, 2021 B ## **[N.V. RAMANA, SURYA KANT AND ANIRUDDHA BOSE, JJ.]** _Arbitration Act, 1940: Arbitral award – Objections against – For the objector/appellant in order to succeed in their challenge against an arbitral award, they must show that the award of the_ C _arbitrator suffered from perversity or an error of law or that the arbitrator has otherwise misconducted himself – Merely showing that there is another reasonable interpretation or possible view on the basis of the material on the record is insufficient to allow for the interference by the Court._ D _Judicial review: Arbitral award – Held: Court does not sit in appeal over an award passed by an arbitrator._ ## **Dismissing the appeals, the Court** **HELD : 1.1 This Court has consistently held that the Court does not sit in appeal over an award passed by an arbitrator. [Para 11][473-A-B]** E _Kwality Manufacturing Corporation v. Central Warehousing Corporation_ **(2009) 5 SCC 142 – relied on.** F **1.2 It is also a settled proposition that where the arbitrator has taken a possible view, although a different view may be possible on the same evidence, the Court would not interfere with the award. [Para 12][473-E]** _Arosan Enterprises Ltd. v. Union of India_ **(1999) 9 SCC 449 : [1999] 2 Suppl. SCR 621 – relied on** G **2. For the objector/appellant in order to succeed in their challenge against an arbitral award, they must show that the award** H 467 468 SUPREME COURT REPORTS [2021] 4 S.C.R. - A **of the arbitrator suffered from perversity or an error of law or that the arbitrator has otherwise misconducted himself. Merely showing that there is another reasonable interpretation or possible view on the basis of the material on the record is insufficient to allow for the interference by the Court. [Para 13][474-C-D]** - B _State of U.P. v. Allied Constructions_ **(2003) 7 SCC 396 : [2003] 2 Suppl. SCR 55;** _Ravindra Kumar Gupta and Company v. Union of India_ **(2010) 1 SCC 409 : [2009] 16 SCR 142;** _Oswal Woollen Mills Limited v. Oswal Agro Mills Limited_ **(2018) 16 SCC 219 : [2018] 3 SCR 1062** C **– relied on.** **3. In the facts at hand, it is an admitted fact that there was** **substantial delay attributable to the appellant in handing over the sites for the 68 B, C and D quarters to the respondent. The appellant has not contested this finding. With respect to the first** D **issue,** _**viz.**_ **, on the issue of refund of rebate, the Arbitrator held that the rebate of 16% on the price of construction of 100 units of A and B quarters was given by the respondent on the condition that he would be able to execute both the works simultaneously. The Arbitrator interpreted the rebate as a conditional one on** E **analysis of the documents on record, particularly the letter dated 14.06.1988 sent by the respondent to the appellant subsequent to the negotiations held between them, the award of both contracts to the respondent on the same date and the works programme (L-2) for both the works. The Arbitrator specifically highlighted that the appellant had not denied the L-2 programme, which** F **indicated that both the works were to be carried out together. From a reading of the above material, the Arbitrator held that the intention of the parties was to complete the work together, which would have enabled the respondent to reduce its costs and optimizing its charges, thereby allowing it to grant the 16%** G **rebate to the appellant. By delaying the handing over of the sites, the appellant had therefore breached the condition for the grant of rebate, entitling the respondent to a refund of the same. [Paras 15, 16][474-F-H; 475-A-C]** H 469 NTPC LTD. v. M/S. DECONAR SERVICES PVT. LTD. **4. The appellant sought to canvas an alternate interpretation regarding the rebate on the basis of the letter dated 14.06.1988, stating that the same was granted merely for the awarding of both sets of contract to the respondent. While such an interpretation is possible, this is not sufficient to interfere with the award passed by the Arbitrator. As already highlighted, the Court does not sit as an appellate Court over the decision of an arbitrator, and cannot substitute its views for that of the Arbitrator as long as the Arbitrator had taken a possible view of the matter. In the present case, the Arbitrator has given clear reasoning for the possible view taken by him on the interpretation of the contract between the parties. As such, the Courts below rightly refused to interfere with the holding of the Arbitrator on the first issue. [Para 17] [475-C-E]** **5. The second issue pertains to the grant of escalation charges for work done by the respondent beyond the scheduled period of the contract. The Arbitrator only allowed a part of the claim made by the respondent under this head. The Arbitrator took a view on the construction of the clauses of the contract that the firm price clause operated only with respect to the period for which the contract subsisted, and would not subsist beyond the scheduled period of the contract. The Arbitrator also noted that the appellant accepted the work undertaken by the respondent beyond the period of the contract without objections. The Arbitrator also carefully assessed the period of delay attributable to the appellant and awarded escalation to the respondent only for the same. With respect to the question of law as to whether the Arbitrator could order such an escalation, this Court has, in a catena of judgments, upheld the same. [Paras 18, 19][475-E-H; 476-A]** _Assam State Electricity Board v. Buildworth Private Limited_ **(2017) 8 SCC 146 : [2017] 7 SCR 123 – relied on.** A B C D E F G _New India Civil Erectors (P) Ltd. v. Oil & Natural Gas Corporation_ **(1997) 11 SCC 75 : [ 1997] 2 SCR 86;** _State of Orissa v. Sudhakar Das (Dead) by Lrs_ **(2000) 3 SCC 27 : [ 2000] 1 SCR 1136;** _General Manager,_ H 470 SUPREME COURT REPORTS [2021] 4 S.C.R. A _Northern Railway v. Sarvesh Chopra_ **(2002) 4 SCC 45 : [2002] 2 SCR 156 – held inapplicable.** **6. Any decision regarding the issue of whether an arbitrator can award a particular claim or not, will revolve on the construction of the contract in that case, the evidence placed before the** B **arbitrator and other facts and circumstances of the case. No general principle can be evolved as to whether some claim can be granted or not. The appellant has neither been able to point out any error apparent on the face of the record, nor otherwise made out a case for interference with the award by the Arbitrator with respect to this issue. [Paras 25, 26][477-F-G; 478-A-B]** C **Case Law Reference** ||**(2009) 5 SCC 142**|**relied on**|**Para 11**| |---|---|---|---| ||**[1999] 2 Suppl. SCR 621**|**relied on**|**Para 12**| |D|**[2003] 2 Suppl. SCR 55**|**relied on**|**Para 13**| ||**[2009] 16 SCR 142**|**relied on**|**Para 13**| ||**[2018] 3 SCR 1062**|**relied on**|**Para 13**| ||**[2017] 7 SCR 123**|**relied on**|**Para 19**| |E|**[1997] 2 SCR 86**|**held inapplicable**|**Para 22**| ||**[ 2000] 1 SCR 1136**|**held inapplicable**|**Para 23**| ||**[2002] 2 SCR 156**|**held inapplicable**|**Para 24**| CIVIL APPELLATE JURISDICTION : Civil Appeal No. 6483 of 2014. F From the Judgment and Order dated 09.04.2010 of the High Court of Delhi at New Delhi in FAO(OS) No. 136/2010. With Civil Appeal No. 6484 Of 2014. G Puneet Taneja, Manmohan Singh, Ms. Laxmi, Advs. for the Appellant. R. Gowrishankar, S. Rajappa, Advs. for the Respondent. H 471 NTPC LTD. v. M/S. DECONAR SERVICES PVT. LTD. The Judgment of the Court was delivered by A ## **N. V. RAMANA, J.** 1. The present Civil Appeals, by way of Special Leave arise out of the impugned common judgment dated 09.04.2010 passed by the Division Bench of the High Court of Delhi, whereby the High Court dismissed the appeals filed by the present appellant against the dismissal of their objections to an award passed by the Arbitrator under the Arbitration Act, 1940. 2. A conspectus of the facts necessary for the disposal of the present appeal is as follows: the appellant had issued two tenders for the construction of certain quarters in which the respondent had participated. The first project related to the construction of 100 units of A and B type quarters. The second, was with respect to construction of 68 units of B, C and D type quarters. It appears that while the respondent was L-3 with respect to the first project, he was L-2 with respect to the second. After negotiations between both parties, the appellant decided to award both contracts to the respondent on the basis of an offer by the respondent of 16% rebate on the prices for completing the first project, in the event he was awarded both contracts. The two letters of award were issued on 29.06.1988 to the respondent. It appears from the record that there was some delay in the handing over of sites by the appellant, which resulted in a delay in the completion of the construction of quarters in both projects. Since there were disputes between the parties regarding the final payment due to the respondent-contractor, the respondent sought arbitration under the dispute resolution clause, and an Arbitrator was appointed. 3. The learned Arbitrator, vide awards dated 07.07.2000, granted relief to the respondent under different heads of the contract. With respect tothe first contract pertaining to the construction of 100 units of A and B type quarters, the Arbitrator awarded a sum of Rs. 23,89,424/- with interest at 18% _per annum pendente lite_ and 21% future interest to the respondent. With respect to the second contract pertaining to the construction of 68 units of B, C and D type quarters, the Arbitrator awarded Rs. 24,36,532/- at 18% per annum _pendente lite_ and 21% future interest to the respondent. 4. Aggrieved by the above awards, the appellant filed objections against both the awards before the Delhi High Court under Sections 30 B C D E F G H 472 SUPREME COURT REPORTS [2021] 4 S.C.R. - A and 33 of the Arbitration Act, 1940. _Vide_ separate orders dated 16.12.2009, the learned Single Judge of the Delhi High Court dismissed the objections of the appellant (except to the extent of modifying the interest rate granted by the Arbitrator) with cost of Rs. 50,000/- and made the award an order of the Court. B 5. The appellant challenged the above orders in appeal before the Division Bench of the High Court under Section 39, Arbitration Act, 1940, which was dismissed _vide_ the common impugned judgment dated 09.04.2010, with cost of Rs. 10,000/-. 6. Aggrieved by the same, the appellant has filed the present Civil C Appeals by way of Special Leave against the impugned judgment. 7. Heard the learned counsel for the appellant and the respondent at length. 8. The learned counsel for the appellant confined his arguments to three main points- the refund of the rebate agreed upon by the parties, D the grant of escalation of charges for work done beyond the scheduled period and the costs imposed on the appellant by all three forums below. Although the first issue of the three arises only in Civil Appeal No. 6484 of 2014, as the latter two issues are common to both appeals, and the facts are connected, all the issues are being taken up together. E 9. The learned counsel for the appellant submitted that the Arbitrator erred in holding that the rebate was a conditional one, as the terms of the offer by the respondent and the letter of award do not indicate the same. Further, the learned counsel also submitted that the Arbitrator erred in granting escalation of prices when the contract F expressly indicated that the “ _quoted price shall remain firm during the execution of the contract_ ”. The Courts below should therefore have interfered with the award passed by the Arbitrator as the same was passed contrary to the terms of the contract between the parties. 10. On the other hand, the learned counsel for the respondent supported the impugned judgment passed by the High Court and stated G that there are concurrent findings against the appellant, who has only been prolonging the litigation. The respondent submitted that the scope of interference in an arbitral award was limited, as the Court did not sit in appeal over an award. As long as the Arbitrator has taken a reasonable view, the Court should not interfere in the same. H 473 NTPC LTD. v. M/S. DECONAR SERVICES PVT. LTD. [N. V. RAMANA, J.] 11. Before proceeding further, it is necessary to make note of the A scope of interference by Courts in arbitral awards passed under the Arbitration Act, 1940. This Court has consistently held that the Court does not sit in appeal over an award passed by an arbitrator. In _**Kwality Manufacturing Corporation v. Central Warehousing Corporation**_ **, (2009) 5 SCC 142** this Court held as follows: B “ **10.** At the outset, it should be noted that the scope of interference by courts in regard to arbitral awards is limited. A court considering an application under Section 30 or 33 of the Act, does not sit in appeal over the findings and decision of the arbitrator. Nor can it reassess or reappreciate evidence or examine the sufficiency or otherwise of the evidence. The award of the arbitrator is final and the only grounds on which it can be challenged are those mentioned in Sections 30 and 33 of the Act. Therefore, on the contentions urged, the only question that arose for consideration before the High Court was, whether there was any error apparent on the face of the awardand whether the arbitrator misconducted himself or the proceedings.” C D ( _emphasis supplied_ ) 12. Further, it is also a settled proposition that where the arbitrator has taken a possible view, although a different view may be possible on the same evidence, the Court would not interfere with the award. This Court in _**Arosan Enterprises Ltd. v. Union of India**_ **, (1999) 9 SCC 449** held as follows: “ **36.** Be it noted that by reason of a long catena of cases, it is now a well-settled principle of law that reappraisal of evidence by the court is not permissible and as a matter of fact exercise of power by the court to reappraise the evidence is unknown to proceedings under Section 30 of the Arbitration Act. In the event of there being no reasons in the award, question of interference of the court would not arise at all. In the event, however, there are reasons, the interference would still be not available within the jurisdiction of the court unless of course, there exist a total perversity in the award or the judgment is based on a wrong proposition of law. In the event however two views are possible on a question of law as well, the court would not be justified in interfering with the award. E F G H 474 SUPREME COURT REPORTS [2021] 4 S.C.R. A **37.** The common phraseology “error apparent on the face of the record” does not itself, however, mean and imply closer scrutiny of the merits of documents and materials on record. The court as a matter of fact, cannot substitute its evaluation and come to the conclusion that the arbitrator had acted contrary to the bargain between the parties. If the view of the arbitrator is a possible B view the award or the reasoning contained therein cannot be examined...” 13. From the above pronouncements, and from a catena of other judgments of this Court, it is clear that for the objector/appellant in order to succeed in their challenge against an arbitral award, they must show C that the award of the arbitrator suffered from perversity or an error of law or that the arbitrator has otherwise misconducted himself. Merely showing that there is another reasonable interpretation or possible view on the basis of the material on the record is insufficient to allow for the interference by the Court [ **See** _**State of U.P. v. Allied**_ **Constructions,** D **(2003) 7 SCC 396; Ravindra** _**Kumar Gupta and Company v. Union of India**_ **, (2010) 1 SCC 409;** _**Oswal Woollen Mills Limited v. Oswal Agro Mills Limited**_ **, (2018) 16 SCC 219** ]. 14. Keeping in view the above principles, the question before us is whether the arbitral awards in question are assailable on any of the E available grounds. While deciding this, due regard must also be given to the fact that both the learned Single Judge, and subsequently the Division Bench, of the Delhi High Court have concurrently held against the appellant herein. 15. Coming to the facts at hand, it is an admitted fact that there F was substantial delay attributable to the appellant in handing over the sites for the 68 B, C and D quarters to the respondent. The appellant has not contested this finding before us. 16. With respect to the first issue, _viz._ , on the issue of refund of rebate,the Arbitrator held that the rebate of 16% on the price of G construction of 100 units of A and B quarters was given by the respondent on the condition that he would be able to execute both the works simultaneously. The Arbitrator interpreted the rebate as a conditional one on analysis of the documents on record, particularly the letter dated 14.06.1988 sent by the respondent to the appellant subsequent to the negotiations held between them, the award of both contracts to the H respondent on the same date and the works programme (L-2) for both 475 NTPC LTD. v. M/S. DECONAR SERVICES PVT. LTD. [N. V. RAMANA, J.] the works. The Arbitrator specifically highlighted that the appellant had A not denied the L-2 programme, which indicated that both the works were to be carried out together. From a reading of the above material, the Arbitrator held that the intention of the parties was to complete the work together, which would have enabled the respondent to reduce its costs and optimizing its charges, thereby allowing it to grant the 16% B rebate to the appellant. By delaying the handing over of the sites, the appellant had therefore breached the condition for the grant of rebate, entitling the respondent to a refund of the same. 17. The learned counsel for the appellant sought to canvas an alternate interpretation regarding the rebate on the basis of the letter dated 14.06.1988, stating that the same was granted merely for the awarding of both sets of contract to the respondent. While we are in agreement with the appellant that such an interpretation is possible, we are of the opinion that this is not sufficient to interfere with the award passed by the Arbitrator. As already highlighted, the Court does not sit as an appellate Court over the decision of an arbitrator, and cannot substitute its views for that of the Arbitrator as long as the Arbitrator had taken a possible view of the matter. We are of the considered opinion that in the present case, the Arbitrator has given clear reasoning for the possible view taken by him on the interpretation of the contract between the parties. As such, the Courts below rightly refused to interfere with the holding of the Arbitrator on the first issue. 18. The second issue pertains to the grant of escalation charges for work done by the respondent beyond the scheduled period of the contract. It is significant to note herein that the Arbitrator only allowed a part of the claim made by the respondent under this head. In Civil Appeal No. 6483 of 2014, the Arbitrator awarded a sum of Rs. 17,86,212/- against a claim of Rs. 66,98,773/-, while in Civil Appeal No. 6484 of 2014, the Arbitrator awarded a sum of Rs. 3,03,419/- as against a claim of Rs. 42,20,261/-. The Arbitrator took a view on the construction of the clauses of the contract that the firm price clause operated only with respect to the period for which the contract subsisted, and would not subsist beyond the scheduled period of the contract. The Arbitrator also noted that the appellant accepted the work undertaken by the respondent beyond the period of the contract without objections. The Arbitrator also carefully assessed the period of delay attributable to the appellant and awarded escalation to the respondent only for the same. C D E F G H 476 SUPREME COURT REPORTS [2021] 4 S.C.R. A 19. With respect to the question of law as to whether the Arbitrator could order such an escalation, this Court has, in a catena of judgments, upheld the same. A three-Judge Bench of this Court in _**Assam State Electricity Board v. Buildworth Private Limited**_ **, (2017) 8 SCC 146,** was faced with almost identical circumstances. In that case, the Arbitrator granted escalation charges beyond what was permissible under the B contract between the parties, which prescribed a cap on the same. Upholding such an award, the Court in that case held as follows: “ **13.** The arbitrator has taken the view that the provision for price escalation would not bind the claimant beyond the scheduled date of completion. This view of the arbitrator is based on a construction C of the provisions of the contract, the correspondence between the parties and the conduct of the Board in allowing the completion of the contract even beyond the formal extended date of 6-91983 up to 31-1-1986. Matters relating to the construction of a contract lie within the province of the Arbitral Tribunal. Moreover, D in the present case, the view which has been adopted by the arbitrator is based on evidentiary material which was relevant to the decision. There is no error apparent on the face of the record which could have warranted the interference of the court within the parameters available under the Arbitration Act, 1940. The arbitrator has neither misconducted himself in the proceedings E nor is the award otherwise invalid.” ( _emphasis supplied_ ) 20. We are of the opinion that the above holding of this Court is directly applicable to the present case. The Arbitrator in the present F case has constructed the present contract, and the fixed price clause, in the same manner. This construction was on the basis of the evidence on record and the submissions of the counsel before him. The Arbitrator has carefully delineated the period of delay attributable to the appellant, and has granted the claim of the respondent only to that limited extent. G 21. The counsel for the appellant has placed on record certain judgments of this Court, which according to him mandate a different view. As such, it would be necessary to analyze the same. H 22. In _**New India Civil Erectors (P) Ltd. v. Oil & Natural Gas Corporation**_ **, (1997) 11 SCC 75** , this Court rejected the claim for escalation of prices during the period of delay on the basis of the specific 477 NTPC LTD. v. M/S. DECONAR SERVICES PVT. LTD. [N. V. RAMANA, J.] stipulation in the contract therein, which specifically excluded price escalation “ _till the completion of work_ ”. On the other hand, in the present case, the contractual clause stipulates only that the price would be firm during the “ _period of execution of the contract_ ”, which the Arbitrator took to refer only to the 12 month period originally stipulated for the execution of the contract. This may appear to be a technical distinction, but it must be remembered that construction of a contract is in the domain of the Arbitrator, and as long as the interpretation given is a possible view, the Court may not interfere with the same. In the _**New India Civil Erectors**_ case ( _supra_ ), this Court was of the opinion that, in view of the specific clause of the contract in that case, the granting of escalation prices was not a possible view. This is not the case in the present matter. As we have already held above, we are of the opinion that in the facts and circumstances of the present case, the view taken by the Arbitrator was a possible one, and cannot therefore be interfered with by the Courts. 23. In _**State of Orissa v. Sudhakar Das (Dead) by Lrs**_ **, (2000) 3 SCC 27** , this Court was not seized of the issue of grant of escalation charges beyond the period of the contract or with respect to delay. As such, it has limited applicability to the present case. 24. In _**General Manager, Northern Railway v. Sarvesh Chopra**_ **, (2002) 4 SCC 45** , the Court was seized of a matter pertaining to a reference to arbitration. The considerations of a Court in such a matter are distinct from those of a Court in appeal over the final award of an Arbitrator. Be that as it may, in that case, a contractual clause between the parties specifically excluded any claims of the contractor arising out of delays attributable to the opposite party, which is not the case in the present matter. 25. It is clear from the above analysis that any decision regarding the issue of whether an arbitrator can award a particular claim or not, will revolve on the construction of the contract in that case, the evidence placed before the arbitrator and other facts and circumstances of the case. No general principle can be evolved as to whether some claim can be granted or not. The judgments placed on record by the appellant, wherein claim for escalation was denied, have to therefore be read in the context of their facts, and cannot be read in isolation. It is clear that all the judgments cited by the appellant can be distinguished on facts. A B C D E F G H 478 SUPREME COURT REPORTS [2021] 4 S.C.R. A 26. In these circumstances, we are of the opinion that the appellant has neither been able to point out any error apparent on the face of the record, nor otherwise made out a case for interference with the award by the Arbitrator with respect to this issue. 27. With respect to the final issue, pertaining to imposition of costs B on the appellant by the forums below, we are not inclined to interfere with the same, in view of the fact that the counsel for the appellant has not pressed the same and looking to the quantum involved. 28. In view of the above, we see no reason to interfere with the impugned judgment passed by the High Court. C 29. Accordingly, the Civil Appeals filed by the appellant are dismissed. The appellant is directed to pay the pending amounts to the respondent within a period of 6 months from the date of this judgment. 30. Pending applications, if any, are accordingly disposed of. D Devika Gujral Appeals dismissed. E F G H
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.