High CourtDivision BenchAppeal dismissed.

N.K. Rajgarhia v. Mahavir Plantation Ltd. and Ors.

Case / Petition Number:Civil Appeal No. 7535 of 2004
Neutral Citation:2005 Supp. 5 S.C.R.

Case Details & Bench

Court
High Court
Hon'ble Judges
  • S. B. Sinha
  • P. Balasubramanyan
Judgment Date
2005-12-16
Court Decision / Holding
Appeal dismissed.
Final Disposition
Appeal dismissed.

Parties to the Case

Appellants / Petitioners

  • N.K. Rajgarhia

Respondents

  • Mahavir Plantation Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • C. Mukund
  • • Ashok Jain
  • • Pankaj Jain
  • • Mrs. Neeraj Anand
  • • Bijoy Kumar Jain

Counsels for Respondents

  • • C. N. Sree Kumar
  • • Ms. Deepa S.

Case Synopsis & Summary

This Supreme Court decision addresses the interpretation of a consent order passed in execution proceedings under the Code of Civil Procedure, 1908. The appellant, N.K. Rajgarhia, had sued for recovery of Rs. 75 lakhs, which culminated in a compromise and a consent decree for Rs. 41,69,110. The compromise clause stated that on dishonour of any cheque, the entire remaining balance would become payable in one lump sum, with the decree-holder entitled to execute the balance and recover interest at 15% per annum. Part of the balance was paid, but the judgment debtor defaulted again, leading to further execution proceedings and a subsequent settlement for the balance of Rs. 42,04,222, with an undertaking from the debtor to pay in instalments and to pay interest. The judgment-debtor ultimately paid the entire amount, including interest, in terms of the consent order, and extensions were granted in execution proceedings. The appellant contends that since the respondent failed to fulfill the undertaking, the original claim should revive and that the Delhi High Court lacked jurisdiction to extend time without consent. The respondent argues that execution-stage settlements are permissible despite Order XXIII Rule 4 CPC, and that the Court should not exercise Article 136 when the amount has been paid. The Court holds that the consent order must be read in its entirety to ascertain true intent, the waived amount did not form part of the decree, and the compromise was valid; the appeal is dismissed.

Provisions of Law Cited

Code of Civil Procedure, 1908, Order XXIII Rule 4Order XXIII Rule 4, CPCOrder 21, Rule 2Section 47Order 20, Rule 11Article 136 of the Constitution of IndiaConstitution of India, 1950

Legal Doctrines & Maxims

  • Consent orders must be read in their entirety to ascertain true intent and purport.
  • Compromise in execution proceedings is permissible and can be recorded/enforced by the executing court under relevant provisions.
  • Courts may extend time to prevent manifest injustice (as in Periyakkal v. Dakshyani) even though ordinarily time should not be extended on mere request.
  • The contract of settlement may merge in the court's order, and the court's power to do justice should not be forfeited; a waiver does not automatically form part of the decree.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the High Court had no jurisdiction to grant time extensions in execution proceedings without consent and that the original claim revives when the undertaking is violated; the ‘balance decree’ cannot be invoked in light of the consent order since the waived amount did not become part of any decree.

Contentions of Respondents

The respondents argue that settlements at the execution stage are permissible under Order XXIII Rule 4 CPC, that the entire amount has since been paid, and that Article 136 should not be invoked to override a complete payment; extension of time can be justified under established equities.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Smt. Periyakkal and Ors. v. Smt. DakshyaniAIR (1983) SC 428PositiveCited to support the proposition that courts may extend time in appropriate cases to prevent manifest injustice and that such orders may reflect the court’s jurisdiction in execution matters.
Moti Lal Banker (dead) by his legal Representative v. Maharaj Kumar Mahmood Hasan KhanAIR (1968) SC 1087PositiveCited to support the permissibility of entering into settlements/compro­mises in execution proceedings and the executing court’s power to enforce such settlements under Section 47 and Order 21, Rule 2.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against N.K. Rajgarhia v. Mahavir Plantation Ltd. and Ors. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

A ## N.K. RAJGARHIA _v._ MIS. MAHAVIR PLANTATION LTD. AND ORS. ## DECEMBER 16,2005 B (S.B. SINHA AND P.K.BALASUBRAMANY AN, JJ.] _Code of Civil Procedure, 1908-0rder XXlll Rule 4.-Recovery suiJCompromise between parties and consent decree passed for half of the_ c· _amount-Part payment made and thereafter, settlement in execution proceedings-Consent order Jo the effect that in case of default in payment, decree holder would be entitled to execute the balance decree-Judgment debtor again defaulted, sought extension of time, grant of, by High CourtThereafter, judgment debtor paid amount in terms of consent order-However, claim of decree holder that original claim revived on default-Sustainability_ D _of-Consent order, interpretation of-Held: Consent order is to be construed in entirety to ascertain its true intent and purport-Word 'decree' after word 'balance' was used loosely-Sum which was waived did not form part of consent decree-It was merely a claim which did not fructifY into any decreeHence, commission of default does not entitle the decree holder to execute the balance decree-Furthermore, such settlement in execution proceedings_ E _is permissible in /aw-Constitution of India, 1950-Article 136._ Appellant filed recovery suit for Rs. 75 lakhs towards repayment of advance with interst and damages against the responde!Jt However, the parties entered into a compromise and the court passed a consent decree for a sum F of Rs. 41,69,110/- and respondents issue cheques. In terms of compromise clause in case of dishonour of cheque, the entire balance amount would be payable at one time failing which the decree holder was entitled to execute the decree for the same with interest. Respondent made only part payment and as such execution proceedings were initiated. Again parties entered into settlement with regard to the balance amount of Rs 42,04,222/- respondent G gave an undertaking that in case of dishonour of any of the cheques the decree holder would be entitled to execute the balance decree. Respondent again defaulted and execution application was filed. However, respondentfiled an application for extension of time for payment of decretal dues and High Court allowed the same. Aggrieved, appellant tiled an appeal. Division Bench of High H 882 **==> picture [4 x 5] intentionally omitted <==** **----- Start of picture text -----**<br> J<br>**----- End of picture text -----**<br> 883 N.K. RA.JGARHIA _v._ MAHAVIR PLANTATION LTD. Court directed the respondent to present the cheques and in case of nonencashment to initiate appropriate proceedings. Respondent was granted another extension. Thereafter, the judgment-debtor paid the entire amount with interest, in terms of the consent order. In the appeal, appellant-creditor contended that since the respondent failed to abide by its undertaking, the original claim of the appellant revived; B and that the High Court had no jurisdiction to grant extension of time for payment of the decretal dues without his consent. Respondent - debtor contended that this Court should not exercise its discretionary jurisdiction under Article 136 of the Constitution in favour of C the appellant since the entire amount stands paid; and that despite Rule 4 of Order XXIll of CPC, there does not exist any bar to enter into a compromise at the execution stage. ## Dismissing the appeal, the Court HELD: 1.1. An order of a court of law and, in particular, a consent order,[D ] must be read in its entirety for the purpose of ascertaining its true intent and purport. It cannot be said that once a default is committed by the respondent, the appellant in terms thereof, would be ·entitled to execute the balance decree immediately which would mean he would be entitled to a further sum of about Rs. 41 lakhs, which was waived by him on the premise that the E respondent had agreed to settle the disputes. The word 'decree' after the word 'balance', has been us.ed loosely. The matter might have been different ifthe amount payable under the compromise entered into by the parties in the execution case would have been less than the amount paid by the respondent to the appellant in terms of the consent decree passed originally. It is not so. F Whereas under the original decree, a sum of Rs. 41,69,110/- was payable, in terms of the consent order passed in the execution case, a sum of Rs. 42,04,222/- became payable. Furthermore, the sum which was waived did not form part of the consent decree. It was merely a claim which never fructified into any decree. (889-E; 890-D-F) G 1.2. Order XXIII Rule 4 of CPC, 1908 states that other provisions thereof are not applicable to an execution proceedings. But, despite the same, the parties may enter into a settlement even in a execution proceedings. Thus, the compromise entered into by and between the parties in the execution proceedings was valid in law. The same was acted upon. Appellant received H SUPREME COURT REPORTS [2005) SUPP. 5 S.C.R. 884 A the entire amount thereunder, albeit belatedly; but even therefor the respondent applied for and obtained extension of time to pay the same. Appellant had accepted such amount and did not question the order granting extension of time, thus the same had attained finality. !888-B; 889-A-C) _Smt. Periyakkal and Ors._ v. _Smt. Dakshyani,_ AIR (1983) SC 428; _Moti_ B _Lal Banker (dead) by his legal Representative_ .v. _Maharaj Kumar Mahmood Hasan Khan,_ AIR (1968) SC 1087, referred to .. 1.3. If the orders of extension have ·validly been passed, the. order of the court stood complied with. The order of the Division Bench of High Court C was ~ot questioned by the r~pondent before this Court but then no direction was issued therein. No judgment was passed. The said order was passed without issuing any notice to the respondents. The appeal was disposed of as having become infructuous. Thus, it was not final. Thereby, merely a liberty had been granted to the appellant to agitate his grievances before the Single Judge of High Court for execution as well as for contempt. By reason of the D said order, alone the appellant could not put forth his claim. Appellant, thus, cannot take any benefit thereof. 1889-D, El .1.4. Respondent agreed to pay not only a lump sum interest but also 15% interest on the principal amount of the further payment On calculation, a sum of Rs. 42,04,222/- was found to be payable out of which the judgment E debtor had paid a sum of Rs. 10,00,000/- by way of three demand drafts. Appropriating the said amount, the outstanding principal sum came to Rs. 26;69,110. However, the balance amount outstanding as on that day came to Rs. 32,()4,222. It was that amount which was to be liquidated by paying instaHment of Rs. 6 lakhs each per month. It is in the aforementioned F backdrop, the undertaking given by the respondent before the Single Judg'( of the High Court is to be construed. (890-B, C) _<_ CIVIL APPELLATE JURISDICTION : Civil Appeal No. 7535 of200~. From the Judgment and Order dated 17 .5.2005 of the Delhi High Court G in E.F.A.(OS) No. 22 of2004. C. Mukund, Ashok Jain, Pankaj Jain, Mrs. Neeraj Anand and Bijoy Kumar Jain for tlie Appellant. C.N. Sree Kumar and Ms. Deepa , S. for the Respondents. I H < N.K. RAJGARHIA v. MAHAVIR PLANTATION LTD. [SINHA, J.] 885 The Judgment. of the Court was delivered by ## **S.B. SINHA, J.** Leave granted. Interpretation of a consent order falls for determination by this Court in this appeal which arises out of a judgment and order dated 17.05.2005 passed by a Division Bench of High Court of Delhi in EFA(OS) No. 22/2004. B The Respondent herein took an advance of certain sum of money from the Appellant herein. A suit for recovery of Rs. 75 lakhs towards refund of the said amount with interest and damages was filed by the Appellant. The parties, however, entered into a compromise in terms whereof the Appellant was to receive a sum of Rs. 41,69,110/-, the relevant clause whereof reads as C under: - " ... .It is specifically made clear that on dishonour of the said cheques or any one of them on any ground whatsoever then and in that event the entire remaining balance amount shall become payable at one time and the plaintiff shall be entitled to execute the decree for realization **D** of the entire remaining balance amount which shall remain payable plus interest to be calculated @15% p.a. and shall also be entitled to take all legal steps as may be permissible under the law to the plaintiff." It is not in dispute that the Respondent herein paid a sum of Rs. 5 lakhs to the Appellant and as it failed and/ or neglected to abide by its undertaking E as regard payment of the balance sum, an execution application came to be filed which was marked as Execution Application No. 58 of 2001. In the said execution proceedings again, the parties entered into a settlement and a learned Single Judge of the Delhi High Court by an order dated 13.9.2001 recorded the same which reads as under: F - " ... These undertakings are accepted. He further agrees that in case any of the cheques is dishonoured he will be liable for not only contempt for violating these undertaking. The decree holder shall be entitled to execute the balance decree immediately. It is also agreed between the parties that the decree holder shall withdraw all civil/ G criminal cases after the entire payment is made by judgment debtor in the manner stated above. However, the decree holder shall not pursue these cases and get these cases adjourned after 20.3.2002 by which time the judgment debtor is supposed to clear the entire decretal amount. **H** SUPREME COURT REPORTS [2005] SUPP. 5 S;C.R. 886 A E The execution petition accordingly is disposed of." Allegedly, the Respondent became a defaulter again. As three cheques out of six post dated cheques were dishonoured, another execution application was filed by the Appellant herein which was marked as Execution Application No. 45 of 2002. The Respondent, however, filed an application for extension B of time and a learned Single Judge of the Delhi High Court, relying on or on the basis of the decision of this Court in _Smt. Periyakkal and Ors._ v. _Smt. Dakshyani,_ AIR (1983) SC 428, granted such extension stating: c D " .. .It is on account of the illness of the Managing Director of the judgment debtor company and on account of the fact that the company is facing financial problems, extension/ enlargement of time for the payment of balance decretal amount is made. The judgment debtor is also agreeable to pay interest at the rate of 15% per annum on the reduced balance amount. Though ordinarily time for payment should not be extended on the mere asking of the judgme::it debtor, but in the present case disallowing the judgment debtors' request would cause great injustice to the judgment debtor. Accordingly, in order to meet the ends of justice, the application for extension of time is allowed. The decree holder would present the cheque dated 20th January, 2002 and 20th February, 2002 for. Rs. 6 lakhs each on 20th March, 2002 along with the third cheque dated 20th March, 2002 for Rs. 2,04,222. The judgment debtor would also pay Rs. 22,500/- towards interest calculated at the rate of 15% per annum on that date. The judgment debtor would, thus, clear the entire decretal amount on 20th March, 2002. The application is accordingly disposed _of."_ The Appellant preferred an appeal thereagainst and by an order dated F 20th March, 2002, a direction was issued hy the Division Bench of the Delhi High Court. The Division Bench directed the Respondent to present three cheques on that day itself and in case those cheques were not encashed it was threatened that appropriate proceedings would be initiated. I_t does not appear that any notice was issued to the Respondent in the said appeal. By G an order dated 1.4.2002, the said appeal was disposed of stating: H "We have perused the record ai:id also the application filed today indicating that two of the cheques given by the judgment debtor have been dishonoured and the fate of the third cheque is not known. The respondent primarily filed an application before the learned Single Judge for grant of extension of time for making payment. The learned N.K. RAJGARHIA v. MAHA VIR PLANTATION LTD. [SINHA . .I. ] 887 Single Judge granted the extension for making payment until 20.3.2002. A Since th·e extended time has already come to an end the appeal to our mind has become infructuous. The appellant will be, however, within his rights to approach the learned Single Judge for execution as well as for contempt. The filing of the appeal will not come in the way of the appellant in pursuing his remedy before the learned Single Judge." B The said order of the Division Bench is said to be still in force. The Respondent, however, obtained another extension from another learned Single Judge of the High Court in terms of an order dated 28.8.2002. The Appellant, herein did not question the said order. The said order, thus, attained finality. It is, however, not in dispute that the judgment debtor has paid the C entire amount together with interest in terms of the consent order dated 5.2.2002 passed in the aforementioned execution petition. It is, furthermore, not in dispute that the contempt application filed against the Respondent herein by the Appellant for violating the undertaking by him has ultimately been dismissed. D The short question. which, thus, arises for consideration is the interpretation of the words "balance decree" occurring in the order dated 13.9.2001, as extracted supra. The contention of the learned counsel appearing on behalf of the E Appellant is· two-fold. Firstly, the High Court of Delhi had no jurisdiction to grant extension of time for payment of the decretal dues without his consent and secondly, having regard to the fact that the Respondent failed to abide by its undertaking, the original claim of the Appellant revived. The contention of Mr. C.N. Sree Kumar, learned counsel appearing on F behalf of the Respondent, on the other hand, was that despite Rule 4 of Order XXIII of the Code of Civil Procedure, there does not exist any bar to enter into a compromise at the execution stage and, in any event, with regard to the fact that the entire amount has now been paid, this Court should not exercise its discretionary jurisdiction under Article 136 of the Constitution of G India in favour of the Appellant. The suit was filed for recovery of a sum of Rs. 75 lakhs. The consent decree passed by the court shows that a decree for a sum of Rs. 41,69, 110 became payable wherefor nine cheques were issued. It is also not in dispute that the plaintiff waived his remaining claim on the premise that the Respondent H 888 SUPREME COURT REPORTS [2005) SUPP. 5 S.C.R. A had agreed to settle the disputes. Clause (b) of the Compromise Petition filed by the parties merely shows that in the event, any of the cheque is dishonoured or returned unpaid, the entire remaining balance amount shall become payable at one time in which event, the decree holder would be entitled to execute the decree for realization B of the entire remaining balance amount plus interest calculated at the rate of 15% per annum. Order _XXW,_ Rule 4 of the Code of Civil Procedure states that other provisions thereof are not applicable to an execution proceedings. But, despite the same, it is now well-settled that the parties may enter into a settlement even in a execution proceedings. c In _Moti Lal Banker (dead) by his legal Representative_ v. _Maharaj Kumar Mahmood Hasan Khan,_ AIR (1968) SC 1087, this Court held such compromise to be permissible in law stating: D E " .. .Independently of Order 23, Rule 3, the provisions of Order 21, Rule 2 and Section 47 enable the executing Court to record and enforce such a compromise in execution proceedings. Nor does Order 20, Rule 11 (2) affect this power of the executing. Court. Order 20, Rule II enables the court passing the decree to order postponement of the payment of the decretal amount on such terms as to the payment of interest as it thinks fit on the application of the judgment-debtor and with the consent of the decree-holder. It does not affect the power of the executing Court under Section 47 and Order 21, Rule 2." Yet again in _Periyakkal,_ (supra),. this Court held that, in certain situations, the court has also jurisdiction to extend the time stating: F G " ... The parties, however, entered into a compromise and invited the court to make an order in terms of the compromise, which the court did. The time for deposit stipulated by the parties became the time allowed by the court and this gave the court the jurisdiction to extend time in appropriate cases. Of course, time would not be extended ordinarily, nor for the mere asking. It would be granted in rare cases to prevent manifest injustice. True the court would not rewrite a contract between the parties but the court would relieve against a forfeiture clause; And, where the contract of the parties has merged in the order of the court, the court's freedom to act to further the ends of justice would surely not stand curtailed." H ## N.K. RAJGARHIAv. MAHAVIR PLANTATION LTD. [SINHA, J.] 889 There cannot, thus, be any doubt that the compromise entered into by A and between the parties hereto in the execution proceedings was valid in law. The Appellant moreover does not say that the same was not acted upon. Admittedly, he received the entire amount thereunder, albeit belatedly; but even therefor the Respondent applied for and obtained extension of time to pay the same. B !lightly or wrongly, the learned Single Judge of the Delhi High Court by an order dated 28.8.2002 extended the time to the Respondent herein for paying the decretal amount with interest upto 23. 7.2002. The Appellant herein had accepted such amount and that order was not questioned and, thus, the same had attained finality. What was questioned was the liability incurred by C the Respondent not being able to adhere to the terms thereof. If the orders of extension have validly been passed, the order of the court stood complied with. It may be true that the order dated 1.4.2002 was not questioned by the Respondent before this Court but then no direction was issued therein. No judgment was passed. The said order was passed D without issuing any notice to the Respondents. The appeal was disposed of as having become infructuous. It was, thus, not final. Thereby, merely a liberty had been granted to the Appellant to agitate his grievances before the learned Single Judge for execution as well as for contempt. By reason of the said order, alone the Appellant could not put forth his claim. The Appellant, thus, cannot take any benefit thereof. E An order of a court of law and, in particular, a consent order, must be read in its entirety for the purpose of ascertaining its true intent and purport. The learned Single Judge in his order dated 13.9.2001 recorded as to how much amount was paid by the Respondent to the Appellant before the F execution case was filed. The execution case admittedly was filed for recovery of the balance sum of Rs. 36,59, l l 0/- together with interest at the rate of 15% per annum. The settlement between the parties was arrived at at this juncture in terms whereof it was agreed: "1. The judgment debtor shall pay the balance amount of Rs. 36,59, 110 G in the instalments. 2. For the past period, i.e., from the date of Decree till date the judgment debtor shall pay the lump sum interest of Rs. 6,35,082. H 890 SUPREME COURT REPORTS (2005] SUPP. _5_ S.C.R. A 3. The judgment debtor shall pay 15% interest on the principal amount of the further period." Not only the Respondent agreed to pay a lump sum interest of Rs. 6,35,082 but also became agreeable to pay 15% interest on the principal amount of the further payment. On calculation, a sum of Rs. 42,04,222/- was B found to be payable out of which the judgment debtor had paid a sum of Rs. 10,00,000/- by way of three demand drafts. Appropriating the said amount, the outstanding principal sum came to Rs. 26,69, 110. However, the balance amount outstanding as on that day came to Rs. 32,04,222. It was that amount which was to be liquidated by paying instalment of Rs. 6 lakhs each per month. It C is in the aforementioned backdrop, the undertaking given before the learned Single Judge of the High Court by the Respondent herein is to be construed. The contention of the learned counsel appearing on behalf of the Appellant is that once a default is committed by the Respondent, the Appellant in terms thereof, would be entitled to execute the balance decree immediately D which would mean he would be entitled to a further sum of about Rs. 41 lakhs, which was waived by him. We do not agree. The word 'decree' after the word 'balance', in our opinion, has been used loosely. The matter might have been different if the amount payable under the compromise entered into by the parties in the execution case would have been less than the amount paid by the Respondent to the Appellant in terms of the consent decree passed E originally. It is not so. Whereas under the original decree, a sum of Rs. 41,69,110/- was payable, in terms of the consent order passed in the execution case, a sum of Rs. 42,04,222/- became payable. The sum which was waived by the Appellant did not form part of the consent decree. It was merely a claim. Such a claim never fructified into any decree and in that view of the F matter the plea of Respondent being liable to pay the said amount to the Appellant despite the fact that no decree i!l relation thereto was passed cannot be countenanced. For the reasons aforementioned, we are of the opinion that the impugned judgment and order cannot be faulted. This appeal is dismissed. However, in G the facts and circumstances of this case, there shall be no order as to costs. N.J. Appeal dismissed.