Nirmala Anand v. Advent Corporation (P) Ltd. and Ors.

Case / Petition Number:
Civil Appeal No. 574 of 1988
Neutral Citation:[2002] 5 SCC 481

Case Synopsis & Summary

The appellant, Nirmala Anand, entered into an agreement dated 6 September 1966 with Respondent Nos. 1 and 2 for Flat No. 71 on the 7th Floor of the building known as Divya Prabha, at 12-A Foreshore Road, Bombay. The sale price was Rs. 60,000, of which Rs. 35,000 had been paid, with Rs. 25,000 outstanding when the completion date of 30 June 1969 approached. Before possession could be delivered, the plot’s lease was cancelled by the Bombay Municipal Corporation, leaving the building incomplete. A suit for specific performance was filed. A Single Judge held that the sellers breached but denied specific performance, awarding damages in lieu; Division Bench affirmed. The two-judge bench agreed on a grant of specific performance but split on an additional payment by the purchaser, leading to a reference to a three-judge Bench to decide any extra sum. The Court ultimately held that the appellant, who had already paid more than half the price and was ready to perform, should not be deprived of the entire benefit of escalating real estate prices and should be required to pay a reasonable additional amount. The result was a conditional decree for specific performance, with the appellant directed to pay Rs. 6,25,000 in addition to sums already paid, while the remaining terms were to be settled as per the agreement and applicable law.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • G. B. Pattanaik
  • Y. K. Sabharwal
  • H. K. Sema
Judgment Date
2002-09-30
Court Decision / Holding
Appeal allowed. The Supreme Court directed a conditional decree for specific performance. The appellant must pay Rs. 6,25,000 in addition to the sums already paid, replacing the previously contemplated Rs. 40,00,000 figure proposed in one opinion. The sale must be executed on an as-is-where-is basis, and the parties must proceed to complete the building as per the agreement, subject to their respective rights and obligations. If the terms are not complied with, the appellant’s entitlement to specific performance would be denied and the earlier judgments would stand, secured by the terms of the decree. The decree also contemplates adjustments relating to lease revival, building completion, and financing, to be resolved by the Commissioner for taking accounts, if required.
Final Disposition
Appeal allowed with modification; conditional decree for specific performance and payment of Rs. 6,25,000 in addition to amounts already paid; terms for completing the building and lease revival to be settled as per the decree.

Parties to the Case

Appellants / Petitioners

  • Nirmala Anand

Respondents

  • Advent Corporation (P) Ltd
  • Gaurav Overseas Private Ltd

Legal Representation & Advocates

Counsels for Petitioners

  • • Gourab Banerji
  • • R. N. Karanjawala
  • • Arunabh Choudhary
  • • Meghna Mishra

Counsels for Respondents

  • • D. P. P. Tripathi
  • • Nina Gupta
  • • Bina Gupta
  • • A. Mahajan
  • • Shalini Rai
  • • Neha Misra
  • • V. N. Raghupathy
  • • C. Mukund
  • • G. K. Singh
  • • Sudha Sharma
  • • T. V. Ratnam
  • • D. N. Mishra

Provisions of Law Cited

Contract Act, 1872

Legal Doctrines & Maxims

  • Discretionary nature of the remedy of specific performance in equity
  • As-is-where-is principle in sale of incomplete property
  • Balancing of equities in grant of relief
  • Avoiding unjust premium on breach by the defaulting party

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends readiness and willingness to perform the contract; the land lease cancellation and resulting incompleteness of construction were beyond her control. She seeks specific performance, accepting the property in its present (incomplete) state on an as-is, where-is basis without demanding a reduction in price or additional burdens. She argues that the equity of enforcement favors performance rather than damages, particularly since she had paid over 50% of the price and faced a prolonged litigation period caused by the seller’s breach. While recognizing that completion may require steps (revival of lease and construction), she contends that imposing a heavy extra sum would be inequitable and amount to penalizing the purchaser for the seller’s default. In essence, she seeks a fair adjustment reflecting market escalation without a ruinous price tag that would defeat specific performance.

Contentions of Respondents

The respondents contend that specific performance is discretionary and should reflect the equities, including the costs of completing the building and reviving the lease. Given the long pendency and the seller’s breach, a substantial additional payment may be warranted to balance interests and prevent a windfall to the purchaser. They argue that the court must consider the risk and expense of completion, as the building’s revival would entail substantial expenditure and time. The defendants emphasize maintaining contractual balance and preserving the vendor’s rights, contending that the terms must align with the underlying agreement and the realities of market values; hence, any relief should be conditioned on the purchaser meeting a fair additional payment and meeting obligations to facilitate completion.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Nirmala Anand v. Advent Corporation (P.) Ltd. and Ors.[2002] 5 SCC 481Mentioned OnlyThe judgment references this same decision as the basis for its own proceedings and for context; it is cited as a related case but not as an external precedential authority within this judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,222 words•~15 min read

In The Court Record

Nirmala Anand v. Advent Corporation (P) Ltd. and Ors.

A ## NIRMALA ANAND _V._ ## ADVENT CORPORATION (P) LTD. AND ORS. ## SEPTEMBER 30, 2002 B [G .B. PATTANAIK, Y.K. SABHARWAL AND H.K .. SEMA, JJ.] ## _Contract Act, 1872:_ _Agreement for purchase of flat-Part payment made by purchaser-_ C _Before completion of constrziction lease of the' land was cancelled by Corporation-Seller could not perform his obligation-Suit for specific performance-Single Judge rejected prayer for specific performance but directed payment of damages-Affirmed by Division Beneh-On appeal, twoJudge Bench Held, purchaser entitled to specific performance of agi:eement-_ D _Difference of opinion between the Judges on the amount to be paid by the purchaser to the seller in .tie11 of unpaid balance-Matter referred to threeJudge Bench-Held, purchaser was ready and willing to perform her part of the contract and seller committed . breach in not performing his part of agreement by denying the possession of flat in question-Purchaser directed to pay to seller certain reasonable additional amount._ E - Appellant-purchaser entered into an a·greement with the sellers - (Respondent Nos. I and 2) for purchase of a flat. Appellant made partpayment of consideration amount. However, before completion of the construction, lease of the land was cancelled by the Municipal Corporation. Appellant filed a suit against the Respondents for the specific performance - F of the agreement. Single Judge of the High Court found sellers guilty of having committed breach in carrying out the terms of the agreement but did not allow the relief of specific performance, but awarded certain amount in lieu of damages. The judgment and decree was affirmed by Division Bench of the High Court. Hence this appeal. The Division Bench - G of this Court allowed the appeal by holding that the appellant was entitled to the specific performance of the agreement. However, there was a difference of opinion among the Judges on the amount to be paid by the purchaser to sellers in lieu of unpaid balance. Hence matter was referred to three-Judge Bench to determine as to whether the appellant/purchaser should be directed to pay any additional sum, and if so, what amount. "· - H 7~ - NIRMALA ANAND _v._ ADVENT CORPORATION (P) LTD. 707 A ## Allowing the appeal, the Court HELD: I. I. It is evident that the appellant is ready to take incomplete flat and pay further sum on account of phenomenal increase in the market price of the flat during the pendency of this litigation for over three decades. There appears no reason why the appellant cannot be allowed to have the entire benefit of manifold 'mega increase of the value B of real estate property in the locality. It would not be unreasonable and inequitable to make the appellant the sole beneficiary of the escalation of real estate prices and the enhanced value of the flat in question. 1710-A-C) 2. While balancing the equities, one of the consideration to be kept C in view is as to who is the defaulting party. It is also to be borne in mind whether a party is trying to take undue advantage over the other as also the hardship that may be caused to the defendant by directing the specific performance. There may be other circumstances on which parties may not have any control. The totality of the circumstances is required to be seen. In the instant case, the suit was filed by the plaintiff within a month D of the date when the posses~i()n under the agreement was to be delivered to her. She had already i)aid more than 50% of the sale consideration. There was no occasion for her to pay the balance consideration to the seller. The Courts have concurrently found that the appellant has always been ready and willing to perform her part of the contract and the seller committed breach in not carrying out the terms of the agreement. While E others left, the appellant has been single handedly fighting for her rights under the agreement. She has agreed to take the flat on as-is-where-isbasis without claiming any reduction in purchase price and without making the seller liable for anything incomplete in the building. (710-F-H; 711-A-B) F 3. For the revival of the building plans, revival of lease and other such steps, the sellers and/or their assignees may have to take steps as per agreement between them but to ask the appellant to pay to Respondeot Nos. 1 and 2, a sum of Rs. 40,00,000 would be too onerous and would almost amount to denying her specific performance. It would also amount G to putting a premium on the breach committed by Respondents I and 2. Along with the remaining amount of the sale consideration, the appellant can also be directed to pay to Respondents 1 and 2 a s,ome reasonable additional amount, they having been deprived of the amount of Rs. 25,000 during all these years. Having regard to the totality of circumstances, H 708 SUPREME COURT REPORTS (2002] SUPP. 2 S.C.R. A appellant is directed to pay to Respondents I and 2 a sum of Rs. 6,25,000 instead of Rs. 25,000. The impugned judgment and decree of the High Court shall stand modified and altered accordingly and there shall IJe a decree in the Suit on the file of the original side of the High Court on the above terms. 1711-B-Fl B _Nirmala Anand_ v. _Advent Corporation (P) ltd and Ors.,_ 120021 5 SCC 481, referred to. CIVIL APPELLATE JURISDICTION Civil Appeal No. 574 of 1988. C From the Judgment and Order dated 15.7.1987 of the Mumbai High Court in A. No. 204 of 1981. Gourab Banerji, R.N. Karanjawala, Arunabh Choudhary and Ms. Meghna Mishra for Mrs. M. Karanjawala, for the Appellants. D .P.P. Tripathi, Ms. Nina Gupta, Ms. Bina Gupta, Ms. A. Mahajan, Ms. Shalini Rai, Ms. Neha Misra, V.N. Raghupathy, C. Mukund, G.K. Singh, Ms. Sudha Sharma, T.V. Ratnam and D.N. Mishra, for the Respondent. The Judgment of the Court was delivered by E Y.K. SABHARWAL, J. The appellant, who was plaintiff No. 4 in the suit, entered into an agreement dated 6th September, 1966 with Respondent Nos. 1and2 for the Purchase offlat No. 71, on the 7th Floor of the building known as 'Divya Prabha' situated at 12-A, Foreshore Road, Bombay. The sale consideration payable under the agreement is Rs. 60,000. The agreement stipulated that the building was to be completed and possession of the flat F delivered to the appellant by 30th June, 1969 up to which time, the appellant had already paid Rs. 35,000 out of the sale consideration leaving a balance of Rs 25,000 Just a few days before the date fixed for completion and delivery of possession, the lease of the plot of land on which the flats were being constructed was cancelled by the Bombay Municipal Corporation. At G that stage, the building was incomplete. Admittedly, it is incomplete till date. Similar agreements in respect of different flats were also entered into by the sellers with other flat purchasers, On 30th July, 1969, a suit , out of which the present appeal has arisen, was filed seeking specific performance \ . of the flat purchase agree!llents. The plaintiffs other than plaintiff Nos. 4 and H 7 settled their case with sellers during the pendency of the suit and plaintiff NIRMALA ANAND _v._ ADVENT CORPORATION (P) LTD. [Y K ~MlHARWAL. J J 709 "' '· _J_ ''oj ' - No. 7 also settled during pendency of the appea: beforeJhe J;).i.vision Bench A of the High court. There was, however, no settlement befween the plaintiffappellant and respondents I and 2. In the decision of the. suit, learned Single Judge of the High Court held that the appellant was always ready and willing to performs her part of the contract and it was the sellers who committed breach in not carrying out the terms of the agreement. L'6arned Single Judge B was, however, of the view that the grant of specific performance being discretionary remedy in equity, taking into account several and serious imponderabilites and further considering that huge sums may be required to complete the building, which amount cannot be properly assessed, the appellant was not entitled to the relief of specific performance and instead it was directed that the seller shall pay to the appellant damages as assessed by the c Commissioner for taking accounts with interest at 6% per a11num from the date of the decree till the date of payment/realization, in addition to the repayment of Rs. 35,000 with interest thereon at 9% per annum from 4th October, 1967 till the date of decree and for the subsequent period, at 6% per annum till the date of payment/realization. The judgment and decree of the learned Single Judge was affirmed by a Division Bench of the High Court in D appeal. Aggrieved therefrom, the present appeal was file.i,9Jl~rant of leave. The appeal was heard by a two Judge Bench. The J'eamed Judges have concurred that the appellant is entitled to the specific :performance of the agreement dated 8th September, 1966. There has, however, been difference E of opinion between learned Judges on the condition in respect of additional amount that may be paid by the appellant to respondent Nos. I and 2 and, therefore, the matter has been placed before this three Judge Bench. The opinions of the learned Judges are reported in _Nirma/a Anand_ v. _Advent Corporation (P.) Ltd. and Ors.,_ [2002] 5 SCC 481. In the opinion expressed by brother Justice Doraiswamy Raju, the appellant has been directed to pay F sum of Rs. 40,00,000 in addition to the sum already paid to respondents I and 2 and in the view of brother Justice Ashok Bhan, it would be unfair to impose the condition of payment of Rs. 40,00,000 and the appellant is entitled to specific perfonnance of agreement to sell on the price mentioned in the agreement. G We have heard learned counsel for the parties. The only question to determine is as to whether the appellant shall be directed to pay respondents I and 2 any additional sum and if so what amount. The appellant is prepared and willing to take possession of the incomplete flat without claiming any reduction in th.e purchase price and would not hold[H ] 710 SUPREME COURT REPORTS [2002) SUPP. 2 S.C.R. A respondent Nos. 1 and 2 responsible for anything incomplete in the building. It has been concurrently held that she did not comm it breach of the agreement to sell. She has always been ready and willing to perform her pan of the agreement. The appellant is ready and willing to pay to respondents I and 2 interest on sum of Rs. 25,000. The breach was committed by respondents 1 and 2 as noticed hereinbefore. It is evident that the appellant is ready to take B incomplete flat and pay further sum as noticed, most likely on account of phenomenal increase in the market price of the flat during the pendency of this litigation for over three decades. We see no reason why the appellant cannot be allowed to have, for her alone, the entire benefit of manifold mega increase of the value of real estate property in the locality. In our view, it C would not be unreasonable and inequitable to make the appellant the sole beneficiary of the escalation of real estate prices and the enhanced value of the flat in question. There is no reason why the appellant, who is not a defaulting party, should not be allowed to reap to herself the fruits of increase in value. D It is true that grant of decree of specific perfonnance lies in the discretion of the court and it is also well settled that it is not always necessary to grant specific performance simply for the reason that it is legal to do so. . It is further well settled that the court in its discretion can impose any reasonable condition including payment of an additional amount by one party to the E other while granting or refusing decree or specific performance. Whether the purchaser shall be directed to pay an additional amount to the seller or converse would depend upon the facts and circumstances of a case. Ordinarily, the plaintiff is not to be denied the relief of specific performance only on account of the phenomenal increase of price during the pendency of litigation. That may be, in a given case, one of the consideration besides many others to be F taken into consideration for refusing the decree of specific performance. As a general rule, it cannot be held that ordinarily the plaintiff cannot be allowed to have, for her alone, the entire benefit of phenomenal increase of the value of the property during the pendency of the litigation. While balancing the equities, one of the consideration to be kept in view is as to who is the G defaulting party. It is also to be borne in mind whether a partly is trying to take undue advantage over the other as also the hardship that may be caused to the defendant by directing the specific performance. There may be other circumstances on which parties may not have any control. The totality of the circumstances is required to be seen. - H In the present case, the suit was filed by the plaintiff within a month NJ RM ALA ANAND 1·. ADVENT CORPORA TJON (P) LTD. [Y.K. SABHARWAL, J.J 7 J ] ... of the date when the possession under the agreement was to be delivered to A her. By that time, she had already paid more than 50% of::1e saie consideration. There was no occasion for her to pay the balance consideration to the seller. The courts have concurrently found that the appellant has always been ready and willing to perform her part of the contract and the seller committed breach in not carrying out the terms of the agreement While others left, the appellant has been single handedly fighting for her rights under the agreements. B She has agreed to take the flat on as is where is basis without claiming any reduction in purchase price and without making the seller liable for anything incomplete in the building. Further the building except the flat in question has been sold by respondents 1 and 2 to the 7th respondent. For the revival of the building plans, revival of lease and other such steps, the sellers and/ C or their assignees may have to take steps as per agreement between them but to ask the appellant to pay to respondent Nos. I and 2, a sum of Rs. 40,00,000 would be too onerous and would almost amount to denying her specific performance. It would also amount to putting a premium on the breach committed by respondents l and 2. Along with the remaining amount of the sale consideration, the appellant can also be directed to pay to respondents D 1 and 2 some reasonable additional amount, they having been deprived of that amount of Rs. 25,000 during all these years. > Having regard to the totality of circumstances, we would direct the appellant to pay to respondents I and 2 a sum of Rs. 6,25,000 instead of Rs. 25,000. The amount of Rs. 40,00,000, Wherever it appears in the opinion of Justice Doraiswamy Raju, would be read as Rs. 6,25,000. all other conditions will remain. The appeal is accordingly allowed and the impugned judgment and decree of the High Court shall stand modified and altered and there shall be F a decree in Suit No. 744 of 1969 on the file of the original side of the High Court, Bombay in the following terms: \ - (i) There shall be conditional decree for specific performance of the agreement dated 8.9.1966 entered into between the 4th plaintiff and Defendants 1 and 2 and Defendants 1 and 2 shall execute a sale deed as envisaged in the agreement for sale of Flat No. 71 on 7th Floor of the building known as "divya Prabha" situated at No. 12-A, Foreshore Road, Bombay, on "as-is-where-is condition". - (ii) That the appellant-plaintiff 4, within a period of six weeks, shall 712 SUPREME COURT REPORTS [2002] SUPP. 2 S.C.R. A pay the defendants-respondents I and 2, a sum of Rs. 6,25,000 (Rupees six lakh and twenty five thousand only) in addition to the sum already paid by her. The appellant shall be entitled to have the sale deed executed in her favour only on prior compliance and satisfaction of this condition. - (iii) The rights and interest in the land shall be as agreed to between parties and as per scheme and arrangement contained in the agreement dated 8-9-1996. B - (iv) Defendants I and 2 and/or the 7th respondent in this appeal viz. Gaurav Overseas / Private Ltd. 92, Maker Chambers, Nariman - c Point Bombay 400 020, as and when they secure the necessary renewal of the lease and revalidation of the building plan, the same shall be for the benefit of the appellant-Plaintiff 4 also, subject to the condition that she shall contribute her share of the monetary commitments and expenses incurred therefor, on being intimated by any of them in writing four weeks from the date of - D such receipt of the intimation. In case of dispute about the quantum, the same shall be got determined and settled before the Commissioner for taking accounts, on being moved by either of them. The sum so determined shall be a charge on the property comprised in Flat No. 71, till it is paid and shall be entitled to be recovered, accordingly. c E ,. - (v) The appellant and the 7th respondent shall be at liberty to mutually agree for completion of the incomplete building at such prevailing market rates as would be applicable for the work and manner of its completion and the mode of payment. If there can be no such mutual agreement among the appellant and the 7th respondent in - F this regard, as and when the sale deed is executed by the I st and 2nd defendants, as per this decree, the appellant shall be at liberty to make her own arrangement to have her flat completed through approved and I icensed architects. - (vi) The sale/conveyance pursuant to the decree in the suit shall be - G subject to all such rights and liabilities and obligations of respective parties (the appellant, respondents I, 2 and 7) under the suit agreement, as are available to each of them against the others, had the sale been effected even without the intervention of this Court, by mutual agreement of parties. H - (vii) The appellant falling to comply with the terms of the conditional NIRMALAANAND _v._ ADVENT CORPORATION (P) LTD. [Y.K. SABHARWAL, J.J 713 decree passed as above, shall stand denied and lose her right and A entitlement to get specific performance of the agreement dated 8-9-1966 in her favour and consequently, the appeal shall stand dismissed with the appellant's rights secured as per the judgments and decrees dated 23-3-1981 and 15-7-1987 firmly affirmed and settled, and the rights to have them executed in the manner known to law, alone serving to the appellant. B B (viii) Each party shall bear their respective costs in this Court. The appeal is allowed in above terms. S.K.S. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (2002) Decisions
2002-12-17

Devender Pal Singh v. State N.C.T. of Delhi

This judgment deals with three review petitions under Article 137 of the Constitution challenging the death sentence in cases involving murder. The petitions focus on whether death should be imposed when one of the three Judges on the bench records acquittal or advocates a life sentence. The Court clarifies that while the scope of review in criminal proceedings has broadened, a review is not a re-hearing of the original appeal and must be grounded in a miscarriage of justice. Review petitions are normally disposed of by circulation, not as full-blown re-arguments, and are permissible only where there is a grave error, manifest on the face of the order, or a miscarriage of justice. The opinion cites P.N. Eswara Iyer and Suthendraraja to stress that review is not routine and cannot be equated with the original hearing; the finality of judgments is preserved unless compelling reasons exist. The majority holds that a death sentence should not be reconsidered merely because two Judges share a different view than one Judge, nor should acquittal by a lower court automatically negate the Possibility of a death sentence if the circumstances still warrant it. The judgment also discusses the “rarest of rare” standard from Bachan Singh and the scope of reference to a larger Bench. A dissent by Shah, J. proposes that altering the death sentence to life imprisonment would meet justice in some cases, but the majority dismisses the petitions.

2002-04-24

Narpat Singh v Jaipur Development Authority

This Supreme Court decision concerns the long-running dispute over land acquired under the Lal Kothi Scheme in Jaipur. Land belonging to four appellants was acquired for a public purpose and an award awarded monetary compensation along with directions to allot residential plots of 1000 or 2000 square yards. On reference, courts enhanced the monetary compensation while upholding the plot allotments. A tripartite settlement among the claimants, the State Government and the Urban Improvement Trust ( UIT, later Ja ipur Development Authority, JDA) reduced the compensation in exchange for plot allotments, with contestants paying a reduced price to acquire plots. Executions proceeded and plots were delivered. The High Court later set aside the compromise decree, holding that the allotment of land by an award in land acquisition proceedings lacked jurisdiction and was inexecutable, relying on precedents such as Jaipur Development Authority v. Radhey Shyam and Secretary v. Daulat Mal Jain. The Supreme Court, while acknowledging the discretionary nature of Article 136, held that this case does not justify upsetting the compromise. It directed the state to restore appeals for merits and to determine quantum of monetary compensation excluding plots, while also directing allotment of smaller plots (about 250 sq yards) in another scheme within three months to maintain consistency with earlier judgments. The land must be used for the public purpose for which it was acquired. The appeals were disposed of with these directions under Article 142 for complete justice.

2002-11-13

Shrawan Bhadaji Bhirad and Ors. v. State of Maharashtra

Shrawan Bhadaji Bhirad and others, members of the Bhirad family, were convicted by an Additional Sessions Judge under sections 147, 148 and 307 read with section 149 IPC for forming an unlawful assembly and assaulting Ganesh Dhage with swords, causing extensive injuries and a prolonged hospitalisation. Ganesh Dhage survived and implicated the appellants, naming them in the dying/dependant statements, which were corroborated by eyewitnesses. The High Court upheld the Sessions Court’s conviction, rejecting the appellants’ contention that the victim did not know the assailants’ names and that the names were a product of enmity. In appeal, the appellants argued that their alleged involvement had no basis and was speculative. The Court emphasised that the dying declaration, though recorded after severe injuries and while the victim was in medical care, had significant content; and even if considered under Section 164 CrPC rather than as a strict dying declaration, it remained corroborated by the testimony of the eye-witnesses. The Court found overwhelming evidence on record supporting the prosecution’s case and concurred with the concurrent findings of the Sessions Judge and the High Court. Accordingly, the appeal was dismissed, bail bonds cancelled, and the appellants were to serve the remainder of their sentences.

2002-10-10

Alla China Apparao and Ors. v. State of Andhra Pradesh

Alla China Apparao and six co-accused were convicted by the trial court under Sections 302/149 and 148 of the IPC, and each was sentenced to life imprisonment, with a concurrent one-year term on the 148 IPC count and a fine. The High Court affirmed the convictions against the appellants while acquitting three others. The prosecution’s case rests on four eyewitnesses who say the deceased was attacked near his house, dragged to a wall, and slain by multiple appellants; medical and objective evidence were said to corroborate the eyewitnesses. The appellants contend that the three acquitted co-accused show the same evidence cannot justify conviction of the others; the witnesses were partisan, and there was no independent corroboration; the lack of injuries beyond what witnesses described and alleged dragging marks undermine the case; and a delay in forwarding the FIR to the Magistrate merits acquittal. The State argues the eyewitnesses were credible, corroborated by medical evidence and police findings, that non-examination of other witnesses is not fatal, and that the absence of dragging marks or blood on weapons does not negate the prosecution. The Court holds that eyewitness credibility is supported by evidence, the delay was within reasonable limits given workload, and the case remains trustworthy. The appeal is dismissed and the convictions upheld.