Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2021Division BenchAppeals allowed; NCLAT judgment set aside; CoC ...

NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE PRIVATE LIMITED & ORS.

Case / Petition Number:
Civil Appeal Nos.3665-3666 of 2020; Civil Appeal Nos.3742-3743 of 2020
Neutral Citation:[2021] 9 S.C.R. 1009

Case Synopsis & Summary

Ngaitlang Dhar, the successful H-1 bidder, challenged the NCLAT's reversal of the NCLT's approval of his resolution plan in the CIRP of Meghalaya Infratech Ltd under the IBC 2016. Four resolution applicants submitted plans, and in the CoC meeting held on 11-12 February 2020, Dhar emerged as H-1 after an open bidding process; the CoC, with 100% voting shares, unanimously approved Dhar's plan, which was subsequently approved by the NCLT in May 2020. PPIPL contended that it had sought time to submit a revised offer (14 February 2020) but was not granted; it challenged the RP's and CoC's actions before the NCLAT, arguing material irregularity, haste, and procedural flaws. The NCLAT allowed the appeals, setting aside both the NCLT and CoC orders. The Supreme Court reversed, holding that the CoC's 'commercial wisdom' is paramount and generally non-justiciable, except for challenges under IBC sections 30(2) or 61(3) for material irregularity. It found no material irregularity in the RP/CoC process: equal opportunity was afforded to all bidders, and the timeline was strictly observed. The Court quashed the NCLAT judgment and restored the CoC's decision, directing the appeals to be allowed with no costs and the CIRP to proceed in line with the Dhar plan.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • L. Nageswara Rao
  • B. R. Gavai
Judgment Date
2021-12-17
Court Decision / Holding
Appeals allowed. The impugned judgment of the NCLAT is quashed and set aside; the CoC's decision to approve Ngaitlang Dhar's Resolution Plan is upheld; the CIRP is effectively resolved in favour of Dhar's plan; there shall be no order as to costs; all pending applications are disposed of.
Final Disposition
Appeals allowed; NCLAT judgment set aside; CoC decision upheld; All pending applications disposed; No costs.

Parties to the Case

Appellants / Petitioners

  • Ngaitlang Dhar
  • Amit Pareek

Respondents

  • Panna Pragati Infrastructure Private Limited
  • Arihant International Limited

Legal Representation & Advocates

Counsels for Petitioners

  • • Mukul Rohatgi
  • • Arvind Kumar Gupta

Counsels for Respondents

  • • Abhijeet Sinha

Provisions of Law Cited

Insolvency and Bankruptcy Code, 2016 – ss. 30(2), 61(3)Insolvency and Bankruptcy Code, 2016 – Section 7Insolvency and Bankruptcy Code, 2016 – Section 15

Legal Doctrines & Maxims

  • Commercial wisdom of the CoC is non-justiciable, except under sections 30(2) and 61(3) of the IBC.
  • Dominant purpose of the IBC is revival of the Corporate Debtor and making it an on-going concern.
  • Material irregularity standard under Section 61(3)(ii) of the IBC.
  • Decision of CoC via voting shares is a 'collective business decision' not to be interfered with except on enumerated grounds.
  • Keshardeo Chamria v. Radha Kissen Chamria and others — words 'illegally' and 'material irregularity' do not cover errors of fact or law; focus is on irregularities in procedure.
  • K. Sashidhar v. Indian Overseas Bank and Others; Committee of Creditors of Essar Steel India Limited Through Authorized Signatory v. Satish Kumar Gupta and Others; Maharashtra Seamless Ltd v. Padmanabhan Venkatesh; Kalpraj Dharamshi and Another v. Kotak Investment Advisors Ltd; Ghanashyam Mishra and Sons Pvt. Ltd. v Edelweiss ARC.
  • Pratap Technocrats (P) Ltd. v. Monitoring Committee of Reliance Infratel Limited and another – referred to.

Submissions & Arguments

Contentions of Appellants / Petitioners

Ngaitlang Dhar's counsel argued that the CoC's decision reflects collective 'commercial wisdom' after equal opportunity for all bidders; the RP/CoC proceedings were fair, transparent and timely; NCLAT's interference was unwarranted; PPIPL's late revised bid had no legal validity, and the IBC's objective of revival was achieved. The 180-day CIRP timeline and potential extension were appropriately managed; the final selection via open bidding was proper and non-arbitrary.

Contentions of Respondents

PPIPL contended that there was a material irregularity in the RP/CoC procedure; it sought time to revise its bid and challenged the hurried approval of Dhar's plan; the NCLAT was correct to scrutinize the procedure under Section 61(3) for irregularities; the extension of CIRP before the NCLT did not justify ignoring procedural norms.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (7)

Case NameCitationTreatmentExplanation
K. Sashidhar v. Indian Overseas Bank and Others2019 (12) SCC 150; [2019] 3 SCR 845PositiveUsed to support the non-justiciability of CoC's commercial wisdom except under specified IBC sections.
Committee of Creditors of Essar Steel India Limited Through Authorized Signatory v. Satish Kumar Gupta and Others2020 (8) SCC 531; [2019] 16 SCR 275PositiveCited for the same principle of CoC's commercial wisdom.
Maharashtra Seamless Limited v. Padmanabhan Venkatesh and others2020 (11) SCC 467; [2020] 2 SCR 1157PositiveCited as part of catena establishing the underpinning law on CoC discretion.
Kalpraj Dharamshi and Another v. Kotak Investment Advisors Limited and Another2021 SCC OnLine SC 204PositiveCited for the consistent reiteration of non-interference with CoC's commercial wisdom.
Ghanashyam Mishra and Sons Private Limited Through the Authorized Signatory v. Edelweiss Asset Reconstruction Company Limited Through the Director & Ors.2021 (9) SCC 657PositiveCited as part of the jurisprudence on IBC processes and CoC discretion.
Keshardeo Chamria v. Radha Kissen Chamria and others[1953] 4 SCR 136PositiveCited for interpretation of 'material irregularity' and procedural irregularities.
Pratap Technocrats (P) Ltd. v. Monitoring Committee of Reliance Infratel Limited and another2021 SCC OnLine SC 569Mentioned OnlyReferred to; not a central basis for decision in this judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,659 words•~26 min read

In The Court Record

NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE PRIVATE LIMITED & ORS.

1009 # [2021] 9 S.C.R. 1009 ## NGAITLANG DHAR A v. PANNA PRAGATI INFRASTRUCTURE PRIVATE LIMITED & ORS. (Civil Appeal Nos.3665-3666 of 2020) B DECEMBER 17, 2021 ## **[L. NAGESWARA RAO AND B. R. GAVAI, JJ.]** _Insolvency and Bankruptcy Code, 2016 – ‘Material irregularity’ – When not – Corporate Insolvency Resolution Process (CIRP) initiated in respect of Corporate Debtor – Resolution Plans were received from four prospective Resolution Applicants including the appellant, respondent no.2 and other two – In the meeting of Committee of Creditors (CoC), the appellant emerged as H-1 bidder – Resolution Plan of the appellant approved by CoC, further approved by NCLT – Respondent No.1- contended that in the proceedings before the CoC it had sought some time to submit its revised Resolution Plan and had accordingly submitted the same – Filed application seeking direction to the Resolution Professional (RP) to take on record its revised Resolution Plan – Rejected by NCLT – RP sought approval to the Resolution Plan submitted by the appellant – Allowed by NCLT – Both the orders challenged by respondent no.1 before NCLAT – Appeals allowed – Held: Commercial wisdom of the CoC should not be interfered with, it is only the process of decision making, which can be challenged if there is any material irregularity in the said proceedings – In the present case, CoC evaluated the Resolution Plans of all the four prospective Resolution Applicants – Equal opportunity was accorded to all – However, the respondent no.1, without improving his bid amount, went on insisting for more time – Procedure adopted by the RP as well as the CoC was fair, transparent and equitable – No material irregularity – NCLAT erred in interfering with the decision of the CoC which was duly approved by the NCLT – Impugned judgment set aside._ C D E F G _Insolvency and Bankruptcy Code, 2016 – ss.30(2), 61(3) – Held: Opinion expressed by Committee of Creditors (CoC) after due deliberations in the meetings through voting, as per voting shares,_ H 1009 1010 SUPREME COURT REPORTS [2021] 9 S.C.R. - A _is the collective business decision – Decision of the CoC’s ‘commercial wisdom’ is non-justiciable, except on limited grounds for challenge u/ss.30(2) or 61(3)._ ## **Allowing the appeals, the Court** - **1.1 The respondent No.1-PPIPL was very much aware that** - B **the CoC has decided to finalise the proceedings by 12th February, 2020. It is also clear that though PPIPL was first called upon by the CoC to enhance the bid amount, it had specifically rejected the same. It insisted on disclosing the basis of score. In the proceedings of the 5th meeting of the CoC dated 11th February,** - C **2020, post lunch, though the appellant had enhanced his bid from Rs.63 crore to Rs.64 crore, the representative of PPIPL subsequently came and requested for adjourning the meeting for few days. The said request was specifically rejected by the CoC by informing the representative of PPIPL that it had to adhere to the IBC timeline and would have to conclude the matter by next** - D **day. On the next day, i.e., 12th February, 2020, when the adjourned proceedings of the CoC were held, the respondent No.1-PPIPL had sent an email, stating therein that the Directors of its Company will not be available for the said meeting and requested for deferring the meeting by a day or two. On the** - E **insistence of all the prospective Resolution Applicants present, the CoC clarified that since the timeline was coming to an end, it had decided to exclude the prospective Resolution Applicants who were not present in the said meeting. In the said meeting, the appellant came to be declared as the highest bidder after he improved his bid in the open bidding held between him and Mr.** - F **‘AA’. The Resolution Plan of the appellant was approved unanimously by Allahabad Bank having 68.34% voting rights and the Corporation Bank having 31.66% voting rights. It could thus be seen that the RP as well as the CoC had acted in a totally transparent manner. An equal opportunity was accorded to all** - G **the prospective Resolution Applicants. However, the respondent No.1-PPIPL, without improving his bid amount, went on insisting for more time, which request was specifically rejected by the CoC. [Paras 25-27][1019-D-H; 1020-A-B]** - **1.2 The procedure adopted by the RP as well as the CoC** - H **was fair, transparent and equitable. The CoC was facing the** NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE 1011 PRIVATE LIMITED & ORS. **timeline, which was to end on 24 th February, 2020, before which** A **it had to finalise its decision. In these circumstances, it cannot be said that the decision of the CoC, to not grant any further time to PPIPL for submission of its revised bid and to finalise the Resolution Plan on 12th February, 2020 itself, can be said to be falling in the category of the term ‘material irregularity’.** B **[Para 29][1020-D]** **1.3 ‘Commercial wisdom’ of the CoC has been given paramount status without any judicial intervention, for ensuring completion of the processes within the timelines prescribed by the IBC. It has been consistently held that it is not open to the Adjudicating Authority (the NCLT) or the Appellate Authority (the NCLAT) to take into consideration any other factor other than the one specified in Section 30(2) or Section 61(3) of the IBC. The opinion expressed by the CoC after due deliberations in the meetings through voting, as per voting shares, is the collective business decision and that the decision of the CoC’s ‘commercial wisdom’ is non-justiciable, except on limited grounds as are available for challenge under Section 30(2) or Section 61(3) of the IBC. No doubt that, under Section 61(3)(ii) of the IBC, an appeal would be tenable if there has been material irregularity in exercise of the powers by the RP during the corporate insolvency resolution period. However, there is no material irregularity. In the present case, leave apart, there being any ‘material irregularity’, there has been no ‘irregularity’ at all in the process adopted by the RP as well as the CoC. On the contrary, if the CoC would have permitted the PPIPL to participate in the process, despite it assuring the other three prospective Resolution Applicants in its meeting held on 11-12th February, 2020, that the absentee prospective Resolution Applicant (PPIPL) would be excluded from participation, it could have been said to be an irregularity in the procedure followed. The dominant purpose of the IBC is revival of the Corporate Debtor and making it an on-going concern. In the present case, the said purpose is already achieved, inasmuch as all the dues of the financial creditors, i.e., the Allahabad Bank and the Corporation bank, have already been paid, and the Corporate Debtor, in respect of which CIRP was initiated, is now an on-going concern. The NCLAT grossly erred in interfering with the decision of the CoC,** C D E F G H 1012 SUPREME COURT REPORTS [2021] 9 S.C.R. - A **which was duly approved by the NCLT. The impugned judgment and order passed by the NCLAT is quashed and set aside. [Paras 31, 32, 34, 37 and 38][1020-F-H; 1021-A, D-E; 1022-B-C, G-H; 1023-A-B]** - _K. Sashidhar v. Indian Overseas Bank and Others_ - B **(2019) 12 SCC 150 : [2019] 3 SCR 845;** _Committee of Creditors of Essar Steel India Limited Through Authorized Signatory v. Satish Kumar Gupta and Others_ **(2020) 8 SCC 531 : [2019] 16 SCR 275;** _Maharashtra Seamless Limited v. Padmanabhan Venkatesh and others_ **(2020) 11 SCC 467: [ 2020] 2 SCR 1157;** _Kalpraj_ - C _Dharamshi and Another v. Kotak Investment Advisors Limited and Another_ **(2021) SCC OnLine SC 204;** _Ghanashyam Mishra and Sons Private Limited Through the Authorized Signatory v. Edelweiss Asset Reconstruction Company Limited Through the Director_ - D _& Ors_ . **(2021) 9 SCC 657;** _Keshardeo Chamria v. Radha Kissen Chamria and others_ **[1953] 4 SCR 136 – relied on.** _Pratap Technocrats (P) Ltd. and others v. Monitoring Committee of Reliance Infratel Limited and anothe_ r **2021** E **SCC OnLine SC 569 – referred to.** ## **Case Law Reference** ||**[2019]**|**3 SCR 845**|**relied on**|**Para 31**| |---|---|---|---|---| ||**[2019]**|**16 SCR 275**|**relied on**|**Para 31**| |F|**[2020]**|**2 SCR 1157**|**relied on**|**Para 31**| ||**[1953]**|**4 SCR 136**|**relied on**|**Para 33**| CIVIL APPELLATE JURISDICTION : Civil Appeal Nos.36653666 of 2020. G From the Judgment and Order dated 19.10.2020 of the National Company Law Appellate Tribunal, New Delhi in Company Appeal (AT) (Insolvency) Nos.515 and 516 of 2020. ## With Civil Appeal Nos.3742-3743 of 2020. H ## NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE 1013 PRIVATE LIMITED & ORS. Mukul Rohatgi, Sr. Adv., Arvind Kumar Gupta, Ravindra Sadanand A Chingale, Ms. Anindita Pujari, Abhijeet Sinha, Shaunak Mitra, Avik Chaudhuri, Soumya Dutta, Rajesh Kumar Gautam, Anant Gautam, Nipun Sharma, Ravi Solanki, Ms. Ekta Choudhary, Chaksu Thakral, Advs. for the appearing parties. The Judgment of the Court was delivered by B ## **B. R. GAVAI, J.** 1. Civil Appeal Nos.3665-3666 of 2020 are filed by Ngaitlang Dhar, the successful Resolution Applicant (H-1 bidder), and Civil Appeal Nos. 3742-3743 of 2020 are filed by Amit Pareek, the Resolution Professional. 2. These appeals assail the judgment and order passed by the National Company Law Appellate Tribunal, New Delhi (hereinafter referred to as “the NCLAT”) dated 19[th] October, 2020, in Company Appeal (AT) (Insolvency) Nos. 515 of 2020 and 516 of 2020, thereby allowing the appeals of the respondent No.1-Panna Pragati Infrastructure Private Limited (hereinafter referred to as “PPIPL”) and the respondent No.2-Arihant International Limited. 3. Company Appeal (AT) (Insolvency) No.515 of 2020 was filed assailing the order dated 18[th] March, 2020, passed by the National Company Law Tribunal, Guwahati Bench, Guwahati (hereinafter referred to as “the NCLT”), in I.A. No.27 of 2020 in CP (IB) No.13/GB/2019, filed by PPIPL and another, by which the application seeking direction to the Resolution Professional (hereinafter referred to as “the RP”) to take on record and consider its revised offer submitted by email dated 14[th] February, 2020, came to be rejected. C D E F 4. Company Appeal (AT) (Insolvency) No.516 of 2020 was filed assailing the order dated 18[th] May, 2020 passed by the NCLT, in an unnumbered I.A. filed by the RP, vide which the appellant-Ngaitlang Dhar’s (H-1 bidder) Resolution Plan came to be approved by the NCLT. 5. Vide the impugned judgment and order dated 19[th] October, 2020, the NCLAT has set aside both the orders, dated 18[th] March, 2020, and 18[th] May, 2020, and directed the Corporate Insolvency Resolution Process (hereinafter referred to as “CIRP”) to be resumed from the stage of consideration of the Resolution Plans. G H 1014 SUPREME COURT REPORTS [2021] 9 S.C.R. A 6. The facts in brief giving rise to the present appeals are as under: 7. An application being CP(IB) No.13/GB/2019 came to be filed under Section 7 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as “the IBC”) for initiation of CIRP in respect of Meghalaya B Infratech Ltd. (hereinafter referred to as “the Corporate Debtor”) by the Allahabad Bank (now known as Indian Bank) (hereinafter referred to as “the Allahabad Bank”). The NCLT vide order dated 28[th] August, 2019 admitted the petition and as such, the CIRP came to be initiated in respect of the Corporate Debtor and Mr. Amit Pareek came to be appointed as the Interim RP, who was subsequently confirmed as the C RP in the first Committee of Creditors (“hereinafter referred to as “the CoC”) meeting, held on 25[th] September, 2019. 8. It is not in dispute that the Allahabad Bank and the Corporation Bank (now known as Union Bank) (hereinafter referred to as “the Corporation Bank”) were the only financial creditors. D 9. In accordance with the provisions of the IBC, Expression of Interest (hereinafter referred to as “EOI”) was invited from the prospective Resolution Applicants by the RP. 10. Appellant-Ngaitlang Dhar, respondent No.1-PPIPL, Mr. E Abhishek Agarwal and Mr. Ashish Jaisasaria submitted their EOI. All the four Resolution Applicants submitted their Resolution Plans. In the CoC meeting held on 11-12[th] February, 2020, the appellant-Ngaitlang Dhar emerged as H-1 bidder, whereas Mr. Abhishek Agarwal emerged as H-2 bidder. F 11. At the 7[th] CoC meeting, held on 6[th] March, 2020, the CoC, with a 100% voting share, approved the Resolution Plan of the appellantNgaitlang Dhar (H-1 bidder), which was further approved by the NCLT vide order dated 18[th] May, 2020. 12. The respondent No.1-PPIPL contended that in the proceedings before the CoC held on 11-12[th] February, 2020, it had sought for one or G two days’ time to submit its revised Resolution Plan, and accordingly, it submitted the same on 14[th] February, 2020. The respondent No.1-PPIPL, accordingly, filed I.A. No. 27 of 2020 in CP(IB) No.13/GB/2019 before the NCLT, seeking a direction to the RP to take on record its revised Resolution Plan, dated 14[th] February, 2020. The same came to be rejected H by the NCLT, vide order dated 18[th] March, 2020. The RP thereafter NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE 1015 PRIVATE LIMITED & ORS. [B. R. GAVAI, J. ] filed an unnumbered I.A. seeking approval to the Resolution Plan submitted by the appellant-Ngaitlang Dhar (H-1 bidder). The said unnumbered I.A. was allowed by the NCLT vide order dated 18[th] May, 2020. Both these orders came to be challenged before the NCLAT by way of aforesaid Company Appeals by the respondent No.1-PPIPL. As stated above, by the impugned judgment and order dated 19[th] October, 2020, the appeals were allowed. Being aggrieved thereby, the present appeals are filed before this Court. 13. We have heard Shri Mukul Rohatgi, learned Senior Counsel appearing on behalf of the appellant-Ngaitlang Dhar, the successful Resolution Applicant (H-1 bidder) and Shri Abhijeet Sinha, learned counsel appearing on behalf of the respondent No.1-PPIPL. 14. Shri Mukul Rohatgi, learned Senior Counsel appearing on behalf of Ngaitlang Dhar, the successful Resolution Applicant (H-1 bidder), submitted that the entire approach adopted by the NCLAT in the impugned judgment and order was erroneous. He submitted that the NCLAT ought to have taken into consideration that the CoC after exercising its ‘commercial wisdom’ has resolved to accept the Resolution Plan submitted by Ngaitlang Dhar. He submitted that the RP had given an equal opportunity to all the bidders/resolution applicants. He submitted that though adequate opportunity was given to all the Resolution Applicants by adjourning the proceedings in CoC meetings on number of occasions, the respondent No.1-PPIPL failed to revise its bid within the stipulated period. He submitted that the CoC, in its meeting, held on 11-12[th] February, 2020, had resolved to declare Ngaitlang Dhar as the successful resolution applicant. He submitted that, not only that, thereafter the NCLT had also allowed the application filed by the RP to approve the Resolution Plan of Ngaitlang Dhar. 15. Shri Rohatgi submitted that it is only after 12[th] February, 2020, the respondent No.1-PPIPL, on 14[th] February, 2020, had sent an email to the RP, revising its offer to Rs.65.65 crore. He submitted that when an initial offer given by the respondent No.1-PPIPL was only of making an upfront payment of Rs.24 crore, it is clear that the revised offer of Rs.65.65 crore was only with a _mala fide_ intention of protracting the proceedings. He submitted that the NCLAT ought not to have interfered with the ‘commercial wisdom’ of the CoC. In this respect, he relies on various judgments of this Court. A B C D E F G H 1016 SUPREME COURT REPORTS [2021] 9 S.C.R. - A 16. Shri Rohatgi further submits that the Resolution Plan of Ngaitlang Dhar now stands implemented, inasmuch as the dues of all the Banks (financial creditors) have been repaid and now the Corporate Debtor, i.e., Meghalaya Infratech Ltd. is an on-going concern. 17. Shri Abhijeet Sinha, learned counsel appearing on behalf of B the respondent No.1-PPIPL would submit that there is a distinction between the decision of the CoC and the procedure adopted by the RP and the CoC to arrive at that decision. He submitted that though a final decision of the CoC cannot be a matter of challenge on the ground that the ‘commercial wisdom’ of the CoC should not be interfered with, yet if there is a material irregularity in the procedure adopted by the RP, an C appeal under Section 61(3) of the IBC would be tenable. He submitted that the RP acted with undue haste in the present matter. Learned counsel submitted that in the proceedings of the meeting of the CoC, held on 1112[th] February, 2020, the Director of PPIPL, had sought one or two days’ time to submit its revised offer. He submitted that, however, the said D time was not granted. He further submitted that the revised offer was submitted within two days and it was the duty of the RP to present its revised offer before the CoC. Having not done that and having hastily approved the plan of Ngaitlang Dhar, the NCLAT has rightly interfered with the decision of the CoC. In this respect, he relies on the judgment of this Court in the case of _**Pratap Technocrats (P) Ltd. and others v.**_ E _**Monitoring Committee of Reliance Infratel Limited and another[1]**_ . - F 18. Shri Sinha further submitted that when the NCLT itself had extended the period of CIRP by another 90 days beyond 180 days vide order dated 26[th] February, 2020, there was no reason for the RP to have hastily accepted the bid of Ngaitlang Dhar. 19. Learned counsel appearing on behalf of the respondents – Banks (the financial creditors) also support the arguments of the learned counsel appearing on behalf of Ngaitlang Dhar. They submit that the Banks have received the entire payment that was owed to them. It is further submitted that the email dated 14[th] February, 2020 sent by PPIPL G was also endorsed to the Allahabad Bank as well as the Corporation Bank. It is submitted that both the Banks had refused to consider the said offer inasmuch as such an offer was not valid in law. 20. The facts are not in dispute in the present matter. > 1 2021 SCC OnLine SC 569 H NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE 1017 PRIVATE LIMITED & ORS. [B. R. GAVAI, J. ] 21. Vide order dated 28[th] August, 2019, the application filed by A Allahabad Bank under Section 7 of the IBC for initiation of CIRP in respect of the Corporate Debtor came to be allowed. Vide the said order dated 28[th] August, 2019, Mr. Amit Pareek came to be appointed as the Interim RP. 22. The interim RP, in compliance with Section 15 of the IBC, made public announcement calling for claims from creditors of the Corporate Debtor. Upon receipt of claims from the creditors, the CoC came to be formed on 17[th] September, 2019. Thereafter, in the first meeting of the CoC, held on 25[th] September, 2019, the Interim RP came to be appointed as the RP. Thereafter, the RP invited EOI from the prospective Resolution Applicants. Four EOIs came to be received from (a) PPIPL & others; (b) Mr. Ngaitlang Dhar; (c) Mr. Abhishek Agarwal; and (d) Mr. Ashish Jaisasaria & others. The provisional list of Resolution Applicants came to be published and objections to the provisional list were invited by 25[th] December, 2019. Since no objection in respect of any of the prospective Resolution Applicants was received, a final list of prospective Resolution Applicants was placed before the CoC for evaluation. Thereafter, all the Resolution Applicants were invited to submit their respective Resolution Plans by 24[th] January, 2020. In response to that, four Resolution Plans were received from the four prospective Resolution Applicants. 23. The 5[th] meeting of the CoC was held on 11[th] February, 2020. The minutes of the said meeting, particularly Agenda No.6, would reveal that the RP informed the CoC that there were numerous anomalies and deficiencies observed in the Resolution Plan of PPIPL and the same was intimated to the Resolution Applicant through email dated 30[th] January, 2020 with a request to rectify/correct the same and submit the same by 1[st] February, 2020. However, PPIPL had failed to do so within the stipulated period. It would further reveal that an email dated 1[st] February, 2020, was received from PPIPL with a request to grant time for submission of rectified Resolution Plan by 3[rd] February, 2020. Accordingly, the rectified Resolution Plan came to be filed by PPIPL on 3[rd] February, 2020. In the said meeting, the CoC evaluated the Resolution Plans of all the four prospective Resolution Applicants. Paragraph 5 of the consideration of the proposed Resolution Plan of PPIPL reads thus: “5. The CoC requested PRA to improve their bid amount the PRA refused to do so unless individual score of all disclosed further B C D E F G H 1018 SUPREME COURT REPORTS [2021] 9 S.C.R. A for increase of the bid amount he has to discuss with BOD of the applicant” 24. It would further reveal that the CoC continued the second round of negotiation after a lunch break. It will be relevant to refer to the following excerpt of the minutes of the meeting of the CoC dated 11[th] B February, 2020: “2. The CoC decided to invite Panna Pragati Infrastructure Pvt. Ltd. for further negotiation. The RP informed that in first round of negotiation the PRA has not revised their bid amount and informed the CoC about the brief details of plan. The PRA also want to C know about the basis of score, the RP & CoC informed at this mature stage of CIRP this is not the right time and place to discuss about the evaluation and also informed that the evaluation has been done as per the RFRP, IM & evaluation matrix which has been circulated to all the PRA in due time. D 3. The CoC & RP informed the PRA about the anomalies & deficiency in the rectified Resolution Plan submitted by them still persist despite of given them opportunity earlier after the submission of original resolution plan for the rectification. The PRA requested to allow some more time for the rectification and submit revise plan. The casual approach of PRA noted. E 4. The CoC requested to improve the bid amount to the PRA, the PRA states that at this stage we will not increase the bid amount” 25. The minutes of the 5[th] meeting of the CoC would further reveal that the CoC thereafter invited Ngaitlang Dhar for negotiation of the bid F and requested him to enhance the bid amount. Ngaitlang Dhar agreed to enhance the bid amount from Rs.63 crore to Rs.64 crore. Thereafter again, the representative of PPIPL returned back and requested to adjourn the meeting for a few days. The said request was specifically rejected by the CoC informing the representative of PPIPL that they were bound to follow the IBC timeline and wanted to conclude the matter by next G day. The said 5[th] meeting of the CoC was adjourned to next day and was held on 12[th] February, 2020. The minutes of the said meeting would further reveal that the representative of PPIPL had informed the CoC/ RP that the Directors of their Company will not be available for the meeting to be held on 12[th] February, 2020 and the meeting should be H NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE 1019 PRIVATE LIMITED & ORS. [B. R. GAVAI, J. ] deferred by one or two days. The minutes of the meeting would further reveal that all the prospective Resolution Applicants present in the meeting sought clarification from the CoC members and the RP about the status of Resolution Applicant, who was absent in the meeting, as to whether it would be allowed to participate in the further bidding process or not. The CoC members specifically replied that since they were at the neck of the timeline (i.e. 180 days were to get over on 24[th] February, 2020), it was decided to exclude the respondent No.1-PPIPL, who was not present in the said meeting. The proceedings commenced after lunch break, wherein only two prospective Resolution Applicants, i.e., Ngaitlang Dhar and Mr. Abhishek Agarwal were present. Thereafter, the CoC adopted Swiss Challenge open bidding method. In the said bidding process, both prospective Resolution Applicants present increased their offer. In the said open bidding process between the two prospective Resolution Applicants present, Ngaitlang Dhar was found to be the highest bidder/ prospective Resolution Applicant having offered the bid of an upfront amount of Rs.64.30 crore plus CIRP costs. The said Resolution Plan of Ngaitlang Dhar was approved unanimously by Allahabad Bank having 68.34% voting rights and the Corporation Bank having 31.66% voting rights. 26. It is thus clear that the respondent No.1-PPIPL was very much aware that the CoC has decided to finalise the proceedings by 12[th] February, 2020. It is also clear that though PPIPL was first called upon by the CoC to enhance the bid amount, it had specifically rejected the same. It insisted on disclosing the basis of score. In the proceedings of the 5[th] meeting of the CoC dated 11[th] February, 2020, post lunch, though Ngaitlang Dhar had enhanced his bid from Rs.63 crore to Rs.64 crore, the representative of PPIPL subsequently came and requested for adjourning the meeting for few days. The said request was specifically rejected by the CoC by informing the representative of PPIPL that it had to adhere to the IBC timeline and would have to conclude the matter by next day. On the next day, i.e., 12[th] February, 2020, when the adjourned proceedings of the CoC were held, the respondent No.1-PPIPL had sent an email, stating therein that the Directors of its Company will not be available for the said meeting and requested for deferring the meeting by a day or two. On the insistence of all the prospective Resolution Applicants present, the CoC clarified that since the timeline was coming to an end, it had decided to exclude the prospective Resolution Applicants who were not present in the said meeting. In the said meeting, Ngaitlang A B C D E F G H 1020 SUPREME COURT REPORTS [2021] 9 S.C.R. - A Dhar came to be declared as the highest bidder after he improved his bid in the open bidding held between him and Mr. Abhishek Agarwal. 27. It could thus be seen that the RP as well as the CoC had acted in a totally transparent manner. An equal opportunity was accorded to all the prospective Resolution Applicants. However, the respondent No.1B PPIPL, without improving his bid amount, went on insisting for more time, which request was specifically rejected by the CoC. 28. Shri Abhijeet Sinha, learned counsel, fairly concedes that though the final decision of the CoC would not be challenged on the ground that the ‘commercial wisdom’ of the CoC should not be interfered with, it is C only the process of decision making, which can be challenged if there is any material irregularity in the said proceedings. 29. As already discussed hereinabove, we find that the procedure adopted by the RP as well as the CoC was fair, transparent and equitable. The CoC was facing the timeline, which was to end on 24[th] February, D 2020, before which it had to finalise its decision. In these circumstances, it cannot be said that the decision of the CoC, to not grant any further time to PPIPL for submission of its revised bid and to finalise the Resolution Plan on 12[th] February, 2020 itself, can be said to be falling in the category of the term ‘material irregularity’. E 30. We have extracted the minutes of the proceedings of the 5[th] meeting of the CoC in extenso. It could be seen that the CoC, after due deliberations, evaluated all the proposed Resolution Plans submitted by all the prospective Resolution Applicants and after giving sufficient opportunity to all the prospective Resolution Applicants, arrived at a considerate decision of accepting the Resolution Plan of the appellantF Ngaitlang Dhar in its meeting held on 11-12[th] February, 2020. 31. It is trite law that ‘commercial wisdom’ of the CoC has been given paramount status without any judicial intervention, for ensuring completion of the processes within the timelines prescribed by the IBC. It has been consistently held that it is not open to the Adjudicating G Authority (the NCLT) or the Appellate Authority (the NCLAT) to take into consideration any other factor other than the one specified in Section 30(2) or Section 61(3) of the IBC. It has been held that the opinion expressed by the CoC after due deliberations in the meetings through voting, as per voting shares, is the collective business decision and that the decision of the CoC’s ‘commercial wisdom’ is non-justiciable, except H ## NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE 1021 PRIVATE LIMITED & ORS. [B. R. GAVAI, J. ] on limited grounds as are available for challenge under Section 30(2) or A Section 61(3) of the IBC. This position of law has been consistently reiterated in a catena of judgments of this Court, including: - _**(i) K. Sashidhar v. Indian Overseas Bank and Others[2]**_ - _**(ii) Committee of Creditors of Essar Steel India Limited**_ B - _**Through Authorized Signatory v. Satish Kumar Gupta and Others[3] ,**_ - _**(iii) Maharashtra Seamless Limited v. Padmanabhan Venkatesh and others[4] ,**_ - _**(iv) Kalpraj Dharamshi and Another v. Kotak Investment**_ C _**Advisors Limited and Another[5]**_ . - _**(v) Ghanashyam Mishra and Sons Private Limited Through the Authorized Signatoryv. Edelweiss Asset Reconstruction Company Limited Through the Director & Ors.[6]**_ 32. No doubt that, under Section 61(3)(ii) of the IBC, an appeal would be tenable if there has been material irregularity in exercise of the powers by the RP during the corporate insolvency resolution period. However, as discussed hereinabove, we do not find any material irregularity. 33. We may gainfully refer to the following observations of this Court in the case of _**Keshardeo Chamria v. Radha Kissen Chamria and others[7]**_ while considering the scope of the words ‘material irregularity’, as are found in Section 115 of the Code of Civil Procedure, 1908: “Reference may also be made to the observations of Bose, J. in his order of reference in _Narayan Sonaji_ v. _Sheshrao Vithoba_ [AIR 1948 Nag 258] wherein it was said that the words “illegally” and “material irregularity” do not cover either errors of fact or law. They do not refer to the decision arrived at but to the D E F G 2 (2019) 12 SCC 150 3 (2020) 8 SCC 531 - 4 (2020) 11 SCC 467 5 (2021) SCC OnLine SC 204 6 (2021) 9 SCC 657 7 (1953) 4 SCR 136 H 1022 SUPREME COURT REPORTS [2021] 9 S.C.R. - A manner in which it is reached. The errors contemplated relate to material defects of procedure and not to errors of either law or fact after the formalities which the law prescribes have been complied with.” 34. In the present case, leave apart, there being any ‘material B irregularity’, there has been no ‘irregularity’ at all in the process adopted by the RP as well as the CoC. On the contrary, if the CoC would have permitted the PPIPL to participate in the process, despite it assuring the other three prospective Resolution Applicants in its meeting held on 1112[th] February, 2020, that the absentee prospective Resolution Applicant (PPIPL) would be excluded from participation, it could have been said C to be an irregularity in the procedure followed. 35. Insofar as the contention of the learned counsel, Shri Abhijeet Sinha, that the NCLT had already extended the CIRP period by 90 days vide order dated 26[th] February, 2020 and therefore, there was no necessity to hastily approve the Resolution Plan of Ngaitlang Dhar on 12[th] February, D 2020, is concerned, we find the same to be without substance. It will be relevant to mention that the period of 180 days was to expire on 24[th] February, 2020, and therefore, in the meeting dated 12[th] February, 2020 itself, the CoC after resolving to declare Ngaitlang Dhar as H-1 bidder had resolved to authorise the RP to seek an extension of CIRP period E before the NCLT. 36. It will be relevant to refer to paragraph 2 of the order dated 26[th] February, 2020 passed by the NCLT, which reads thus: - “2. It is the submission of the RP that the CoC in its 5[th] meeting held on 11.02.2020 concluded on 12.02.2020 declared one Mr. N. - F Dhar as highest bidder and the said decision of theCoC is under consideration for approval with the higher authority of the CoC and, therefore, prayed for further extension of CIRP period to 90 days with effect from 25.02.2020” 37. It could thus be seen that the contention in that regard is also G without substance. It is further to be noted that, as has been consistently held by this Court in catena of judgments, referred to hereinabove, the dominant purpose of the IBC is revival of the Corporate Debtor and making it an on-going concern. In the present case, the said purpose is already achieved, inasmuch as all the dues of the financial creditors, i.e., H the Allahabad Bank and the Corporation bank, have already been paid, ## NGAITLANG DHAR v. PANNA PRAGATI INFRASTRUCTURE 1023 PRIVATE LIMITED & ORS. [B. R. GAVAI, J. ] and the Corporate Debtor, in respect of which CIRP was initiated, is A now an on-going concern. 38. We are, therefore, of the considered view that the NCLAT has grossly erred in interfering with the decision of the CoC, which was duly approved by the NCLT. The appeals are, therefore, allowed. The impugned judgment and order passed by the NCLAT, dated 19[th] October, B 2020 is quashed and set aside. There shall be no order as to costs. All pending applications shall stand disposed of. Divya Pandey Appeals allowed. C D E F G H
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.