Court Decision / Holding
The writ petition is allowed. Exts.P3, P4, Ext.P6 and Ext.P11 are quashed. The respondents are directed to convene an adhoc DPC to consider the petitioner using confidential reports for three years preceding her long leave (before 31.08.2005). The select list for 2014 should be revised to include the petitioner as Sl.No.2, with notional promotion from the date the 4th respondent was promoted, and all consequential benefits except pay and allowances, to be disbursed within four months.
Final Disposition
Writ petition allowed; supersession set aside; adhoc DPC to consider three-year confidential reports prior to rejoining; petitioner to be included as Sl.No.2 with notional promotion and other consequential benefits (except pay) to be disbursed within four months; neutral on pay and allowances initially.

Parties to the Case

Appellants / Petitioners

  • Neena Majeed

Respondents

  • Kerala Water Authority, Jala Bhavan, Thiruvananthapuram (Rep. by Managing Director)
  • The Departmental Promotion Committee (Technical Higher), Kerala Water Authority (Rep. by Convener and Managing Director)
  • The Secretary, Water Resources (Water Supply-B) Department, Secretariat, Thiruvananthapuram
  • Smt. Sandhya P., Executive Engineer, Kerala Water Authority, P.H. Division, Alappuzha
  • Smt. Usha Radhakrishnan, Executive Engineer, KWA, P.H. Circle, Thrissur
  • Sri.G.K. Sujathkumar, Executive Engineer, KWA, Project Division, Piravom
  • Sri. V.K. Retnakumar, Executive Engineer, KWA, Southern Region, Thiruvananthapuram
  • Sri.E. Mohammed, Executive Engineer, KWA, Works South, Head Office, Thiruvananthapuram
  • Smt. Anitha Puthenpuray, Executive Engineer, KWA, J.I.C.A Project, Thiruvananthapuram
  • Sri. Abraham N.T., Executive Engineer, KWA, Quality Control Division, Thiruvananthapuram
  • Sri Kishore Babu S., Executive Engineer, KWA, Project Division, Alappuzha
  • Sri.K.V.M Abdul Latheef, Executive Engineer, KWA, now Deputy Director, Environmental Regional Project Management Unit, KRWSA, Perinthalmanna

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. Shaji Thomas
  • • Sri. H. Kiran

Counsels for Respondents

  • • Sri. P. Benjamin Paul, SC
  • • Sri. Joseph John, SC

Case Synopsis & Summary

The petitioner, Neena Majeed, an Assistant Executive Engineer in the Kerala Water Authority, challenges her supersession for promotion to Executive Engineer in the year 2014. After joining as AE in 1994 and being promoted to Assistant Executive Engineer in 2002, she took leave without allowance from 31.08.2005 to 17.12.2013 and rejoined on 18.12.2013. The Departmental Promotion Committee (DPC) for Executive Engineer promotion, convened on 23.08.2014, superseded her name on the ground that confidential reports for three years were not available and that she had not completed one year of service after rejoining. The initial select list (Ext.P3) contained 9 officers, with the petitioner at rank 4 being superseded; an adhoc DPC (Ext.P4) also superseded her. The petitioner challenged Ext.P11 (02.07.2015) rejecting her representation. The court examined Rule 28(b)(i)(4a) of KS&SSR, noting that where the three-year confidential reports are not available, one-year reports after rejoining may be substituted. Relying on Vishnu Namboothiri and Shobanakumar, which held that one year after rejoining is not mandatory, the court found the supercession unsustainable. It quashed Exts.P3, P4, P6 and Ext.P11, and directed an adhoc DPC using three years’ confidential reports prior to rejoining (before 31.08.2005) to consider the petitioner as Sl. No.2, with notional promotion and other consequential benefits (excluding pay). The petition is allowed.

Provisions of Law Cited

Rule 28(b)(i) KS&SSRRule 28(b)(i)(4a) KS&SSR

Legal Doctrines & Maxims

  • Completion of one year after rejoining is not mandatory for eligibility to promotion; 3-year confidential reports prior to rejoining may be considered as per KS&SSR 28(b)(i)(4a). This doctrine is supported by Vishnu Namboothiri v. State of Kerala and Shobanakumar v. State of Kerala.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner argues that the rule requiring three years of confidential reports is not upset by the absence of three-year reports because the officer rejoined after long leave and the judgments Vishnu Namboothiri and Shobanakumar held that one year after rejoining need not delay eligibility for promotion. She contends that confidential reports for the three years prior to rejoining (i.e., before 31.08.2005) should be considered, and that Exts.P3, P4, P6 and Ext.P11 are unsustainable, calling for inclusion as Sl.No.2 with notional promotion.

Contentions of Respondents

The respondents contend that confidential reports for three years preceding the DPC were not available, and since the officer had not completed one year after rejoining, she was not eligible for promotion at that time. They rely on Rule 28(b)(i)(4a) to assess suitability using the available period and assert that the petitioner could be considered only after the required period of confidential reports post-rejoining; they ultimately promoted her in 2015 when she became eligible.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Vishnu Namboothiri v. State of Kerala2000 (3) KLT 627PositiveCourt held that completion of one year after rejoining is not mandatory for eligibility; three-year confidential reports prior to rejoining should be used if three years are not available.
Shobanakumar v. State of Kerala2004 2 KLT 755PositiveCourt adopted same principle as Vishnu Namboothiri, allowing eligibility based on three years prior to rejoining, not waiting for one year.
W.P.(C) No.27442/2014W.P.(C) No.27442/2014PositiveEarlier judgment directing the government to consider representations within one month; cited to support the approach of timely consideration and reliance on prior decisions.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Neena Majeed v. Kerala Water Authority & Others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT:** ## **THE HONOURABLE SMT. JUSTICE P.V.ASHA** **TUESDAY, THE 29TH DAY OF AUGUST 2017/7TH BHADRA, 1939** ## **WP(C).No. 10184 of 2015 (W)** **----------------------------** ## **PETITIONER :** **----------------------** **NEENA MAJEED, ASSISTANT EXECUTIVE ENGINEER, OFFICE OF THE CHIEF ENGINEER (SR), KERALA WATER AUTHORITY, THIRUVANANTHAPURAM.** **BY ADVS.SRI.SHAJI THOMAS SRI.H.KIRAN** **RESPONDENT(S):** **---------------------------** **1. KERALA WATER AUTHORITY, JALA BHAVAN, THIRUVANANTHAPURAM - 695 033, REP. BY ITS MANAGING DIRECTOR.** **2. THE DEPARTMENTAL PROMOTION COMMITTEE (TECHNICAL HIGHER), KERALA WATER AUTHORITY, REP. BY ITS CONVENER AND MANAGING DIRECTOR, KERALA WATER AUTHORITY, JALA BHAVAN, THIRUVANANTHAPURAM- 695 033.** **3. THE SECRETARY, WATER RESOURCES, (WATER SUPPLY-B) DEPARTMENT, SECRETARIAT, THIRUVANANTHAPURAM -695 001.** **4. SMT. SANDHYA P., EXECUTIVE ENGINEER, KERALA WATER AUTHORITY, P.H. DIVISION,** **ALAPPUZHA - 688 001.** **5. SMT. USHA RADHAKRISHNAN, EXECUTIVE ENGINEER, KERALA WATER AUTHORITY,** - **P.H. CIRCLE, THRISSUR - 680 001.** **6. SRI.G.K. SUJATHKUMAR, EXECUTIVE ENGINEER, KERALA WATER AUTHORITY, PROJECT DIVISION, PIRAVOM - 686 664.** **2/-** **-2-** ## **WP(C).No. 10184 of 2015 (W)** **7. SRI. V.K. RETNAKUMAR, EXEECUTIVE ENGINEER, KERALA WATER AUTHORITY,** **SOUTHERN REGION, THIRUVANANTHAPURAM - 695 033.** **8. SRI.E. MOHAMMED, EXECUTIVE ENGINEER, KERALA WATER AUTHORITY, WORKS SOUTH,** **HEAD OFFICE, THIRUVANANTHAPURAM - 695 033.** **9. SMT. ANITHA PUTHENPURAY, EXECUTIVE ENGINEER, KERALA WATER AUTHORITY, J.I.C.A PROJECT, THIRUVANANTHAPURAM - 695 033.** **10. SRI. ABRAHAM N.T., EXECUTIVE ENGINEER, KERALA WATER AUTHORITY,** **QUALITY CONTROL DIVISION, THIRUVANANTHAPURAM - 695 033.** **11. SRI. KISHORE BABU S., EXECUTIVE ENGINEER, KERALA WATER AUTHORITY,** **PROJECT DIVISION, ALAPPUZHA - 688 001** **12. SRI.K.V.M ABDUL LATHEEF, EXECUTIVE ENGINEER, KERALA WATER AUTHORITY, NOW WORKING AS DEPUTY DIRECTOR, ENVIRONMENTAL REGIONAL PROJECT MANAGEMENT UNIT, K.R.W.S.A, JALA NIDHI, PERINTHALMANNA, MALAPPURAM - 679 322.** **R1 TO R3 BY SRI.P.BENJAMIN PAUL, SC, SRI.JOSEPH JOHN, SC,** **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 29-08-2017, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **sts** ## **WP(C).No. 10184 of 2015 (W)** ## **------------------------------------------** ## **APPENDIX** ## **PETITIONER(S)' EXHIBITS -------------------------------------** ## **EXHIBIT-P1- TRUE COPY OF G.O(RT).NO.662/2010/WRD DATED 04/06/2010** **EXHIBIT-P2- TRUE COPY OF THE ORDER NO. KWA/JB/E1-12596/03 ISSUED BY THE IST RESPONDENT DATED 05/08/2010.** **EXHIBIT-P3- TRUE COPY OF THE MINUTES OF THE DEPARTMENTAL PROMOTION COMMITTEE WHICH MET ON 23/08/2014.** **EXHIBIT-P4- TRUE COPY OF THE MINUTES OF THE DEPARTMENTAL PROMOTION COMMITTEE MEETING HELD ON 17/09/2014.** **EXHIBIT-P5- TRUE COPY OF THE REPRESENTATION DATED 30/09/2014.** **EXHIBIT-P6- TRUE COPY OF THE COMMUNICATION NO. 18028/B1/14/WRD DATED 09/10/2014 ISSUED BY THE 3RD RESPONDENT.** **EXHIBIT-P7- TRUE COPY OF THE RELEVANT PORTION OF THE STATEMENT CONTAIN IN THE SENIORITY POSITION AS ON 10/10/2014.** **EXHIBIT-P8- TRUE COPY OF THE REPRESENTATION DATED 17/10/2014.** **EXHIBIT-P9- TRUE COPY OF THE JUDGMENT IN W.P(C) 27442/2014 DATED 21/10/2014.** **EXHIBIT-P10- TRUE COPY OF THE HEARING NOTES DATED 01/12/2014.** **EXHIBIT-P11- TRUE COPY OF THE ORDER NO. KWA/JB/E2A/201313/2014 DATED 07/02/2015.** **RESPONDENT(S)' EXHIBITS:** **NIL** **------------------------------------------** **/TRUE COPY/** **P.A.TO JUDGE** **sts** ## _**P.V.ASHA, J.**_ -------------------------- W.P(C) No.10184 of 2015-W ------------------------------------------- _Dated this the 29[th] day of August, 2017_ ## _**JUDGMENT**_ The petitioner, who is an Assistant Executive Engineer is aggrieved by the denial of promotion as Executive Engineer in preference to her juniors. 2. The petitioner was appointed as Assistant Engineer on 28.12.1994. She was promoted as Assistant Executive Engineer w.e.f 5.1.2002. Her probation in the cadre of Assistant Executive Engineer was declared w.e.f 8.1.2003. She availed leave without allowance for the period from 31.8.2005 to 17.12.2013. She rejoined duty on 18.12.2013. The next promotion is to the post of Executive Engineer. 3. The Departmental Promotion Committee (`D.P.C' for short) for promotion to the post of Executive Engineers was convened on 23.8.2014. But she was superseded on the ground that confidential reports for a period of 3 years were not available and she had not completed one year duty after availing leave without allowance. As per Ext.P3 minutes, the D.P.C had drawn a select list of Assistant Executive Engineers who were found 2 W.P(C) No.10184 of 2015-W suitable for promotion as Executive Engineer for the year 2014. 9 Assistant Executive Engineers who were ranked 3, 5, 6, 8, 9, 11, 13, 16 and 17 in the seniority list were included in the select list. The petitioner who was rank No.4 was superseded on the ground that confidential report was not completed, and that she had not completed one year duty after availing leave without allowance. An adhoc DPC was convened on 17.9.2014 in order to review the cases of the officers who were overlooked. The petitioner was again superseded on the same ground. The select list was modified adding one more officer i.e with 10 officers. The petitioner thereupon submitted Ext.P5 representation against her supersession on 30.09.2014. Thereafter she submitted a statutory representation Ext.P8 on 17.10.2014 before the 2[nd] respondent under Rule 28 (b)(i)(8)(a) of KS&SSR. She thereafter approached this Court in W.P.(C) No.27442/2014 and this Court as per Ext.P9 judgment dated 21.10.2014 directed the 2[nd] respondent to consider the representations within a period of one month. Thereafter, as per Ext.P11 order dated 7.2.2015 the 2[nd] respondent rejected her representation saying that the petitioner had not completed one year at the time when D.P.C met after she rejoined duty. It was stated that when the confidential reports for the preceding 3 years were not available, it was necessary to submit the 3 W.P(C) No.10184 of 2015-W confidential reports for at least one year, as provided in Rule 28(b)(i)(4a) of KS&SSR. Therefore, it was stated that the petitioner's right can be considered after the confidential reports for one year is placed before the D.P.C. The petitioner filed this writ petition challenging the non inclusion of her name in the select list and the order Ext.P11. 4. The Kerala Water Authority has filed counter affidavit reiterating their stand in Ext.P11 order. According to the respondents, confidential reports for a period of at least one year after re-joining duty was essential for consideration by D.P.C; when the petitioner had not completed one year service after she rejoined duty on 17.12.2013, she was not eligible for consideration by the D.P.C. It is further stated that the petitioner was considered and promoted in the year 2015 when she became eligible. 5. The petitioner relies on the judgments of this Court in **Vishnu Namboothiri v. State of Kerala** [2000 (3) KLT 627 and **Shobanakumar v. State of Kerala** [2004 2 KLT 755] in support of her claim that completion of one year is not necessary after rejoining duty for the purpose of considering her for promotion. 6. Heard the learned counsel appearing for the petitioner as well 4 W.P(C) No.10184 of 2015-W ## as the learned Standing Counsel. ## 7. Rule 28(b)(i)(4a) provides as follows: “28(b)(i) Promotion and appointment by transfer according to merit and ability:-- xxxx xxxxx xxxxx xxxxx xxxx xxxx xxxx 4(a) Where confidential reports for the three years mentioned in subclause (4) are not available in respect of an officer who was under suspension but has been reinstated or who was or is on long leave the suitability of the officer shall be assessed-- (i) in the case of an officer who has been reinstated after suspension fully exonerating him of the charges or in the case of an officer [who was or is on long leave], on the basis of the confidential reports for a period of three years excluding the period during which the officer was under suspension or on long leave or is on long leave, as the case may be preceding the date of the meeting and if the Confidential Reports for the said period are not available on the basis of the Confidential Report for the one year immediately after reinstatement or, as the case may be, immediately after rejoining duty after leave; (ii) in the case of an Officer who has been reinstated after suspension imposing a penalty, on the basis of the confidential reports for the period after reinstatement (which shall not be less than one year).” The suitability of an officer who was on long leave is to be assessed on the basis of confidential reports for a period of 3 years preceding the meeting. In the case of an officer who availed long leave, the confidential reports for the preceding three years shall be before she entered on long leave, if 3 year period is available. It is only in a case when such confidential reports for the 3 year period before she availed long leave are not available, that the confidential reports for one year after rejoining duty is to be insisted. 8. In the present case the respondents do not have a case that the petitioner did not have 3 years confidential reports. Their contention is that W.P(C) No.10184 of 2015-W 5 confidential reports are not available for the 3 years preceding the meeting of DPC. Petitioner's promotion as Assistant Executive Engineer was from 5.1.2002. She had completed her probation on 8.1.2003. She availed leave after completion of about 3 years and 7 months of her promotion as Assistant Executive Engineer. The learned Standing Counsel argued that she had not completed 3 years service after she completed probation and therefore she is not eligible for promotion. But no rule is pointed out which insists three years' service after probation, either for the purpose of consideration by the D.P.C, or for promotion as Executive Engineer. There is no provision of law that the service rendered prior to declaration of probation shall not be considered for the purpose of promotion. 9. In the judgments in **Vishnu Namboodiri** 's case ( _supra_ ) and in **Shobhakumar** 's case ( _supra_ ), this Court has, after interpreting the provisions contained in Rule 28(b)(i)(4a), held that an officer who rejoined after long leave need not wait for a period of one year and that the eligibility for promotion shall be considered on the basis of the confidential reports for a period of 3 years immediately before one availed leave. Those judgments hold the field even now. Therefore, going by the dictum laid down in those decisions, the supercession of the petitioner was unsustainable. The order W.P(C) No.10184 of 2015-W 6 Ext.P11 rejecting the claim of the petitioner is unsustainable, as the respondents have not looked into the confidential reports or even its availability before she entered on leave without allowance. The petitioner was entitled to be promoted in preference to her juniors in Exts.P3, P4 as well as Ext.P6. In the light of her position in the seniority list, the petitioner was liable to be included as Sl.No.2 in the select list above the 4[th] respondent. 10. Even though notice was ordered and sent to respondents 4 to 12, who were granted promotion superseding the petitioner, none of them have entered appearance. In the above circumstances, the supercession of the petitioner in Exts.P3 and P4 and her non-inclusion in the select list Ext.P6 and the order Ext.P11 are quashed. The official respondents are directed to convene an adhoc D.P.C to consider the case of the petitioner based on the confidential reports for a period of 3 years prior to her entering on long leave, i.e, prior to 31.08.2005. Based on such consideration the select list of Assistant Executive Engineers for the year 2014 shall be reviewed and revised including the petitioner as Sl.No.2. Thereafter she shall be granted notional promotion with effect from the date on which the 4[th] respondent was granted 7 W.P(C) No.10184 of 2015-W promotion. The petitioner shall be entitled to all consequential benefits except for pay and allowances. All such benefits shall be disbursed to her within a period of 4 months from the date of receipt of a copy of the judgment. The writ petition is accordingly allowed. Sd/- _**(P.V.ASHA, JUDGE)**_ _rtr/_