NEELAKANTAN & BROS. CONSTRUCTION v. SUPERINTENDING ENGINEER, SALEM & ORS.

Case / Petition Number:
Special Leave Petition (Civil) Nos. 11650-58 of 1987
Neutral Citation:1988 Supp. 2 S.C.R.

Case Synopsis & Summary

Neelakantan & Bros. Construction v. Superintending Engineer, Salem and Others concerns arbitration invoked under the Arbitration Act, 1940. A construction firm undertook widening and strengthening pavements on National Highway No. 7 between Madurai and Kanyakumari, divided into fourteen reaches, with fourteen separate contracts. The Superintending Engineer of the Salem circle referred the disputes to arbitration and the parties filed statements and evidence. Before the adjudication could be completed, the initial arbitrator was transferred and his successor-in-office assumed the task with knowledge, consent, and active participation of the petitioner. Time for a final award could not be met, and an extension was sought and granted by the petitioner. The arbitrator issued an award after time extensions, and the petitioner challenged it under sections 30 and 33 of the Arbitration Act, arguing that the successor lacked jurisdiction to conclude the reference and that natural justice was violated. The District Judge held the successor competent; the High Court affirmed; the Special Leave Petitions were then brought to the Supreme Court. The Court held that where parties acquiesce in the appointment or participate with knowledge of the circumstances, they are precluded from challenging the appointment as invalidating subsequent proceedings. The Court rejected arguments of natural justice violation in this factual matrix and emphasized that, absent patent legal error or gross misstatement leading to miscarriage of justice, the award remains unassailable. Consequently, the petitions were dismissed and the award stood.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Sabyasachi Mukharji
  • S. Ranganathan
Judgment Date
1988-08-16
Court Decision / Holding
Special Leave Petitions dismissed; the award stood.
Final Disposition
Special Leave Petitions dismissed; the award is not interfered with and stands as valid.

Parties to the Case

Appellants / Petitioners

  • Neelakantan & Bros. Construction

Respondents

  • Superintending Engineer, National Highways, Salem and Others

Legal Representation & Advocates

Counsels for Petitioners

  • • A.K. Sen
  • • V. Krishnamurthy
  • • V. Balachandran

Counsels for Respondents

  • • A. V. Rangam

Provisions of Law Cited

Arbitration Act, 1940 – Section 2Arbitration Act, 1940 – Section 20Arbitration Act, 1940 – Section 30Arbitration Act, 1940 – Section 33

Legal Doctrines & Maxims

  • Acquiescence in appointment defeats subsequent objections to the validity of the appointment.
  • Attending and taking part in proceedings with full knowledge of the facts equates to acquiescence.
  • No appeal from the verdict of the arbitrator; the Court cannot review, or correct, the arbitrator’s award in the absence of patent error or gross misstatement of law or fact.
  • Unless there is patent mistake of law and gross misstatement of facts resulting in miscarriage of justice or in equity, the award remains unassailable.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contended that once an arbitrator had entered into reference, the successor-in-office had no jurisdiction to conclude it, and the award violated the principles of natural justice. They argued there was no fresh agreement, and the change of arbitrator without fresh consent rendered the proceedings invalid, thereby challenging the award.

Contentions of Respondents

The respondents argued that the successor was competent to pass the award; the petitioner had knowledge of the change and participated in proceedings, constituting acquiescence. They submitted that there was no violation of natural justice, that extensions of time were granted with the petitioner’s assent, and that the award should not be interfered with in the absence of patent legal error.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (7)

Case NameCitationTreatmentExplanation
Chowdhury Murtaza Hossein v. Mussumat Bibi Bechunnissa3 I.A. 209PositiveCited for the principle that acquiescence defeats a later objection to appointment, foundational to the court’s reasoning on continued proceedings before a successor arbitrator.
N. Challappan v. Secretary, Kerala State Electricity Board and another[1975] 1 S.C.C. 289PositiveAffirms that acquiescence defeats the right to object at a later stage, supporting the majority view on continued arbitration before a successor.
Prasun Roy v. The Calcutta Metropolitan Development Authority and another[1982] 2 Scale 125PositiveCited in the context of acquiescence and admissibility of subsequent conduct in arbitration proceedings.
Jupiter General Insurance Co. Ltd. v. Corporation of CalcuttaAIR 1956 Cal. 470PositiveUsed to illustrate principles related to natural justice and the conduct of arbitration proceedings.
Champsey Bhara & Company v. Jivrai Ballo Spinning and Weaving Company Ltd.50 I.A. 324PositiveSupports the proposition that no broad review lies against an arbitrator’s award within the statutory framework.
Firm Madanlal Roshanlal Mahajan v. Hukumchand Mills Ltd., Indore[1967] 1 S.C.R. 105PositiveCited for limitations on revisiting arbitrator’s award and the exclusive grounds for interference.
Russell on Arbitration(Ed. 18th/20th)PositiveTreatise cited for general principles on acquiescence and arbitral procedure.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,830 words•~9 min read

In The Court Record

NEELAKANTAN & BROS. CONSTRUCTION v. SUPERINTENDING ENGINEER, SALEM & ORS.

A B D E F NEELAKANTAN & BROS. CONSTRUCTION _v._ SUPERINTENDING ENGINEER, NATIONAL HIGHWAYS, SALEM & ORS. G AUGUST 16, 1988 [SABYASACHI MUKHARJI AND S. RANGANATHAN, JJ.] _Arbitration Act,_ _1940:_ _Sections_ 2, _20,_ _30 and 33-Arbitration-_ _Statements_ _of parties filed-Evidence adduced-Change of Arbitrator_ _-Parties did not protest and participate_ _in proceedings before succes-_ _sor-Whether amounts_ _to_ _acquiescence-Appointment of successor-_ _Whether_ _can_ _be_ _challenged_ _as_ _invalidating_ _proceedings-Award-_ _Unreasoned-No_ _legal_ _proposition made-Whether can_ _be_ _interfered_ _with._ The petitioner-Construction lirm entered into agreements with respondent No. 3, Superintending Engineer of a Circle for execution of certain civil works. Respondent No. I-Superintending Engineer of another Circle entered into a reference for arbitration and parties liled statements and adduced evidence. Before the adjudication was com pleted, respondent No. 1 was transferred and his successor-in-office entered into the task of adjudication with the knowledge, consent and active participation of the petitioner in the proceeding. Since the arbitrator could not complete the award within time, be sought exten· sion of time by a letter to the petitioner and the petitioner agreed to such extension by a letter. The petitioner did not ask for any further or fresh opportunity for adducing any evidence. Thereafter, the arbitrator made his award. The petitioner challenged the award under ss. 30 and 33 of the Arbitration Act, 1940 before the District Judge on the ground that the previous arbitrat11r having entered into reference, his successor-inoflice had no jurisdiction to conclude it and the award was violative of principles of natural justice. The District Judge held that the successor-in-office to the origill1"'' arbitrator was competent to pass the award. Upholding this, the High Court rejected the challenge to the award. Hence the petitioner liled the Special L~ave Petition in this Court contending that once an arbitrator bad entered into a reference, the next incumbent could not conclude the H said arbitration proceedings without a fresh agreement, that there was 462 NEELAKANTAN _v._ SUPT1JG ENGINEER 463 violation of principles of natural justice and that the award was bad. A Dismissing the Special Leave Petition, HELD: I. If the parties to the reference either agree before-hand to the method of appointment, or afterwards acquiesce in the appointment ·made, with full knowledge of all the circumstances, they B will be precluded from objecting to such_ appointment as invalidating subsequent proceedings. Attending and taking part in the proceedings with full knowledge of the relevant fact will amount to such acquiescence. [465G] _N. Challappan_ v. _Secretary, Kera/a State Electricity Board and_ C 1 _another,_ [1975] 1 S.C.C. 289 relied on. _Chowdhury Murtaza Hossein_ v. _Mussumat Bibi Bechunnissa,_ 3 I.A. 209 and _Prasun_ _Roy_ v. _The Calcutta Metropolitan Development_ _Authority and another,_ [1982] 2 Scale 125, referred to. _Russell on Arbitration,_ 18th Edition/20th Edition, pages 105/432435, referred to. In the instant case, the petitioner had full knowledge of the change of the new incumbent. Thus, the petitioner had knowledge of the alleged the iitcumbent and did not protest and proceedings went on before - . defect, and had acquiesced in the proceedings before the successor. There was; therefore, no violation of principles of natural justice. [465C, Fl 2. Unless there was a patent mistake of law and gross misstatement of facts resulting in miscarriage of justice or of equity, the award remalris unassaila6fo. [466C] _Champsey Bhara_ & _Company_ v. _Jivrai Ballo Spinning and_ _Weaving Company Ltd.,_ 50 I.A. 324 and _Firm Madan/al Roshanlal_ _Mahajan_ v. _Hukumchand Mills Ltd., Indore,_ [1967] I S.C.R. 105, referred to. / In the instant case, the arbitrator gave no reason for tlie award. There is no legal proposition which is the basis of the award, far less any legal proposition which is erroneous. There is no appeal from the ver**dict of the arbitrator. The Court cannot review, in such circumstances,** the award and correct any mistake in the adjudication by the arbi D E F G trator. [466D] H A B ## c 464 SUPREME COURT REPORTS [1988] Supp. 2 S.C.R. 3. In the facts and circumstances of the case, the award is unassailable. The High Court was right in upholding the District Judge's dismissal of the challenge to the award. [466F] CIVIL APPELLATE JURISDICTION: Special Leave Petition (Civil) Nos. 11650-58 of 1987. From the Judgment and Order dated 31.7.1987 of the Madras High Court in Appeal against" Order Nos. 541 to 544 and 558 to 562 of 1981. A.K. Sen, V. Krishnamurthy and V. Balachandran for the Petitioner. A. V. Rangam for the Respondents. The Judgment of the Court was delivered by D SABYASACHI MUKHARJI, J. These are pet1t10ns under Article 136 of the Constitution seeking leave to appeal against the judgment and order of the High Court of Madras dated 3 lst July, 1987. The petitioner company undertook the work of widening and strengthening pavements in National Highway No. 7, Madurai-Kanyakumari Road from Reaches 37.6 k.m. to 2'13 k.m. on the MaduraiE Kanyakumari Road and the work was divided into fourteen Reaches and 14 separate agreements were entered into between the petitioner and the Superintending Engineer, National Highways, Tirunelveli, respondent No. 3 to the present petitions. There is not much dispute on this point. At the relevant time, according to the petitioner, the Superintending Engineer, National Highways, Salem was one Thim F Mohan. He entered into reference. He took up the matter for arbitration and called for st8ctements from the parties. Statements were filed before him and evidence were also adduced before him. But before he could complete the adjudication he was transferred and was succeeded by one Thim J.R. Cornelius, Superintending Engineer. The contention of the petitioner in this case was that he had no jurisdiction to G proceed and complete the arbitration. It appears, however, that he entered into the task of adjudication with the knowledge and consent of the petitioner and the,petitioner had participated actively in the proceeding before him. From the notices served by Thiru Mohan previously and subsequently by Thim Cornelius, it is apparent that the petitioner had knowledge of the change of the incumbent of the H Superintending· Engineer who was to arbitrate in the matter.. This is NEELAKANTAN _v._ SUPTDG ENGINEER IMUKHARJI, J.] 465 evident from the documents appearing at pages 164 and 165 of the present paper book and both the parties had notice of the succession in office. The arbitrator could not complete the award within time :and there was need for extension of time. He wrote a lttter to the petitioner on 1st May, 1977 stating "extension of time was necessary to pass orders on reference and hearing has been concluded". In reply to that letter on 11th May, 1977 the petitioner agreed to such extension. The petitioner was content with that situation and never asked for any further or fresh opportunity either to make any submission or to adduce any evidence_. ln that light the arbitrator has made the award. This was challenged before the learned District Judge by means of a suit under sectidns. 30 and 33 of the Arbitration Act, 1940 that the previous arbitrator Thiru Mohan having entered into reference and Thiru Cornelius ·had no jurisdiction to conclude. It was violative of the principles of natural justice, it was submitted. But as mentioned hereinbefore, the petitioner had knowledge of the change of the incumbent.. He did not protest arid the proceedings went on before Thiru Cornelius. - It is apparendrom the terms of the agreement between the parties that the Superintending Engineer of the Circle for the time being was the named arbitrator. The learned District Judge held that Thiru _Cornelius was competent to pass the award. The High Court also upheld that and rejected the challenge to the award on this ground made by the petitioner. A B ## c D Shr(A:·K. Sen, _learned counsel for the petitioners, urged before us E that once an arbitrator had entered into reference, the next incumbent could not conclude the said arbitration proceeding without a fresh agreement. In the facts of this case, as the petitioner had knowledge of _the alleged defect arid bad acq4iesced in the proceedings before the successor, namely, Thiru .Cornelius;· we are of the opinion; that this contention of Shri Sen cannot be entertained. It was contepded that F !here was violation ol.the principles of natural justice. This objection cannot be entertained. If .the parties to the reference either agree -beforehand to the method of appoiritni_ent, or afterwards acquiescence in the appointment made, with full knowledge of all the.circumstances, they will be precluded from objecting to such appointment as invalidating subsequent proceedings. Attend1ng and taking part in the pro- G ceedings with full knowledge _of the relevant fact will amount to such_:_ acquiescence, explains Russell· on Arbitration. 18th Edition a.t page 105. This was stated by the Judicial Committee long ago in _Chow4hury_ _Murtaza Hossem_ v'- _MUssilmat Bibi;Bechunnissa,_ 3 i.A. 209. See also the observations of P.B. Mukharji;J. in the decision of the Calcutta Hig_h Cour-t _in.Jupiier General lnsurante_ _Co.__ _Ltd._ v. _Corporation_ _of_ H 466 SUPREME COURT REPORTS [1988] Supp. 2 S.C.R. A _Calcutta,_ A.I.R. 1956 Calcutta 470 at 472. This Court held in _N._ _Challappan_ v. _Secretary, Kera/a State Electricity Board and another,_ [1975] 1 S.C.C. 289 that acquiescence defeated the right of the appellant at a latter stage. See also the observations of this Court in _Prasun_ _Roy_ v. _The Calcutta Metropolitan Development Authority and another,_ B [1982] 2 Scale 125. See Russell on Arbitration, 20th Edition, pages 432-435. Shri Sen contended that no notice was issu.ed after the appointment of the new arbitrator. This was factually incorrect, as mentioned before. Then, it was said that the award was bad as it did not consider all the claims. This also cannot be entertained. It must be assumed that the arbitrator had considered all the evidence adduced before him. There was no disregard of any principle of law. There was C nothing to indicate that the arbitrator had not considered all the evidence. Unless there was a patent mistake of law and gross misstate-. ment of facts resulting in miscarriage of justice or of equity, the award remains unassailable. In this case the arbitrator gave no reason for the award. There is no legal proposition which is the basis of the award, D far less any legal proposition which is erroneous. There is no appeal from the verdict of the arbitrator. The Court cannot review, in such circumstances, the award and correct any mistake in the adjudication by the arbitrator-See _Champsey Bhara_ _&_ _Company_ v. _Jivray Balla_ _Spinning and Weaving Company Ltd.,_ 50 I.A. 324 and the observations of Bachawat, J. in _Firm Madan/al Roshanlal Mahajan_ v. _Hukumchand Mills Ltd., Indore,_ [1967] 1 S.C.R. 105 of this Court. E F In the facts and circumstances of the case, in our opinion, this award is not assailable. The High Court was, therefore, right in upholding the learned District Judge's dismissal of the challenge to the award. These petitions, therefore, fail and are dismissed accordingly, without any order as to costs. N.P.V. Petitions dismissed. # (
End of Judgment Record
Browse All Supreme Court of India (1988) Decisions
1988-10-05

GIRJA SHANKAR TIWARI AND ANR. v. HIRDAY RANJAN CHAKRABORTY AND ANR.

This case concerns a dispute over occupancy and vacancy of a shop premises at Rae Bareli under the U.P. Urban Buildings (Regulation of Letting, Rent and Eviction) Act, 1972. The landlord’s successors claimed the premises had fallen vacant and sought allotment under Section 12, which deems vacancy if a landlord ceases to occupy the building or allows non-family occupancy. The premises had been rented originally to M/s Dhacca Swastic Aushadhalaya in 1946/1947. After its dissolution, an employee of the Aushadhalaya, Hirday Ranjan Chakraborty, continued occupying the premises and paid rent in the name of the Aushadhalaya, not in his own name. The Rent Controller found vacancy, and a Rent Control appeal upheld the controller’s view. The Allahabad High Court reversed, treating the Aushadhalaya as the tenant and the rent paid in its name as rent on behalf of Chakraborty, effectively denying deemed vacancy. The Supreme Court reversed the High Court, holding that Chakraborty’s occupation was by someone other than the tenant and that the deemed vacancy under Section 12 had occurred even though the building was not physically vacant. The Rent Controller’s order was restored, and the High Court’s decision set aside, with the appeal allowed.

1988-09-09

U.P. Bhoodan Yagna Samiti v. Braj Kishore

This appeal concerns land grants under the Uttar Pradesh Bhoodan Yagna Act, 1952 (Sections 14 and 15) made in 1968 to respondents described as traders living in Kanpur. The Additional Collector cancelled these pattas in 1976 on grounds that the respondents did not reside in the village where the plots were located, did not belong to the category of landless persons, and that the grants lacked government approval. The Allahabad High Court, in Misc. Writ Petitions, quashed the cancellation order and upheld the grants, holding that the respondents fell within the definition of “landless persons,” notwithstanding their urban residence and business. The UP Bhoodan Yagna Samiti challenged this in a Civil Appeal before the Supreme Court. The Court emphasizes interpreting the statute against its background and the philosophy of the Bhoodan movement, noting reliance on Vinoba Bhave and Jaya Prakash Narayan, and discusses the 1975 Amendment substituting “landless agricultural labourers” for “landless persons” in Section 14. It concludes that grants were to be made in accordance with the Bhoodan Scheme and to landless agricultural labourers resident in the village whose livelihood is agriculture; hence the basis for the amendment and its thrust to correct interpretation. Consequently, the appeals are allowed, the High Court’s judgment is set aside, the Additional Collector’s orders are restored, and costs are awarded to the appellants.

1988-08-16

A.S. GOKHALE v. R.T. OFFICER

Achyut Shivram Gokhale challenged the Bombay Regional Transport Authority’s refusal to issue a five‑day special permit under section 63(6) of the Motor Vehicles Act for the route Bombay–Shirdi, on grounds that the Maharashtra government had issued a scheme (under section 68‑D(3)) conferring exclusive contract carriage rights on the Maharashtra State Road Transport Corporation (MSRTC). The scheme listed seven saved categories and operated to exclude others from contract carriage on those routes, but the appellant argued that such a scheme does not bar special permits under section 63(6). The Regional Transport Authority had demanded a No Objection Certificate from MSRTC, and the Maharashtra State Transport Appellate Tribunal had held that a special permit is not a contract carriage permit and the scheme does not prevent issuing such permits. The Bombay High Court, however, set aside the Tribunal’s view. The Supreme Court clarified the law: a contract carriage permit under section 51 and a special permit under section 63(6) are distinct, though a special permit may share some features with a contract carriage permit. It held that the scheme’s exclusivity pertains to contract carriages under section 51 and does not bar special permits under section 63(6). It also distinguished Andhra Pradesh and Karnataka authorities, and found Adarsh Travels Bus Service distinguishable. The result is that a special permit can be issued notwithstanding the exclusive scheme, and the No Objection Certificate requirement was unwarranted.

1988-05-11

Bharat Petroleum Staff v. Bharat Petroleum Corporation Ltd.

This Supreme Court judgment concerns the pension rights of erstwhile Burmah Shell management staff following nationalisation under the Burmah Shell (Acquisition of Undertakings in India) Act, 1976, and their subsequent transfer to Bharat Petroleum Corporation Limited (the government company). The petitioners, i.e., the Burmah Shell management staff pensioners, sought two reliefs: (i) restoration of the commuted pension after 15 years as laid down in the Supreme Court’s Common Cause decision (AIR 1987 SC 210); and (ii) adequate escalation in pension to protect purchasing power given the rupee’s depreciation and rising living costs. The respondents argued that Burmah Shell’s pension scheme was funded, that the Common Cause decision could not be automatically extended to a public sector undertaking, and that any escalation would require funds beyond the existing pension fund, possibly necessitating government support. The Court held that the petitioners were entitled to a pension hike at the same rate as Hindustan Petroleum Corporation, directing the respondent to implement the increase from May 1, 1988 and to disburse the additional pension by July 31, 1988. It, however, reserved adjudication on restoration of commuted pensions, noting that issue was not to be decided in this petition. The judgment underscores the state’s welfare liability and judicial notice of the rupee’s devaluation, while ensuring a timely remedy for the petitioners.