National Highways Authority of India v. Gayatri Jhansi Roadways Limited
Case Synopsis & Summary
This civil appeal centers on the proper regime for fixing arbitrator fees under the Arbitration and Conciliation Act, 1996, after the 2015 amendments and subsequent policy Circulars. The dispute arose from a contract between the National Highways Authority of India (NHAI) and Gayatri Jhansi Roadways Limited, which contained a detailed fee schedule for arbitrators. When disputes arose, the Arbitral Tribunal began applying the 2017 circular replacing the earlier 2004 schedule, and both sides challenged this approach. A Delhi High Court decision (Gayatri Jhansi Roadways Limited) had held that the Fourth Schedule would govern arbitrator fees, a view later characterized by the Supreme Court as misapplied. The judgments traverse sections 31(8) and 31A, clarifying that costs are governed by those provisions but not to the extent of directly overriding pre-existing fee structures unless the legislative framework expressly prescribes so. The Supreme Court, with R. F. Nariman and Surya Kant, ultimately held that the 01.06.2017 circular would operate, superseding the Fourth Schedule and old fee arrangements; arbitrators may charge ratified amounts under the updated schedule. It set aside the High Court judgment, noting that termination of the arbitrators’ mandate was unwarranted, and directed the arbitration to proceed expeditiously, granting up to one year for delivering the award. The decision clarifies the interaction between party-agreed fee terms and statutory cost provisions in the post-amendment regime.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- R. F. Nariman
- Surya Kant
- Judgment Date
- 2019-07-10
- Court Decision / Holding
- Appeals allowed. The impugned judgments are set aside. The arbitrators are directed to proceed with the arbitration as expeditiously as possible, with a time extension of one year for delivering the arbitral award. Civil Appeal No. 5383 of 2019: the impugned judgment is set aside; the appeal stands disposed of. Civil Appeal No. 5384 of 2019: the judgment in the related matter is set aside; the final award remains enforceable. The decision confirms that the 01.06.2017 circular governs arbitrator fees, superseding the Fourth Schedule, and disapproves the earlier Gayatri Jhansi Roadways reliance on the Fourth Schedule banked on by the Delhi High Court.
- Final Disposition
- Appeals disposed of; impugned judgments set aside; arbitrators to proceed with arbitration; time extended to one year for delivery of award.
Parties to the Case
Appellants / Petitioners
- National Highways Authority of India
Respondents
- Gayatri Jhansi Roadways Limited
Legal Representation & Advocates
Counsels for Petitioners
- • P. S. Nariman
- • Ms. Meenakshi Arora
- • Manish K. Bishnoi
- • Archit Gupta
- • Prashant Kumar
- • Ms. Awantika Manohar
- • M/s. AP & J Chambers
Counsels for Respondents
- • Bharat Singh
- • Balendu Shekar
- • Ms. Sindoora G VNL
- • Rahul Tanwani
- • Santosh Kumar - I
- • Kaushik Laik
- • Angad Mehta
- • P. S. Sudheer
- • Ms. Anne Mathew
- • Sayid Marzook Bafaki
Provisions of Law Cited
Legal Doctrines & Maxims
- de jure unable to perform
- per incuriam
Submissions & Arguments
Contentions of Appellants / Petitioners
The applicants argued that the arbitrators’ remuneration and expenses were fixed by the parties’ contract and that the 2017 policy circular should not override an agreement already making the fee structure. They contended that Section 31(8) read with Section 31A pertains to costs, not to contracts where a fee structure has already been agreed, and that the Delhi High Court’s Gayatri Jhansi Roadways Limited decision misapplied the law by effectively mandating the Fourth Schedule irrespective of the agreement between the parties. They urged that any modification should arise from express legislative change, not from mid-course circulars, and that the Section 14 application to terminate the arbitrators was unfounded.
Contentions of Respondents
The respondents contended that the Fourth Schedule under the amended Act governs arbitrator fees and that policy updates (the 01.06.2017 circular) were valid and should apply, superseding earlier schedules. They relied on the law as interpreted by the Delhi High Court in Gayatri Jhansi Roadways Limited, arguing that parties cannot contract out of the applicable fee regime, especially where costs are concerned. They maintained that the Arbitral Tribunal’s adherence to the Fourth Schedule reflected the proper legal framework, and that the High Court’s ruling should not stand. They also pressed that the tribunal’s orders should be treated as consistent with the amended statute and policy changes.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (1)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Gayatri Jhansi Roadways Limited | — | Overruled | The Court states that the declaration of law by the learned Single Judge in Gayatri Jhansi Roadways Limited is not a correct view of the law, effectively overruling the proposition that 31(8)/31A would directly govern contracts with pre-existing fee structures and mandating Fourth Schedule application. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
National Highways Authority of India v. Gayatri Jhansi Roadways Limited
Related Decisions & Precedents from Supreme Court of India (2019)
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.
STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.
This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.
PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.
Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).
RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.
Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.