NARENDRA & ORS. v. STATE OF UTTAR PRADESH & ORS.

Case / Petition Number:
Civil Appeal Nos. 10429-10430 of 2017

Case Synopsis & Summary

This appeal arises from the compulsory acquisition of land in Village Makanpur, Ghaziabad, under the Land Acquisition Act, 1894, for development by the Ghaziabad Development Authority (GDA). An award of Rs. 50 per square yard was made in 1990, with a reference court increasing it to Rs. 90 per square yard in 1999; landowners pursued further enhancement. While other villagers under the same notification were later awarded Rs. 297 per square yard, the appellants’ case before the High Court was capped at Rs. 115 per square yard, on the ground that they claimed that amount and had paid court fees accordingly. The pivotal question is whether the High Court was precluded from granting the higher Rs. 297 per square yard to these appellants, who were similarly situated to others. The Court affirms that it is the duty of the court to award just and fair compensation based on true market value and other relevant factors, irrespective of the rate claimed, and that there is no cap on the maximum compensation that can be awarded. Citing Ashok Kumar, Bhag Singh, Krishi Utpadan Mandi Samiti, Bhimasha and others, the judgment endorses higher compensation where warranted, aided by sections 25 (amended), 28A and the social justice objective. Consequently, the appeals are allowed and the appellants are entitled to Rs. 297 per square yard, with necessary adjustments and costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • A.K. Sikri
  • Ashok Bhushan
Judgment Date
2017-09-11
Court Decision / Holding
Appeal is allowed. The appellants are entitled to compensation at Rs. 297 per square yard for lands under the same notification, with the difference in amount and related statutory benefits under the Act to be calculated and paid within three months from the date of the judgment. The appellants must make good the deficiency in court fees, if any, before the High Court. Costs of these appeals are awarded in favour of the appellants.
Final Disposition
Appeal allowed; compensation enhanced to Rs. 297 per square yard for appellants; adjustments of difference in compensation and court fees to be made within three months; costs awarded to appellants.

Parties to the Case

Appellants / Petitioners

  • Narendra
  • Others

Respondents

  • State of Uttar Pradesh
  • Ghaziabad Development Authority

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Rohit Kumar Singh, AOR

Counsels for Respondents

  • • Mr. Rakesh Uttamchandra Upadhyay, AOR

Provisions of Law Cited

Section 4(1) of the Land Acquisition Act, 1894Section 6(1) of the Land Acquisition Act, 1894Section 18 of the Land Acquisition Act, 1894Section 25 (amended) of the Land Acquisition Act, 1894Section 28A of the Land Acquisition Act, 1894Section 9 of the Land Acquisition Act, 1894Section 11 of the Land Acquisition Act, 1894

Legal Doctrines & Maxims

  • Justice as Fairness (Rawls)
  • Distributive Justice (Hume)
  • Reflective Equilibrium (Nelson Goodman; elaborated by John Rawls)
  • Purposive interpretation
  • Access to justice
  • Fair treatment of similarly situated landowners

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that the duty of the court is to grant just and fair compensation based on true market value, independent of the rate claimed by the landowner. The 1984 amendment to Section 25 removed the maximum cap, permitting the court to award higher compensation, guided by fair valuation and relevant factors. Relying on Bhag Singh, Bhimasha, Ashok Kumar and Krishi Utpadan Mandi Samiti, they urged that similarly situated landowners under the same notification should receive uniform, fair compensation (Rs. 297 per sq yd), regardless of their pleadings, and invoked Section 28A to redetermine for others. They highlighted precedents such as Pardeep Kumar v. NOIDA demonstrating adherence to fair compensation across acquisitions and the social justice aim of the Act.

Contentions of Respondents

The respondents contended that the appellants had pleaded and paid court fees according to a lower rate, and that the High Court’s limitation to Rs. 115 per sq yd was consistent with ensuring uniform treatment grounded in the pleadings and court-fee considerations. They argued for consistency with the claimed amounts and cautioned against creating divergent outcomes for landowners under the same notification, urging adherence to statutory pleadings and established practices until a final judicial pronouncement. They relied on the principles that punitive or ad hoc deviations undermine predictability and administrative efficiency.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Ashok Kumar and Another v. State of Haryana(2016) 4 SCC 544PositiveUsed to support the proposition that a court must award just and fair compensation based on true market value, irrespective of the claimed amount; no cap on maximum compensation.
Bhag Singh and Ors. v. Union Territory of Chandigarh(1985) 3 SCC 737PositiveHeld that higher compensation than claimed may be awarded in appropriate cases; supports principle of fair valuation beyond pleadings.
Krishi Utpadan Mandi Samiti v. Kanhaiya Lal(2000) 7 SCC 756PositiveAffirms amended Section 25 allows higher compensation than claimed.
Bhimasha v. Special Land Acquisition Officer and Ors.(2008) 10 SCC 797PositiveThree-judge bench endorses the principle that higher compensation can be awarded; reinforces Bhag Singh.
Pardeep Kumar and Others v. NOIDACivil Appeal No. 1506-1517 of 2016PositiveHeld that same enhanced rate (Rs 297) can be awarded in subsequent acquisitions under the same notification; supports uniform fair compensation.
Kashi Ram Case (Ghaziabad Development Authority (supra))Kashi Ram case / Kanshi Ram lineagePositiveUsed as authority for setting the fair rate of Rs 297 per sq yard for lands under the same notification.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,002 words•~19 min read

In The Court Record

NARENDRA & ORS. v. STATE OF UTTAR PRADESH & ORS.

**REPORTABLE** # **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** # **CIVIL APPEAL NOS. 10429-10430 of 2017 (ARISING OUT OF SLP (C) NOS. 2354-2355 OF 2017)** NARENDRA & ORS. .....APPELLANT(S) **VERSUS** STATE OF UTTAR PRADESH & ORS. .....RESPONDENT(S) ## **J U D G M E N T** ## **A.K. SIKRI, J.** Signature Not Verified Digitally signed by BALA PARVATHI Date: 2017.09.12 10:00:04 IST Reason: A very limited, but pertinent, question of law arises for consideration in these appeals. Land of the appellants was acquired by the Government of Uttar Pradesh vide Notification dated 12[th] September, 1986 issued under Section 4(1) of the Land Acquisition Act, 1894 (hereinafter referred to as the ‘Act’). It was followed by the declaration dated 24[th] February, 1988 issued under Section 6(1) of the Act. It may be mentioned that vide the aforesaid Notification, large tracts of land were acquired, belonging to various land owners/villagers of Village Makanpur Paragana Loni, Tehsil - Dadri, District Ghaziabad, Uttar Pradesh for planned development of Vaishali. After the acquisition of this _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 1 of 16**_ land, it was handed over to Ghaziabad Development Authority (for short, ‘GDA’) for development. - 2) The award dated 18[th] January, 1990 was passed by the Special Land Acquisition Officer determining the market value of the acquired land at the rate of Rs. 50 per square yard. The appellants as well as other villagers were not satisfied with the rates so fixed and, therefore, sought the reference under Section 18 of the Act. Matter was referred to the Additional District Judge, Ghaziabad for determination of market value of the acquired land. Reference court, vide its judgment and order dated 19[th] April, 1999, increased the rate of compensation from Rs.50/- per sq. yards to Rs.90/- per square yards. Even this increase in the compensation was not to the satisfaction of the land owners. Various appeals came to be filed. Appeals were also filed by these appellants claiming that the compensation be enhanced to Rs. 115/- per square yards. Some of the other land owners whose lands were acquired, however, had claimed higher compensation. The first batch of appeals filed by others was decided by the High Court by judgment dated 13[th] November, 2014. The High Court found merit in those appeals and fixed the compensation at the rate of Rs.297/- per square yards. When the appeals of the appellants herein came up for hearing before the _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 2 of 16**_ High Court, the High Court took note of its earlier judgment and accepted the fact that the land of the appellants was acquired by the same Notification vide which land of others was acquired wherein the High Court had awarded the compensation at the rate of Rs.297/- per square yards. Notwithstanding the same, insofar as the appellants are concerned, the High Court has limited the compensation to Rs.115/- per square yards because of the reasoning that the appellant had demanded compensation at that rate only and had paid the court fees also accordingly. Therefore, opined the High Court, it was difficult to allow compensation at a rate higher than the rate claimed by the appellants. - 3) In this backdrop, the question that falls for consideration is as to whether the High Court was precluded from granting compensation at the rate of Rs.297/- per square yards which was the rate of compensation awarded to other farmers of the said village whose lands were acquired under the same Notification and were similarly situated. - 4) Before proceeding to discuss the aforesaid question, we may mention that insofar as the order of the High Court fixing compensation at the rate of Rs.297/- per square yards is concerned, special leave petition was filed by the GDA which was _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 3 of 16**_ dismissed by this Court. Review thereof was sought which was also dismissed. Even the curative petition filed by the GDA came to be dismissed. Thus, the order of the High Court granting compensation at the rate of Rs.297/- per square yards in respect of these acquisition proceedings has attained finality. 5) After hearing the counsel for the parties, we are of the opinion that the issue has already been settled by this Court in _**Ashok Kumar and Another**_ vs. _**State of Haryana[1]**_ wherein it is held that it is the duty of the Court to award just and fair compensation taking into consideration true market value and other relevant factors, irrespective of claim made by the land owner and there is no cap on the maximum rate of compensation that can be awarded by the court and the courts are not restricted to awarding only that amount that has been claimed by the land owners/applicants in their application before it. The relevant paras of this judgment is quoted as under: “6. Prior to amendment Act 68 of 1984, the amount of compensation that could be awarded by the Court was limited to the amount claimed by the applicant. Section 25 read as under- Section 25. Rules as to amount of compensation-(1) When the applicant has made a claim to compensation, pursuant to any notice given Under Section 9, the amount awarded to him by the court shall not exceed the amount so claimed or be less 1 (2016) 4 SCC 544 _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 4 of 16**_ than the amount awarded by the Collector Under Section 11. (2) When the applicant has refused to make such claim or has omitted without sufficient reason (to be allowed by the Judge) to make such claim, the amount awarded by the court shall in no case exceed the amount awarded by the Collector. (3) When the applicant has omitted for a sufficient reason (to be allowed by the Judge) to make such claim, the amount awarded to him by the court shall not be less than, and may exceed, the amount awarded by the Collector. The amended Section 25 reads as under: “Section 25. Amount of compensation awarded by Court not to be lower than the amount awarded by the Collector- The amount of compensation awarded by the Court shall not be less than the amount awarded by the Collector under Section 11.” The amendment has come into effect on 24.09.1984. 7. The pre-amended provision put a cap on the maximum; the compensation by court should not be beyond the amount claimed. The amendment in 1984, on the contrary, put a cap on the minimum; compensation cannot be less that what was awarded by the Land Acquisition Collector. The cap on maximum having been expressly omitted, and the cap that is put is only on minimum, it is clear that the amount of compensation that a court can award is no longer restricted to the amount claimed by the applicant. It is the duty of the Court to award just and fair compensation taking into consideration the true market value and other relevant factors, irrespective of the claim made by the owner. ## 8. xxx xxx xxx 9. In Bhag Singh and Ors. v. Union Territory of Chandigarh [(1985) 3 SCC 737], this Court held that there may be situations where the amount higher than _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 5 of 16**_ claimed may be awarded to the claimant. The Court observed- “3. ... It must be remembered that this was not a dispute between two private citizens where it would be quite just and legitimate to confine the claimant to the claim made by him and not to award him any higher amount than that claimed though even in such a case there may be situations where an amount higher than that claimed can be awarded to the claimant as for instance where an amount is claimed as due at the foot of an account. Here was a claim made by the Appellants against the State Government for compensation for acquisition of their land and under the law, the State was bound to pay to the Appellants compensation on the basis of the market value of the land acquired and if according to the judgments of the learned single Judge and the Division Bench, the market value of the land acquired was higher than that awarded by the Land Acquisition Collector or the Additional District Judge, there is no reason why the Appellants should have been denied the benefit of payment of the market value so determined. To deny this benefit to the Appellants would tantamount to permitting the State Government to acquire the land of the Appellants on payment of less than the true market value. There may be cases where, as for instance, under' agrarian reform legislation, the holder of land may, legitimately, as a matter of social justice with a view to eliminating concentration of land in the hands of a few and bringing about its equitable distribution, be deprived of land which is not being personally cultivated by him or which is in excess of the ceiling area with payment of little compensation or no compensation at all, but where land is acquired under the Land Acquisition Act, 1894, it would not be fair and just to deprive the holder of his land without payment of the true market value when the law, in so many terms, declares that he shall be paid such _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 6 of 16**_ market value.... 10. In Krishi Utpadan Mandi Samiti v. Kanhaiya Lal [(2000) 7 SCC 756], this Court held that under the amended provisions of Section 25 of the Act, the Court can grant a higher compensation than claimed by the applicant in his pleadings- 11. Further, in Bhimasha v. Special Land Acquisition Officer and Ors. [(2008) 10 SCC 797], a three-Judge bench reiterated the principle in Bhag Singh (supra) and rejected the contention that a higher compensation than claimed by the owner in his pleadings cannot be awarded by the Court..... (Emphasis supplied)” ## 6) Matter can be looked into from another angle as well, viz., in the light of the spirit contained in Section 28A of the Act. This provision reads as under: “(1) Wherein an award under this Part, the Court allows to the applicant any amount of compensation in excess of the amount awarded by the Collector under Section II, the persons interested in all the other land covered by the same notification under Section 4, sub-section (1) and who are also aggrieved by the award of the Collector may, notwithstanding that they had not made an application to the Collector under Section 18, by written application to the Collector within three months from the date of the award of the court require that the amount of compensation payable to them may be re-determined on the basis of the amount of compensation awarded by the court......” It transpires from the bare reading of the aforesaid provision that even in the absence of exemplars and other evidence, higher compensation can be allowed for others whose land was acquired under the same Notification. _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 7 of 16**_ - 7) The purpose and objective behind the aforesaid provision is salutary in nature. It is kept in mind that those land owners who are agriculturist in most of the cases, and whose land is acquired for public purpose should get fair compensation. Once a particular rate of compensation is judicially determined, which becomes a fair compensation, benefit thereof is to be given even to those who could not approach the court. It is with this aim the aforesaid provision is incorporated by the Legislature. Once we keep the aforesaid purpose in mind, the mere fact that the compensation which was claimed by some of the villagers was at lesser rate than the compensation which is ultimately determined to be fair compensation, should not be a ground to deny such persons appropriate and fair compensation on the ground that they claimed compensation at a lesser rate. In such cases, strict rule of pleadings are not be made applicable and rendering substantial justice to the parties has to be the paramount consideration. It is to be kept in mind that in the matter of compulsory acquisition of lands by the Government, the villagers whose land gets acquired are not willing parties. It was not their voluntary act to sell of their land **.** They were compelled to give the land to the State for public purpose. For this purpose, the consideration which is to be paid to them is also not of their _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 8 of 16**_ choice. On the contrary, as per the scheme of the Act, the rate at which compensation should be paid to the persons divested of their land is determined by the Land Acquisition Collector. Scheme further provides that his determination is subject to judicial scrutiny in the form of reference to the District Judge and appeal to the High Court etc. In order to ensure that the land owners are given proper compensation, the Act provides for ‘fair compensation’. Once such a fair compensation is determined judicially, all land owners whose land was taken away by the same Notification should become the beneficiary thereof. Not only it is an aspect of good governance, failing to do so would also amount to discrimination by giving different treatment to the persons though identically situated. On technical grounds, like the one adopted by the High Court in the impugned judgment, this fair treatment cannot be denied to them. - 8) No doubt the judicial system that prevails is based on adversarial form of adjudication. At the same time, recognising the demerits and limitations of adversarial litigation, elements of social context adjudication are brought into the decision making process, particularly, when it comes to administering justice to the marginalised section of the society. - 9) History demonstrates that various forms of conflict resolution _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 9 of 16**_ have been institutionalized from time to time. Presently, in almost all civil societies, disputes are resolved through courts, though the judicial system may be different in different jurisdictions. Traditionally, our justice delivery system is adversarial in nature. Of late, capabilities and method of this adversarial justice system are questioned and a feeling of disillusionment and frustration is witnessed among the people. After all, what is the purpose of having a judicial mechanism – it is to advance justice. Warren Burger once said: “The obligation of the legal profession is… to serve as healers of human conflict…(we) should provide mechanisms that can produce an acceptable result in shortest possible time, with the least possible expense and with a minimum of stress on the participants. That is what justice is all about.” 10) Prof. (Dr.) N.R. Madhava Menon explains the meaning and contour of social justice adjudication as the application of equality jurisprudence evolved by the Parliament and the Supreme Court in myriad situations presented before courts where unequal parties are pitted in adversarial proceedings and where courts are called upon to dispense equal justice. Apart from the socio-economic inequalities accentuating the disabilities of the poor in an unequal fight, the adversarial process itself operates to the disadvantage of the weaker party. In such a situation, the _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 10 of 16**_ Court has to be not only sensitive to the inequalities of parties involved but also positively inclined to the weaker party if the imbalance were not to result in miscarriage of justice. The Courts, in such situations, generally invoke the principle of fairness and equality which are essential for dispensing justice. Purposive interpretation is given to subserve the ends of justice particularly when the cases of vulnerable groups are decided. The Court has to keep in mind the ‘problem solving approach’ by adopting therapeutic approaches to the maximum extent the law permits rather than ‘just deciding’ cases, thereby bridging the gap between law and life, between law and justice. The notion of access to justice is to be taken in a broader sense. The objective is to render justice to the needy and that means fair solutions to the conflict thereby providing real access to ‘justice’. - 11) Justice is a core value of any judicial system. It is the ultimate aim in the decision making process. In post-traditional liberal democratic theories of justice, the background assumption is that all humans have equal value and should, therefore, be treated as equal, as well as by equal laws. This can be described as ‘Reflective Equilibrium’. The method of Reflective Equilibrium was first introduced by _Nelson Goodman_ in _‘Fact, Fiction and Forecast’_ (1955). However, it is _John Rawls_ who elaborated this _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 11 of 16**_ method of _Reflective Equilibrium_ by introducing the concept of _‘Justice as Fairness’_ . While on the one hand, we have the doctrine of _‘justice as fairness’_ , as propounded by _John Rawls_ and elaborated by various jurists thereafter in the field of law and political philosophy, we also have the notion of _‘Distributive Justice’_ propounded by _Hume_ which aims at achieving a society producing maximum happiness or net satisfaction. When we combine Rawls’s notion of ‘ _Justice as Fairness’ with_ the notions of ‘ _Distributive Justice’_ , to which Noble Laureate Prof. Amartya Sen has also subscribed, we get jurisprudential basis for achieving just results for doing justice to the weaker section of the society. - 12) From the human rights perspective, persons belonging to the weaker sections are disadvantaged people who are unable to acquire and use their rights because of poverty, social or other constraints. They are not in a position to approach the courts even when their rights are violated; they are victimized or deprived of their legitimate due. Here lies the importance of access to justice for socially and economically disadvantaged people. When such people are denied the basic right of survival and access to justice, it further aggravates their poverty. Therefore, even in order to eliminate poverty, access to justice to _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 12 of 16**_ the poor sections of the society becomes imperative. In the instant case, it is the poverty which compelled the appellants to restrict the claim to Rs.115/- per sq. yard, as they were not in a position to pay the court fee on a higher amount. - 13) It is the aforesaid weighty consideration which justify award of compensation to the appellants at the rate of Rs.297/- per square yards. Though, the aforesaid reasons are enough to allow the appeals, in the present case, there is yet another additional circumstance which justifies this outcome. - 14) This Court in Civil Appeal No. 1506-1517 of 2016 titled Pardeep Kumar etc. etc. v. NOIDA which pertains to subsequent acquisition proceeding in the same village Makanpur, but falling under NOIDA, had on 16[th] February, 2016 set aside the order passed by the High Court of Judicature at Allahabad and remanded the matter back to the High Court for reconsideration in view of the judgments passed by the coordinate benches of the same High Court in Kashi Ram’s case as well as other cases. The High Court, after the remand vide its judgment dated 11[th] April, 2016 in First Appeal No. 522 of 2009 titled, Pardeep Kumar and Others vs. State of U.P. & Anr. awarded the same enhanced compensation at the rate of Rs. 297/- per sq. Yard even in the same case also. The High Court while awarding the _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 13 of 16**_ ## compensation at the same rate held: “27. Therefore, one of the questions which needs to be examined by us is, can the appellants be denied the same rate of compensation only because the filed by them before the reference court did not disclose the rate which they seek now in terms of the judgment of the High Court in the case of Ghaziabad Development Authority (supra). Kanshi Ram case. ## xxx xxx xxx 29. It is settled law that the compensation under the Act, 1894 had to be fair and just. Fairness requires that all those similarly situated are treated similarly. Technicalities qua rate as per exemplars filed by poor farmers, who are illiterate, has to be given only such importance as may not defeat their right of fair and just compensation qua compulsory acquisition of land holdings. 30. The determination of acquisition at the rate of Rs.297/- per square yard in the case of Ghaziabad Development Authority (supra) **Kashi Ram** case has therefore, to be taken as the fair rate determined for the land situated in the village Makanpur with regard to the notification issued on 12[th] September, 1986 as well as under Notification dated 15[th] March, 1988.” - 15) The High Court, in the process, also took aid of Section 28 - of the Act. Thus, even those villagers whose land was acquired subsequently, are given compensation at the rate of Rs.297/- per square yards. Depriving this rate to the appellants herein would be nothing but travesty of justice. - 16) Simply because the appellants had paid court fee on the claim at the rate of Rs.115/- square yards could not be the reason to deny the compensation at a higher rate. This could be taken _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 14 of 16**_ care of by directing the appellants to pay the difference in court fee after calculating the same at the rate of Rs.297/- per square yards. - 17) In fine, the judgment of the High Court is set aside and these appeals are allowed holding that appellants are also entitled to compensation at the rate of Rs.297/- per square yards. The difference in compensation along with other statutory benefits under the Act shall be calculated and paid to the appellants within a period of three months from today. It is also directed that the appellants shall make good in deficiency of court fee before the High Court. Appellants shall also be entitled to costs of these appeals. **.............................................J. (A.K. SIKRI)** **.............................................J. (ASHOK BHUSHAN)** **NEW DELHI; SEPTEMBER 11, 2017.** _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 15 of 16**_ **ITEM NO.1502 COURT NO.5 SECTION III-A** **S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS** **Civil Appeal No(s). 10429-10430/2017** **NARENDRA & ORS. Appellant(s)** **THE STATE OF UTTAR PRADESH & ORS. Respondent(s)** **Date : 11-09-2017 This matter was called on for pronouncement of judgment today.** **For Appellant(s) Mr. Rohit Kumar Singh, AOR For Respondent(s) Mr. Rakesh Uttamchandra Upadhyay, AOR** **UPON hearing the counsel the Court made the following O R D E R** **Hon'ble Mr. Justice A.K. Sikri pronounced the judgment of the Bench comprising His Lordship and Hon'ble Mr. Justice Ashok Bhushan.** **Appeal is allowed in terms of signed Reportable Judgment.** **Pending applications, if any, stand disposed of.** **(B.PARVATHI) (MALA KUMARI SHARMA) COURT MASTER COURT MASTER** **(Signed reportable judgment is placed on the file)** _**- - Civil Appeal Nos. 10429 10430 of 2017 [@SLP(C) Nos. 2354 2355 of 2017]**_ _**Page 16 of 16**_
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.