Nandakumar, Vijayakumar, Sreekumar and Rajakumar v. Kerala State Electricity Board

Case / Petition Number:
C.R.P. Nos. 190 and 38 of 2008
Neutral Citation:/

Case Synopsis & Summary

These Civil Revision Petitions arise from a dispute over enhanced compensation for damages caused by laying a 110 kV electric line through private land in Ernakulam district. The petitioners—Nandakumar, Vijayakumar, Sreekumar and Rajakumar—challenged an order passed in O.P.(Ele) No.204 of 2004 by the Additional District Judge (Adhoc II), Ernakulam, under the Indian Telegraph Act (Sections 10 and 16(3)) in conjunction with the Indian Electricity Act (Section 51). The Board (KSEB) took possession of about 11.154 cents to install towers for the Bhrahmapuram–Panampally Nagar line, while compensation was calculated as Rs. 52,618 per Are with 60% injurious affectation for the tower area and Rs. 5,41,502 for the line-drawn area (64.325 cents), totaling Rs. 6,82,362. The District Judge reassessed, holding that 100% compensation should be provided for the entire tower area and found greater injurious affectation than the Board had determined, resulting in an enhanced total of Rs. 14,75,360 with 6% interest. The revision petitions criticized the failure to apply Supreme Court guidelines, including those in K.S.E.B. v. Levisha, which emphasize factors like land situs, proximity to institutions, and overall diminution in land value. The High Court set aside the impugned order and directed remand for fresh disposal, allowing new evidence and expediting hearing, with a conditional deposit arrangement.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • S.S. Satheesachandran
Judgment Date
2009-10-14
Court Decision / Holding
Revisions disposed; impugned order set aside; remanded for fresh determination in light of the guiding principles from K.S.E.B. v. Levisha, with opportunity to lead further evidence; expedited hearing; 25% of enhanced compensation to be deposited and credited as appropriate.
Final Disposition
Revisions disposed; impugned order set aside; remand for fresh determination in light of K.S.E.B. v. Levisha; opportunity to lead further evidence; expedited hearing; deposit provisions maintained.

Parties to the Case

Appellants / Petitioners

  • M. Nandakumar
  • M. Vijayakumar
  • M. Sreekumar
  • Rajakumar @ Rajagopalan

Respondents

  • Kerala State Electricity Board, represented by its Secretary, Vydyuthi Bhavan, Thiruvananthapuram
  • Deputy Chief Engineer, KSE Board, Transmission Circle, Kalamassery

Legal Representation & Advocates

Counsels for Petitioners

  • • C. S. Ajith Prakash
  • • Rajakrishnan K.

Counsels for Respondents

  • • N. N. Sugunapalan, SC
  • • S. Sujin

Provisions of Law Cited

Indian Telegraph Act, 1885 – Section 10Indian Telegraph Act, 1885 – Section 16(3)Indian Electricity Act – Section 51

Legal Doctrines & Maxims

  • K.S.E.B. v. Levisha, 2007 (6) SCC 792 – guidelines for determining compensation in cases involving land injuriously affected by overhead lines
  • Principles for assessing land value: situs, proximity to public offices/educational institutions, and other relevant factors as they affect potential value and diminution

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contended that the District Judge did not apply the Supreme Court guidelines for compensation of land injuriously affected by overhead lines (K.S.E.B. v. Levisha). They argued for full (100%) compensation for the area taken for towers and appropriate enhancement for injurious affectation, considering proximity to institutions and the land's market value. They sought remand with liberty to lead further evidence and to ensure correct computation, including the deposit arrangements and credit of amounts already paid.

Contentions of Respondents

The Board contended that the initial compensation already paid was reasonable and adequate. It argued that the District Judge wrongly fixed 100% compensation for the entire tower area and that the approach to determining injurious affectation was flawed. It urged upholding or reducing the enhanced figure in line with established valuations and the cited jurisprudence, while supporting the stay and deposit provisions during remand.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
K.S.E.B. v. Levisha2007 (6) SCC 792Mentioned OnlyThe judgment cites the guidelines from K.S.E.B. v. Levisha as a guiding principle for remand but does not apply them as a binding ruling in the present order; it notes that those guidelines were not considered by the lower court and must be taken into account on remand.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,403 words•~7 min read

In The Court Record

Nandakumar, Vijayakumar, Sreekumar and Rajakumar v. Kerala State Electricity Board

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** ## **THE HONOURABLE MR. JUSTICE S.S.SATHEESACHANDRAN** ## **WEDNESDAY, THE 14TH OCTOBER 2009 / 22ND ASWINA 1931** ## **CRP.No. 190 of 2008()** **-----------------------------------** ## **OP(ELE).204/2004 of ADDL.DISTRICT COURT (ADHOC)-II, ERNAKULAM** **....................** ## **REVN. PETITIONER(S): PETITIONERS IN EL(OP):** **---------------------------------------** **1. M.NANDAKUMAR, MITTATHULLIL HOUSE, MARAR ROAD, TRICHUR.** **2. M.VIJAYAKUMAR, MITTATHULLIL HOUSE, MARAR ROAD, TRICHUR.** **3. M.SREEKUMAR, MITTATHULLIL HOUSE, MARAR ROAD, TRICHUR.** **4. RAJAKUMAR @ RAJAGOPALAN, MITTATHULLIL HOUSE, MARAR ROAD, TRICHUR.** **BY ADVS.MR.C.S.AJITH PRAKASH** - **MR.RAJAKRISHNAN. K** ## **RESPONDENT(S): RESPONDENTS IN EL (OP):** **------------------------------** **1. KERALA STATE ELECTRICITY BOARD, REPRESENTED BY ITS SECRETARY, VYDYUTHI BHAVAN, THIRUVANANTHAPURAM.** **2. DEPUTY CHIEF ENGINEER, KSE BOARD, TRANSMISSION CIRCLE, KALAMASSERY.** **R1 & R2 BY ADVS. MR.N.N.SUGUNAPALAN, SC, MR . S.SUJIN .** **THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON 14/10/2009, ALONG WITH CRP NO. 38 OF 2008 THE COURT ON THE SAME DAY PASSED THE FOLLOWING:** **tss** ## **S.S.SATHEESACHANDRAN, J.** ## **-----------------------------** ## **C.R.P.Nos.190 AND 38 OF 2008 -------------------------Dated this the 14[th] day of October 2009 -------------------------------------** ## **ORDER** **These two revisions are filed against the order dated 18/08/2007 in O.P(Ele) No.204 of 2004 passed by the learned Additional District Judge(Adhoc II), Ernakulam. The above Original petition was filed under Section 10 and 16(3) of the Indian Telegraph Act 1885 r/w Section 51 of the Indian Electricity Act seeking enhanced compensation for the damages caused on the drawing of overhead lines through the property of the revision petitioners in C.R.P No.190 of 2008, having an extent of 2.05 Acres comprised in survey numbers 815/1, 815/2, 1079/3 and 814/2 of Elamkulam village in Ernakulam district. The respondent in the above revision, namely Kerala State Electricity Board, herein after referred as the Board, took** C.R.P.Nos.190 AND 38 OF 2008 Page numbers **possession of an area of 11.154 cents from the above property for installation of towers to draw 110Kv line for drawing Bhrahmapuram Panampally Nagar electric line. Fixing a market value of Rs.52,618/- (Rupees fifty two thousand six hundred and eighteen only) per Are compensation for the area injuriously affected for erecting the tower was fixed at 60%, and a sum of Rs.1,40,860/(Rupees One lakh forty thousand eight hundred and sixty only) was assessed. Towards the drawing of the overhead lines an area of 64.325 cents was determined as injuriously affected, and towards compensation thereof, assessing such injurious affectation at 40% of the aforesaid market value, compensation was fixed at Rs.5,41,502/- (Rupees five lakh forty one thousand five hundred and two only). Thus a total compensation of Rs.6,82,362/(Rupees six lakh eighty two thousand three hundred and sixty two only) was provided for loss and injury suffered by the claimants. Dissatisfied with the compensation so awarded and impeaching the** C.R.P.Nos.190 AND 38 OF 2008 Page numbers **assessment made as unreasonable and inadequate, the above claim petition was filed before the court. The Board resisted the claim by filing objections contending that reasonable and adequate compensation had been paid. In the enquiry conducted over the petition, on behalf of the claimants PW1 was examined and Exts.A1 to A5 were exhibitted. Board got examined one witness as RW1 and exhibitted as R1. The learned District Judge after appreciating the materials produced and hearing the counsel on both sides reassessed the compensation payable taking a view that, towards compensation for erection of the tower, 100% compensation has to be provided for the entire area taken for putting up the tower. So far as, the diminution of land value on account of the drawing of line, on the materials placed, the court formed an opinion that a larger extent than what was determined by the Board had been injuriously affected and with reference to a registered title deed produced showing the market value of a nereby** C.R.P.Nos.190 AND 38 OF 2008 Page numbers **property which is stated to be situated closeby fixing the centage value of the property at Rs.1,31,000/- (Rupees One lakh thirty one thousand only) the learned District Judge awarded compensation of Rs.10,29,200/- (Rupees Ten lakh twenty nine thousand two hundred only). Thus the claimants were found entitled to a total compensation of Rs.14,75,360/- (Rupees fourteen thousand seventy five thousand three hundred and sixty only) from which deducting the sum already paid to the petitioners, enhanced compensation of Rs.7,92,998/- (Rupees Seven lakh ninety two thousand nine hundred and ninety eight only) was awarded. In the award, 6% interest was also directed to be paid from the date of filing of the petition for enhanced compensation. The Board has challenged the compensation so awarded by filing C.R.P No.38/2008, and the claimants, C.R.P No.190/2008.** C.R.P.Nos.190 AND 38 OF 2008 Page numbers **2. Since both the revisions arise from** **the same order, after being heard together theyare disposed by this common order. I heard the counsel on both sides.** **3. Perusing the order passed by the learned District Judge, impugned in the revision, it is noticed that the guidelines enunciated in** _**“K.S E.B v Levisha” (2007(6) SCC 792)**_ **have not been considered in determining the enhanced compensation payable towards the drawing of the overhead lines through the property of the claimants. The impugned order would show that after fixing the centage value of the property on the basis of a registered document at Rs.1,31,000/-(Rupees One lakh thirty one thousand only), the learned District Judge proceeded to fix the area which is injuriously affected by drawing of the line and also the percent at which such land suffered diminution in its value. A reference is seen made to the commission report as to the proximity of the** C.R.P.Nos.190 AND 38 OF 2008 Page numbers **land through which the line was drawn, to a nereby road. There is no more discussion in the order as to the importance of the land to close by institutions, concerns and such other factors which are relevant in determining the potential value of the land and also assessing of its diminution on account of the overhead lines drawn. In the above reported decision rendered by the apex court, it has been pointed out that the citus of the land, the distance between the high voltage electric line laid there over, the extent of the land thereof and whether the line was drawn over a small track of land or middle of the land and such other matters are relevant, from which, determinative steps have to be taken for assessment of the compensation payable. Citus of the land and its proximity to public offices, educational institutions etc. may also be of much significance in determining its potential value and how far overhead lines drawn through that property will injuriously diminish its value. Of course, the Board has a case that the** C.R.P.Nos.190 AND 38 OF 2008 Page numbers **land at the time of drawing of line was water logged. If that be so, that circumstance also has to be taken into account with such other relevant factors applicable for determining the potential value of the land and, then, ascertaining of its diminution in value on account of the drawing of the overhead lines. Since the principles applicable for determination of compensation have not been considered by the court below while passing the impugned order, it has become imperative and necessary to set aside the order and remit it for fresh disposal taking note of the decision rendered by the apex court referred to above. Both sides will be given opportunity to lead further evidence, if sought for, to prove their respective case. During the pendency of the revision, conditional stay of operation of the impugned Order was ordered directing the Board to deposit 25% of the enhanced compensation. Such deposit being made the claimant was permitted to withdraw the sum. Amount so deposited and** C.R.P.Nos.190 AND 38 OF 2008 Page numbers **released to the claimant shall be given to credit to in the enhanced compensation by the court after redetermination of compensation, on remission of the case. Bond already executed by the petitioner for release of the amount deposited as indicated above shall continue to be in force, and will be subject to the final orders to be passed in the petition.** **4. The court below is directed to give the petition top priority in hearing and dispose it as expeditiously as possible, at any rate before the closing of the courts for mid summer vacation. Petition is disposed as indicated above.** ## **Sd/-** ## **S.S.SATHEESACHANDRAN, JUDGE** ## **//TRUE COPY//** ## **P.A TO JUDGE** vdv
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.