Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Single JudgeThe writ petition is partly allowed. Interim me...

Muthoot Hotels and Infrastructure Ventures Pvt. Ltd. v. K. I. Varghese

Case / Petition Number:
WP(C).No.3815 of 2009(D)

Case Synopsis & Summary

This writ petition, filed by Muthoot Hotels and Infrastructure Ventures Pvt. Ltd., challenges the order of temporary injunction granted in I.A.7426/2008 in O.S.903/2008 (Ernakulam Sub Court), confirmed in CMA No.105/2008 by the District Court. The suit seeks declaration of title and possession for plaint A schedule property (an extent of 2 acres 62 cents, with portions already acquired for road and by KINFRA) and a mandatory injunction directing removal of piles and a permanent prohibitory injunction restraining construction on the plaint B schedule property or any obstruction to constructing a boundary wall on the A schedule property. The defendant, after purchasing land to build a hotel, began piling on the B schedule land and subsequently on the A schedule as per Ext.A16. The plaintiff contends there is excess land (about 19.1 cents) due to resurvey and that the defendant’s activity would cause irreparable injury. The courts below held a prima facie case and granted temporary injunction. The High Court, however, while acknowledging the urgency, sets aside those orders and remands for fresh consideration after demarcation by the Commissioner, with a report due by 15.6.2009 and a decision within a month thereafter, maintaining an interim injunction against construction on the disputed A schedule land. It clarifies that no opinion is expressed on merits and discusses a Supreme Court decision (AIR 2008 SC 2291) only to distinguish it on facts.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K.T.SANKARAN
Judgment Date
2009-04-08
Court Decision / Holding
Writ petition allowed to the extent indicated: set aside the trial court’s order dated 12.11.2008 in I.A.No.7426/2008 and CMA 105/2008, and remand for fresh consideration by the trial court after the Commissioner’s demarcation report is filed (due by 15.6.2009). The trial court should dispose of I.A.7426/2008 within one month of receiving the report. Till disposal, an interim injunction restraining construction on plaint A schedule item 1 (19.1 cents) remains in effect; any construction on plaint B schedule property will be subject to the outcome of I.A.7426/2008. The court reserves its opinion on the merits of I.A.7426/2008. Governmental reports and plan submissions by the Commissioner are expected to guide the final determination.
Final Disposition
The writ petition is partly allowed. Interim measures preserved; fresh consideration ordered with Commissioner’s report guiding the process.

Parties to the Case

Appellants / Petitioners

  • M/S.MUTHOOT HOTELS AND INFRASTRUCTURE VENTURES PVT.LTD., MUTHOOT CENTER, PUNNEN ROAD, THIRUVANANTHAPURAM-24, REP.BY ITS SENIOR MANAGER, SABU ZACHARIAS.K

Respondents

  • K.I.VARGHESE, S/O.ITTOOP, KACHAPPALLY HOUSE, MULANTHURUTHI, ERNAKULAM, REP.BY THE POWER HOLDER MR.BIJU ROY

Legal Representation & Advocates

Counsels for Petitioners

  • • SRI.K.P.DANDAPANI
  • • SRI.MILLU DANDAPANI

Counsels for Respondents

  • • SRI.G.RAJAGOPAL
  • • SMT.S.LEELALAKSHMI

Provisions of Law Cited

Kerala Building RulesLand Acquisition Act

Legal Doctrines & Maxims

  • Land definitely does not grow by itself
  • Prima facie case is enough for granting temporary injunction
  • Balance of convenience
  • Status quo
  • Survey demarcation and Commissioner report are material in deciding property disputes

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that title to plaint A schedule property remains with the plaintiff despite various disjointed survey records and that the defendant’s conversion of surplus land and continuous construction threaten irreparable injury. They rely on the plan and title documents (Exts.A2–A14) and emphasize the need for measured demarcation by a Commissioner to determine boundaries, with the interim injunction justified to preserve status quo until a final decision. They oppose any construction on the disputed 19.1 cents until rights are clarified.

Contentions of Respondents

The respondent-defendant argues changes in land records post-survey and asserts ownership and use for hotel construction, supported by the resurvey and Ext.A14, with a willingness to deposit security and bond and to permit construction on certain portions if necessary. They urge that the court consider road and boundary adjustments and contend that the plaintiff’s title is not conclusively established, suggesting the matter requires fresh verification and that a deposit could secure possible decrees.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Mandali Ranganna and others v. T.Ramachandra and othersAIR 2008 SC 2291DistinguishedThe court cites this decision but states it is distinguishable on facts, thus not applying its principle to the present case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,296 words•~11 min read

In The Court Record

Muthoot Hotels and Infrastructure Ventures Pvt. Ltd. v. K. I. Varghese

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE K.T.SANKARAN WEDNESDAY, THE 8TH APRIL 2009 / 18TH CHAITHRA 1931 ## **WP(C).No. 3815 of 2009(D)** AGAINST THE ORDER DATED 17/01/2009 IN CMA.NO.105/2008 IN IA 7426/2008 IN OS.903/2008 of I ADDL.SUB COURT,ERNAKULAM PETITIONER: --------------- M/S.MUTHOOT HOTELS AND INFRASTRUCTURE VENTURES PVT.LTD,MUTHOOT CENTER,PUNNEN ROAD, THIRUVANANTHAPURAM-24,REP.BY ITS SENIOR MANAGER, SABU ZACHARIAS.K. BY SENIOR ADV. SRI.K.P.DANDAPANI SRI.MILLU DANDAPANI RESPONDENT: --------------- K.I.VARGHESE, S/O.ITTOOP, KACHAPPALLY HOUSE, MULANTHURUTHI, ERNAKULAM,REP.BY THE POWER HOLDER MR.BIJU ROY. ADV. SRI.G.RAJAGOPAL SMT.S.LEELALAKSHMI THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 03/04/2009, THE COURT ON 08/04/2009 DELIVERED THE FOLLOWING: ## **APPENDIX** PETITIONER'S EXHIBITS: EXT.P1 TRUE COPY OF THE PLAINT IN O.S.NO.903/2008 ON THE FILE OF THE SUB COURT, ERNAKULAM. EXT.P2 TRUE COPY OF THE WRITTEN STATEMENT IN O.S.NO.903/2008 ON THE FILE OF THE SUB COURT, ERNAKULAM. EXT.P3 TRUE COPY OF THE ORDER DATED 12.11.2008 IN I.A.NO. 7426/2008 IN O.S.NO.903/2008 ON THE FILE OF THE FIRST ADDITIONAL SUB COURT, ERNAKULAM. EXT.P4 TRUE COPY OF THE MEMORANDUM OF CIVIL MISCELLANEOUS APPEAL NUMBERED AS CMA.105/2008 ON THE FILE OF THE DISTRICT COURT, ERNAKULAM. EXT.P5 TRUE COPY OF THE ORDER DATED 19.1.2009 IN CMA.NO.105/2008 ON THE FILE OF THE 2ND ADDL. DISTRICT COURT, ERNAKULAM. RESPONDENTS' EXHIBITS: NIL //TRUE COPY// AHZ/ ## **K.T.SANKARAN, J.** **-----------------------------------------------------W.P.(C) NO. 3815 OF 2009 D -----------------------------------------------------Dated this the 8[th] April, 2009** ## **JUDGMENT** This Writ Petition is filed by the defendant in O.S.No.903 of 2008, Sub Court, Ernakulam, challenging the order of temporary injunction granted in I.A.No.7426 of 2008, which was confirmed in C.M.A.No.105 of 2008 on the file of the Court of the District Judge of Ernakulam. 2. The respondent herein instituted the suit for declaration of title and recovery of possession of plaint A schedule item 1, for a mandatory injunction directing the defendant to remove the concrete piles therein and for a permanent prohibitory injunction restraining the defendant from constructing any building in the plaint B schedule property or obstructing the plaintiff from constructing a compound wall on the southern side of the A schedule property or from trespassing upon the A schedule property. I.A.No.7426 of 2008 was filed for temporary injunction. W.P.(C) NO.3815 OF 2009 :: 2 :: 3. The case of the plaintiff inter alia, is as follows: The property including plaint A schedule property, having an extent of 2 acres 62 cents in old survey No.298/1 (Re-Survey No.118/5), was acquired by the plaintiff as per Ext.A2 settlement deed executed by his father in 1958. An extent of 11.950 cents was taken for a way and another extent of 11.550 cents was acquired by KINFRA from the said extent of 2.62 acres. The balance extent of 2 acres 38.5 cents is the plaint A schedule property. The plaint B schedule property, situated on the southern side of A schedule property, belonged to Mathai Ittoop and after several transactions, evidenced by Exts.A6 to A14, it came to vest in D.V.Deo. In these title deeds (Exts.A6 to A14), the total extent shown is 75.234 cents situated in old survey No.297/5 (Re-survey No.118/4). D.V.Deo assigned the property to the defendant as per Ext.A14 assignment deed No.1406/07, wherein the extent shown is 97.85 cents equivalent to 39 Ares and 60 sq.m. The excess extent was shown in the title deed by the defendant and his predecessor by manipulation of re-survey records. The excess extent of 19.1 cents is shown as plaint A schedule item 1, which is sought to be recovered from the defendant. W.P.(C) NO.3815 OF 2009 :: 3 :: 4. The plaintiff contended that the defendant started construction of a multi storied building in the plaint B schedule property and started the piling work. Though initially the piling work was confined to B schedule property, later the defendant started pile driving in plaint A schedule item 1 property also. The building is being constructed by the defendant in violation of the Kerala Building Rules. The plaintiff will be put to irreparable injury and great hardship if the defendant is allowed to construct the building. 5. The defendant contended that many changes occurred to the properties of the parties. The property of the plaintiff was a paddy field, while the property of the defendant is a dry land. The defendant purchased the property having an extent of 39.60 Ares in Re-survey No.118/4. The predecessor in interest of the defendant was in possession of that much extent of land. The defendant purchased the property for constructing a hotel for which the necessary permit was obtained from the local authority and sanction was granted by the Tourism Department. The re-survey was completed several years ago and at this point of time, the plaintiff cannot question it. W.P.(C) NO.3815 OF 2009 :: 4 :: 6. The defendant put forward the contention that after resurvey, the extent in almost every survey number has increased. It was pointed out that Exts.A3 and A4 would show that the plaintiff has paid basic tax for 7.95 acres in Thandaper No.2968. After resurvey, the plaintiff has paid basic tax for an extent of 7.66 acres, evidenced by Ext.B20 in Thandaper No.1498. The difference in extent in the old Thandaper and new Thandaper is 29 cents. It was admitted by the plaintiff that an extent of 11.95 cents and 11.55 cents respectively were taken for road and acquired by KINFRA, the total extent being 23.5 cents. It is also pointed out that an extent of 2.965 cents was acquired under the Land Acquisition Act and thus the total deficit will be 2.535 cents, which according to the defendant, must have been included in the adjacent lands, where after resurvey, the extent has increased, as is evident from Exts.B10, B13 and other documents. According to the defendant, the case of trespass over an extent of 19.1 cents is clearly ruled out from the documentary evidence available in the case. 7. The plaintiff contended that the lie of the defendant's W.P.(C) NO.3815 OF 2009 :: 5 :: property, as shown in the plan attached to Ext.A16, is such that it is bounded by roads and the property of the plaintiff. The excess land found in the possession of the defendant certainly must be part of the plaintiff's property. 8. The trial court as well as the appellate court found that the plaintiff has established prima facie case for the grant of temporary injunction and that the balance of convenience is also in favour of the plaintiff. Thus temporary injunction was granted by the courts below. 9. The learned counsel appearing for the parties pointed out that on the application of the plaintiff, a Commissioner was appointed to inspect the properties and to identify the properties in accordance with survey records and title deeds. The Commissioner and surveyor have commenced the work and it is not completed. 10. The courts below mainly laid stress on the excess extent shown in Ext.A14 title deed executed in favour of the defendant, while all the prior documents from 1960 to 1987 show a lesser W.P.(C) NO.3815 OF 2009 :: 6 :: extent. The courts below also thought that excess extent would not be available with the plaintiff unless there is some manipulation or trespass. While considering the case in that angle, proper exphasis was not laid on the fundamental aspect that the plaintiff has to prove his title to enable him to get a decree based on title. Any excess found in the possession of the defendant would not automatically vest in the plaintiff, the neighbouring property owner. 11. The trial court noticed in the order thus: “Plaintiff has already filed application for measurement of property. Item 1 of plaint A schedule property is to be located based on the document, in which the property is described with old survey records. Hence I am of the view that unless and until the interim injunction prayed for is granted plaintiff will be sustained with irreparable loss and hardships.” 12. The lower appellate court, while dealing with the excess extent shown in Ext.A14 than the extent shown in prior title deeds, held thus: “Land definitely does not grow by itself. Hence the defendant is bound to explain how his predecessor who purchased the property only in 1987 got excess land. Apart from the roads, covering the southern and eastern side of his property, the remaining boundaries W.P.(C) NO.3815 OF 2009 :: 7 :: are adjoining the property of the plaintiff alone. If the defendant's predecessor did not encroach public road, it has necessarily to be an encroachment from the plaintiff's property. The fact that the members of the plaintiff's family are also in possession of excess land is no reason for the defendant to clinge on to the excess land found in his possession.” 13. I do not think the approach made by the courts below as mentioned above is correct. It is true that to preserve the disputed property and to maintain status quo, temporary injunction can be granted even if the plaintiff has not fully established his case. Establishment of a prima facie case is enough for granting temporary injunction. But, at the same time, a case cannot be entirely built up by the plaintiff on the basis of the title deed in favour of the defendant, in the facts and circumstances of the case, particularly when it is shown by documentary evidence that re-survey has resulted in excess land having been found in several survey numbers. 14. Then, the question is whether the case put forward by the plaintiff would constitute a prima facie case justifying the grant of temporary injunction and whether the balance of convenience is in favour of granting temporary injunction. W.P.(C) NO.3815 OF 2009 :: 8 :: 15. I would like to take note of some suggestions made by the learned Senior Counsel appearing for the defendant in this regard. He submitted that the defendant is prepared to deposit Rs.One Crore and produce the fixed deposit receipt before Court as security and it could be placed at the disposal of the Court for satisfying any decree or order that may be passed by the Court. It is pointed out that the sum of Rs.One Crore would be the market value of the plaint A schedule item 1 property which is sought to be recovered. The learned Senior Counsel also pointed out that the defendant is also prepared to execute a bond for the aforesaid sum in any manner the court directs. The only request made by the defendant in this regard is that permission may be granted to the defendant to construct the building in the property of the defendant, including the disputed extent of 19.1 cents of land. The learned Senior Counsel for the defendant also submitted that the defendant is prepared to file an affidavit undertaking to demolish that portion of the building, if ultimately it is found that such portion is included in the plaintiff's property. Reliance was placed on the decision of the Supreme Court in **Mandali Ranganna and others** v. **T.Ramachandra and others** (AIR 2008 SC 2291). W.P.(C) NO.3815 OF 2009 :: 9 :: 16. In answer, the learned counsel for the plaintiff submitted that the plaintiff does not intend to sell his property or any portion thereof and therefore he cannot agree to the suggestions made by the defendant. He also submitted that the decision in AIR 2008 SC 2291 is distinguishable on facts. 17. The learned counsel for the plaintiff also relied on several decisions to support the order and judgment passed by the courts below. 18. In the facts and circumstances of the case, I am of the view that the matter requires fresh consideration by the trial court, particularly in view of the subsequent developments and in the light of the suggestions made by the defendant. I would not have thought of directing the trial court to consider the matter afresh, but for the fact that the Commissioner, with the help of surveyor, has commenced the work of identifying the property with the aid of survey records and title deeds. In the nature of the dispute involved in the case, survey demarcation with reference to old survey and re- W.P.(C) NO.3815 OF 2009 :: 10 :: survey is very material. If the report and plan are submitted by the Commissioner, they would be helpful to the court to arrive at a right conclusion on surer grounds. 19. For the aforesaid reasons, I set aside the order passed by the trial court dated 12.11.2008 in I.A.No.7426 of 2008 and the judgment dated 19.1.2009 in C.M.A.No.105 of 2008 on the file of the Court of the District Judge, Ernakulam. The trial court shall consider I.A.No.7426 of 2008 afresh after the report and plan are submitted by the Commissioner. The Commissioner shall file the report and plan on or before 15.6.2009. The trial court shall dispose of the application within one month from the date of receipt of the Commissioner's report and plan. The trial court shall also take note of the suggestions made by the defendant as noted in paragraph 14 above and the reply thereto by the plaintiff. 20. Till the disposal of the application for temporary injunction (I.A.No.7426 of 2008) by the trial court, there will be an interim injunction restraining the defendant, their men and agents from making any construction in plaint A schedule item 1 property, which W.P.(C) NO.3815 OF 2009 :: 11 :: is the disputed property having an extent of 19.1 cents. Any construction which the defendant may make in the plaint B schedule property will be subject to the result of the order in I.A.No.7426 of 2008. 21. It is made clear that I have not expressed any opinion on the merits of I.A.No.7426 of 2008. The Writ Petition is allowed to the extent indicated above. **(K.T.SANKARAN) Judge** ahz/
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.