MUNICIPAL COUNCIL GONDIA v. DIVI WORKS & SUPPLIERS, HUF & ORS.

Case / Petition Number:
Civil Appeal No. 1538 of 2022
Neutral Citation:[2022] 2 S.C.R. 426

Case Synopsis & Summary

This matter concerns a municipal procurement for desks, benches, almirahs and tables for a school. The Municipal Council Gondia invited bids; Divi Works & Suppliers, HUF was declared the successful bidder and a work order dated 07.02.2020 was issued. After the Covid-19 outbreak and ensuing lockdown, Maharashtra government GRs dated 04.05.2020 directed curbing non-priority expenditures due to financial strain. Pursuant thereto, the Council suspended the work order on 18.05.2020 and eventually cancelled it after a report from the Education Officer indicated respondent No.1 had not taken further steps and that supply was not urgent in the pandemic context. Respondents challenged these actions in a writ petition, and the High Court quashed the suspension and directed continuation of the work order with payments as per the contract. This Court’s interim order on 07.02.2022 required the Council to inspect goods at respondent No.1’s premises and identify materials immediately required (not less than 25% of the manufactured quantity) and to prepare a schedule for the balance. On inspection, the manufactured goods reportedly did not meet the work order’s specifications, and there was no clear evidence that they had been manufactured as required. The Court held the High Court erred in granting mandamus and annulled the order of continuation; the matter was remitted to civil remedies for damages, if any. The appeal was allowed; writ petition dismissed; no costs; damages may be pursued in civil court.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • M. R. Shah
  • B. V. Nagarathna
Judgment Date
2022-02-28
Court Decision / Holding
Appeal allowed. The High Court’s judgment is quashed and set aside; the writ petition is dismissed. The petitioner may pursue damages in civil court if warranted, in accordance with law and on evidence. No costs.
Final Disposition
Appeal allowed; writ petition dismissed; damages may be pursued in civil court.

Parties to the Case

Appellants / Petitioners

  • Municipal Council Gondia

Respondents

  • Divi Works & Suppliers, HUF
  • Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • Mohit P. Khajanchi
  • • Mahesh Dhatrak
  • • C. George Thomas
  • • Gaurav Agrawal

Counsels for Respondents

  • • R. L. Khapre, Senior Advocate
  • • Ms. Anagha S. Desai
  • • Rahul Chitnis
  • • Sachin Patil
  • • Aaditya A. Pande
  • • Geo Joseph
  • • Ms. Shwetal Shepal

Provisions of Law Cited

Constitution of India — Article 226

Legal Doctrines & Maxims

  • Writ of mandamus
  • Doctrine of seeking specific performance of a contract through writ petition under Article 226
  • Remedy for damages via civil suit where writ relief is inappropriate

Submissions & Arguments

Contentions of Appellants / Petitioners

The Municipal Council Gondia contends that the High Court’s writ directing continuation of the work order and payments effectively amounted to specific performance of the contract, which is not permissible under writ jurisdiction. There are disputed questions of fact as to whether respondent No.1 actually manufactured goods as per the specifications, and whether such manufacturing occurred at all. The record lacks evidence of ready, compliant goods. The 07.02.2022 directive to identify a minimum 25% of manufactured goods and to prepare a schedule demonstrates that enforcement of performance under Article 226 is unwarranted in writ proceedings. The GR of 04.05.2020 and the lockdown-period suspension/cancellation were valid responses to Covid-19-financial constraints. The Council should be permitted to relegated to civil remedies for damages, if any, rather than mandating contract performance in a writ petition; no writ can compel delivery absent proof of compliance with the contract terms.

Contentions of Respondents

The respondents argued they had manufactured customized goods in accordance with the work order and that the Council’s suspension due to Covid-19 was a legitimate response to financial constraints. They asserted that the High Court erred in setting aside the suspension and directing continued performance and payments. The respondents contended that the GR dated 04.05.2020 justified such suspension, and that the Education Officer’s report indicated lack of further steps by the petitioner. They maintained the goods were produced and ready, and that the relief sought would prevent substantial losses; a civil action for damages would be inappropriate where the writ could enforce contract performance, and the Court should have upheld the contract remedy in writ jurisdiction or recognized damages as appropriate.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,773 words•~13 min read

In The Court Record

MUNICIPAL COUNCIL GONDIA v. DIVI WORKS & SUPPLIERS, HUF & ORS.

426 SUPREME COURT REPORTS[2022] 2 S.C.R. 426 [2022] 2 S.C.R. A ## MUNICIPAL COUNCIL GONDIA v. ## DIVI WORKS & SUPPLIERS, HUF & ORS. ## (Civil Appeal No. 1538 of 2022) B FEBRUARY 28, 2022 ## **[M. R. SHAH AND B. V. NAGARATHNA, JJ.]** _Constitution of India: Art. 226 – Appellant-Municipal Council is running educational institutions – A resolution was passed for purchasing school furniture – Original writ petitioner no. 1_ C _(respondent No.1) was declared successful bidder and work order was issued in its favour – However, on outbreak of Covid-19 pandemic and lockdown in force, the State Government published G.R. dated 4.5.2020 providing that owing to Covid-19 restrictions impacting government finances, non-priority expenditure should not_ D _be incurred – Pursuant thereto, Municipal Council informed respondent No.1 regarding suspension of work order until further orders – Municipal Council cancelled the work order after obtaining report from the Education officer that respondent No.1 had not taken any further steps in regard to supply of furniture as per the work order and that since the supply of furniture was not urgent in nature_ E _– On writ petition, High Court held that respondent No.1 is entitled to make the supply in pursuance of the work order – Hence the instant appeal – Respondent No.1 submitted that they have already manufactured the goods which are customized and therefore, if the Municipal Council is not directed to lift the goods prepared/got_ F _prepared as per the work order, it would suffer a huge loss – This Court directed on 7.2.2022 that as the schools have restarted, the official of the appellant would visit the place where the manufactured goods are kept and identify the goods which are immediately required, at this stage which shall not be less than 25% of the total quantity manufactured – On inspection of the goods, the official_ G _found that the goods did not meet the requirement of the work order – Even respondent No.1 had admitted that goods were not available – Held: There are disputed questions of fact such as whether in fact the goods were manufactured as per the specifications or not – Nothing was on record before the High Court that goods were in_ H _fact and actually manufactured by respondent No.1, as per the_ 426 427 MUNICIPAL COUNCIL GONDIA v. DIVI WORKS & SUPPLIERS, HUF & ORS _specifications and the requirements of the Council and as per the work order – In absence of any evidence on record and there being disputed questions of facts, High Court ought not to have passed the impugned judgment directing the Council to continue the work order and accept the goods from respondent No.1 and to make the payments as per the work order – Even otherwise, no writ of mandamus could have been issued virtually granting the writ for specific performance of the contract/work order in a writ petition under Art.226 of the Constitution of India – Respondent No.1 ought to have been relegated to file a civil suit for appropriate relief of losses/damages, if any, sustained – Writ jurisdiction._ ## **Allowing the appeal, the Court** A B C **HELD: By the impugned judgment, the High Court has issued a writ of mandamus virtually granting the relief of specific performance of the contract/work order. From the impugned judgment, it appears that the High Court was made to believe** D **that the original writ petitioners had already manufactured the goods which are customized and as per the specifications and the work order. However, it is now found that there are no manufactured goods readily available which can be supplied to the appellant-Council. There are disputed questions of fact such as whether in fact the goods were manufactured as per the** E **specifications or not. Nothing was on record before the High Court that goods were in fact and actually manufactured by the original writ petitioner No.1, as per the specifications and the requirements of the Council and as per the work order. In absence of any evidence and disputed questions of facts, the** F **High Court ought not to have passed the impugned judgment and order directing the Council to continue the work order and accept the goods from the original writ petitioner No.1 and to make the payments as per the work order. Even otherwise, no writ of mandamus could have been issued virtually granting the writ for specific performance of the contract/work order in a** G **writ petition under Article 226 of the Constitution of India. The original writ petitioners ought to have been relegated to file a civil suit for appropriate relief of losses/damages, if any, sustained. Even otherwise on merits also the High Court has** H 428 SUPREME COURT REPORTS [2022] 2 S.C.R. - A **erred in setting aside the communication dated 18.05.2020 and 07.07.2020. The High Court has not at all appreciated the reasons for suspending/cancelling the work order till further orders. It is to be noted that the decision dated 07.07.2020 was taken pursuant to the G.R. dated 04.05.2020 which was necessitated due to Covid-19 Pandemic and there was a lockdown and the** - B **schools were closed and that the Council had no sufficient funds. Even the said decision was taken after calling for a report from the Education Officer in regard to the tender/work order issued to the original writ petitioner No.1 and the Education Officer informed that the original writ petitioner No.1 has not taken** - C **any further steps in regard to supply of material as per the work order. [Paras 8, 8.1][431-E-H; 432-A-D]** CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1538 of 2022. - From the Judgment and Order dated 05.01.2021 of the High Court - D of Judicature at Bombay, Nagpur Bench at Nagpur in Writ Petition No.1984 of 2020. Mohit P. Khajanchi, Mahesh Dhatrak, C. George Thomas, Gaurav Agrawal, Advs. for the Appellant. E R. L. Khapre, Sr. Adv., Ms. Anagha S. Desai, Rahul Chitnis, Sachin Patil, Aaditya A. Pande, Geo Joseph, Ms. Shwetal Shepal, Advs. for the Respondents. The Judgment of the Court was delivered by ## **M. R. SHAH, J.** F 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 05.01.2021 passed by the High Court of Judicature at Bombay, Nagpur Bench at Nagpur in W.P.No.1984 of 2020, by which, the High Court has allowed the said writ petition preferred by respondent No.1& 2 herein – original writ petitioners (hereinafter referred to as the G original writ petitioners) and has quashed and set aside the action on the part of the appellant in cancelling the work order and by which the High Court has held that original writ petitioner No.1 is entitled to make the supply in pursuance of the work order dated 07.02.2020 to the appellant H 429 MUNICIPAL COUNCIL GONDIA v. DIVI WORKS & SUPPLIERS, HUF & ORS [M. R. SHAH, J.] herein and consequent to which it will be entitled to the payments as per A the terms of the work order, original respondent No.2 – Municipal Council, Gondia through its Chief Officer has preferred the present appeal. 2. The appellant – Municipal Council is running educational institutions/schools. There was a requirement for benches, almirahs and tables in a school run by it. Accordingly, resolution dated 12.12.2018 B came to be passed for purchasing desks, benches, almirahs and tables. An e-tender was issued by the appellant vide letter dated 19.09.2019 by virtue of which, bids were invited. That original writ petitioner No.1 participated in the tender and was declared the successful bidder and the same was sanctioned by the Standing Committee of the Municipal C Council. Thereafter, an Agreement came to be executed between the original writ petitioner No.1 and the appellant, as a result of which, work order dated 07.02.2020 came to be issued in favour of original writ petitioner No.1. However, in view of the Covid-19 Pandemic and the lockdown in force, the Government of Maharashtra published G.R. dated 04.05.2020 by which it was provided that owing to Covid 19 restrictions D impacting government finances, non-priority expenditure like in the present case, should not be incurred. In pursuance of above G.R., the President of Municipal Council, Gondia vide communication dated 18.05.2020 informed the Chief Officer that as the Municipal Council was not having any income due to ongoing lockdown and most of the schools were E closed due to pandemic, no purchases should be made and no proposal for the same should be forwarded. In view of the above, the Chief Officer of the Municipal Council informed the original writ petitioner No.1 that the work order had been suspended until further orders. It is the case on behalf of the appellant that after obtaining the report from the Education Officer that the original writ petitioner No.1had not taken any further F steps in regard to supply of material as per the work order and having found that since the supply of desks, benches etc., was not urgent in nature during the time of pandemic and considering the G.R. dated 04.05.2020, the Municipal Council cancelled the work order till further orders. D G 2.1 Feeling aggrieved and dissatisfied with the action of the Municipal Council vide letter dated 07.07.2020 suspending/cancelling the work order till further orders respondent No.1 & 2 herein – original writ petitioners preferred W.P. No.1984 of 2020 before the High Court. By the impugned judgment and order the High Court has set aside the H 430 SUPREME COURT REPORTS [2022] 2 S.C.R. A action of the Municipal Council vide letters dated 18.05.2020 and 07.07.2020 and has held that original writ petitioner No.1 is entitled to make the supply in pursuance of the work order dated 07.02.2020 to the Municipal Council and consequent to which it is entitled to the payments as per the terms of the work order. B 3. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court, the Municipal Council has preferred the present appeal. 4. The present appeal was heard by this Court on 07.02.2022. It was submitted on behalf of the original writ petitioners that in fact they C have already manufactured the goods which are customized and therefore, if the Municipal Council is not directed to lift the customized manufactured goods which the original writ petitioners prepared/got prepared as per the work order, the original writ petitioners would suffer a huge loss. This Court passed the following order on 07.02.2022: - D “Having heard learned counsel appearing on behalf of the respective parties and considering the fact that as such on the order being placed by the petitioner, the respondent has already manufactured the goods which are customized and during the last two years, there may be some difficulty faced by the petitioner due to COVID-19 pandemic. But, now as the schools have reE started, we direct the official of the petitioner to visit the place where the manufactured goods are kept and identify the goods which are immediately required, at this stage which shall not be less than 25% of the total quantity manufactured and also make a schedule with respect to the balance goods manufactured and F when the goods will be lifted and payment shall be made. Put up on 21.02.2022.” 5. Shri Gaurav Agrawal, learned counsel appearing on behalf of the appellant – Municipal Council has submitted that pursuant to the order passed by this Court on 07.02.2022, the official of the Council G visited the premises of respondent No.1 on 10.02.2022. The officials of the Council were asked to visit Nagpur which they did on 11.02.2022. On inspection of the goods, it was seen that the goods do not meet the requirement of the work order and that they were not prepared for the Council as claimed by the original writ petitioners before this Court. It is pointed out that even vide communication dated 18.02.2022 respondent H 431 MUNICIPAL COUNCIL GONDIA v. DIVI WORKS & SUPPLIERS, HUF & ORS [M. R. SHAH, J.] No.1 had admitted that goods were not available. It is therefore submitted that there are no manufactured goods available as per the specifications and the requirements of the Council and as per the work order and even the manufactured goods are not available till date, and hence there is no question of accepting any goods as per the work order as directed by the High Court. 6. Shri R.L. Khapre, learned Senior Advocate appearing on behalf of the original writ petitioners has tried to explain the reasons as to why the manufactured goods are not available. It is submitted that as more than two years have passed and the goods manufactured with specifications were dismantled for proper storage as well as maintenance including polishing thereof and were kept in the available space/storage at Nagpur as it was practically impossible to store such huge quantity of material for such a long period due to unavailability of space as well as having regard to the their maintenance. Therefore, it is requested to grant some time for reassembling the goods in question for supply as early as possible. A B C D 7. We have heard the learned counsel appearing on behalf of the respective parties at length. 8. At the outset, it is required to be noted that by the impugned judgment and order the High Court has issued a writ of mandamus virtually granting the relief of specific performance of the contract/work order. From the impugned judgment and order passed by the High Court it appears that the High Court was made to believe that the original writ petitioners had already manufactured the goods which are customized and as per the specifications and the work order. However, it is now found that there are no manufactured goods readily available which can be supplied to the appellant – Council. There are disputed questions of fact such as whether in fact the goods were manufactured as per the specifications or not. Nothing was on record before the High Court that goods were in fact and actually manufactured by the original writ petitioner No.1, as per the specifications and the requirements of the Council and as per the work order. In absence of any evidence and material on record and there being disputed questions of facts the High Court ought not to have passed the impugned judgment and order directing the Council to continue the work order and accept the goods from the original writ petitioner No.1 and to make the payments as per the work order. Even otherwise, no writ of mandamus could have been issued E F G H 432 SUPREME COURT REPORTS [2022] 2 S.C.R. - A virtually granting the writ for specific performance of the contract/work order in a writ petition under Article 226 of the Constitution of India. The original writ petitioner sought to have been relegated to file a civil suit for appropriate relief of losses/damages, if any, sustained. - 8.1 Even otherwise on merits also the High Court has erred in - B setting aside the communication dated 18.05.2020 and 07.07.2020. The High Court has not at all appreciated the reasons for suspending/cancelling the work order till further orders. It is to be noted that the decision dated 07.07.2020 was taken pursuant to the G.R. dated 04.05.2020 which was necessitated due to Covid-19 Pandemic and there was a lockdown and the schools were closed and that the Council had no sufficient funds. - C Even the said decision was taken after calling for a report from the Education Officer in regard to the tender/work order issued to the original writ petitioner No.1 and the Education Officer informed that the original writ petitioner No.1 has not taken any further steps in regard to supply of material as per the work order. Therefore, the High Court has erred - D in quashing and setting aside the communication dated 07.02.2020 in exercise of powers under Article 226 of the Constitution of India. 9. In view of the above and for the reasons stated above the present appeal succeeds. The impugned judgment and order passed by the High Court in W.P. No.1984/2020 is quashed and set aside. E Consequently, the original writ petition stands dismissed. However, it is made clear that this shall not preclude the original writ petitioners in initiating appropriate proceedings before the civil court for the damages/ losses, if any suffered by them, which may be considered in accordance with law and on its own merits and on the basis of the evidence to be led. The present appeal is accordingly allowed to the aforesaid extent. F No costs. Devika Gujral Appeal allowed. G H
End of Judgment Record
Browse All Supreme Court of India (2022) Decisions
2022-12-09

MOHD. SABEER @ SHABIR HUSSAIN v. RM, U. P. STATE ROAD TRANSPORT CORP.

The appellant, Mohd. Sabeer (also known as Shabir Hussain), a scrap dealer, was a passenger in a UP State Road Transport Corporation bus when the driver rashly and negligently drove the vehicle, causing a collision near Ghaziabad in 2009. He sustained grave injuries including an amputation of the right lower limb and other bodily injuries. The Motor Accident Claims Tribunal (MACT) awarded Rs. 15,76,465 with interest; the High Court of Delhi enhanced the amount to Rs. 16,70,932. The Disability Certificate recorded 70% permanent disability. The High Court had treated the claimant’s functional disability as 35%, relying on post‑accident income reflected in IT returns, and erred in not adequately recognizing the impact on earning capacity of a self‑employed person who cannot drive. The Supreme Court held that the appellant’s functional disability should be treated as 60% for loss of future earning capacity and that permanent disablement warrants consideration of future prospects in addition to future income. It invoked National Insurance Co. v. Pranay Sethi to apply a 40% addition for future prospects, and directed compensation for prosthetic limb purchase and maintenance, as well as enhanced non‑pecuniary damages. The final award was increased to Rs. 38,70,120 with 9% interest from the date of application, and the appeals were allowed, emphasizing liberal, holistic justice to restore the claimant to his pre‑accident position in light of socio‑economic factors.

2022-01-25

Intercontinental Hotels Group (India) Pvt. Ltd. & ANR. v. Waterline Hotels Pvt. Ltd.

Intercontinental Hotels Group (India) Pvt. Ltd. & Anr. v Waterline Hotels Pvt. Ltd. is a Supreme Court decision addressing appointment of a sole arbitrator under Section 11(6) read with Section 11(12)(a) of the Arbitration and Conciliation Act, 1996, in a dispute arising from a Hotel Management Agreement (HMA) for renovating the Holiday Inn & Suites Bengaluru, Whitefield. The petitioners allege breach by Waterline Hotels, including non-payment of incentive management fee and related charges, culminating in Waterline’s email termination of the HMA on 12 October 2018 after rebranding the hotel as Miraya. The petitioners invoked arbitration; Waterline challenged the enforceability of the arbitration clause on the ground that the HMA is an unstamped instrument under the Karnataka Stamp Act. A Karnataka High Court ad‑interim relief was granted in 2018, but the Supreme Court’s judgment focuses on the scope of judicial interference at the pre‑appointment stage. The Court reiterates a pro‑arbitration stance, noting that arbitrability/validity are generally matters for the arbitrators, with a narrow exception to cut deadwood or to refer for authoritative settlement where necessary, invoking Vidya Drolia. It also analyzes stamp duty, observing that stamp duty has been paid (albeit disputed) and that the question of the correct stamp duty may be resolved later, not as a precondition to appointing an arbitrator. Consequently, the Court appoints Justice A. V. Chandrashekara as a sole arbitrator, directs SIAC to proceed under its rules, and allows the petition in terms stated, while leaving stamp duty issues for arbitration to determine later.

2022-02-01

The State of Sikkim v. Jasbir Singh & ANR

This appeal by the State of Sikkim challenges a High Court judgment upholding a Sessions Judge’s order directing a written notice to the Army’s commanding officer to transfer the case to a court-martial. The case concerns concurrent jurisdiction between a court-martial and an ordinary criminal court under the Army Act for an offence allegedly committed by Lance Naik Jasbir Singh during active service in Sikkim, with the FIR under IPC 302 and related charges. The High Court held that the procedure under Sections 125/126 Army Act, the 1978 Rules (Rules 3-5) and CrPC Rule 475 had not been observed and that the Army authorities had exercised their discretion to prefer a court-martial; thus, the court-martial alone would have jurisdiction. The Supreme Court, however, held that the offence falls into a category with concurrent jurisdiction under Sections 69 and 70 of the Army Act, and that where there is concurrent jurisdiction, the first instance discretion to choose the forum lies with the designated officer under Section 125. In the present case there was no decision by the designated officer to institute proceedings before a court-martial, and the sequence of events showed significant cooperation with the CrPC process. Consequently, the Sessions Judge’s competence to proceed in the criminal court was not in error, the High Court’s order is set aside, and the respondent-accused is to be transferred to civil custody to face trial in the criminal court. The appeal is allowed.

2022-07-22

Hemant Kumar Verma & Ors. v. Employees State Insurance Corporation & Ors.

This writ petition concerns whether junior resident doctors in ESIC-run medical colleges should be eligible for the 50% in-service reservation for postgraduate medical courses, a benefit presently available to Insurance Medical Officers Grade-II (IMO-II) recruited through competitive selection. ESIC recruits IMO-II and provides a 50% in-service quota for PG seats; however junior residents, who complete MBBS under bond and serve as part of ESIC's residency scheme, are not deemed in-service doctors. The petitioners argued parity with IMO-II because their qualifications, duties, and work environment are similar, and urged the Court to treat them as in-service to extend the 50% reservation to their batch. ESIC contends that junior residents are contractual, bond-based appointees governed by the ESIC Residency Scheme; IMO-II is a permanent post governed by the ESIC Staff and Condition of Service Regulations 1959; the bond reduction in 2020 and the 2018/2020 memoranda cannot convert junior residents into in-service doctors. The Court relies on precedents establishing institutional preference in PG admissions—Saurabh Chaudri v. Union of India, Yatin Kuma Jasubahi v. State of Gujarat, and Pradeep Jain v. Union of India — to acknowledge the legitimacy of institutional preference, but ultimately holds that junior residents and regular ESIC doctors are distinct categories and the in-service quota cannot be equitably extended to junior residents. The petition is dismissed.