High Court of KeralaKerala High Court · 2009Division BenchRevision petition dismissed; with directions.

Muhammed Abdurahiman and Noorudheen v. Puthenveettil Abdul Salam and others

Case / Petition Number:
RCR No. 282/2008 (R.C.R.No.282/08)

Case Synopsis & Summary

This is a Division Bench judgment of the Kerala High Court in Rent Control Revision (RCR No. 282/2008) arising from eviction proceedings under the Kerala Buildings (Lease and Rent Control) Act, 1965. The revision petitioners- tenants challenge an eviction order passed by the Rent Control Court, Ponnani in R.C.P. No. 29/2004 under sections 11(2), 11(3), 11(4)(iii) and 11(8), affirmed by the District Judge, Manjeri in RCA No. 24/2005 on 18-10-2008. The landlords contend rent arrears since December 2001, bonafide need to use the petition schedule shop to conduct a textile business, and to provide access to an upstairs portion; they also assert there are other rooms in the locality and that the tenants are not dependent on the petition schedule building. The tenants deny rent arrears, contest the bonafide need, and note that one respondent shifted to another building while the first petitioner depends on income from the shop. The High Court examines evidence, including PW1, the Commissioner’s report, and Exts. A1–A7, and applies established law on tenancy, dependency and bona fides. It cites Jess Raphel v. Regina, Krishnan Thampi v. Sankaradas, Albert Mendez v. Rema Chandran, and Prasannan v. Haris to address pleadings and proof requirements, and ultimately upholds the concurrent eviction orders while granting time to vacate with conditions.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Pius C. KuriaKose
  • P. Q. Barkath Ali
Judgment Date
2009-07-14
Court Decision / Holding
The revision petition is dismissed with the above directions.
Final Disposition
Revision petition dismissed; with directions.

Parties to the Case

Appellants / Petitioners

  • Muhammed Abdurahiman
  • Noorudheen

Respondents

  • Puthenveettil Abdul Salam
  • Shamsudheen
  • Ashraf
  • Majeed

Legal Representation & Advocates

Counsels for Petitioners

  • • K. Ramakumar
  • • J.R. Prem Navaz
  • • T. Ramprasad Unni

Counsels for Respondents

  • • John Joseph Vettikkad
  • • C. Joseph Johny

Provisions of Law Cited

Section 20 of the Kerala Buildings (Lease and Rent Control) Act, 1965Section 11(2)Section 11(3)Section 11(4)(iii)Section 11(8)Section 11(2)(c)First proviso to Sub Section 3 of Section 11Second Proviso to Sub Section 3 of Section 11Section 11(12)

Legal Doctrines & Maxims

  • Burden on the tenant to prove that the building in possession is not reasonably sufficient to conduct his business (Jess Raphel v. Regina, 2003 KLT SN 9).
  • Dependency is not financial dependency, but dependency for the building which belongs to the landlord (Krishnan Thampi v. Sankaradas, 2002(1)KLT 930).
  • Tenant has to plead and prove both ingredients of the Second Proviso to Sub Section 3 of Section 11 (Prasannan v. Haris, 2005(2) KLT 365).

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contended that rent arrears were not established; bonafide need stated by landlords was not genuine; second respondent had shifted to another building; the first petitioner depended on income from the petition schedule shop; several rooms in the locality were vacant, and the petition schedule room was not indispensable for the landowners’ textile venture. They argued the case law requiring dependency pleadings should be strictly interpreted against the landlords and that the landlords possessed other properties to meet their needs.

Contentions of Respondents

The landlords argued that rent arrears existed and must be paid; they require the petition schedule shop to start a textile business and to provide access to the upstairs; there are no suitable alternative arrangements available within the locality; the second provisos to Section 11(3) were not applicable given the landlords’ bonafide need; they contended that the tenants failed to plead or prove dependency and that the court rightly upheld eviction.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Jess Raphel v. Regina2003 KLT SN 9PositiveBurden on the tenant to prove the building in possession is not reasonably sufficient to conduct his business.
Albert Mendez v. Rema Chandran2007(3) KLT 23DistinguishedThe court declined to follow the proposition that dependency must be pleaded by the landlord; distinguishing its own application on facts.
Krishnan Thampi v. Sankaradas2002(1)KLT 930PositiveDefined dependency as dependency for the building which belongs to the landlord, not financial dependency.
Prasannan v. Haris2005(2) KLT 365PositiveTenant must plead and prove both ingredients of the Second Proviso to Sub Section 3 of Section 11.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,219 words•~11 min read

In The Court Record

Muhammed Abdurahiman and Noorudheen v. Puthenveettil Abdul Salam and others

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE PIUS C.KURIAKOSE &** **THE HONOURABLE MR. JUSTICE P.Q.BARKATH ALI** **TUESDAY, THE 14TH JULY 2009 / 23RD ASHADHA 1931** **RCRev..No. 282 of 2008()** **------------------------** **RCA.24/2005 of DISTRICT COURT, MANJERI RCP.29/2004 of MUNI-MAGI.COURT,PONNANI** **....................** ## **PETITIONERS/APPELLANTS/ RESPONDENTS** **-----------------------------------------------------** **1. MUHAMMED ABDURAHIMAN, AGED 50 YEARS, S/O.K.BEERAN, THERUVATHU VEETTIL, OM THRIKOVU RAOD, PONNANI-679577.** **2. NOORUDHEEN, AGED 48 YEARS, S/O. K.BEERAN THERUVATHU VEETTIL, OM THRIKOVU ROAD, PONNANI-679577.** **BY ADV. SRI.K.RAMAKUMAR, SENIOR ADVOCATE SRI.J.R.PREM NAVAZ SRI.T.RAMPRASAD UNNI** ## **RESPONDENT(S): RESPONDENTS/PETITIONER** **-------------------------------------** ## **1. PUTHENVEETTIL ABDUL SALAM,** - **S/O.MANAMKULATHU MOIDEENKOYA, GURUVAYOOR AMSOM, PALAYUR DESOM, CHAVAKKAD TALUK,THRISSUR DIST.R/B THE P/A HOLDER MR.SHAMSUDHEEN, S/O.MANAMKULATHU MOIDEENKOYA, GURUVAYOOR AMSOM, PALAYUR DESOM, CHAVAKKAD TALUK, THRISSUR DIST(2ND RESPONDENT)** **2. SHAMSUDHEEN, S/O.MANAMKULATHU MOIDEENKOYA, GURUVAYOOR AMSOM, PALAYUR DESOM, CHAVAKKAD TALUK, THRISSUR DISTRICT.** **3. ASHRAF S/O.MANAMKULATHU MOIDEENKOYA, GURUVAYOOR AMSOM, PALAYUR DESOM, CHAVAKKAD TALUK, THRISSUR DIST,R/B THE P/A HOLDER MR.SHAMSUDHEEN, S/O.MANAMKULATHU MOIDEENKOYA, GURUVAYOOR AMSOM, PALAYUR DESOM, CHAVAKKAD TALUK, THRISSUR DIST. (2ND RESPONDENT HEREIN).** ## **RCR.NO.282/08** **4. MAJEED, S/O.MANAMKULATH MOIDEENKOYA, GURUVAYOOR AMSOM, PALAYUR DESOM, CHAVAKKAD TALUK, THRISSUR DIST.R/B. P/A.HOLDER MR.SHAMSUDHEEN, S/O.MANAMKULATHU MOIDEENKOYA, GURUVAYOOR AMSOM, PALAYUR DESOM, CHAVAKKAD TALUK, THRISSUR DIST. (2ND RESPONDENT HEREIN)** **ADV. SRI.JOHN JOSEPH VETTIKAD FOR RPTS.** **SRI.C.JOSEPH JOHNY FOR RPTS.** **THIS RENT CONTROL REVISION HAVING BEEN FINALLY HEARD ON 14/07/2009, THE COURT ON THE SAME DAY PASSED THE FOLLOWING:** ## **PIUS.C.KURIAKOSE & P.Q.BARKATH ALI, JJ.** - - - - - - - - - - - - - - - - - - - - - ## **R.C.R.No.282 OF 2008** - - - - - - - - - - - - - - - - - - - - - - - - - - Dated this the 14[th] day of July, 2009 ## **ORDER** ## Barkath Ali, J. In this rent control revision under Section 20 of the Kerala Buildings ( Lease and Rent Control) Act 1965, the defeated tenants challenge the order of eviction passed against them by the Rent Control Court, Ponnani in R.C.P.No.29/2004 under Section 11(2), 11(3), 11(4) (iii) and 11(8) of the Act, which is confirmed by the Appellate Authority in R.C.A.No. 24/2005 by judgment dated 18/10/2008. 2. The revision respondents/landlords filed R.C.P.No.29/2004 before the Rent Control Court, Ponnani against the revision petitioners/tenants seeking eviction under Sections 11(2), 11(3), 11(4) (iii) and 11(8) of the Rent Control Act alleging that the tenants have kept rent in arrears from December 21, 2001 onwards, that landlords bonafide require the petition schedule shop room for conducting textile business, that the landlords intend to provide a staircase to the upstairs portion of the building from the petition schedule room, that tenants are not depending for their livelihood on the income derived from the RCR.No.282/2008 2 business conducted in the petition schedule shop room, that there are other suitable rooms available in the locality to conduct their business and that tenants have other rooms in their possession. 3. The revision petitioners/tenants resisted the claim contending that they have not kept the rent in arrears, that the bonafide need put forward by the landlords is not genuine, that second respondent in the rent control petition has shifted his residence and business to another building and that first petitioner is depending for his livelihood on the income derived from the business conducted in the petition schedule building. 4. The second petitioner in the rent control petition who is the second respondent in the revision petition was examined as PW1 and Exts.A1 to A7 were marked on the side of the landlords before the Rent Control Court. Advocate Commissioner was examined as CW1 and his report and plan were marked as Ext.C1 and C2. Exts.X1 to X4 were also marked. On the side of the tenants, RW1 was examined . 5. The Rent Control Court on an appreciation of evidence allowed the Rent Control Petition on all grounds. On appeal by the RCR.No.282/2008 3 tenants, the Appellate Authority ( District Judge), Manjeri confirmed the said findings of the Rent Control Court. Now the tenants have come up in revision. 5. The point which arises for consideration is whether the concurrent findings of the Rent Control Court as well as that of the Appellate Authority ordering eviction under Section 11(2), 11(3), 11(4) (iii) and 11(8) of the Act can be sustained ? 6. As regards the order of eviction passed under Section 11(2) of the Act, it is not seen challenged by the revision petitioners. Therefore, we confirm the said order passed by the Rent Control Court which is confirmed by the Rent Control Appellate Authority. The tenants shall deposit arrears of rent to get the order vacated under Section 11(2)(c) of the Act within one month from this date. 7. Regarding the claim for eviction under Section 11(4)(iii) of the Act, it is admitted by the revision petitioners that second revision petitioner is not doing any business in the petition schedule building and that few years ago, he started a new business in another shop room about 100 metres away from the petition schedule building. The first RCR.No.282/2008 4 revision petitioner as RW1 before the Rent Control Court admitted that he is in possession of two shop rooms nearby, where he keeps the stock in trade. The Commissioner has also reported about the said room. It is settled law and held in _**Jess Raphel v. Regina**_ (2003 KLT SN 9) that burden is on the tenant to prove that the building in possession is not reasonably sufficient to conduct his business. The tenants have not adduced any evidence to establish the above point. That being so, the Rent Control Court as well as the Appellate Authority are justified in finding concurrently that landlords are entitled to an order of eviction under Section 11(4)(iii) of the Act and we confirm the same. 8. Regarding the claim for eviction on the ground of bonafide need for additional accommodation, the case of the landlords is that they intend to start a textile business in the petition schedule building and that the petition schedule room is required to provide a staircase to the up stair of the building . 9. Sri.K.Ramkumar, learned senior counsel for the revision petitioners/tenants citing the decision in _**Albert Mendez v. Rema Chandran**_ (2007(3) KLT 23) argued that dependency has to be pleaded RCR.No.282/2008 5 and proved, that in the present case the landlords have not pleaded that revision respondents 2 and 3 and their children are dependent on the first revision respondent with whom revision respondents 2 and 3 intend to start the business and further the landlords have several other buildings of their own and that therefore the bonafide need put forward by the landlords is not genuine. We are unable to agree. It is not disputed that dependency has to be pleaded and proved. It is settled law and held in _**Krishnan Thampi v. Sankaradas**_ (2002(1)KLT 930) that dependency does not mean financial dependency, but dependency for the building which belongs to the landlord. 10. Sri.K.Ramkumar, learned senior counsel for the tenants took us through the Rent Control Petition as well as the the evidence of PW1. On going through the Rent Control Petition, we feel that there is sufficient pleadings regarding the dependency of the revision respondents and their sons. But in evidence, PW1 did not say in so many words regarding the dependency of other revision respondents. But he has stated that the sons of revision respondents have no job of their own. But in our view the question of dependency does not arise in RCR.No.282/2008 6 this case. Revision respondents 2 and 3 are also the landlords. They need not plead and prove dependency as they bonafide need the petition schedule shop room to conduct a textile business. The specific case of the landlords is that they require the petition schedule room to have an access to the upstairs by providing staircase in that petition schedule room. Admittedly, the up stair portion of the building is vacant and is in the possession of landlords and the landlords have no other buildings in their possession in Ponnani Taluk. Therefore, we find no merit in the above argument advanced by the learned senior counsel for the revision petitioners and reject the same. 11. It was next argued by Sri.Ramkumar, learned senior counsel for the revision petitioners that PW1 admitted in cross examination that himself and his brothers have a big shopping complex in Chavakkad and have several other business establishments and that therefore it is very unlikely that they will start any business in the petition schedule building and that therefore the bonafide need put forward by the landlords is only a pretext for evicting the tenants. We do not agree. Merely because the landlords have several other establishments, they are RCR.No.282/2008 7 not prevented from starting any business in the petition schedule building. Further, all their business establishments are in Chavakkad which is about 25-30 Kms. from Ponnani. Sri.John Joseph Vettikkad, learned counsel for the landlords submitted that landlords actually intend to start textile business in the petition schedule building. The tenants have no case that the said building is not suitable to start textile business. For all these reasons, we confirm the findings of the Rent Control Court as well the Appellate Authority that the landlords bonafide require the petition schedule building to start textile business. 12. The next question for consideration is whether the tenants are entitled to the benefit of first and second provisos to Sub Section 3 of Section 11. On this point also, both the courts below have concurrently found against the tenants. Admittedly, the second revision petitioner is conducting a business in a nearby building and the first revision petitioner is conducting a ration shop in another shop room. Exts.X1 to X4 show that first revision petitioner is the licencee of the shop for conducting the business therein. The first revision petitioner as RW 1 would say that the said ration shop was conducted by somebody RCR.No.282/2008 8 else though licence is in his name which is not proved. RW1 has not adduced any evidence to show the income from his business conducted in the petition schedule shop room and from the ration shop. Further in cross examination RW1 admitted that there are several other rooms in the locality lying vacant. The Commissioner has also reported about the several closed nearby shop rooms. It is settled law and held in _**Prasannan v. Haris**_ (2005(2) KLT 365) that tenant has to plead and prove both the ingredients of Second Proviso to Sub Section 3 of Section 11 of the Act. In the present case, tenants have failed to prove that aspect. Therefore, both the courts below is justified in finding this point against the tenants. We confirm the said findings of the Rent Control Court and the Appellate Authority. 13. Sri.K.Ramkumar, learned senior counsel pointed out that admittedly the landlords are in possession of other buildings which disentitle them to claim eviction under Section 11(3) of the Act as provided under first proviso to Sub Section 3 of Section 11 of the Act. Sri.John Joseph Vettikkad, learned counsel for the landlords correctly pointed out that all the buildings in the possession of the landlords are in Chavakkad RCR.No.282/2008 9 about 25-30 Kms from Ponnani where the petition schedule building is situated. That being so, we find no merit in the above argument advanced by the learned senior counsel and hold that tenants are not entitled to the benefit of first proviso to Sub Section 3 of Section 11. 14. We therefore confirm the findings of the Rent Control court as well as the Appellate Authority ordering eviction under Section 11 (2), 11(3) and 11(8) of the Act. The tenants shall deposit arrears of rent as ordered by the courts below and get the order under Section 11(2) of the Act vacated. Learned counsel for the landlords submitted that after getting eviction under Section 11(3) of the Act, revision respondents 1 and 2 will occupy the same and that they will start business along with other landlords. If they do not occupy the petition schedule building within one month from getting vacated, the tenants can apply to the Rent Control Court for getting themselves re-inducted in the building under Section 11(12) of the Act. The landlords counsel submitted that the landlords are agreeable to suffer the above direction. 15. Sri.K.Ramkumar, learned senior counsel requested atleast one year's time for vacating the building, which is opposed by Sri.John RCR.No.282/2008 10 Joseph Vettikkad, learned counsel for the respondents. Taking into consideration the fact that the tenants are conducting business in the petition schedule building, we feel that time till 31/03/2010 can be granted to vacate the building on the following conditions; 1) The tenants shall file an affidavit before the Rent Control Court within one month from today stating that they will surrender petition schedule room to the landlords on or before 31/03/2010. 2) The tenants shall pay the rent upto date within one month from this date and future rent till the date of surrender as and when the same falls due, failing which the benefit of time granted by this order will not be available for the revision petitioners. The revision petition is dismissed with the above directions. No costs. ## **PIUS.C.KURIAKOSE JUDGE** ## **P.Q.BARKATH ALI JUDGE** sv. RCR.No.282/2008 11 RCR.No.282/2008 12
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.