Supreme Court of IndiaSupreme Court · 1965Division BenchAppeal dismissed.

Mugneeram Bangur & Co. v. Sardar Gurbachan Singh

Case / Petition Number:
Civil Appeal No. 180 of 1962
Neutral Citation:1965 SCR 630

Case Synopsis & Summary

Mugneeram Bangur & Co. v. Sardar Gurbachan Singh deals with a May 1941 contract for the purchase of plots in the Lake Colony Scheme, wherein the purchaser paid earnest money and undertook to complete the transaction within one month from the date of completion of development work. During World War II, large tracts were requisitioned under Defence of India Rules, preventing the developer from completing roads and drains. In December 1943 the company issued a circular offering purchasers two options: (i) refund of earnest money, or (ii) complete the conveyance within one month on the condition of taking land in its undeveloped state and with development to be completed later. The respondent sought to enforce the contract while the land remained requisitioned; the company argued that the contract was discharged by frustration since performance became unlawful due to government orders, and that the suit for specific performance was premature since a sale deed could be obtained only after development. The Calcutta High Court decreed for the respondent; on appeal the Supreme Court examined whether requisitioning rendered performance unlawful to an extent that discharged the contract. The Court held that temporary illegality did not automatically discharge the contract; time was not shown to be of the essence, and the parties anticipated difficulties. The appeal was dismissed with costs, reaffirming that discharge requires time‑essence or permanent illegality, not merely temporary disruption.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. N. Wanchoo
  • J. R. Mudholkar
Judgment Date
1964-12-16
Court Decision / Holding
Appeal dismissed with costs.
Final Disposition
Appeal dismissed.

Parties to the Case

Appellants / Petitioners

  • Mugneeram Bangur & Co.

Respondents

  • Sardar Gurbachan Singh

Legal Representation & Advocates

Counsels for Petitioners

  • • B. Sen
  • • S. N. Mukherjee

Counsels for Respondents

  • • Hem Chandra Dhar
  • • S. S. Khanduja
  • • Ganpat Rai

Provisions of Law Cited

Section 56 of the Indian Contract Act, 1872Section 46 of the Indian Contract Act, 1872Section 32 of the Indian Contract Act, 1872

Legal Doctrines & Maxims

  • Time is of the essence of the contract
  • Frustration of contract
  • Unlawful performance
  • Reasonable time

Submissions & Arguments

Contentions of Appellants / Petitioners

Applicants argued that the contract was discharged by frustration due to government requisitioning which rendered performance unlawful, and that the suit for specific performance was premature since the sale deed could not be obtained until the development work was completed.

Contentions of Respondents

Respondents resisted the suit on several grounds, contending that the contract could not be said to be discharged merely because of requisition; that the time for performance was not necessarily essential; and that the circular letter of December 1943 offered options affecting cancellation or completion, implying a potential for continuing performance or termination within the contemplated framework.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Denny Mott & Diskon Ltd. v. James B. Fraser & Co. Ltd.[1944] A.C. 265PositiveCited to discuss how unlawfulness and duration of impediments affect discharge, aiding the court’s view that temporary illegality does not automatically discharge a contract.
Satyabrata Ghose and Ors. v. Mugneeram Bangur & Co.[1954] SCR 310PositiveEarlier decision binding on the question of frustration and requisition; the court notes it would be covered by that decision and thus relies on its principles.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,717 words•~17 min read

In The Court Record

Mugneeram Bangur & Co. v. Sardar Gurbachan Singh

630 MUGNEERAM BANGUR & CO. v. SARDAR GURBACHAN SINGH _December_ 16, 1964 A (K. N. WANCHOO AND J. R. MUDHOLKAR, JJ.] B _Contract Act,_ _s._ _56-Contract_ _to_ _purchase plot-Subject to_ comp~_twn_ _of_ _development work-Government requisitioning_ _/and-Rendering_ _completion temporarily unlawful-Whether contract_ _disc.harged._ In May 1941, the respondent had entered into a contract with the appellant company for the purchase of a plot of land in a Colony Scheme. #### He had paid the earnest money and had undertaken to complete the c transaction within one month from the date of completion of certain development work by the appellant. Thereafter, the land in question was requisitioned by the Government under the Defence of India Rules and the company was therefore unable to undertake the development work during the continuance of the war. On learning that the Government proposed to de-requisition the lands taken over by them, in May 1946, the respondent approached the com- D pany to ascertain when it would complete development work after the de-requisitioning of the land, so that be might complete the transaction within one :nonth thereafter. The company claimed that the contract 1tood cancelled since the respondent had failed to comply with the terms of a circular Jetter issued by it in December 1943, offering all purchasers an option between' accepting refund of the earnest money or completing the transaction immediatoly by accepting the land in an undeveloped state. The respondent denied having received the circular letter and filed a auit E in August 1946, which was decreed by the trial court and the decree was upheld by the High Court in appeal. In the Supreme Court it was contended on behalf of the company that the contract was discharged by reason of frustration because its .performance was rendered unlawful as a result of the requisitioning orders made by the Government, and furthermore, that the suit for specific performance was premature, because, under the contract the respondent did F not get the right to obtain a sale deed till after the development work wu complete. HELD : (i) It cannot be said 'ihat because of the requisitioning orders which had the effect. of making the entry by or on behalf of the company on the land illegal, during the subsistence of the period of requisitioning, the contract stood discharged by frustration. (637 HJ If time is of the essence of the contract, or if the time for the perfor- G mance is set out in the contract, the contract would stand discharged. even though its performance may have been rendered unlawful for an .. indeterminate time, provided unlawfulness attached to the performance at the time when the contract ought to have been performed. [637 A-CJ In the· present case, it could not~ be said that time was of the essence of the contract or that the contract had been discharged because it had not been performed in a reasonable time within the meaning of s. 46 of H the Contract Act. When the parties entered into the contract, they k.nc:;; [1] .v the prevailing circumstances and must have borne in mind the possibility of difficulties in obtaining the necessary material or the possibility of the land being requisitioned by the Government. (637 E-HJ ·..,.. '-.. ##### • •MUGNEERAM co. _v._ GURBACHAN · _(Mudholkar,_ _l.)_ 631 #### . . ': .. '• . ::. A,· _Denny Mott_ & Dicks~n _Ltd._ ',;;l~',n~j _B."F;:isser_ & _Co. Ltd._ [1944) A.C. 265 and _Satyabrata Ghose and Ors._ v. _Mugneeram Bangur_ & _Co._ __&c_ _A.nr._ [1954] S.C.R. 310. referred to., (ii) Tue contention that the suit was prematnre could not be accepted because the development work had been completed when the appeal was heard by the High Conrt. ln such a case the conrt would be justified in taking notice of subsequent events in moulding its relief accordingly. [638 B .A-BJ _ D Mudholkar, J. This appeal, like _Satyabraia Ghose_ v. _Mugnee-_ _ram Bangur_ _&_ _Co. and another(_ _[1 ]_ _)_ relates to the effect of requisitioning orders made by the Government during the last war under . which they took possession of land belonging to the appellant company which had been 'divided into building plots by them in purE suance of what is known as the Lake Colony Scheme, by constructing roads and drains. The plaintiff-respondent was one of the _various persons who had entered into contracts with the company for purchase of plots, in pursuance of the public offers made by the company. _This he did by addressing the following letter to the company and paying Rs. 202/- by way of earnest money. F "To ### c Civn.: APPELLATE JURISDICTION: Civil Appeal No. 180 of 1962. . Appeal by special leave from the judgment and decree dated January 28, 1959, of the Calcutta High Court from original Decree No. 226 of 1952. _B. Sen_ and S. _N. Mukherjee,_ for the appellant .. _Hem Chandra Dhar,_ S. S. _Khanduja_ and _Ganpat Rai,_ for the respondent. The Judgment of the Court was delivered by G H Mugneeram Bangur and Company Land Department. Russa Road, South, Tollygunge, Calcutta. No. 499, Phone: South 135. # Through Babu- . Re: Plots Nos. New Nos. 245 and 246 on 30 feet road in the premises No. Lake Colony Scheme No. l, Northern Block. Area measuring-IO ks. x ch. x sqr. ft more or less. (I) [1954] S.C.R. 310. 632 SUPllEl\O COtll.T llEPOllTS (1965)2 S.Cll. Dear Sir, A I am willing to purchase the above plot of land from you at the average rate of Rs. 1,075/- (Rupees one thousand and seventyfive only) per katta irrespective of the condition of the soil and I am ready to deposit Rs. 2'f2/- of the actual value as an earnest money at once. I undert.ike to complete the transaction within B one month from the date on(?) (of) completion of road on payment of the balance of the consideration money and time must ##### be deemed as essence of the contract. If I fail to do so within the said period the earnest money deposited by me will be forfeited and you will be free to resell the land and I shall be liable for all damages that may result thereby. I also agree to sign a formal C agreement in the form required by you if you so desire. Yours faithfully, Name, Gurbachan Singh, Address: 48/1, Chakraberia Road, North. Dated the . . . . . . . . . . . . 19 .... Witness : (lllegible) Address .....•.. N.B. I agree to pay half of the value at the time of registration of the deeds and the balance within 6 years bearing interest at the rate of 6 per cent per annum with half yearly rests and the said plots Nos : 245 and 246 purchased by me shall remain charged for the payment of the balance of the purchase money in manner as aforesaid and the necessary security deed charged should be executed and registered by me at my own cost. Name : Gurbachan Singh ### Address: ....... . Witness (Illegible) 4, Baktiar Shah Road, Tollygunge. The letter does not bear any date; but probably it was written on May 14, 1941 which is the date on which the company issued a receipt in his favour. Different portions of the land covered by the scheme were requisitioned by Government between Novem D F G ber 12, 1941 and July 25, 1944. The plots which the respondents had contracted to purchase are said to form part of the ff; land whii:h was requisitioned by virtue of an order made by the Government on February 18, 1944. MUGNEERAM co. _v._ GURBACHAN _(Mudholkar, I.)_ 633 **A** According to the company, on December 24, 1943, a circular notice was sent to all those persons who had entered into contracts for purchase of plots from them stating that a considerable portion of the land comprised in the Lake Colony Scheme area had been requisitioned under the Defence of India Rules and was taken into possession by the Government. It was not possible to say **B** how long the Government would continue to be in possession and, therefore, it was not possible for the company to carry on the work of the construction of roads and drains during the continuance of the war and possibly for many years even after the termination of the war. The circular then proceeded to state as follows :### c "In these circumstances we have decided to treat the D "In these circumstances we have decided to treat the agreement as cancelled and give you the option of taking of the refund of the earnest money deposited by you within one month from the receipt of this letter. In the event of yous refusal to treat the contract as cancelled, we are offering you, in the alternative, to complete the registration of the conveyance of the sale deed within one month from the receipt of this letter. In such a case )'ou have to take the lands as it is now, the road and drain will be made by us as soon as circumstance will permit after the termination of the War. ##### If you do not exercise your option in any of the two ways mentioned above the agreement will be deemed to have been cancelled and your earnest money forfeited." On May 8, 1946 the respondent's attorneys, acting under instructions, wrote to the company saying that the respondent had learnt from the company's office that the government would be de-requiF sitioning lands taken ove~ by them and inquiring of the company as to when it would be possible for the company to deliver possession of the plots to the respondent. In reply to that letter the company wrote on May 29, 1946 drawing his attention to their circular letter and said that by reason of tbe failure of the respondent to exercise the opti9ns given by them therein the agreeG ment stood cancelled and the earnest money had been forfeited. On June 13, 1946, the respondent's attorneys expressed surprise at the company's reply and stated tbat the respondent had not received the circular referred to in the company's reply and ended by saying as follows : **H** "That my said client, therefore, now hereby asks you as to when you are going to complete the roads, so that he may do the needful for completion of the conveyi\)lces 634 SUPREME COURT REPORTS (1965] 2 S.C.R. within one month from such date of completion of the A roads. That my said client hereby calls upcn you to intimate to him within seven days from date the expected exact date of completion of roads to enable him to com. plete the conveyance as per agreement, failing which he B will be forced to take legal steps against you in the matter as he may be advised in the matter, without further reference which please note." Apparently the company did nothing with the result that the present suit was instituted by the respondent on August 8, 1946 C in the court of the Second Subordinate Judge at Alipore. The company resisted the suit on various grounds but only two are material for the purpose of this appeal because Mr. Sen has con. fined his argument only to those matters. One is that the contract has been discharged by reason of frustration and the second 0 is that the suit was premature. The suit was decreed and that. decree was upheld by the High. Court in appeal. A certificate that the case was fit for appeal to this Court having been refused by the High Court the company sought and obtained from this court special leave to appeal. That is how the matter comes up before us. E This case would really appear to be covered by the decision of this court to which we have referred at the outset. Mr. Sen, however, points out that the question as to whether the contract could be said to have been discharged because of the fact that its performance was rendered unlawful as a result of the requisitioning F orders made by the Government which was sought to be raised before this Court in that case was not permitted to be raised by it and has been ·left open. He admits that certain observations made by this Court towards the concluding portion of the judgment would indicate that this Court was not prepared to accept the contention sought to be urged before it. But, Mr. Sen says that as G the contention was not permitted to be raised, the observations of this Court could be said to havti been made merely in passing and at best be regarded as a tentative expression of its views. We think Mr. Sen is right in the sense that the question has been actually left open by this Court. But even so, we will have to consider whether the grounds upon which the previous decision H rests would not be relevant for consideration in connection with the 'argument advanced by Mt. Sen. MUGNEERAM co. _v._ GURBACHAN _(Mudholkar,_ I.) 635 A In so far as discharge of contract by reason of frustration is concerned there is no question of implying a term in the contract a term· fundamental for its performance, as is done by the courts in England because we have here the provisions of s. 56 aS well as those of s. 32 of the Contract Act. This is what was held by this Court in the earlier case and that decision binds us. No B doubt, a contract can be frustrated either because of supervening impossibility of performance or because performance has become unlawful by reason of circumstances for which neither of the parties was responsible. In the earlier case this Court has held that where the performance · of an essential condition of the contract has C become in,:ipossible due to supervening circumstances the contract would be discharged. This Court has further held that the impossibility need not be an absolute one but it is sufficient if further performance becomes impracticable by some cause for which neither of the parties was responsible. It, however, held that the mere fact that the performance of an essential term of the contract that is to say, of undertaking development of the area under the 0 scheme could not be undertaken because the land had been requisitioned, did not have the effect of frustrating the contract. For though the term regarding development was an essential term of the contract, the requisitioning of the land was only for a temporary period. Further the parties had deliberately not placed E any time limit within which roads and drains had to be made apparently because they were aware of the difficulties in carrying on the work on account of scarcity of materials and the various restrictions which the Government had placed on such activities. This Court also pointed out: A B F "Another important thing that requires notice in this connection is 'that the war was already on, when the parties entered into the contract. Requisition orders for taking temporary possession of lands for war purposes were normal events during this period." (pp. 326-327). G Though these observations were made while dealing with the argument that the contract has been frustrated by reason of impossibility of performanqe they would not be wholly out of place while considering the argument based upon the ground that continued performanc~ of the contract had been rendered unlawful. What s. 56 speaks of is a contract, the performance of which H has become unlawful. Now, it is true that no order was made under the Defence of India Rules prohibiting the company from carrying on the work of consb 11ction of roads and drains. The 636 SUPllEMB COUllT llEPOllTS [1965] 2 S.C.ll. ##### actual order served upon the company, among other things, pro- A. vides: "The owner/ occupier of the said land : (a) shall place the said land at the disposal and under the control of the Military Estates Officer Bengal Circle ### on and from the 14th November, 1941 at r P.M. Bengal B time until six months after,the termination of the present war unless relinquished earlier." In consequence of this order the company lost possession of the land and automatically lost access thereto. Without getting on # to the land the company could not carry out its obligation to the c purchasers of constructing the roads and drains. If, in disobedience of this order, the company's servants, agents or contractors were to carry on the work of construction of the roads and drains by entering on the land of which the possession was with the government, they would have been liable to punishment under subr. (7) of r. 75 (a) of the Defence of India Rules and also the com- D pany. We were informed that the land was used by the Government for military purposes. It is, therefore, possible that the land might have been declared as a protected place under r. 7 of the Defence of India Rules. Even, however, without such a declaration, we agree with Mr. Sen that it would not have been possible for the company, its agents, servants or contractors to go on the land I. during the continuance in fore.:: of the order of requisition without being rendered liable at law. Even so it is clear that all that had become unlawful was to construct roads and drains while the land was bound to be given up by the Government sometime or other and, therefore, in essence _1_ the activities which were rendered unlawful were not forbidden for all time but only temporarily. It may be that the duration of the embargo was uncertain but not permanent. It would, therefore, be relevant to enquire whether a contract could properly be held to be frustrated because for a certain period of time its performance has become unlawful. According to Mr. Sen the moment it G became unlawful for one of the parties to the contract to continue with the performance, the contract was discharged and in this connection he referred us to certain observations of _Lord Wright_ _in Denny Mott_ & _Diskson Ltd._ v. _James B. Fraser_ & _Co. Ltd.,(_ _[1 ]_ _)_ and certain other portions of the report. We put to him the question as to what would be the. effect of a requisitioning, say, for B a period of one month. Would that operate as discharge of the (I) [1944) A.C. _26S,_ 274. MUGNEERAM co. _v._ GURBACHAN _(Mudholkar, 1.)_ &37 A contract ? To that his answer was in the negative and we think that the answer was right. The question then would be : would it make any difference if unlawfulness would attach to the performance of the contract for an indeterminate period ? In our judgment if time is of the essence of the contract or if time for performance is set out in the contract it may be that the contract B would stand discharged even though its performance may have been rendered unlawful for an indeterminate time provided unlawfulness attached to the performance of the contract at the time when the contract ought to have been performed. Thus, where the performance of a contract had been rendered unlawful by reason of some subsequent event the contract would stand dis## c charged but such discharge will take place not necessarily from the date on which the further performance was rendered unlawful, unless further performance was rendered unlawful for all time. ##### If the performance of the contract is rendered unlawful either for a determinate period of time or for an indeterminate period of D time the contract would not stand discharged unless the ban on its performance existed on the day or during the time in which it has to be performed. Here it is pointed out by Mr. Sen that the respondent had made time the essence of the contract but that only applies to the grant of conveyance after the completion of the roads and drains. As already pointed out, parties were wholly E silent as to the time within which the roads and drains were to be completed. Therefore, in so far as this aspect of the contract is concerned time was in no sense made the essence of the contract. According to Mr. Sen, however, where the parties have failed to specify in the contract time within which it has to be performed s. 46 of the Contract Act comes in and the parties may be presumed F to have agreed that the contract will be performed within reasonable time. To that the answer would-be the same as that given in the earlier case, that is, the parties when they entered into the contract, knew the prevailing circumstances and must have borne in mind the possibility that something like what actually happened may happen and, therefore, did not specify the time within which G the land had to be developed. In other words, the parties intended to exclude from the computation of reasonable time such time as was taken up in procuring the necessary material which was not easy to obtain nnd such as may be taken up if the land were requisitioned by government. Thus, in our view it cannot be said that because of the requisitioning orders which had the effect of makH ing the entry by or on behalf of the company on the land illegal --during the subsistence of the period of requisitioning the contract stood discharged. USup.Sl-7 638 SUPREME COURT REPORTS [1965) 2 S.C.ll. Then remains the other point argued by Mr. Sen. He said **A** **that** the suit for specific performance was premature because under the agreement the respondent did not get a right to obtain a sale deed till after the development of the land comprised in the scheme was completed. That is perfectly true. But the fact remains that this work had been completed when the appeal was heard by the High Court. The Court would in such a case be justified in tiling **B** notice of subsequent events in moulding its relief accordingly. In our judgment the courts below were right in upholding the respondent's claim. The apeal is dismis$ed with costs. _Appeal dismissed._
End of Judgment Record
Browse All Supreme Court of India (1965) Decisions
1965-10-26

C.I.T. v. Moon Mills Ltd.

Moon Mills Ltd., a Bombay-based factory, suffered a fire on 6 August 1948 destroying stock-in-trade, machinery and buildings. Insurance policies totalled Rs. 1,48,92,390, and the company received Rs. 65 lakhs in full settlement, paid on 27 March 1950. Of this amount, Rs. 27,06,593 related to losses on buildings and machinery. For 1949-50, Moon Mills did not include this sum in its return since it was received only in 1950. The Income-tax Officer treated the amount as receivable in December 1948 and included it in the 1949-50 assessment. The Appellate Assistant Commissioner held that such compensation could be taxed only under the fourth proviso to section 10(2)(vii) upon actual receipt. The Tribunal and Calcutta High Court upheld this view. The Commissioner contended that, on mercantile accounting, profits should be computed under section 13, and since the assessee had a right to receive the money in December 1948, it became part of taxable income in that accounting year. The Supreme Court held that compensation for loss of a capital asset, not actually received during the accounting year, cannot be taxed in that year. It distinguished between commercial profits and statutory income, and held that the expression "received" cannot be read as "receivable." The appeal was dismissed with costs."

1971-11-05

S. P. Jain v. Kalinga Tubes Ltd.

Two rival shareholder groups, Patnaik and Loganathan, dominated Kalinga Tubes Ltd., a company initially private and later converted into a public company. In 1954 they struck an agreement with S. P. Jain intending equal capitalisation and board representation, with Jain to be chairman. Although the company’s resolutions followed the agreement, no formal amendment to the Articles reflected its terms. By 1957–58 the company sought funds to expand and issued new shares. Disputes arose over whether these shares should be offered to existing shareholders in proportion (as per Section 81, Act 1956) or privately to outsiders. The appellant alleged oppression of the minority and mismanagement under sections 397 and 398 of the Act, claiming the March 1958 general meeting and July 1958 allotments were illegal and oppressive, especially as seven outsiders were allotted shares in haste after an injunction was vacated. The High Court held oppression existed; the Division Bench reversed, stating the 1954 agreement did not bind the public company and no oppression was shown. The Supreme Court held oppression requires continuous, burdensome conduct by the majority, not mere loss of confidence. The 1954 agreement could not bind the public company, and the March/July 1958 actions did not prove oppression or mismanagement. The appeals were dismissed with costs, clarifying the scope of oppression and the availability of alternative remedies to winding up.

1965-01-21

A State of Rajasthan and Others v. Ghasilal

This appeal concerns penalties imposed under the Rajasthan Sales Tax Act for delay in payment of tax following challenges to the validity of Rajasthan Sales Tax Rules (1955). The petitioner (Ghasilal) had challenged the rules; interim High Court orders required filing of accounts and returns but not assessment. An Ordinance (No. 5 of 1959) then validated the Rules, followed by the Rajasthan Sales Tax Validation Act (43 of 1959), and the petitioner withdrew his writ petition. Subsequently, show-cause notices were issued, returns were filed, and taxes deposited for certain periods; the Sales Tax Officer assessed tax and imposed penalties under Section 16(1)(b) for failure to pay or file on time. The Deputy Commissioner and the High Court concluded the penalties violated statutory provisions, and the High Court quashed them on constitutional grounds. The Supreme Court held that no breach of Section 16(1)(b) had occurred because tax was not due until its liability was ascertained under Section 10 or Section 7(2). The court reasoned that Rule 31 applies only after an assessment, and that the stay order directing proper accounts and returns did not obligate immediate payment of tax. The penalties could not stand; the appeals were dismissed with costs.

1965-10-27

UTKAL MACHINERY LTD. v. SHANTI PATNAIK

This Supreme Court decision concerns industrial adjudication over termination of an employee during a probationary period and the scope of appellate review of an Industrial Tribunal. Miss Shanti Patnaik, appointed in December 1961, was discharged on April 30, 1962. The Labour Court found the termination mala fide, illegal and unjustified, and awarded Rs. 9,600 as compensation in lieu of reinstatement. The management contended that the appointment was on probation for six months and that, in the absence of standing orders on punishment, unsatisfactory work could constitute misconduct, permitting termination as a contractual right. The Court clarified that while a discharge may be within a contract, a bona fide exercise of power by management is not automatically free from review; the Industrial Tribunal may examine whether the order is mala fide, amounts to victimisation or an unfair labour practice, or is capricious or irrational. The Court assumed, for argument, a six-month probation but found no proof of such probation in the evidence; it concluded the discharge was punitive and mala fide due to lack of evidence of unsatisfactory work. While upholding the Labour Court’s general approach, the Court reduced the compensation from two years’ salary to Rs. 4,800, with 6% interest, noting the modest tenure of service and absence of special circumstances.