Supreme Court of IndiaSupreme Court · 2019Division BenchDisposed of accordingly.

M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LTD v. NORTHERN COAL FIELD LTD.

Case / Petition Number:
Special Leave Petition (Civil) No. 11476 of 2018
Neutral Citation:[2019] 14 S.C.R. 999

Case Synopsis & Summary

This Special Leave Petition concerns whether the Madhya Pradesh High Court correctly rejected a Section 11 reference to arbitration under the Arbitration and Conciliation Act, 1996 on the ground that the claims were time-barred. The petitioner, Uttarakhand Purv Sainik Kalyan Nigam Ltd., contracted to provide security services to Northern Coal Field Ltd. The contract contained an arbitration clause appointing a Sole Arbitrator nominated by Director (Pers.) of NCL, and the agreement contemplated continuation of work during arbitration. After disputes arose and notices were issued to nominate an arbitrator, the Respondent did not respond. The petitioner invoked Section 11 in 2016 to obtain pre-reference arbitration, but the High Court held the claims barred by limitation, thus refusing to appoint an arbitrator. The Supreme Court, however, emphasized the 2015 Amendment Act, which added Section 11(6A) and narrowed judicial scrutiny to the existence of an arbitration agreement, leaving threshold issues to the arbitrator under Section 16 (Kompetenz-Kompetenz). The Court set aside the High Court’s order, appointed Retired Justice A. M. Sapre as Sole Arbitrator, stated the seat at Singrauli, and directed the parties to appear before the arbitrator on 02.12.2019. The decision reinforces minimal judicial intervention and the Kompetenz-Kompetenz principle, while preserving the arbitration process and time limits under the Act.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Indu Malhotra
  • Ajay Rastogi
Judgment Date
2019-11-27
Court Decision / Holding
The High Court’s order rejecting reference under Section 11 is set aside. The Court appoints Mr. Justice (Retd.) A. M. Sapre as Sole Arbitrator, with independence declarations under Section 12 and compliance with Section 29A. The seat is Singrauli, Madhya Pradesh; proceedings may be conducted at a venue convenient to the arbitrator and parties; costs to be shared equally; the arbitration to proceed on the subject disputes with the limitation issue to be decided by the arbitral tribunal under Section 16.
Final Disposition
Disposed of accordingly.

Parties to the Case

Appellants / Petitioners

  • M/S. Uttarakhand Purv Sainik Kalyan Nigam Ltd

Respondents

  • Northern Coal Field Limited

Legal Representation & Advocates

Counsels for Petitioners

  • • Kailash Pandey
  • • Ranjeet Singh
  • • Ms. Jyoti Kumar Mishra
  • • Ms. Sushmita Mishra

Counsels for Respondents

  • • Ashwani Kumar Dubey
  • • Pankaj Sharma
  • • Chandra Shekhar Mishra

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 – s.11Arbitration and Conciliation Act, 1996 – s.11(6A)Arbitration and Conciliation Act, 1996 – s.16Arbitration and Conciliation Act, 1996 – s.21Arbitration and Conciliation Act, 1996 – s.12Arbitration and Conciliation Act, 1996 – s.29AArbitration and Conciliation Act, 1996 – Fourth ScheduleContract Act, 1872 – s.7UNCITRAL Model Law – Article 16New York Convention – Article V(1)(a)Arbitration and Conciliation Act, 1996 – Section 11(6A) (non-obstante clause)Section 47 of the 1996 Act (implied references)

Legal Doctrines & Maxims

  • Kompetenz-Kompetenz (Competence-Competence) doctrine
  • Non-obstante clause (Section 11(6A))
  • Fraud/deception exception to Kompetenz-Kompetenz

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contended that the 2015 Amendment Act to Section 11(6A) confines the High Court to a prima facie determination of the existence of an arbitration agreement, leaving all other threshold issues, including limitation, to the arbitral tribunal under Section 16. They argued that the arbitration clause in the 2010 contract is valid and applicable, the notices were issued in 2016 for nomination of a Sole Arbitrator, and the High Court erred in holding the claims time-barred. They urged that Kompetenz-Kompetenz and the non-obstante provision ensure minimal judicial intervention and permit the arbitration to proceed, with the Court appointing a Sole Arbitrator and requiring independence declarations under Section 12 and time frames under Section 29A.

Contentions of Respondents

The respondents argued that limitation is a threshold jurisdictional issue that could bar the appointment of an arbitrator under Section 11. They contended that the High Court correctly assessed the petition under the pre‑amendment regime and that the existence of the arbitration agreement should be examined, with the arbitral tribunal determining issues under Section 16. They maintained the arbitration clause exists and the seat is Singrauli, so appointment should have proceeded, subject to the tribunal’s review of such threshold questions.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (12)

Case NameCitationTreatmentExplanation
SBP & Co. v. Patel Engineering Ltd.[2005] 4 Suppl. SCR 688OverruledLegislative amendment by the 2015 Amendment Act (s.11(6A)) legislatively overruled Patel Engineering’s threshold-resolving approach.
National Insurance Co. v. Boghara Polyfab (P) Ltd.[2009] 1 SCC 267; [2008] 13 SCR 638OverruledOverruled by the 2015 Amendment Act’s confinement of examination to existence of arbitration agreement.
Union of India & Ors. v. Master Construction Co.[2011] 12 SCC 349; [2011] 5 SCR 853OverruledAmendments to s.11 and the Kompetenz-Kompetenz principle supersede this threshold-issues ruling.
Dresser Rand SA v Bindal Agro-Chem Ltd.[2006] 1 SCC 751PositiveCited to illustrate Kompetenz-Kompetenz and threshold issues; not overruled.
ITW Signode India Ltd. v. Collector of Central Excise[2004] 3 SCC 48PositiveCited to support that limitation is a jurisdictional issue to be decided in arbitration.
NTPC Ltd. v. Siemens Atkein Gesell Schaft[2007] 4 SCC 451PositiveCited for Kompetenz-Kompetenz and Section 16 role.
M/s Indian Farmers Fertilizers Cooperative Ltd. v. Bhadra Products[2018] 2 SCC 534; [2018] 1 SCR 848PositiveCited for Kompetenz-Kompetenz framework and related jurisprudence.
Duro Felguera S.A. v Gangavaram Port Limited[2017] 9 SCC 729PositiveCited for Kompetenz-Kompetenz and related exceptions.
Dresser Rand SA v Bindal Agro-Chem Ltd.[2006] 1 SCC 751PositiveCited for threshold jurisdiction concepts.
BSNL v Telephone Cables Ltd.[2010] 5 SCC 213Mentioned OnlyMentioned as authorities in related arbitration jurisprudence.
Nehru Port Trust & Anr.[2018] 10 SCC 525Mentioned OnlyMentioned in background/arbitration context.
PSA Mumbai Investments PTE Ltd. v Board of Trustees of the Jawaharlal Nehru Port Trust:nullMentioned OnlyMentioned as supporting reference; not central to the decision.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,951 words•~18 min read

In The Court Record

M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LTD v. NORTHERN COAL FIELD LTD.

999 [2019] 14 S.C.R. 999 ## M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LIMITED A v. ## NORTHERN COAL FIELD LIMITED (Special Leave Petition (C) No. 11476 of 2018) B ## NOVEMBER 27, 2019 ## **[INDU MALHOTRA AND AJAY RASTOGI, JJ.]** _Arbitration and Conciliation Act, 1996: s.11 – Whether the High Court was justified in rejecting the application filed under_ C _s.11 for reference to arbitration, on the ground that it was barred by limitation – Arbitration agreement between the parties – Dispute arose between them – Petitioner sent notices calling upon the Respondent to nominate a Sole Arbitrator in terms of the arbitration clause – Respondent did not respond to the notices – Petitioner filed application under s.11 invoking the default power_ D _of the High Court to make the appointment of a sole arbitrator – High Court held that the claims of the Petitioner were barred by limitation, and therefore an arbitrator could not be appointed under s.11 of the Act – Hence the instant special leave appeal – Held: Notice of Arbitration was issued on 09.03.2016 – Since the_ E _invocation took place after s.11 was amended by the 2015 Amendment Act, which came into force on 23.10.2015, the amended provision is applicable to the instant case – In view of the legislative mandate contained in s.11(6A), the Court is required only to examine the existence of the arbitration agreement – All other preliminary or threshold issues were left to be decided by the_ F _arbitrator under s.16, which enshrines the Kompetenz-Kompetenz principle – The doctrine of “Kompetenz-Kompetenz”, also referred to as “Compétence-Compétence”, or “Compétence de la recognized”, implies that the arbitral tribunal is empowered and has the competence to rule on its own jurisdiction including_ G _determining all jurisdictional issues, and the existence or validity of the arbitration agreement – This doctrine is intended to minimize judicial intervention, so that the arbitral process is not thwarted at the threshold, when a preliminary objection is raised by one of the parties – In view of the provisions of s.16, and the legislative policy_ G H 999 1000 SUPREME COURT REPORTS [2019] 14 S.C.R. - A _to restrict judicial intervention at the pre-reference stage, the issue of limitation would require to be decided by the arbitrator – Thus, the issue of limitation is a jurisdictional issue, which would be required to be decided by the arbitrator under s.16, and not the High Court at the pre-reference stage under s.11 of the Act – In the instant case, the issue of limitation was raised by the Respondent-_ - B _company to oppose the appointment of the arbitrator under s.11 before the High Court – The issue of limitation being a jurisdictional issue, the same has to be decided by the tribunal under s.16, which is based on Article 16 of the UNCITRAL Model Law which enshrines the Kompetenze principle – The order of High_ - C _Court is, therefore, set aside – Retired judge of Supreme Court appointed as the Sole Arbitrator – Parties directed to appear before the Arbitrator on 02.12.2019 – Matter disposed of – Doctrine of kompetenz-kompetenz._ - _Doctrines/Principles: Doctrine of kompetenz-kompetenz –_ - D _Applicability of, exception – Held: The doctrine is subject to the exception i.e. when the arbitration agreement itself is impeached as being procured by fraud or deception – This exception would also apply to cases where the parties in the process of negotiation, may have entered into a draft agreement as an antecedent step prior to executing the final contract – The draft agreement would be a mere_ - E _proposal to arbitrate, and not an unequivocal acceptance of the terms of the agreement – s.7 of the Contract Act, 1872 requires the acceptance of a contract to be absolute and unqualified – If an arbitration agreement is not valid or non-existent, the arbitral tribunal cannot assume jurisdiction to adjudicate upon the disputes_ - F _– Appointment of an arbitrator may be refused if the arbitration agreement is not in writing, or the disputes are beyond the scope of the arbitration agreement – Article V(1)(a) of the New York Convention also states that recognition and enforcement of an award may be refused if the arbitration agreement ‘is not valid under the law to which the parties have subjected it or, failing any indication_ - G _thereon, under the law of the country where the award was made’ – Arbitration law – Contract Act, 1872 – s.7._ _ITW Signode India Ltd._ v. _Collector of Central Excise_ **(2004) 3 SCC 48 : [2003] 5 Suppl. SCR 751;** _NTPC v._ H ## M/S.UTTARAKHAND PURV SAINIK KALYAN NIGAM LTD. v. 1001 NORTHERN COAL FIELD LTD. _Siemens Atkein Gesell Schaft_ **(2007) 4 SCC 451 : [2007] 3 SCR 399 ;** _M/s. Indian Farmers Fertilizers Cooperative Ltd._ v. _Bhadra Products_ **(2018) 2 SCC 534 : [2018] 1 SCR 848 – relied on.** _SBP & Co._ v. _Patel Engineering Ltd._ **(2005) 8 SCC 618 : [2005] 4 Suppl. SCR 688 ;** _National Insurance Co. v. Boghara Polyfab (P) Ltd._ **(2009) 1 SCC 267 : [2008] 13 SCR 638 ;** _Union of India & Ors._ v. _Master Construction Co._ , **(2011) 12 SCC 349 : [2011] 5 SCR 853 ;** _Duro Felguera S.A._ v. _Gangavaram Port Limited_ **(2017) 9 SCC 729 : [2017] 10 SCR 285;** _Dresser Rand SA_ v. _Bindal Agro-Chem Ltd._ **(2006) 1 SCC 751 : [2006] 1 SCR 308 – referred to.** A B C ## **Case Law Reference** |**[2005]**|**4 Suppl. SCR 688**|**referred to**|**Para 9.4**|| |---|---|---|---|---| |**[2008]**|**13 SCR 638**|**referred to**|**Para 9.4**|D| |**[2011]**|**5 SCR 853**|**referred to**|**Para 9.4**|| |**[2017]**|**10 SCR 285**|**referred to**|**Para 9.7**|| |**[2006]**|**1 SCR 308**|**referred to**|**Para 9.9**|| |**[2003]**|**5 Suppl. SCR 751**|**relied on**|**Para 9.12**|E| |**[2007]**|**3 SCR 399**|**relied on**|**Para 9.12**|| |**[2018]**|**1 SCR 848**|**relied on**|**Para 9.12**|| F CIVIL APPELLATE JURISDICTION: Special Leave Petition (Civil) No. 11476 of 2018 From the Judgment and Order dated 11.01.2018 of the High Court of Madhya Pradesh, Jabalpur in Arbitration Case No.56 of 2016 Kailash Pandey, Ranjeet Singh, Ms. Jyoti Kumar Mishra, Ms. Sushmita Mishra (for Gaichangpou Gangmei), Advs. for the Petitioner. G Ashwani Kumar Dubey, Pankaj Sharma, Chandra Shekhar Mishra, Advs. for the Respondent. H 1002 SUPREME COURT REPORTS [2019] 14 S.C.R. A The Order of the Court was passed by ## **INDU MALHOTRA, J.** 1.The issue which has arisen for consideration is whether the High Court was justified in rejecting the application filed under Section 11 for reference to arbitration, on the ground that it was barred by limiB tation. 2. The factual background of the case arises from an agreement dated 21.12.2010 entered into between the parties, under which the Petitioner – Contractor was to provide security to the Respondent – Company around the clock on need basis, as per the agreed contractual C rates. The Agreement contained an arbitration clause which reads as follows : ## _“_ _**13. Arbitration :**_ - D _13.1 If any dispute, difference, question or disagreement shall at any time hereafter arise between the parties hereto or the respective or assigns in connection with or arising out of or in respect of contract, application of provision thereof, anything there-under contained or arising there-under or as to rights, liabilities or duties_ - E _of the said parties hereunder or any matter whatsoever incidental to this contract shall be referred to the sole Arbitration of the person appointed by Director (Pers.) of NCL. CONTRACTOR shall have no objection to any such appointment that the arbitrator so appointed is an_ - F _employee of NCL or that he had dealt with the matter to which the contract related and that in the course of his duties as NCL employees he has expressed views on all or any of the matter of disputes or difference._ - _13.2 If the arbitrator to whom the matter is originally by_ - G _referred dies or refused to act or resigns for any reason from the position of arbitrator, it shall be lawful, for Director (Pers.) of NCL to appoint another person to act as Arbitrator. Such person shall be_ H ## M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LTD.v. 1003 NORTHERN COAL FIELD LTD. [INDU MALHOTRA, J.] _entitled to proceed with the reference from the stage at_ A _which it was left by his predecessor or to precede denovo._ - _13.3 It is agreed that no person other than the person appointed by Directed (Pers.) of NCL as aforesaid shall act as Arbitrator._ - B - _13.4 It is term of the contract that the CONTRACTOR shall not stop the work under this contract and the work shall continue whether the arbitration proceedings were commenced or not._ - _13.5 It is term of this contract that the parties invoking the arbitration shall specify the dispute to be referred for arbitration._ - C - _13.6 The Arbitrator shall give reasoned award in respect of each of the difference referred to him. The award as aforesaid shall be final and binding on all the parties_ D _to this contract in accordance with the law._ - _13.7 The venue of arbitration shall at Singrauli in India and subject as aforesaid, the provisions of Indian Arbitration and Conciliation Act, 1996 and any statutory modification or reenactment thereof and rules made there-under and for the time being in force shall apply to the arbitration proceedings under this clause.”_ E (emphasis supplied) 3. Disputes arose between the parties with respect to payment of amounts under the contract by the Respondent – Company, and the deduction of the security amount from the running bills. The Petitioner – Contractor issued a Legal Notice dated 29.05.2013demanding payment of amounts to the tune of Rs. 1,43,69,309/ - alongwith interest from the Respondent – Company. F G 4. On 09.03.2016, the Petitioner – Contractor issued a Notice of Arbitration calling upon the Respondent – Company to nominate a Sole Arbitrator in terms of the arbitration clause, to adjudicate the disputes between the parties. H 1004 SUPREME COURT REPORTS [2019] 14 S.C.R. A The Respondent – Company did not respond to the Notice dated 09.03.2016. 5. The Petitioner – Contractor sent a further notice on 30.05.2016 to the Respondent – Company proposing the name of Mr. Jai Singh, a retired Additional District Judge for appointment as the Sole Arbitrator. B C The Respondent – Company did not respond to this Notice as well. 6. The Petitioner – Contractor filed an Application on 20.09.2016, under Section 11 invoking the default power of the High Court to make the appointment of a sole arbitrator. 7. The High Court _vide_ the impugned Order held that the claims of the Petitioner – Contractor were barred by limitation, and thereforean arbitrator could not be appointed under Section 11 of the 1996 Act. 8. Aggrieved by the impugned Order dated 11.01.2018, the D Petitioner has filed the present Special Leave Petition before this Court. 9. We have heard learned Counsel for the parties and perused the pleadings. E - 9.1 Section 21 of the 1996 Act provides that arbitral proceedings commence on the date on which a request for disputes to be referred to arbitration is received by the respondent. - 9.2. In the present case, the Notice of Arbitration was issued by the Petitioner – Contractor to the Respondent – Company on 09.03.2016. - The invocation took place after Section 11 was amended by the - F 2015 Amendment Act, which came into force on 23.10.2015, the amended provision would be applicable to the present case. - 9.3. The 2015 Amendment Act brought about a significant change in the appointment process under Section 11 : first, the - G default power of appointment shifted from the Chief Justice of the High Court in arbitrations governed by Part I of the Act, to the High Court; second, the scope of jurisdiction H M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LTD.v. 1005 NORTHERN COAL FIELD LTD. [INDU MALHOTRA, J.] under sub-section (6A) of Section 11 was confined to the A examination of the existence of the arbitration agreement at the pre-reference stage. - 9.4. Prior to the coming into force of the 2015 Amendment Act, much controversy had surrounded the nature of the power of appointment by the Chief Justice, or his designate under Section 11. A seven judge constitution bench of this Court in _SBP & Co._ v. _Patel Engineering Ltd._ ,[1] defined the scope of power of the Chief Justice under Section 11. The Court held that the scope of power exercised under Section 11 was to first decide : B C i. whether there was a valid arbitration agreement; and ii.whether the person who has made the request under Section 11, was a party to the arbitration agreement; and iii. whether the party making the motion had approached the appropriate High Court. Further, the Chief Justice was required to decide all threshold issues with respect to jurisdiction, the existence of the agreement, whether the claim was a dead one; or a time-barred claim sought to be resurrected; or whether the parties had concluded the transaction by recording satisfaction of their mutual rights and obligations, and received the final payment without objection, under Section 11, at the pre-reference stage. The decision in _Patel Engineering_ (supra) was followed by this Court in _Boghara Polyfab_[2] , _Master Construction_[3] , and other decisions. D E F 9.5 The Law Commission in the246[th] Report[4] recommended that: _“the Commission has recommended amendments to sections 8 and 11 of the Arbitration and Conciliation Act, 1996. The_ G > 1 (2005) 8 SCC 618. > 2 _National Insurance Co._ v. _Boghara Polyfab (P) Ltd._ (2009) 1 SCC 267. > 3 _Union of India & Ors._ v. _Master Construction Co._ (2011) 12 SCC 349. > 4 _Amendments to the Arbitration & Conciliation Act, 1996,_ Report No. 246, Law Commission of India (August 2014), p. 20. H 1006 SUPREME COURT REPORTS [2019] 14 S.C.R. - A _scope of the judicial intervention is only restricted to situations where the Court/Judicial Authority finds that the arbitration agreement does not exist or is null and void. In so far as the nature of intervention is concerned, it is recommended that in the event the Court/Judicial Authority is prima facie satisfied against the argument challenging the_ - B _arbitration agreement, it shall appoint the arbitrator and/or refer the parties to arbitration, as the case may be. The amendment envisages that the judicial authority shall not refer the parties to arbitration only if it finds that there does not exist an arbitration agreement or that it is null and void._ - C _If the judicial authority is of the opinion that prima facie the arbitration agreement exists, then it shall refer the dispute to arbitration, and leave the existence of the arbitration agreement to be finally determined by the arbitral tribunal.”_ (emphasis supplied) - D 9.6. Based on the recommendations of the Law Commission, Section 11 was substantially amended by the 2015 Amendment Act, to overcome the effect of all previous judgments rendered on the scope of power by a non obstante clause, and to reinforce the _kompetenz-kompetenz_ principle enshrined - E in Section 16 of the 1996 Act. The 2015 Amendment Act inserted sub-section (6A) to Section - 11 which provides that: - _“The Supreme Court or, as the case may be, the High Court, while considering any application under sub-section (4) or_ - F _sub-section (5) or sub-section (6), shall, notwithstanding any judgment, decree or order of any Court, confine to the examination of the existence of an arbitration agreement.”_ (emphasis supplied) - By virtue of the _non obstante_ clause incorporated in Section - G 11(6A),previous judgments rendered in _Patel Engineering_ (supra) and _Boghara Polyfab_ (supra), were legislatively over-ruled. The scope of examination is now confined only to the existence of the arbitration agreement at the Section 11 stage, and nothing more. H ## M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LTD.v. 1007 NORTHERN COAL FIELD LTD. [INDU MALHOTRA, J.] - 9.7 Reliance is placed on the judgment in _Duro Felguera S.A._ v. A _Gangavaram Port Limited_ ,[5 ] wherein this Court held that : _“From a reading of Section 11(6A), the intention of the legislature is crystal clear i.e. the Court should and need only look into one aspect-the existence of an arbitration agreement. What are the factors for deciding as to whether there is an arbitration agreement is the next question. The resolution to that is simple-it needs to be seen if the agreement contains a Clause which provides for arbitration pertaining to the disputes which have arisen between the parties to the agreement.”_ B C (emphasis supplied) - 9.8 In view of the legislative mandate contained in Section 11(6A), the Court is now required only to examine the existence of the arbitration agreement. All other preliminary or threshold issues are left to be decided by the arbitrator under Section 16, which enshrines the _Kompetenz-Kompetenz_ principle. - 9.9. The doctrine of “ _Kompetenz-Kompetenz_ ”, also referred to as “ _Compétence-Compétence_ ”, or “ _Compétence de la recognized_ ”, implies that the arbitral tribunal is empowered and has the competence to rule on its own jurisdiction, including determining all jurisdictional issues, and the existence or validity of the arbitration agreement. This doctrine is intended to minimize judicial intervention, so that the arbitral process is not thwarted at the threshold, when a preliminary objection is raised by one of the parties. D E F The doctrine of _kompetenz-kompetenz_ is, however, subject to the exceptioni.e. when the arbitration agreement itself is impeached as being procured by fraud or deception. This exception would also apply to cases where the parties in the process of negotiation, may have entered into a draft agreement as an antecedent step prior to executing G 5 (2017) 9 SCC 729. Refer to _T.R.F. Ltd._ v. _Energo Engineering Projects Ltd._ (2017) 8 SCC 377. H 1008 SUPREME COURT REPORTS [2019] 14 S.C.R. - A the final contract. The draft agreement would be a mere proposal to arbitrate, and not an unequivocal acceptance of the terms of the agreement. Section 7 of the Contract Act, 1872 requires the acceptance of a contract to be absolute and unqualified[6] .If an arbitration agreement is not valid or non-existent, the arbitral tribunal cannot assume jurisdiction to adjudicate upon the disputes. Appointment of an arbitrator - B may be refused if the arbitration agreement is not in writing, or the disputes are beyond the scope of the arbitration agreement. Article V(1)(a) of the New York Convention states that recognition and enforcement of an award may be refused if the arbitration agreement ‘is not valid under the law to which the parties C have subjected it or, failing any indication thereon, under the law of the country where the award was made’. - 9.10. The legislative intent underlying the 1996 Act is party autonomy and minimal judicial intervention in the arbitral process. Under this regime, once the arbitrator is appointed, - D or the tribunal is constituted, all issues and objections are to be decided by the arbitral tribunal. - E - 9.11. In view of the provisions of Section 16, and the legislative policy to restrict judicial intervention at the pre-reference stage, the issue of limitation would require to be decided by the arbitrator. Sub-section (1) of Section 16 provides that the arbitral tribunal may rule on its own jurisdiction, “including any objections” with respect to the existence or validity of the arbitration agreement. Section 16 is as an inclusive provision, which would comprehend all preliminary issues touching upon the jurisdiction of the arbitral tribunal. The issue of F limitation is a jurisdictional issue, which would be required to be decided by the arbitrator under Section 16, and not the High Court at the pre-reference stage under Section 11 of the Act. Once the existence of the arbitration agreement is not disputed, all issues, including jurisdictional objections are to be decided by the arbitrator. - G 9.12. In the present case, the issue of limitation was raised by the Respondent – Company to oppose the appointment of the arbitrator under Section 11 before the High Court. > 6 _Dresser Rand SA_ v. _Bindal Agro-Chem Ltd._ (2006) 1 SCC 751. See also _BSNL_ v. _Telephone Cables Ltd._ (2010) 5 SCC 213. - Refer to _PSA Mumbai Investments PTE Ltd._ v. _Board of Trustees of the Jawaharlal_ - H _Nehru Port Trust & Anr._ (2018) 10 SCC 525. M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LTD.v. 1009 NORTHERN COAL FIELD LTD. [INDU MALHOTRA, J.] Limitation is a mixed question of fact and law. In _ITW Signode India Ltd._ v. _Collector of Central Excise_[7] a three judge bench of this Court held that the question of limitation involves a question of jurisdiction. The findings on the issue of limitation would be a jurisdictional issue. Such a jurisdictional issue is to be determined having regard to the facts and the law. Reliance is also placed on the judgment of this Court in _NTPC_ v. _Siemens Atkein Gesell Schaft_[8] , wherein it was held that the arbitral tribunal would deal with limitation under Section 16 of the 1996 Act. If the tribunal finds that the claim is a dead one, or that the claim was barred by limitation, the adjudication of these issues would be on the merits of the claim. Under sub-section (5) of Section 16, the tribunal has the obligation to decide the plea; and if it rejects the plea, the arbitral proceedings would continue, and the tribunal would make the award. Under sub-section (6) a party aggrieved by such an arbitral award may challenge the award under Section 34. In _M/s. Indian Farmers Fertilizers Cooperative Ltd._ v. _Bhadra Products_[9] this Court held that the issue of limitation being a jurisdictional issue, the same has to be decided by the tribunal under Section 16, which is based on Article 16 of the UNCITRAL Model Law which enshrines the _Kompetenze_ principle. 10. In view of the aforesaid discussion, we set aside the impugned judgment and order dated 11.01.2018 passed by the High Court, and direct that the issue of limitation be decided by the arbitral tribunal. 11. With the consent of Counsel for the parties, we appoint Mr. Justice (Retd.) A. M. Sapre, former Judge of this Court, as the Sole Arbitrator, subject to the declarations being made under Section 12 of the 1996 Act (as amended)with respect to the independence and impartiality of the arbitrator, and the ability to devote sufficient time to complete the arbitration within the period specified by Section 29A of the 1996 Act. A B C D E F 12. The arbitration agreement states that the arbitration will beat G Singrauli, Madhya Pradesh. Consequently, the seat of arbitration is at Singrauli, subject to any modification that may be made by consent of 7 (2004) 3 SCC 48 8 (2007) 4 SCC 451 9 (2018) 2 SCC 534. H 1010 SUPREME COURT REPORTS [2019] 14 S.C.R. - A the parties. The arbitrator is, however, at liberty to conduct the proceedings at a convenient venue as per the convenience of the arbitrator and the parties if so required. The Arbitrator will be paid fees in accordance with the Fourth Schedule of the 1996 Act. Both parties will share the costs of the B arbitration equally. 13. The Registry is directed to despatch a copy of this Order to Mr. Justice (Retd.) A. M. Sapre, Former Judge, Supreme Court of India at the following address: “Mr. Justice (Retd.) A. M. Sapre, C Former Judge, Supreme Court of India, C-203, Second Floor Sarvodaya Enclave New Delhi – 110017 Tel No.: 011-40254823 Mob. No.: 7042955488" D The parties are directed to appear before the learned Arbitrator on 02.12.2019 at 2 p.m. The matter is disposed of accordingly. E Devika Gujral Matter disposed of. F G H
End of Judgment Record
Browse All Supreme Court of India (2019) Decisions
2019-09-03

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.

2019-07-19

STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.

This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.

2019-01-07

PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.

Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).

2019-12-06

RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.

Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.