Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2022Division BenchAppeal allowed; impugned High Court order quash...

M/S TIRUPATI STEELS v. M/S SHUBH INDUSTRIAL COMPONENT & ANR.

Case / Petition Number:
Civil Appeal No. 2941 of 2022
Neutral Citation:[2022] 3 S.C.R. 356

Case Synopsis & Summary

The appeal concerns enforcement of an arbitral award under the MSMED Act, 2006 and the initial deposit requirement under section 19 of that Act when challenging an award under section 34 of the Arbitration and Conciliation Act, 1996. The appellant, Tirupati Steels, had obtained a Rs. 2.72 crore award before the Micro and Small Enterprises Facilitation Council (MSME Council) that was subsequently executed. Respondent No.1 challenged the award under section 34 before a Special Commercial Court, while the appellant sought a direction under section 19 to deposit 75% of the award as a predeposit. The Special Commercial Court granted six weeks to deposit; the High Court later allowed the section 34 proceedings to proceed without insisting on the deposit, relying on a Division Bench decision (M/s Mahesh Kumar Singla) that the predeposit was directory rather than mandatory. The Supreme Court, applying Gujarat State Disaster Management Authority v. Aska Equipments Limited and Goodyear (India) Ltd. v. Norton Intech Rubbers (P) Ltd., held that the deposit is technically mandatory under section 19, but a court may permit installment payment in cases of undue hardship. It overruled the contrary view in M/s Mahesh Kumar Singla to the extent that the deposit is mandatory. Consequently, the impugned High Court order is quashed; the appellant’s appeal is allowed, and the respondent is directed to deposit 75% before the section 34 application is entertained, with execution to proceed if not deposited. No costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • M. R. Shah
  • B. V. Nagarathna
Judgment Date
2022-04-19
Court Decision / Holding
Appeal allowed; the High Court order quashed; mandatory deposit of 75% of the awarded amount under Section 19 MSMED Act is affirmed, with the possibility of installments in cases of undue hardship. Until 75% is deposited, the Section 34 challenge shall not be entertained; execution may continue otherwise. No costs.
Final Disposition
Appeal allowed; impugned High Court order quashed and set aside; 75% deposit under Section 19 MSMED Act mandated before entertaining Section 34 challenge; installments possible in case of undue hardship; execution to continue if deposit not made; no costs.

Parties to the Case

Appellants / Petitioners

  • M/S TIRUPATI STEELS

Respondents

  • M/S SHUBH INDUSTRIAL COMPONENT & ANR.

Legal Representation & Advocates

Counsels for Petitioners

  • • Pankaj Bhagat

Counsels for Respondents

  • • Dr. Vinod Kumar Tewari

Provisions of Law Cited

Section 19 of the Micro, Small and Medium Enterprises Development Act, 2006Section 34 of the Arbitration and Conciliation Act, 1996

Legal Doctrines & Maxims

  • Mandatory pre-deposit under Section 19 MSMED Act; hardship carve-out permitting installments.
  • Hardship principle allowing installment deposits in exceptional cases.

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicant contends that deposit of 75% of the award under Section 19 MSMED Act is mandatory before entertaining a Section 34 application; hardship considerations should not undermine the mandatory nature; installments may be allowed only if undue hardship is shown.

Contentions of Respondents

The respondents submit that pre-deposit of 75% should not be required to entertain a Section 34 challenge; the High Court's permissive approach should stand; deposit may be insisted only later.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Gujarat State Disaster Management Authority v. Aska Equipments Limited(2022) 1 SCC 61PositiveRelied on to support that the deposit under Section 19 is mandatory.
Goodyear (India) Ltd. v. Norton Intech Rubbers (P) Ltd.(2012) 6 SCC 345PositiveCited as authority for the mandatory nature of the deposit and related considerations.
M/s Mahesh Kumar Singla and another v. Union of India and othersCWP No. 23368 of 2015Partly Overruled / LimitedHigh Court decision relied upon; Supreme Court overruled it to the extent that the deposit under Section 19 is mandatory (not directory).
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,104 words•~10 min read

In The Court Record

M/S TIRUPATI STEELS v. M/S SHUBH INDUSTRIAL COMPONENT & ANR.

356 SUPREME COURT REPORTS [2022] 3 S.C.R. 356 [2022] 3 S.C.R. A ## M/S TIRUPATI STEELS ## v. M/S SHUBH INDUSTRIAL COMPONENT & ANR. (Civil Appeal No. 2941 Of 2022) B ## APRIL 19, 2022 ## **[M. R. SHAH AND B. V. NAGARATHNA, JJ.]** - _Micro, Small and Medium Enterprise Development Act, 2006_ - _(MSMED Act) – s.19 – Parties governed by provisions of MSMED Act – Appellant preferred claim petition before Micro and Small_ - C _Enterprises Facilitation Council constituted under the MSMED Act – On failure of conciliation, dispute referred to Arbitrator – Arbitrator, appointed through MSME Facilitation Council, passed award in favour of appellant – Appellant filed execution petition – Respondent No.1 filed application u/s.34 of the Arbitration Act for_ - D _setting aside the arbitral award – Appellant submitted application u/s.19 of the MSMED Act for direction to respondent no.1-judgment debtor to deposit 75% of the arbitral award – Special Commercial Court allowed the application moved by appellant granting six weeks’ time to Respondent No.1 to deposit 75% of the arbitral award before its’ application u/s.34 of the Arbitration Act, could be_ - E _entertained by the Court – Respondent No.1 filed appeal before High Court which permitted proceedings u/s.34 of the Arbitration Act to go on, without insisting for pre-deposit of 75% of the awarded amount – Whether pre-deposit of 75% of the awarded amount as per s.19 of the MSMED Act, while challenge to the award u/s.34 of_ - F _the Arbitration Act is made mandatory or not – Held: Requirement of deposit of 75% of the amount in terms of the award as a predeposit as per s.19 of the MSMED Act, is mandatory – However, considering the hardship which may be projected before the appellate court and if the appellate court is satisfied that there shall be undue hardship caused to the appellant /applicant to deposit_ - G _75% of the awarded amount as a pre-deposit at a time, the court may allow the pre-deposit to be made in installments – Unless and until respondent No.1 deposits 75% of the awarded amount, its application u/s.34 of the Arbitration Act, challenging the award not to be entertained and decided on merits and, in that case, the_ H 356 357 M/S TIRUPATI STEELS v. M/S SHUBH INDUSTRIAL COMPONENT & ANR. _execution proceedings to continue – Arbitration and Conciliation_ A _Act, 1996 – s.34._ ## **Allowing the appeal, the Court** **HELD:1.1. The requirement of deposit of 75% of the amount in terms of the award as a pre-deposit as per section 19 of the Micro, Small and Medium Enterprise Development Act, 2006, is mandatory. However, at the same time, considering the hardship which may be projected before the appellate court and if the appellate court is satisfied that there shall be undue hardship caused to the appellant /applicant to deposit 75% of the awarded amount as a pre-deposit at a time, the court may allow the predeposit to be made in installments. Therefore, pre-deposit of 75% of the awarded amount under section 19 of the MSMED Act, 2006 is a mandatory requirement. [Para 4][360-A-C]** **1.2. The impugned order passed by the High Court permitting the proceedings under section 34 of the Arbitration and Conciliation Act, 1996 without insistence for making pre-deposit of 75% of the awarded amount is unsustainable. [Para 5][360-F]** _Gujarat State Disaster Management Authority v. Aska Equipments Limited_ , **(2022) 1 SCC 61** and _Goodyear (India) Ltd. v. Norton Intech Rubbers (P) Ltd._ , **(2012) 6 SCC 345 – relied on.** _M/s Mahesh Kumar Singla and another v. Union of India and others_ [Decision of High Court in CWP No. 23368 of 2015] – **partly overruled.** **2. Respondent No.1 is directed to deposit 75% of the awarded amount before its application under section 34 of the Arbitration and Conciliation Act, 1996 challenging the award is entertained and considered on merits. Unless and until respondent No.1 deposits 75% of the awarded amount, its application under section 34 of the Arbitration and Conciliation Act, 1996, challenging the award shall not be entertained and decided on merits and, in that case, the execution proceedings may continue. [Para 6][361-A-C]** B C D E F G H 358 SUPREME COURT REPORTS [2022] 3 S.C.R. |A<br>**(2022) 1 SCC 61**<br>**(2012) 6 SCC 345**|**Case Law Reference**<br>**relied on**<br>**Para 4**<br>**relied on**<br>**Para 4**| |---|---| CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2941 B of 2022. From the Judgment and Order dated 09.04.2019 of the High Court of Punjab and Haryana at Chandigarh in FAO-Com No.4 of 2019. Pankaj Bhagat, Adv. for the Appellant. Dr. Vinod Kumar Tewari, Adv. for the Respondents. C The Judgment of the Court was delivered by ## **M. R. SHAH, J.** 1. Feeling aggrieved and dissatisfied with impugned order dated 09.04.2019 passed by the Division Bench of the High Court of Punjab D and Haryana at Chandigarh in Commercial Appeal Case No. FAO-COM/ 4/2019 (O&M), by which in the proceedings under section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act, 1996) which was filed under section 19 of the Micro, Small and Medium Enterprise Development Act, 2006 (hereinafter referred to as E the ‘MSMED Act, 2006’), the Division Bench of the High Court has directed the first appellate court to proceed under section 34 of the Arbitration Act, 1996 without insistence for making pre-deposit of 75% of the awarded amount, the judgment creditor has preferred the present appeal. F 2. The parties are governed by the provisions of the MSMED Act, 2006. The appellant herein preferred a claim petition before the Micro and Small Enterprises Facilitation Council constituted under the MSMED Act, 2006 for recovery of Rs.1,40,13,053/- and interest amounting to Rs. 1,32,20,100/- which comes to a total amounting to Rs.2,72,33,153/-. On the failure of conciliation, the dispute was referred G to the Arbitrator. The Arbitrator, appointed through the MSME Facilitation Council at Chandigarh, passed an award in favour of the appellant vide award dated 16.07.2018. Thereafter, the appellant herein filed the execution petition before the District and Sessions Judge, Faridabad. Respondent No.1 herein filed an application under section 34 of the H Arbitration Act, 1996 for setting aside the arbitral award before the Special 359 M/S TIRUPATI STEELS v. M/S SHUBH INDUSTRIAL COMPONENT & ANR. [M. R. SHAH, J.] Commercial Court, Gurugram. That the appellant herein submitted an A application under section 19 of the MSMED Act, 2006 directing respondent No. 1 herein – judgment debtor to deposit 75% of the arbitral award. The learned Additional District Judge cum Special Commercial Court, Gurugram allowed the said application moved by the appellant herein granting six weeks’ time to the Respondent No.1 herein to deposit B 75% of the arbitral award before the application filed under section 34 of the Arbitration Act, 1996 could be entertained by the Court. Feeling aggrieved with the order passed by the Special Commercial Court, Gurugram directing the judgment debtor – respondent No. 1 herein to deposit 75% of the arbitral award and on that condition the petition under section 34 of the Arbitration Act, 1996 was to be entertained, which C order was passed on considering section 19 of the Arbitration Act, 1996, respondent No. 1 filed the commercial appeal being FAO-COM/4/2019 before the High Court. By the impugned order, considering the decision of the Division Bench of the High Court rendered in CWP No.23368 of 2015 **(M/s Mahesh Kumar Singla and another Vs. Union of India** D **and others),** by which, the Division Bench,while up holding the vires of section 19 of the MSMED Act, 2006, held that the pre-deposit of 75% of the arbitral award under section 19 of the MSMED Act, 2006 is directory and not mandatory, has permitted the proceedings under section 34 of the Arbitration Act, 1996 to continue without insistence on making a pre-deposit of 75% of the awarded amount. Feeling aggrieved and E dissatisfied with the impugned order passed by the Division Bench of the High Court permitting the proceedings under section 34 of the Arbitration Act, 1996, to go on without insistence for making pre-deposit of 75% of the awarded amount, the appellant herein – original judgment creditor has preferred the present appeal. F 3. We have heard learned counsel appearing on behalf of the respective parties at length. 4. The question which is posed for consideration of this Court is, whether, the pre-deposit of 75% of the awarded amount as per section 19 of the MSMED Act, 2006, while challenge to the award under section 34 of the Arbitration Act, 1996, is made mandatory or not, is now no longer res integra in view of the decision of this Court in the case of **Gujarat State Disaster Management Authority Vs. Aska Equipments Limited; (2022) 1 SCC 61** . While interpreting section 19 of the MSMED Act, 2006 and after taking into consideration the G H 360 SUPREME COURT REPORTS [2022] 3 S.C.R. - A earlier decision of this Court in the case of **Goodyear (India) Ltd. Vs. Norton Intech Rubbers (P) Ltd.; (2012) 6 SCC 345,** it is observed and held that the requirement of deposit of 75% of the amount in terms of the award as a pre-deposit as per section 19 of the MSMED Act, is mandatory. It is also observed that however, at the same time, considering the hardship which may be projected before the appellate court and if - B the appellate court is satisfied that there shall be undue hardship caused to the appellant/applicant to deposit 75% of the awarded amount as a pre-deposit at a time, the court may allow the pre-deposit to be made in instalments. Therefore, it is specifically observed and held that pre-deposit of 75% of the awarded amount under section 19 of the MSMED Act, - C 2006 is a mandatory requirement. In para 13 of the aforesaid judgment, it is observed and held as under:- - **“13.** On a plain/fair reading of Section 19 of the MSME Act, 2006, reproduced hereinabove, at the time/before entertaining the application for setting aside the award made under Section 34 of - D the Arbitration and Conciliation Act, the appellant-applicant has to deposit 75% of the amount in terms of the award as a predeposit. The requirement of deposit of 75% of the amount in terms of the award as a pre-deposit is mandatory. However, at the same time, considering the hardship which may be projected before the appellate court and if the appellate court is satisfied that there - E shall be undue hardship caused to the appellant-applicant to deposit 75% of the awarded amount as a pre-deposit at a time, the court may allow the pre-deposit to be made in instalments.” 5. In view of the aforesaid decision of this Court, the impugned order passed by the High Court permitting the proceedings under section F 34 of the Arbitration Act, 1996 without insistence for making pre-deposit of 75% of the awarded amount is unsustainable and the same deserves to be quashed and set aside. As observed hereinabove, while passing the impugned order, the Division Bench of the High Court has relied upon an earlier decision of the Division Bench in the case of **M/s Mahesh** G **Kumar Singla** (supra) which has taken a contrary view. Therefore, the decision of the Division Bench in the case of **M/s Mahesh Kumar Singla** (supra), which has been relied upon by the Division Bench of the High Court while passing the impugned order, is held to be not good law and is specifically overruled to the extent that it holds that pre-deposit of 75% of the awarded amount under section 19 of the MSMED Act, H 2006, is directory and not a mandatory requirement. 361 M/S TIRUPATI STEELS v. M/S SHUBH INDUSTRIAL COMPONENT & ANR. [M. R. SHAH, J.] 6. In view of the above discussion and for the reasons stated A above, the present appeal is allowed. The impugned order passed by the High Court is hereby quashed and set aside. Respondent No. 1 is directed to deposit 75% of the awarded amount before its application under section 34 of the Arbitration Act, 1996 challenging the award is entertained and considered on merits. B It is observed and held that unless and until respondent No. 1 deposits the 75% of the awarded amount, its application under section 34 of the Arbitration Act, 1996, challenging the award shall not be entertained and decided on merits and, in that case, the execution proceedings may continue. The present appeal is accordingly allowed. There shall be no order as to costs. C Bibhuti Bhushan Bose Appeal allowed. D E F G H
End of Judgment Record
Browse All Supreme Court of India (2022) Decisions
2022-12-09

MOHD. SABEER @ SHABIR HUSSAIN v. RM, U. P. STATE ROAD TRANSPORT CORP.

The appellant, Mohd. Sabeer (also known as Shabir Hussain), a scrap dealer, was a passenger in a UP State Road Transport Corporation bus when the driver rashly and negligently drove the vehicle, causing a collision near Ghaziabad in 2009. He sustained grave injuries including an amputation of the right lower limb and other bodily injuries. The Motor Accident Claims Tribunal (MACT) awarded Rs. 15,76,465 with interest; the High Court of Delhi enhanced the amount to Rs. 16,70,932. The Disability Certificate recorded 70% permanent disability. The High Court had treated the claimant’s functional disability as 35%, relying on post‑accident income reflected in IT returns, and erred in not adequately recognizing the impact on earning capacity of a self‑employed person who cannot drive. The Supreme Court held that the appellant’s functional disability should be treated as 60% for loss of future earning capacity and that permanent disablement warrants consideration of future prospects in addition to future income. It invoked National Insurance Co. v. Pranay Sethi to apply a 40% addition for future prospects, and directed compensation for prosthetic limb purchase and maintenance, as well as enhanced non‑pecuniary damages. The final award was increased to Rs. 38,70,120 with 9% interest from the date of application, and the appeals were allowed, emphasizing liberal, holistic justice to restore the claimant to his pre‑accident position in light of socio‑economic factors.

2022-01-25

Intercontinental Hotels Group (India) Pvt. Ltd. & ANR. v. Waterline Hotels Pvt. Ltd.

Intercontinental Hotels Group (India) Pvt. Ltd. & Anr. v Waterline Hotels Pvt. Ltd. is a Supreme Court decision addressing appointment of a sole arbitrator under Section 11(6) read with Section 11(12)(a) of the Arbitration and Conciliation Act, 1996, in a dispute arising from a Hotel Management Agreement (HMA) for renovating the Holiday Inn & Suites Bengaluru, Whitefield. The petitioners allege breach by Waterline Hotels, including non-payment of incentive management fee and related charges, culminating in Waterline’s email termination of the HMA on 12 October 2018 after rebranding the hotel as Miraya. The petitioners invoked arbitration; Waterline challenged the enforceability of the arbitration clause on the ground that the HMA is an unstamped instrument under the Karnataka Stamp Act. A Karnataka High Court ad‑interim relief was granted in 2018, but the Supreme Court’s judgment focuses on the scope of judicial interference at the pre‑appointment stage. The Court reiterates a pro‑arbitration stance, noting that arbitrability/validity are generally matters for the arbitrators, with a narrow exception to cut deadwood or to refer for authoritative settlement where necessary, invoking Vidya Drolia. It also analyzes stamp duty, observing that stamp duty has been paid (albeit disputed) and that the question of the correct stamp duty may be resolved later, not as a precondition to appointing an arbitrator. Consequently, the Court appoints Justice A. V. Chandrashekara as a sole arbitrator, directs SIAC to proceed under its rules, and allows the petition in terms stated, while leaving stamp duty issues for arbitration to determine later.

2022-02-01

The State of Sikkim v. Jasbir Singh & ANR

This appeal by the State of Sikkim challenges a High Court judgment upholding a Sessions Judge’s order directing a written notice to the Army’s commanding officer to transfer the case to a court-martial. The case concerns concurrent jurisdiction between a court-martial and an ordinary criminal court under the Army Act for an offence allegedly committed by Lance Naik Jasbir Singh during active service in Sikkim, with the FIR under IPC 302 and related charges. The High Court held that the procedure under Sections 125/126 Army Act, the 1978 Rules (Rules 3-5) and CrPC Rule 475 had not been observed and that the Army authorities had exercised their discretion to prefer a court-martial; thus, the court-martial alone would have jurisdiction. The Supreme Court, however, held that the offence falls into a category with concurrent jurisdiction under Sections 69 and 70 of the Army Act, and that where there is concurrent jurisdiction, the first instance discretion to choose the forum lies with the designated officer under Section 125. In the present case there was no decision by the designated officer to institute proceedings before a court-martial, and the sequence of events showed significant cooperation with the CrPC process. Consequently, the Sessions Judge’s competence to proceed in the criminal court was not in error, the High Court’s order is set aside, and the respondent-accused is to be transferred to civil custody to face trial in the criminal court. The appeal is allowed.

2022-07-22

Hemant Kumar Verma & Ors. v. Employees State Insurance Corporation & Ors.

This writ petition concerns whether junior resident doctors in ESIC-run medical colleges should be eligible for the 50% in-service reservation for postgraduate medical courses, a benefit presently available to Insurance Medical Officers Grade-II (IMO-II) recruited through competitive selection. ESIC recruits IMO-II and provides a 50% in-service quota for PG seats; however junior residents, who complete MBBS under bond and serve as part of ESIC's residency scheme, are not deemed in-service doctors. The petitioners argued parity with IMO-II because their qualifications, duties, and work environment are similar, and urged the Court to treat them as in-service to extend the 50% reservation to their batch. ESIC contends that junior residents are contractual, bond-based appointees governed by the ESIC Residency Scheme; IMO-II is a permanent post governed by the ESIC Staff and Condition of Service Regulations 1959; the bond reduction in 2020 and the 2018/2020 memoranda cannot convert junior residents into in-service doctors. The Court relies on precedents establishing institutional preference in PG admissions—Saurabh Chaudri v. Union of India, Yatin Kuma Jasubahi v. State of Gujarat, and Pradeep Jain v. Union of India — to acknowledge the legitimacy of institutional preference, but ultimately holds that junior residents and regular ESIC doctors are distinct categories and the in-service quota cannot be equitably extended to junior residents. The petition is dismissed.