Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1997Division BenchPetition dismissed

M/S. Swastic Industries v. Maharashtra State Electricity Board

Case / Petition Number:
Special Leave Petition (C) No. 765 of 1997
Neutral Citation:[1997] 1 S.C.R.

Case Synopsis & Summary

Swastic Industries, the petitioner, challenges a supplementary bill issued by the Maharashtra State Electricity Board (MSEB) for Rs. 3,17,659, dated February 5, 1993, demanding payment for energy. The petitioner paid under protest and approached the State Consumer Disputes Redressal Commission, which held the claim barred by three-year limitation. The National Consumer Disputes Redressal Commission (NCDRC) reversed, holding there is no limitation for making a demand by way of a supplementary bill, relying on a Bombay High Court decision in Bharat Barrel & Drum Manufacturing Co. Pvt. Ltd. v. Municipal Corporation of Greater Bombay & Anr., AIR 1978 Bombay 369. The petitioner contends that Section 24 of the Indian Electricity Act, 1910 enables the Board to demand and disconnect for non-payment, while Section 60-A of the Electricity (Supply) Act, 1948 prescribes a three-year period for instituting suits after the Board’s constitution. The Board argues that the right to recover is inseparable from the right to discontinue, and the existence of a remedy by suit does not erase the Board’s power to disconnect or demand timely payment. The court notes that the Board’s power to demand and disconnect exists, and that deficiency of service by staff could justify penalties under the Consumer Protection Act, but finds no illegality in the supplementary demand. The SLP is dismissed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • G. T. Nanavati
Judgment Date
1997-01-24
Court Decision / Holding
The Special Leave Petition is accordingly dismissed
Final Disposition
Petition dismissed

Parties to the Case

Appellants / Petitioners

  • M/S. Swastic Industries

Respondents

  • Maharashtra State Electricity Board

Legal Representation & Advocates

Counsels for Petitioners

  • • Shankar Divate
  • • Naresh Kaushik
  • • Mrs. Lalitha Kaushik

Counsels for Respondents

  • • A.S. Bhasme

Provisions of Law Cited

Indian Electricity Act, 1910 - Section 24Electricity (Supply) Act, 1948 - Section 60-A

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicants argued that Section 60-A imposes a three-year limitation on suits, so the Board cannot recover arrears after that period. They contended Section 24 of the Indian Electricity Act, 1910 enables the Board to demand and disconnect for non-payment, but the mere existence of a remedy by suit does not permit bypassing limitation. They challenged the National Commission’s reliance on the Bombay High Court’s decision in Bharat Barrel & Drum Manufacturing Co. Pvt. Ltd. v. Municipal Corporation of Greater Bombay & Anr. to hold there is no limitation for supplementary billing. They urged that the proper remedy is to pursue a timely suit for recovery and that limitation must apply to such suits.

Contentions of Respondents

The respondents argued that Section 24 empowers the licensee to demand charges and to disconnect for non-payment, and that Section 60-A sets a limitation for suits but does not bar demands or disconnection. They contended there is mutual obligation: the Board supplies energy and the consumer must pay. They supported the National Commission’s view that there is no limitation for making a demand by supplementary bill, and that any deficiency of service by staff can be addressed under the Consumer Protection Act but does not render the supplementary demand illegal.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
M/s Bharat Barrel & Drum Manufacturing Co. Pvt. Ltd. v. Municipal Corporation of Greater Bombay & Anr.AIR (1978) Bombay 369PositiveApproved by the Supreme Court; it supported the proposition that there is no limitations for making the demand by way of supplementary bill.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,091 words•~5 min read

In The Court Record

M/S. Swastic Industries v. Maharashtra State Electricity Board

A .... ## M/S. SWASTIC INDUSTRIES _v._ MAHARASHTRA STATE ELECTRICITY BOARD JANUARY 24, 1997 B (K. RAMASWAMY AND G.T. NANAVATI, JJ.] _Indian Electricity Act, 1910/Electricity (Supply) Act, 1948:_ _S. 24/ S. 60-A-Electricity supply-Demand by Electricity Board-Con-_ C _sumer neglecting to pay-Held : The mere fact that a right is given to the Electricity Board to file suit and limitation prescribed therefore, does not take away the 1ight conferred on it to make demand for payment of charges-Consumer neglecting to pay the same-Board has power to discontinue the supply or cut-off the supply._ D _M/s. Bharat Barrel & Dmm Manufacturing Co. Pvt. Ltd._ v. _The Municipal Corporation of Greater Bombay & Anr.,_ AIR (1978) Born. 369 approved. CIVIL APPELLATE JURISDICTION: Special Leave Petition (C) No. 765 of 1997. E From the Judgment and Order dated 30.8.96 of the National Consumers Disputes Redressal Commission, New Delhi in F.A. No. 520 of 1995. Shankar Divate, Naresh Kaushik and Mrs. Lalitha Kaushik for the • F Petitioner. A.S. Bhasme for the Respondent. > The following Order of the Court was delivered : G The petitioner is canvassing the correctness of the decision of the National Consumers' Disputes Redressal Commission, New Delhi, made on August 30, 1996 in Appeal No. 520/95. The admitted position is that the respondent-Electricity Board had issued a supplementary Bill to the petitioner on February 5, 1993 demandH ing payment of Rs. 3,17,659. The petitioner objected to the bill by his letter 532 _MIS_ SWASTIC INDUSTRIES _v._ M.S.E.B. 533 dated February 16, 1993. However, when letter was issued for payment of A the said amount, the petitioner paid it under protest and filed the complaint before the State Consumers Disputes Redressal Commission. The Commission by order dated May 24, 1995 allowed the complaint and held that the claim was barred by limitation of 3 years. Feeling aggrieved, the Electricity Board filed an appeal. The National Commission relying upon B the judgment of a Division Bench of the Bombay High Court in _Mis. Bharat Barrel & Dmm Manufactwing Co. Pvt. Ltd._ v. _The Municipal Corporation of Greater Bombay & Anr.,_ AIR (1978) Born. 369 has held that there is no limitation for making the demand by way of supplementary bill. Section 24 of the Indian Electricity Act, 1910 gives power to the Board to issue such demand and to discontinue the supply to a consumer who neglects to pay C the charges. It is contended by the learned counsel for the petitioner that Section 60-A of the Electricity (Supply) Act, 1948 prescribes a limitation of 3 years for the Board to institute any suit, after its constitution, for recovery of the arrears. Thereby the limitation of 3 years is required to be observed. The Board in negation of Section 60A of Supply Act cannot be D permitted to exercise the power under Section 24 of the Electricity Act, 1910. We find no force in the contention. --'. Section 60-A of the Electricity (Supply) Act, 1948 envisages the enlargement of the period of limitation in certain circumstance, i.e., intervening period of the constitution of the Board, and the right of the State to recover the amounts due to the State for consumption of electricity delegating the power to the Board. In that behalf, clauses (i) and (ii) therein operate as under : "(i) where it has been constituted before the commencement of the Electricity (Supply) Amendment Act, 1966 (8 of 1966) within three years· of such commencement; and (ii) where it has been constituted after such commencement, within three years of its constitution." This is an enabling provision to recover the amounts due by way of suit despite the fact that Section 24 of the Indian Electricity Act clearly empowers the Board to demand and collect any charge from the Consumer and collect the same towards the electrical energy supplied by the Board in the following trrms : E F G H 534 [1997] 1 S.C.R. A ## SUPREME COURT REPORTS B "Where any per3on neglects to pay any charge for energy or any sum, other than a charge for energy, due from him to a licensee in respect of the supply of energy to him, the licensee may, after giving not less than seven clear days notice in writing to such person and without prejudice to _his light to recover such charge_ or _other sum by suit,_ cut off the supply and for that purpose cut or disconnect any electric supply-line or other work, being the property of the licensee, through which energy may be supplied, and may discontinue the supply until such charge· or other sum, together with any expenses incurred by him in cutting off and reconnecting the supply, are paid, but no longer." c It would, thus, be clear that the right to recover the charges is one part of it and right to discontinue supply of electrical energy to the consumer who neglects to pay charges is another part of it. The right to file a suit is a matter of option given to the licensee, the Electricity Board. D Therefore, the mere fact that there is a right given to the Board to file the suit and the limitation has been prescribed to file the suit, it does not take : away the right conferred on the Board under Section 24 to make demand · for payment of the charges and on neglecting to pay the same. They have the power to discontinue the supply or cut-off the supply, as the case may be, when the consumer neglects to pay the charges. The intendment E appears to be that the obligation are mutual. The Board supply electrical _1_ energy and the consumer is under corresponding duty to pay the sum due towards the electricity consumed. Thus the Electricity Board, having exercised that power, since admittedly the petitioner had neglected to pay the bill for additional sum, was right in disconnecting the supply without recourse to filing of the suit to recover the same. The National Commission, F therefore, was right in following the judgment of the Bombay High Court and allowing the appeal setting aside the order of the State Commission. Moreover, there is no deficiency of service in making supplementary demand for escaped billing. There may be negligence or collusion by subordinate staff in not properly recording the reading or allowing pilferage to the consumers. That would be deficiency of service under the G Consumer Protection Act. We do not find any illegality warranting interference. \. The Special Leave Petition is accordingly dismissed H G.N. Petition dismissed.
End of Judgment Record
Browse All Supreme Court of India (1997) Decisions
1997-12-17

Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.

This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.

1997-11-18

National Insurance Co. Ltd. v. Santro Devi and Ors.

National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.

1997-02-03

JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.

This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.

1997-07-07

Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.

Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.