This writ petition challenges orders of the Debt Recovery Tribunal (DRT), Ernakulam, and the Appellate Tribunal, directing the petitioners to deposit a portion of the decretal amount as a condition for setting aside an ex parte decree in OA 244 of 2007. The petitioners, defendants in the OA, faced an ex parte decree followed by a recovery certificate and attached proceedings. They filed IA(s) to condone delay, set aside the ex parte decree, and stay recovery. The DRT allowed the IA(s) subject to the petitioners depositing 10% of the OA claim amount (Rs. 2,55,37,270.82) within a time frame. The Appellate Tribunal sustained the reasoning but increased the deposit to 20%, effectively doubling the liability. The petitioners challenged the orders on multiple grounds, arguing that neither the DRT nor the Appellate Tribunal had power to direct deposit of decretal amounts as a condition to set aside an ex parte decree, contending that at most costs could be imposed. They rely on Supreme Court authority including VK Industries v M.P. Electricity Board Rampur and Vijay Kumar Madan. The Bank and Kerala Financial Corporation contend that such conditions are permissible, citing VK Industries and Ramesh v Ratnakar Bank. The High Court ultimately held the 10% deposit within the four walls of the law and set aside the 20% deposit, granting one month to effect the deposit, with the matter to be disposed on merits if paid in time.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- P. R. Ramachandra Menon
- Judgment Date
- 2009-08-11
- Court Decision / Holding
- The writ petition is allowed to the extent of (i) upholding the DRT Ext. P1 order directing 10% deposit of the claim amount, and (ii) setting aside Ext. P2, the Appellate Tribunal’s order doubling the deposit to 20%. The Court grants petitioners one month to effect the 10% deposit; if paid within that period, the matter shall be disposed of on merits. The petitioners are thus required to deposit Rs. 2,55,37,270.82/- within one month; failure to do so may affect merits proceedings.
- Final Disposition
- Writ Petition disposed of (Ext. P2 set aside; Ext. P1 sustained); petitioners granted one month to deposit 10% of the OA claim amount; matter to be disposed on merits if paid within time; final disposal on merits thereafter.
Parties to the Case
Appellants / Petitioners
- M/S. Summer Sand Hill Resorts & Ayurvedic Centre
- Jacob Mathew
- Annamma Mathew
Respondents
- State Bank of India
- Kerala Financial Corporation
Legal Representation & Advocates
Counsels for Petitioners
- • K.P. Dandapani, Senior Advocate
- • Millu Dandapani
Counsels for Respondents
- • K.K. Chandran Pillai, SC
- • K. Jaju Babu, SC
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
Petitioners argued that neither the DRT nor the Appellate Tribunal has the power to direct deposit of a portion of the decretal amount as a condition to setting aside an ex parte decree; such deposit exceeds the scope of Order IX Rule 13 CPC and converts relief into payment; relied on VK Industries v M.P. Electricity Board Rampur and Vijay Kumar Madan to show that only costs or security should be imposed, not decretal amounts pre-decree. They challenged Ext. P1 (10% deposit) and Ext. P2 (20% deposit) as unwarranted and sought setting aside both orders.
Contentions of Respondents
Respondents contended that courts may impose costs or security, including deposit of decretal amounts or portions thereof, when setting aside an ex parte decree, provided such conditions are reasonable; relied on VK Industries (AIR 2002 SC 1151) and Ramesh v Ratnakar Bank Ltd (2006) 12 SCC 111 to justify the powers exercised by the tribunals; submitted that the 10% deposit was within the law, while the 20% deposit was excessive.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (3)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| V.K. Industries vs. M.P. Electricity Board, Rampur | AIR 2002 SC 1151 | Positive | Three-member bench held that courts may impose costs or decretal amount or portion thereof, or require security, as a condition for setting aside an ex parte decree, provided the condition is reasonable. |
| Vijay Kumar Madan v. R.N. Gupta Technical Education Society | (2002) 5 SCC 30 | Distinguished | Two-member bench case; treated as distinguishable on facts, not directly applicable to the present pre-decree deposit issue and not controlling for ex parte decree settings in the present context. |
| Ramesh v. Ratnakar Bank Ltd | (2006) 12 SCC 111 | Positive | Recognized as supportive authority that deposit of a portion of decretal amount or security can be ordered, subject to reasonableness. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/S. Summer Sand Hill Resorts & Ayurvedic Centre, Jacob Mathew and Annamma Mathew v State Bank of India and Kerala Financial Corporation
Related Decisions & Precedents from High Court of Kerala (2009)
Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality
This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.
Abdul Majeed Kalathil v. District Collector, Malappuram & Others
This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.
WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)
This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."
M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others
The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.