Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2014Division BenchAppeal dismissed with costs; the contract award...

M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. v. DMRC LTD. & ORS.

Case / Petition Number:
Civil Appeal No. 2068 of 2014
Neutral Citation:[2014] 2 S.C.R. 824

Case Synopsis & Summary

This is an appeal by Siemens challenging the Delhi Metro Rail Corporation (DMRC) award of a contract for 486 Standard Gauge Electric Multiple Units for Phase-III of Delhi’s Mass Rapid Transit System. The contract was awarded to Hyundai Rotem Company (HR) after a two-bid process where bids were evaluated on the basis of both price and GEC (X and Y) values, which had to be loaded into the price bids. Siemens contended that HR’s GEC values were untenable and that the tender terms did not require or permit validation of these values; Siemens also argued for independent verification of GEC values and for scrutiny of the government’s parallel, MoUD-initiated Committee which was formed while the matter was sub judice. The High Court of Delhi had held the DMRC process to be transparent, fair, and free from illegality. The Supreme Court affirmed, stressing judicial restraint and that review under tender/contract awards is limited to legality and regularity of the process, not substitution of one’s own assessment of technical/economic data. It held that the Government erred in initiating a parallel review, but found no illegality in the DMRC’s evaluation and award. The appeal was dismissed with costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • T. S. Thakur
  • C. Nagappan
Judgment Date
2014-02-14
Court Decision / Holding
Appeal dismissed. The Court held that the bidding process and the ultimate award were lawful, fair, and transparent; it rejected Siemens’ challenge to the GEC-value verification as required, and it admonished the Government for initiating a parallel review while the matter was sub judice. It affirmed the High Court’s decision and upheld the contract award to HR, with costs.
Final Disposition
Appeal dismissed with costs; the contract award in favor of HR stands upheld.

Parties to the Case

Appellants / Petitioners

  • M/S SIEMENS AKTIENGESELISCHAFT & S. LTD.

Respondents

  • DMRC Ltd. and Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • U. U. Lalit

Counsels for Respondents

  • • T. R. Andhyarujina
  • • Mr. Venugopal

Provisions of Law Cited

Article 32Article 13Article 299Article 14

Legal Doctrines & Maxims

  • Judicial restraint in administrative action
  • Wednesbury principle of reasonableness
  • Three-fold test for judicial review: illegality, irrationality, procedural impropriety
  • Special features of reviewing tenders/contract awards

Submissions & Arguments

Contentions of Appellants / Petitioners

Siemens contends that the DMRC tender process must be scrutinized for legality and regularity, arguing that the GEC values (X and Y) used to load into price bids were not verified for achievability and that outside expert validation or an independent review was necessary. It further challenges the Government of India’s MoUD-issued Committee as a parallel process interfering with sub judice adjudication, and it seeks either re-evaluation or setting aside of HR’s award, given potential non-achievability of the GEC values.

Contentions of Respondents

DMRC defended the process as transparent, fair, and in line with tender terms; it explained that multiple internal committees reviewed the bids, that DMRC performed internal simulations to verify achievability, and that the outside Committee’s proceedings were not binding. HR argued that the tender allowed loading of GEC values and that no outside validation was mandated; it emphasized the sufficiency of internal checks and the need to protect DMRC’s financial interests.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (16)

Case NameCitationTreatmentExplanation
Tata Cellular v. Union of India1994 (2) Suppl. SCR 122PositiveUsed as a foundational authority establishing the judicial review framework for tender/contract awards and the three-limbed test.
Ramana Dayaram Shetty v. International Airport Authority of India and Ors.1979 (3) SCR 1014PositiveCited as part of the historical development of judicial review of administrative action.
MP. Oil Extraction v. State of M.P. & Ors.1997 (1) Suppl. SCR 671PositiveCited to illustrate caution in economic/policy decision review and the limited scope of interference.
Jagdish MandaI v. State of Orissa & Ors.2007 (14) SCC 517PositiveCited for its articulation of special features to be borne in mind while reviewing tenders and contract awards.
Heinz India (P) Ltd. & Anr. v. State of U.P. & Ors.2012 (3) SCR 898PositiveCited for the judicial review dimensions and constraints on second-guessing technical findings.
Federation of Railway Officers Association v. Union of India2003 (2) SCR 1085PositiveCited for the principle that when technical issues are contested, the Government may consider all factors; court should refrain from re-evaluating expert data.
ND Jayal v. Union of India2003 (3) Suppl. SCR 152 = (2004) 9 SCC 362PositiveCited for limitations on court review in safety-related or technical decision-making.
Amrik Singh Lyalpuri v. Union of India & Ors.2011 (5) SCR 560 = (2011) 6 SCC 535PositiveCited to illustrate deference to expert opinion within judicial review.
Union of India v. K.M. Shankarappa2000 (5) Suppl. SCR 117 = (2001) 1 SCC 582PositiveCited for the standard that Government decisions in tender processes should be informed by relevant factors.
The King v. Parmanand and Ors.AIR 1949 Patna 222PositiveCited as a precedent related to improper interference with judicial processes.
D. Jones Shield v. N. Ramesam & Ors.AIR 1955 AP 156PositiveCited for the principle against improper interference with court proceedings.
In Re: P.C. Sen1969 SCR 649 = AIR 1970 SC 1821PositiveCited in the context of supervisory standards over judicial proceedings.
Jang Bahadur Singh v. Baij Nath Tiwari1969 SCR 134 = AIR 1969 SC 30PositiveCited for principles governing judicial review in tender-related matters.
Asia Foundation & Construction Ltd. v. Trafalgar House Construction1996 (10) Suppl. SCR 209 = (1997) 1 B SCC 738PositiveCited to emphasize expert considerations and evaluation criteria in tenders.
Monarch Infrastructure (P) Ltd. v. Ulhasnagar Municipal Corpn.2000 (3) SCR 1159 = (2000) 5 SCC 287PositiveCited for the limits of judicial review in economic/municipal decision contexts.
Reid v. Secy. of State for Scotland1999 (1) All ER 481PositiveCited for general principles of judicial review and the non-s willingness to substitute the court’s view on technical data.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•10,424 words•~48 min read

In The Court Record

M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. v. DMRC LTD. & ORS.

## [2014] 2 S.C.R. 824 A M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ DMRC LTD. & ORS. (Civil Appeal No. 2068 of 2014) B FEBRUARY 14, 2014 [T.S. **THAKUR AND C. NAGAPPAN, JJ.]** ## _CONSTITUTION OF IND/A, 1950:_ c . _Art. 32 r/w Arts. 13 and 299_ - _Government contracts_ - _Contract for supply of Standard Gauge Cars Electrical_ - _Multiple Units for use in Mass Rapid transit system Award of contract to lowest bidder (L-1)_ - _Challenged_ - _Held: In any challenge to award of contract, the legality and regularity of the process leading to the award of contract is to be examined_ 0 -- _Court has to constantly keep in mind that it does not sit in_ - _appeal over the soundness of the decision Court can only examine whether the decision making process was fair,_ - _reasonable and transparent In cases involving award of_ E _contracts, court ought to exercise judicial restraint where the decision is bonafide with no perceptible injury to public interest_ - _High Court has, in the case at hand, undertaken that exercise and concluded that there was neither any illegality nor any irregularity in the process of evaluation of the bids or_ - _the final allotment of contract The allotment of contract did_ F _not suffer from any illegality as it is understood in the matter_ -- _of judicial review of administrative action The process by which the bids were evaluated and eventually accepted was transparent, fair and reasonable and does not, therefore, call_ - _for any interference Judicial review Judicial restraint._ G ## _ADMINISTRATIVE LAW:_ H - _Government contract Award of contract challenged_ - _before court Thereafter, Government directing constitution_ 824 M/S SIEMENS AKTIENGESEUSCHAFT & S. 1-TD. _v._ 825 DMRC LTD. & ORS. _of_ a _Committee_ - _Held: Government ought to have stayed its_ A _hands once the matter landed in court_ - _Inasmuch as_ - _Government did nothing of this kind, it did not act properly Even otherwise, solong as the view taken by the experts of the authority competent to take_ a _final decision is_ a _possible view, the very fact that some other experts have expressed_ B _doubts about the sustainability of the GEC values wiH not be enough to declare that the values offered by respondent no. 2 are unachievable._ The award of contract for the supply of 486 Standard Gauge Cars Electrical Multiple Units meant for use in ~hase-111 of the Mass Rapid Transit Sy~tem ('MRTS') for Delhi and its extension corridors, in favour of the lowest bidder (L-1), namely, respondent No.2(HR), was challenged by the two unsuccessful bidders, namely, the appellant and another. The High Court held that the process of evaluating the bids received and award of contract in favour of respondent no. 2 was transparent and did not suffer from any illegality, irregularity or -perversity to warrant interference. C 0 E In the instant appeal, it was contended for the appellant that while the GEC value offered by the appellant was the highest, the one offered by the respondent successful bidder for 'X' factor was wholly untenable. It was submitted that the terms of the tender F notice required the GEC values offered by the bidders to be validated before they could be used for processing the bids; and that the report submitted by the Director, Ministry of Urban Development, Government of India, indicated that the stimulation test conducted by DMRC G as a part of the process of verification and validation of the GEC value offered by respondent. no. 2 was not accurate. It was urged that the Government of India had appointed a two-member Committee to check the evaluation process of the bids and the report of the H 826 SUPREME COURT REPORTS [2014] 2 S.C.R. A Committee filed by the Government in the Court in a· sealed cover could throw considerable light on the subject and help in deci~ing whether an independent verification of the GEC values was necessary. ## 8 Dismissing the appeal, the Court HELD: 1.1 Judicial review would apply even to exercise of contractual powers by the Government and Government instrumentalities in order to prevent arbitrariness or favouritism. In any challenge to the award C of contact before the High Court and so also before this Court what is to be examined is the legality and regularity of the process .leading to award of contract. What the Court has to constantly keep in mind is that it does not sit in appeal over the soundness of the decision. The D Court can only examine whether the decision making process was fair, reasonable and transparent. In cases involving award of contracts, the Court ought to exercise judicial restraint where the decision is bonafide with no perceptible injury to public interest. The High Court has, E . in the case at hand, undertaken that exercise and concluded that there was neither any illegality nor any irregularity in the process of evaluation of the bids or the final allotment of the contract. [para 17,22 and 23) [842F; 846-E-H] F _Tata Cellular v. Union of India_ 1994 (2) Suppl. SCR 122 = (1994) 6 SCC 651; _Ramana Dayaram Sheffy v. lntemational Airport Authority of India and Ors._ 1979 (3) SCR 1014 = (1979) 3 sec 489 - relied on. G H _MP. Oil Extraction v. State of M.P._ & _Ors._ 1997 (1) Suppl. SCR 671 = (1997) 7 SCC 592; _Jagdish Manda/ v. State of Orissa_ & _Ors._ 2006 (10) Suppl. SCR 606 = (2007) 14 SCC 517; _Heinz India (P) Ltd._ & _Anr. v. State of U.P._ & _Ors._ 2012 (3) SCR 898 = (2012) 5 SCC 443 - referred to M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 827 DMRC LTD. & ORS. _Reid v. Secy. of State for Scotland_ (1999) 1 All ER 481· referred to; A 1.2 The allotment of contract did not suffer from any illegality as it is understood in the matter of judicial review of administrative action and as that expression has been 8 used by this Court in Tata Cellular's case. It is also not the case of the appellant that the decision taken by the DMRC is so outrageous in its defiance of logic or accepted moral standards that no sensible person who had applied his mind could have arrived at the same. C Perversity or irrationality in the decision or the decision making process_is also not a ground that can be invok~d in the case at hand. [para 23] [847·E·G] 1.3 It is common ground that the price bid offered by the tenderers was not itself determinative. What was D equally important was the GEC values comprising X and Y factors which the tenderers had to disclose in their techn°ical .bids. That the values offered had to be converted into Indian Rupees and loaded to the price bid of the tenderers. is also beyond question. That each one E of the bidders had offered their GEC values comprising Xand Y factors separately was also beyond doubt. There is no error even in the conversion of such values in terms of Indian Rupees nor is there any dispute about the effect of such loading of values to the price bid of all the F tenderers. because of which loadingthe bid offered by respondent no. 2 eventually emerged as L-1 with appellant sliding to L-4 position. That being so, the process of evaluation of bids cou_ld not be faulted as the same was strictly in accordance with the nor111.s G stipulated for such evaluation. [para 24] [848-B-E] 1.4 There is nothing in the tender document to suggest that the GEC values had to be, tested for their achievability. All the six bidders declared eligible are H ## 828 SUPREME COURT REPORTS (2014) 2 S.C.R. - A world leaders in the field and have sufficient expertise and know-how not o~!Y about the design and technology which they use but also about their capacity to validate their respectiv~ GEC values. Therefore, DMRC did not tommit any, error in considering that the GEC values - B offered 'by respondent no. 2 were achievable especially when/such values offered by some of the bidders for X 1 - and Y factors were lower than those offered by respondent no. 2. At any rate the DMRC had sufficiently protected itself because under the terms and conditions - c stipulated in the tender notice failure of the successful tender to make good the GEC values offered by them would result in a penalty which was higher than the GEC value factor that was loaded to the price bid. Therefore, there was no basis for the DMRC to go any further than - D it did in protecting its interest. In the absence of any specific stipulation or requirement for validation of the GEC values by the DMRC and its experts or by any outside agency such a requirement could not be implied into the tender process. Inasmuch as the DMRC found - E the bid offered by respondent no. 2 to be acceptable, keeping in view the GEC values offered by it, the former had committed no illegality in the evaluation of the bids or in making its choice of the contractor. [para 24] [848G-H; 849-A-D] F 1.5 Even assuming that the process of validation of the GEC values and their achievability was an implied condition in the evaluation process, DMRC had on the basis of an internal simulation satisfied itself that the GEC values were not unachievable. The High Court has G referred to the simulation results and the original record has also been produced by DMRC before this Court. There is no illegality or irregularity in the process of verification conducted by the DMRC to test the achievability of the GEC values. [para 25] [849-E-F] H M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 829 DMRC LTD. & ORS. 1.6 Therefore, this Court is satisfied that the process by which the bids were evaluated and eventually accepted was transparent, fair and reasonable and does not, therefore, call for any interference from this Court. [para 25] [829-A] A B 2.1 Once the Government had known that the entire issue regarding the validity of the process adopted by DMRC including the transparency and fairness of the process of evaluation of the bids was sub judice before the High Court and later before this Court, it ought to have C kept its hands off and let the law take its course. It could have doubt{ess placed all such material as was relevant, before the High Court and invited a judicial pronouncement on the subject instead of starting a parallel exercise. The Government could even approach 0 the High Court and seek its permission to review the process of evaluation either by itself or through an expert Committee if it felt that any such process would help the court in determining the issues falling for consideration before the court more effectively. Nothing of that sort E was, however, done. On the contrary even when the Secretary to the MoUD pointed out that the matter is subjudice and any further action in the matter could await the pronouncement of the court, the Minister heading MoUD directed the constitution of the Committee. [para F 26] (850-E-H; 851-A] 2.2 The terms of reference give a clear indication that the process initiated by the Government w.as a parallel process of the adjudication of the very same issue as fell for consideration before the High Court and at a later G stage before this Ccurt. The.Government could not have done this. Continuance of the process of review even after the High Court had delivered its judgfT!ent amounted to subjecting the judicial pronouncement to an administrative review. There was no question of any H 830 SUPREME COURT REPORTS [2014] 2 S.C.R. A such judicial determination or adjudication being subjected to any administrative review albeit in the name of a Committee constituted for the purpose. [para 27] [851-B-C, F-G] 2.3 Suffice it to say fhat the Government ought to 8 have stayed its hands once the matter landed in the Court. Inasmuch as the Government did nothing of this kind, it did not act properly. [para 28] (852-B] > 2.4 Even assuming that the Committee has taken C expert advice regarding the tenability of the GEC values offered by respondent no. 2, it would simply mean that there is a conflict between the views taken by the experts of DMRC and those consulted by the Committee. Any such conflict cannot be resolved by this Court in exercise D of its powers of judicial review. So long as the view taken > by the experts of the authority competent to take a final decision is a possible view, the very fact that some other experts have expressed doubts about the sustainability of the GEC values will not be enough to declare that the E values offered by respondent no. 2 are unachievable. [para 29] (852-E-G] _Federation of Railway Officers Association v. Union of India_ (2003) 2 SCR 1085; _N.D. Jayal v. Union oflnOia_ 2003 (3) Suppl. SCR 152 = (2004) 9 SCC 362 - referred to. F 2.5 Besides, the preparation and submission of a report that does not even take the view point of the party affected by it into consideration can hardly provide to this Court a good reason to scuttle the entire process at this G stage when respondent no. 2, the successful bidder, has already taken substantial steps in the direction of executing the works allotted to it. (para 31] [854-A-B] _Amrik Singh Lyal/puri v. Union of India_ & _Ors._ 2011 (5) SCR 560 = (2011) 6 SCC 535 and _Union of India v. K.M._ H _Shankarappa_ 2000 (5) Suppl. SCR 117 = (2001) 1 SCC 582; MIS SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 831 DMRC LTD. & ORS. _The King v. Parmanand and Ors._ AIR 1949 Patna 222 and A _D. Jones Shield v. N. Ramesam_ & _Ors._ AIR 1955 AP 156; In Re: P.C. Sen 1969 SCR 649 =AIR 1970 SC 1821 and _Jang Bahadur Singh v. Baij Nath Tiwari_ 1969 SCR 134 = AIR 1969 SC 30; _Asia Foundation_ & _Construction Ltd. v. Trafalgar House Construction_ 1996 (10) Suppl. SCR 209 = (1997) 1 B SCC 738; _Monarch Infrastructure (P) Ltd. v. U/hasnagar Municipal Corpn._ 2000 (3) SCR 1159 = (2000) 5 SCC 287; _Jagdish Manda/ v. State of Orissa_ 2006 (10) Suppl. SCR 606 = (2007) 14 SCC 517 and _Heinz India (P) Ltd. v. State of U.P._ 2012 (3) SCR 898 = (2012) 5 sec 443- cited. c c ## Case Law Reference: ||2011 (5) SCR 560|cited|Para16|| |---|---|---|---|---| ||2000 (5)Suppl.SCR 117|cited|Para16|D| ||AIR 1949 Patna 222|cited|Para 16|| ||AIR 1955 AP 156|cited|Para16|| ||1969SCR649|cited|Para 16|| |||||E| ||1969SCR134|cited|para 16|| |' , 1994 (2) Suppl. SCR 122|' , 1994 (2) Suppl. SCR 122|cited|Para 16|| |'·|'·1996 (10)Suppl.SCR 209|cited|Para 16|| ||2000 (3)SCR1159|cited|Para 16|F| ||2006 (10) Suppl. SCR 606|cited|Para16|| ||2012 (3)SCR898|cited|Para 16|| ||1979 (3) SCR 1014|reliedon|para 17|G| ||1997.(1) Suppl. SCR671|referredto|para 19|| ||2006 (10)' Suppl. SCR 606|referredto|para21|| ||2012 (3) SCR 898|referredto|para21|H| 832 SUPREME COURT REPORTS [2014] 2 S.C.R. A (1999) 1 All ER 481 referred to para 21 (2003) 2 SCR 1085 referred to Para 29 2003 (3) Suppl. SCR 152 referred to Para 30 CIVIL APPELLATE JURISDICTION : Civil Appeal No. 8 2068 of 2014. From the Judgment and Order dated 15.05.2013 in WPC ~o. 1853/2013 of the High Court of Delhi at New Delhi. C Mohan Parasaran, SG, U.U. Lalit, T.R. Andhyarujina, Maninder Singh, K.K. Venugopal, Dr. Rajeev Dhawan, C. Mukund, Pankaj Jain, Firdouse Qutb Wari, P.V. Saravanaraja, Anvesh Verma, Ashok Jain, Bijoy Kumar Jain, V.K. Biju, D.L. Chidanand, Ashwin Kumar D.S., Rajiv Nanda, Padma Laxmi D Nigam, Sushma Surim Shawna Singh Dev, Tarun Johri, Payal Chandra, Soumik Ghosal, Ankur Gupta, Santosh Kumar fol the. appearing parties. The Judgment of the Court was delivered by E T.S. THAKUR, J. 1. Leave granted. 2. A Division Bench of the High Court of DeLtJi has by a common order passed in Writ Petition (C) No.1853 of 2013 filed by the appellant and Writ Petition No.2615 of 2013 filed F by Alstom Transport India Ltd. declined to interfere with the · award of a t:ontract for the supply of 486 Standard Gauge Cars Electrical MultiP.le Units meant for use in Phase-Ill of the Mass Rapid Transit System ('MRTS' for short) fot Delhi and its extension corridors. The High Court has taken the view that the G process of evaluation of the bids received from eligible bidders culminating in the award of a contract in favour of respondent No.2-Hyundai Rotem Company ('HR' for short) was transparent and did not suffer from any illegality, irregularity or perversity of any kind to warrant interference by it. The High Court held H that the bidders were well aware of and had accepted the MIS SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 833 DMRC LTD. & ORS. [T.S. THAKUR, J.] . tender conditions which were free from any vagueness or A uncertainty. The parameters of evaluation conditions were also held to have been applied uniformly to all the bidders under a procedure that was open, transparent and fair as required by law. The present appeal assails the correctness of that judgment and order. Alstom Transport India Ltd. & Ors.-WritB Petitioners in connected Writ Petition No.2615 of 2013 have, however, remained content with the view taken by the High Court and have not chosen to appeal. 3: Respondent-Delhi Metro Rail Corporation ('DMRC' for ' short) bas planned to implement Phase-Ill of the MRTS for Delhi to keep pace with the ever increasing traffic demands in Delhi. Phase-Ill of the MRTS, Delhi comprises metro corridors of Mukundpur-Rajori Garden-Dhaula Kuan - Maujpur - Gokulpuri and Janakpuri (West)-Munirka - Kalkaji - Kalindi Kunj - Botanical Garden - (Naida). The project, it is common ground, is financed with the help of a loan secured by the DMRC from Japan International Cooperation Agency ('JICA' for short). The loan agreement, inter alia, stipulates the bid procedure to be followed by DMRC. What is noteworthy is that the procedure, inter alia, provides for submission of tenders to JICA for review, concurrence and analysis of bids by the DMRC and reserves with the JICA the diSCJ"P.tion to convey its views regarding the analysis of the bids ana the proposal for award of the works C D E 4. In keeping with the requirements of the agreement . betw~en DMRC and JICA, the former invited sealed tenders in two parts (Technical & Price Bid) on International Competitive Bid ('ICB' for short) basis for the design, manufacture, supply, testing, commissioning and training of 486 number of Standard Gauge Cars Electrical Multiple units referred to earlier at an estimated budget cost of Rs.3500 crores funded by JICA. Prebid meetings were held to answer the queries, if any, raised · by the bidders. The DMRC in the meantime issued as many as 9 Addenda which necessitated the change in the dates fixed F G tf [2014] 2 S.C.R. ## 834 SUPREME COURT REPORTS - A for submission of bids to enable the bidders to formulate their offers and make their bids in accordance with the terms and conditions finally stipulated for the purpose. DMRC eventually received eight bids including one submitted by the appellant before us. The technical bids were opened on 18th September, - B 2012 whereupon only six of the bidders including the appellant were declared to be eligible. With the opening of the technical bids GEC values which the bidders were required to submit as a part of their technical bid and which were relevant and to a great extent critical for evaluation of the price bid under the - c applicable terms and conditions also became knovvn to the bidders. The financial bids offered by these six bidders were then opened on 9th February, 2013 and the bid amount plong with GEC values offered by each bidder announced by the DMRC. The price quotations of the six bidders found eligible - o were as under: |were as under:||||| |---|---|---|---|---| |Bidder|Grand Total<br>inINR<br>.|INRper<br>Car (with-<br>out<br>loading)|~~.~~<br>Position<br>before<br>Loading<br>dueto<br>differ-<br>ence in<br>GEC<br>values|~~.~~·| |Siemens Consortium|. 3625,27,92,409|7,45,94,223|L-1|| |Bombardier Consortium 4242,27,83,378|Bombardier Consortium 4242,27,83,378|8;72,89,678 .|8;72,89,678 .L-2|| |Hyundai ROTEM|4290,57,94,689|8,82,83,528|L-3|| |Alstom Consortium|. 4373,87,65,001|8,99,97,459|L-4..<br>L-5|| |CAF Consortium|4614,18,66,794|9,49,42,113|L-5|| |Hitachi + BHEL|4891,32,60,656|10,06,44,569|10,06,44,569<br>L-6|| 5: Significantly, however, the above did not represent the G true inter se position of the bidders. That was so because apart from the price quotation, the terms and conditions of the tender notice required loading of GEC values duly converted into Indian rupee to the price quotation of each eligible bidder. The GEC values in turn comprised two distinct components, namely, H 'X' factor representing the electricity consumption for the M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 835 DMRC LTD. & ORS. [T.S. THAKUR, J.] operation of the train without HVAC and 'Y' factor for operation A of HVAC. The GEC values offered by the six bidders found technically compliant were as under: |operation of the train without HVAC and 'Y' factor for operation<br>of HVAC. The GEC values offered by the six bidders foundHVAC. The GEC values offered by the six bidders found<br>technically compliant were as under:|operation of the train without HVAC and 'Y' factor for operationof the train without HVAC and 'Y' factor for operationthe train without HVAC and 'Y' factor for operation<br>of HVAC. The GEC values offered by the six bidders foundHVAC. The GEC values offered by the six bidders found<br>technically compliant were as under:|operation of the train without HVAC and 'Y' factor for operationof the train without HVAC and 'Y' factor for operationthe train without HVAC and 'Y' factor for operation<br>of HVAC. The GEC values offered by the six bidders foundHVAC. The GEC values offered by the six bidders found<br>technically compliant were as under:|operation of the train without HVAC and 'Y' factor for operationof the train without HVAC and 'Y' factor for operationthe train without HVAC and 'Y' factor for operation<br>of HVAC. The GEC values offered by the six bidders foundHVAC. The GEC values offered by the six bidders found<br>technically compliant were as under:|operation of the train without HVAC and 'Y' factor for operationof the train without HVAC and 'Y' factor for operationthe train without HVAC and 'Y' factor for operation<br>of HVAC. The GEC values offered by the six bidders foundHVAC. The GEC values offered by the six bidders found<br>technically compliant were as under:| |---|---|---|---|---| |technically compliant were as under:|technically compliant were as under:|||| |technically compliant were as under:<br>S.No.|technically compliant were as under:<br>Bidder|technically compliant were as under:<br>Other than<br>HVAC('X)|.<br>HVAC ('Y') Total|HVAC ('Y') Total| |1|ALSTOM|1434|595|2029| |2|BTC|1621-|564|2185| |3|CAFC|1159|790|1949| |4|HBC|1767|514|2281| |5|HRC|1259|567|1826| |6<br>SIEMENS<br>1560<br>786<br>2346||||| 6. In terms of Annexure ITT-8 the GEC value of respondent No.2 which was the lowest was taken as the baseline for the purpose of loading the rupee equivalent of the higher values o offered by other bidders on to their price bids. The Indian rupee conversion of the said value above the baseline, proportionate to the higher GEC values was worked out as under: .. |to the higher GEC values was worked out as under:|to the higher GEC values was worked out as under:|to the higher GEC values was worked out as under:|to the higher GEC values was worked out as under:|to the higher GEC values was worked out as under:<br>..| |---|---|---|---|---| |S.No.|S.No.Bidder|GEC<br>('X'+'Y') loading<br>KWH|GEC for<br>'Y') loading|INR| |1|ALSTOM|2029|203|6,911,264,587.08| |2|BTC|2185|359|12,222,384, 171.24| |3|CAFC|1949<br>.|123|4, 187 ,613,518.28| |4|HBC|2281|455|15,490, 765453.80| |5|HRC|1826.<br>.|0<br>(baseline)|0| |6|SIEMENS|2346|520|17,703,731,947.20| 7. The position that emerged after the GEC values component was loaded to the price bid of the bidder was as under: H )> OJ () 0 m :c (j) Tl |Bidder|Grand Total<br>inlNR|INRper<br>Car.<br>(without<br>loading)|Position Grand Total<br>before<br>Loading loading)|Position Grand Total<br>(with energy<br>Loading loading)<br>inlNR|INR.per<br>Car (with<br>loading)|Position<br>after<br>loading|Total<br>Energ~<br>(kWH)|Energ~<br>SEC<br>value<br>(kWH/<br>1000<br>GTKM)| |---|---|---|---|---|---|---|---|---| |Siemens<br>Consortium|3625,27,92,409|7,45,94,223|L-1|5395,65,24,355|11,10,21,655|L-4|2346|55.71| |Bombardier<br>Consortium|4242,27,83,378|8,72,89,678|L-2|5464,51,67,548|11,24,38,616|L-5|2185|51.89| |Hyundai<br>ROTEM|4290,57,94,689|8,82,83,528|L-3|4290,57,94,690|8,82,83,528|L-1|1826|43.36| |Alstom<br>Consortium|4373,87,65.001|8,99,97,459|L-4|5065,00,29,588|10,42,18,168|L-3|2029|48.18| |CAF<br>Consortium|4614, 18,66, 794|9,49,42, 113|L-5|5032,94,80,313|10,35,58,601|L-2|1949|46.28| |Hitachi+<br>BHEL|4891,32,60,656|10,06,44,569|L-6|6440,40,26, 108|13,25, 18,572|L-6|2281|54.17| M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 837 DMRC LTD. & O~S. [T.S. THAKUR, J.] 8. It is evident from a comparative study of the charts extracted above, that while the appellant was L-1 in the price bid, it went down to L-4 after GEC value was loaded to its price bid. On the contrary respondent No.2-HR who was L-3 in the price bid rose to L-1 position on account of its low GEC value in comparison to a higher GEC value offered by the appellant. A B 9. Allotment of the award in favour of HR as the lowest bidder, thus, appeared as a writing on the wall to the appellant who ~nt a communication dated 12th February, 2013 to DMRC alleging that the GEC values offered by HR were untenable and unsustainable and pointing out that since the appellant's price bid was lesser than that of the HR by 665 crores (approx.) it should be taken as L-1 instead of determining the inter se position of the bidders on the basis of a supposedly anticipated saving in the consumption of energy on a lifecycle of 30 years. Yet another letter dated 25th February, 2013 the appellant called for· evaluation of energy values by an independent third party agency so as to ascertain whether the GEC values offered by HR were achievable. Yet another letter dated 1st March, 2013 to the same effect having failed to cut any ice with the DMRC, the appellant preferred Writ Petition No.1853 of 2013 before the High Court of Delhi. Tbat writ petition was 11otified for hearing on 1st May, 2013. In the meantime DMRC issued a Letter of Acceptance in favour of HR under intimation to the appellant. The appellant, therefore, sought a restraint order against the award of the contract before the High Court whq in turn accepted an undertaking given by the counsel for the DMRC and HR that they will not act in pursuance of the letter of award pending disposal of the writ petition. C D E F 10. Alstom Transport India Ltd. was the only other bidder G. aggrieved by the award of the contract who filed Writ Petition No.2615 of 2013 challenging the tender process. Both the writ petitions were eventually heard by the High Court on 1st May, 2013 and dismissed by the order under appeal before us. , 11. Appearing for the appellant, Mr. U.U. Lalit, learned H [2014] 2 S.C.R. ## 838 SUPREME COURT REPORTS A senior counsel, fairly conceded that the appellant had not alleged any mala tides, bias or bad faith in the matter of evaluation of the bids by the DMRC or any process connected therewith nor even in the award of the contract in favour of HR, the successful bidder. He contended that the tender notice no B doubt required GEC values to be offered by the bidders to be made use of in the process of tile evaluation of the bids but such values were not sacrosanct or immune from scrutiny and evaluation to determine whether the same were at all achievable. He submitted that since all the six bidders c competing for the contract are significant players in the international market, they could with a reasonable amount of certainty say whether or not the GEC values offered by the bidders were sustainable. It was contended by Mr. Lalit that while the GEC value offered by the appellant was the highest, 0[the one offered by the respondent successful bidder for 'X' ] factor was wholly untenable. He urged that the terms of the tender notice required the GEC values offered by the bidders to be validated before they could be used for processing the bids. He drew considerable support from a report submitted by the Director, Ministry of Urban Development, Government E of India, to suggest· that the stimulation test conducted by DMRC as a part ofttie process of verification and validation of the GEC value offered by HR was not accurate and urged that the Government of India had appointed a two-member Committee to check the evaluaticm process of the bids. The F report of the Committee filed· by the Go'ii'ernment in this Court in a sealed cover could, according to the learned Counsel, throw considerable light on the subject and help this Court in deciding whether an independent verification of the GEC values was necessary. ## G ,. 12. Mr. Andhyarujina, learned counsel for the respondentDMRC, on the other hand, argued that the bids offered by the eligible tenderers were evaluated by three different Committees i.e. the Evaluation Committee, the Appraisal Committee and H finally by the Tender Committee in a fair and transparent M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 839 DMRC LTD. & ORS. [T.S. THAKUR, J.] manner. On receipt of the representations ~rom the appellantA Siemens, Bombardier, Alstom and Hitachi regarding the GEC values offered by HR, the Board of Directors of DMRC constituted a sub-Committee to consider the said representations. The Board sub-Committee consisted of six directors out of whom three were Functional Directors besides B MD of the DMRC, a nominee Director of MoUD of Indian Railways and one independent Director. The Sub-Committee met on 4th and 5th March, 2013 and thoroughly examined the issues raised in the representation and found the detailed explanations provided in the Tender Committee Minutes to be c satisfactory. The Sub-Committee, therefore, agreed with the recommendations of the Tender Committee culminating in the issue of a Letter of Acceptance to respondent-HR. Our attention was drawn to the counter- affidavit filed by the DMRC in which the process of evaluation of the bids and the GEC values has been set out. The counter-affidavit further states that the DMRC D was fully satisfied about the achievability of the GEC values offered by HR. There was, therefore, no room for validation of · the GEC values by any outside agency. 13. It was further contended by Mr. Andhyarujina that the E tender conditions specifically provide for levy of a penalty in case of failure of the committed GEC values. He referred to ERTC 3.24.1 according to which the defaulting Contractor shall be liable to pay penalty at the rate ofRs.4.03 crores per unit of electricity committed in excess of the GEC values declared by F it. The penalty stipulated thus works out to be approximately 18.47% which is significantly higher than the rupee component loaded for each unit, argued the learned counsel. This implies that the lowest tenderer is under an onerous obligation to make good the GEC values or else end up paying a penalty at a rate G which is higher than the amount by which the financial bid has been loaded on a per unit of energy basis. 0 The Letter of Acceptance issued to ·HR also makes a specific provision for levy of penalty and, thus, fully secures the interest of the DMRC. H · [2014] 2 S.C.R. ## 840 SUPREME COURT REPORTS A A 14. Reliance upon the adaitional documents and the report of the Committee appointed by the MoUD was, according to Mr. Andhyarujina, wholly misplaced. He submitted that there was no occasion for the Government to appoint a Committee for evaluation of the bids received by DMRC which was an B autonomous,entity. The appointment of the Committee at the instance of the Minister in disregard of the observations made by the Secretary MoUD was not proper, argued the learned counsel, especially when the matter was pending adjudication before the High Court. The appointment of the Committee was c in any case not disclosed to the High Court by the Union of India on 1st May, 2013 when the matter was taken up for hearing. It was contended that the DMRC had at all times maintained that there was no question of any enquiry by an outside body regarding the evaluation ofthe bids received by it not even by the Government of India. He drew support for that submission D from the following statement made in the affidavit filed ,by the Union of India in this Court: E _''All tenders are floated and finalized by respective Metro Rail Corporations including DMRC. MoUD has no role in award/cancellation of any contractlten8er."_ 15. It was argued that the DMRC had also in its reply dated 14th August, 2013 sent to the Government clearly stated that it would not respond to the preliminary observations 'of the F Committee as the matter had in the meantime travelled to this Court and was sub judice. Legal opinion obtained by the DMRC from a Senior Advocate of this Court, also advised that in a matter that is sub judice, any report by any outside Enquiry Committee appointed by the Government. would be G impermissible and improper nor would it be advisable for DMRC to participate in any such exercise. In the premises it was contended that the Report by the Enquiry Committee submitted to this Court in a sealed cover need not be looked into as the same was wholly extraneous.lb a judicial review of the process of evaluation and eventual J~ard of the contract H M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 841 DMRC LTD. & 9RS. [T.S. THAKUR, J.] by DMRC, the authority competent to do so. Relying upon the A decisions of this Court in _Amrik Singh Lya/lpuri v. Union of India_ & _Ors._ (2011) 6 SCC 535 and _Union of India v. K.M. Shankarappa_ (2001) 1 SCC 582, it was argued that administrative review of a judicial decision was not legally permissible. It was also contended by Mr. Andhyarujina that B pursuant to the allotment made in his favour, HR had taken substantial steps towards implementation of the project and that interference with the award of the contract at this belated stage was neither in public interest nor otherwise justified in the facts and circumstances of the case. c c 16, Appearing for the respondent No.2-HR, Mr. Venugopal, learned senior counsel adopted the submiss-ions of ML Andhyarujina and took strong exception to the constitution of a Committee by the Minister of Urban Development, Government of India on a subject which was subjudice before the High Court. It was contended by Mr. Venugopal that the constitution of the Committee was not only against the sound advice tendered by the Secretary to the Government, Minister of Urban Development Department but was tantamount to interference· with the. course of justice. Relying upon the decision of the Full Bench of the High Court of Patna _in The King v. Parrnanand and_ Ors. AIR 1949 Patna 222 and _D. Jones Shield v. N._ Ramesam & _Ors._ AIR 1955 AP 156; In Re: P.C. Sen AIR ~970 SC 1821 and Jang Bahadur Singh v. Baij Nath Tiwari AIR 1969 SC 30, Mr. Venugopal argued that when a matter is pending adjudication before a Court of law, nothing can be done which might disturb the course of justice by either interfering with the judicial process or prejudging the merits of the case or by usurping the functions of the Court having seisin over the proceedings. Any such practice, argued the learned counsel, was fraught with danger and would ~mount to opening the door for contempt for those responsible for such interference. It was further contended by Mr. Venugopal that judicial review in tender cases was limited to examining the decision-making process and not the decision itself. Reliance in support of that D E F G H ## 842 SUPREME COURT REPORTS [2014] 2 S.C.R. A submission was placed by the learned counsel upon the decisions of this Court in _Tata Cellular v. Union of India_ (1994) 6 SCC 651; _Asia Foundation_ & _Construction Ltd. v. Trafalgar House Construction_ (1997) 1 SCC 738; _Monarch Infrastructure (P) Ltd. v. Ulhasnagar Municipal Corpn.,_ (2000) B 5 SCC 287; _Jagdish Manda/ v. State of Orissa_ (2007) 14 SCC 517 and _Heinz India (P) Ltd. v. State of U.P._ (2012) 5 SCC 443. It was submitted that the decision making process in the in.stant case was transparent, fair and reasonable and that the High Court had after a careful examination of all aspects c correctly held that there was no illegality or irregularity in the said process to warrant interference. 17. Principles governing judicial review of administrative decisions are now fairly well-settled by a long line of decisions rendered by this Court, since. the decision of this Court in D _Ramana Dayaram Shetty v. International Airport Authority of India and Ors._ (1979) 3 sec 489 which is one of the earliest cases in which this Court judicially reviewed the process of allotment of contracts by an instrumentality of the State and declared that such process was amenable to judicial review. E Several subsequent decisions followed and applied the law to varied situations but among the latter decisions one that · reviewed the law on the subject comprehensively was delivered by this Court in _Tata Cellular's_ case (supra) where this Court once again reiterated that judicial review would apply even to F exercise of contractual powers by the Government' and Government instrumentalities in order to prevent arbitrariness or favouritism. Having said that this Court noted the inherent · limiti;itions in the exercise of that power and declared that the State was free to protect its interest as the guardian of; its G finances. This Court held that there could be no infringement of Article 14 if the Government tried to get the best person or the best quotation for the right to choose cannot be considered to be an arbitrary power unless the power is exercised for any collateral purpose.· The scope of judicial review, observed this H Court, was confined to the following three distinct aspects: · MIS SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 843 DMRC LTD. & ORS. [T.S. THAKUR, J.] - _(i) Whether there_ was _any .illegality in the decision_ A _which would imply whether the decision making authority has understood correctly the law that regulates his decision making power and whether it has given effect to it;_ - B - _(ii) Whether there was any irrationality in the decision taken by the authority implying thereby whether the decision is so outrageous in its defiance of logic or accepted moral standards that ho sensible person who had applied his mind to the question_ · C _to be decided could have arrived at the same; and_ - _(iii) whether there was any procedural impropriety committed by the decision making authority while arriving at the decision._ D 18. The principles governing judicial review were then formulated in the following words: - _(i) The modern trend points to judicial restraint in administrative action._ E - _(ii) The court does not sit as_ a _court of appeal but merely reviews the manner in which the decision was made._ - _(iii) The court does not have the expertise to correct_ F _the administrative decision. If_ a _review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible._ - _(iv) The terms of the invitation to tender cannot be_ G _open to judicial scrutiny because the invitation to tender is in the realm of contract. Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than_ H ## 844 SUPREME COURT REPORTS [2014] 2 S.C.R. - A _not, such decisions are made qualitatively by experts._ - _(v) The Government must have freedom of contract. In other words,_ a _fair play in the joints_ is a _necessary concomitant for an administrative body_ - B _functioning in an administrative sphere. However, the decision must not only be tested by the application of Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not_ - c _affected by bias or actuated by_ ma/a _fides._ - _(vi) Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure._ D 19. In _M.P. Oil Extraction v. State of M.P._ & Ors. (1997) 7 sec 592, this Court held that if an objective and rational foundation for the fixation of royalty is disclosed, the Court will not interfere with the exercise of governmental decision by undertaking an exercise to determine whether or not a better E fixation was possible in the circumstances. This Court struck a note of caution that in economic and policy matters the scope of judicial review was limited. 20. It is unnecessary and platitudinous for us to burden this F judgment with reference to the decisions of this Court on the subject for the governing principles are so well-known and wellsettled that any review of the law on the subject is bound to be simply repetitive without any meaningful contribution tc5 the existing legal literature on the subject. We remain content by G referring to two only of a plentitude of judicial pronouncements on the subject in which the legal position has been succinctly restated. One of these decisions was delivered in _Jagdish Manda/ v. State of_ Orissa & Ors. (2007) 14 SCC 517, where too this Court was dealing with the exercise of power of judicial H review in matters relating to tenders and award of contracts. _MIS_ SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 845 DMRC LTD. & ORS. [T.S. THAKUR, J.] This Court identified the special features should be borne in mind while judicially reviewing award of contracts. We can do no better than extract the following observations of this Court in this regard: · A "22. Judicial review of administrative action is intended to prevent arbitrariness, irrationality, unreasonableness, bias and mala tides. Its purpose is to check whether choice or decision is made "lawfully" and not to check whether choice or decision is "sound". When the power of judicial review is invoked in matters relating to tenders or award of contracts, certain special features should be borne in mind. A contract is a commercial trarn)action. Evaluating tenders and awarding contracts are essentially commercial functions. Principles of equity and natural justice stay at a distance. If the decision relating to award of contract is bona fide and is in public interest. courts will not. in exercise of power of judicial review. interfere even if a procedural aberration or error in assessment or prejudice to a tenderer. is made out. The power of judicial review will not be permitted to be invoked to protect private interest at the cost of public interest. or to decide contractual disputes." B c D E (emphasis supplied) 21. More recently in _Heinz India (P) Ltd._ & _Anr. v._ State _of U.P._ & _Ors._ (2012) 5 SCC 443, this Court speaking through one of us (Thakur, J.) examined the legal dimensions of judicial review and quoted with approval the following passage from _Reid v._ Secy. _of_ State _for Scotland_ (1999) 1 All ER 481 which succinctly sums up the law. F G _"Judicial review involves_ a _challenge to the legal validity of the decision. It does not allow the court of review to examine the evidence with a view to forming its own view about the substantial merits of the case. It may be that the tribunal whose decision is being challenged has_ H 846 SUPREME COURT REPORTS [2014] 2 S.C.R. A B c D _done something which it had no lawful authority to do. It may have abused or misuse.d the authority which it had. It may have departed from the procedures which either by statute or at common law_ as _a matter of_ fairness _it ought to have observed._ As _regards the decisions itself it may be found to be perverse, or irrational or grossly disproportionate to what was required. Or the decision may be found to be erroneous in respect of a legal deficiency,_ as _for example, through the absence of evidence, or of sufficient evidence, to support it, or through account being taken of irrelevant matter, or through a failure for any reason to take account of_ a _relevant matter, or through_ some _misconstruction of the terms of the statutory provision which the deCision-maker_ is _required to apply. But while the evidence may have to be explored in order to_ see _if the decision_ is _vitiated by such legal deficiencies it_ is _perfectly clear that in_ case _of review,_ as _distinct from an ordinary appeal, the court may not set about forming its own preferred view of evidence."_ E E 22. There is no gainsaying that in any challenge to the award of contact before the High Court and so also before this Court what is to be examined is the legality and regularity of the process leading to award of contract. What the Court has to constantly keep in mind is that it does not sit in appeal over F the soundness of the decision. The Court can only examine whether the decision making process was fair, reasonable and transparent. In cases involving award of contracts, the Court ought to exercise judicial restraint where the decision is bonafide with no perceptible injury to public interest. G 23. The High Court has, in the case at hand, undertaken that exercise and concluded that there was neither any illegality nor any irregularity in the process of evaluation of the bids or the final allotment of the contract. That view has come to be assailed by the appellant on what is essentially a short point H M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 847 DMRC LTD. & ORS. [T.S. THAKUR, J.] raised by Mr. Lalit in support of the appeal. The contention, as noticed earlier, is that while no malafide or extraneous considerations have prevailed to vitiate the decision of the DMRC allotting the contract in favour of HR, the process of evaluation of the bids offered by the eligible bidders should have in the facts and circumstances of the case included validation of the GEC values offered by HR to determine whether they were achievable having regard to the ground realities and the laws of physics relevant to the consumption of energy. That contention does not suggest any illegality in the process of allotment of the contract in favour of HR, for no violation of any law, rule or regulation governing the process of invitation of tenders by the DMRC or its evaluation and acceptance has been alleged or argued before us. No such statutory or other provision has been brought to our notice which could possibly provide to the appellant a reason to contend that the allotment of the contract was itself illegal or in breach of any such provision or procedure prescribed thereunder. It is no body's case that the decision-making authority had not understood the law that regulates its decision making power or failed to give effect to it. We have, therefore, no hesitation in holding that the allotment of contract did not suffer from any illegality as it is understood in the matter of judicial review of administrative action and as that expression has been used by this Court in _Tata Cellular's_ case (supra}. It is also not the case of the petitioner that the decision taken by the DMRC is so outrageous in its defiance of logic or accepted moral standards that no sensible person who had applied his mind could have arrived at the same. Perversity or irrationality in the decision or the decision making process is also not a ground that can be invoked in the case at hand. 24. The contention urged by Mr. Lalit may at best constitute an irregularity in the process of evaluation of the bids. That an irregularity can itself, in certain situations result in invalidating a process, cannot be disputed. The question, however, is whether there was any irregularity in the evaluation of the bids A B C D E F G H 848 SUPREME COURT REPORTS [2014] 2 S.C.R. - A in the present case and if so whether the same was sufficient to invalidate the evaluation process or the ultimate award of the contract. Whether or not there was any irregularity in the process of evaluation of the bids shall in turn have to be examined by a reference to the conditions of the tender notice under which the - 8[tenders were invited, received, processed, evaluated and ] eventually accepted. It is common ground that the price bid offered by the tenderers was not itself determinative. What was equally important was the GEC values comprising X and Y factors which the tenderers had to disclose in their technical - C bids. That the values offered had to be converted into Indian Rupees and loaded to the price bid of the tenderers is also beyond question. That each one of the bidders had offered their GEC values comprising X and Y factors separately was also beyond doubt. There is no error even in the conversion of such values in terms of Indian Rupees nor is there any dispute about - D the effect of such loading of values to the price bid of all the tenderers because of which loading the bid offered by HR eventually emerged as L-1 with appellant-Siemens sliding to L-4 position. That being so, the process of evaluation of bids· could not be faulted as the same was strictly in accordance with - E the norms stipulated for such evaluation. Even Mr. Lalit fairly conceded that there was nothing that could be criticized in that process. What DMRC, according to him, should have done was to check whether the GEC values offered by the bidders were achievable. Inasmuch as no such verification was undertaken - F the evaluation process was flawed. There is, in our opinion, no merit in that contention. The reasons are not far to seek. In the first place, the contention urged by Mr. Lalit does not find support from any provision in the tender notice. There is nothing in the tender document to suggest that the GEC values had to - G be tested for their achievability.As rightly contended by Mr. Lalit all the six bidders declared eligible are world leaders in the field and have sufficient expertise and know-how not only about the design and technology which they use but also about their capacity to validate their respectiye GEC values. If that be so, H M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 849 DMRC LTD. & ORS. [T.S. THAKUR, J.] DMRC could be supremely confident that the GEC values A offered by HR were achievable especially when such values offered by some of the bidders for X and Y factors were lower than those offered by HR. At any rate the DMRC had sufficiently protected itself because under the terms and conditions stipulated in the tender notice failure of the successful tender B to make good the GEC values offered by them would result in . a penalty which was higher than the GEC value factor that was loaded to the price bid. We, therefore, do not see any real basis for the contention that the DMRC was supposed to go any further than it did in protecting its interest. In the absence of any c specific stipulation or requirement for validation of the GEC values by the DMRC and its experts or by any outside agency such a requirement could not be implied into the tender process. Inasmuch as the DMRC found the bid offered by HR to be acceptable, keeping in view the GEC values offered by it, the 0 former had committed no illegality in the evaluation of the bids or in making its choice of the contractor. 25. Secondly, because even assuming that the process of validation of the GEC values and their achievability was an implied condition in the evaluation process, DMRC had on the E basis of an internal simulation satisfied itself that the GEC values were not unachievable.The High Court has referred to the simulation results and so has our attention been drawn to the said result from the original record produced by DMRC. We do not see any illegality or irregularity in the process of F verification conducted by the DMRC to test the achievability of the GEC values. It is true that DMRC had conducted the simulation in regard to the GEC values offered by HR only but then in the absence of any condition in the tender notice requiring DMRC to conduct such verification even in regard to G other GEC values, there was no need for it to undertake any such exercise. DMRC was, in our opinion, entitled to adopt such methods as were reasonable to satisfy itself above about the GEC values and their achievability offered by lowest tenderer in whose favour it was considering the award of the H [2014] 2 S.C.R. ## 850 SUPREME COURT REPORTS A contract. The upshot of the above discussion, therefore, is that the process by which the bids were evaluated and eventually accepted was transparent, fair and reasonable and does not, therefore, call for any iriterference from this Court. 26. That brings us to the question whether the Government 8 of India was justified in appointing a Committee to test the evaluation of bids and, if so, whether this Court ought to look into the Report of the Committee. There is more than one aspect that needs to be kept in view in this regard. The first C and foremost is the fact that the Committee was appointed at a stage when the matter was already pending before the High Court. Considerable time was spent by learned counsel for the parties in debating whether the constitution of the Committee by the· Government itself tantamounted to interference with the course of justice, hence contempt. We do not, however, D consider it necessary to pronounce upon that aspect in these proceedings especially because we have not been called upon to initiate such contempt proceedings. All that we need say is tbat once the Government had known that the entire issue regarding the validity of the process adopted by DMRC E including the transparency and fairness of the process of evaluation of the bids was subjudice before the High Court of Delhi and later before this Court, it ought to have kept its hands off and let the law take its course. It could have doubtless placed all such material as was relevant to that question before the F High Court and invited a judicial pronouncement on the subject instead of starting a parallel exercise. The Government could even approach the High Court and seek its permission to review the process of evaluation either by itself or through an expert Committee if it felt that any such process would help the G Court in determining the issues falling for consideration before the Court more effectively. Nothing of that sort was, however, done. On the contrary even when the Secretary to the MoUD pointed out that the matter is subjudice and any further action in the matter could await the pronouncement of the Court, the H Hon'ble Minister heading MoUD directed the constitution of the _MIS_ SIEMENS AKTIENGESELISCHAFT & S., LTD. _v._ 851 DMRC LTD. & ORS. [T.S. THAKUR, J.] Committee with the following terms: A _"2(1) To examine if a fair, equitable and transparent tender process was followed by DMRC, as per the prescribed guidelines"._ B 27. We have no manner of doubt that the terms of reference give a clear indication that the process initiated by the Government was a parallel process of the adjudication of the very same issue as fell for consideration before the High Court and at a later stage before this Court. We fail to appreciate how the Government could have possibly done this. Confronted with C this situation Mr. Mohan Parasaran, learned Solicitor General, argued that a reference to the Committee was not meant to subvert judicial process but to only find ways and means to formulate policies and procedures for future allotment of contracts. We have no hesitation in rejecting that submission. o The Reference Order extracted above speaks for itself. It no where states that the Committee has to look at anything beyond .the process of evaluation of tenders received by DMRC. It does not even remotely suggest that the Government is concerned about the procedures that may be followed in the future or E anxious to devise transparent methods by which such contract should be allotted. What is notable is that the Committee's hands were not stayed by the Government even when the High Court had pronounced upon the validity of the procedures adopted by the DMRC and the matter reached this Court. F Continuance of the process of review even after the High Court had delivered its judgment amounted to subjecting the judicial pronouncement to an administrative review. There was no question of any such judicial determination or adjudication being subjected to any administrative review albeit in the name of a G Committee constituted for the purpose. E F G 28. Mr. Parasaran argued that the Committee's proceedings did not amount to sitting in appeal over the judgment of the High Court. The Committee may have not said anything adverse to view taken by the High Court but if the H 852 SUPREME COURT REPORTS [2014) 2 S.C.R. A Committee were to find fault with the evaluation process which the High Court has held to be valid it indirectly amounted to putting a question mark on the judgment of the High Court itself. Suffice it to say what the Government ought to have stayed its hands once the matter landed in the Court. Inasmuch as the 8[Government did nothing ][of ][this kind, it did not act properly. ] Beyond that we do not consider it necessary or proper to say anything at this stage. 29. It was contended by Mr. Lalit that the report submitted by the Committee appointed by the Government ought to be C taken as expert opinion on the subject and given due weight. That position was disputed by Mr. Andhyarujina appearing for DMRC and Mr. Venugopal appearing for HR. That the Committee comprised a former Finance Secretary to the Government of India and a Civil Engineer, none of whom could D claim to be expert in the field relevant to the achievability of the GEC values, was not disputed by Mr. Parasaran who urged that the Committee may have taken the opinion of some experts on the subject. Even assuming that the Committee has taken expert advice regarding the tenability of the GEC values offered E by HR, it would simply mean that there is a conflict between the views taken by the experts of DMRC and those consulted by the Committee. Any such conflict cannot be resolved by this Court in exercise of its powers of judicial review. So long as the view taken by the experts of the authority competent to take F a final decision is a possible view the very fact that some other experts have expressed doubts about the sustainability of the GEC values will not be enough for us to declare that the values offered by HR are indP.ed unachievable. This Court has in _Federation of Railway Officers Association v. Union of India_ G (2003) 2 SCR 1085, stated the wholesome principle applicable in such situations in the following words: _"Further,· when technical questions arise and experts in the field have expressed various views and all those aspects have been taken into consideration by the_ H M/S SIEMENS AKTIENGESELISCHAFT & S. LTD. _v._ 853 DMRC LTD. & ORS. [T.S. THAKUR, J.] _Government in deciding the matter, could it still be said_ A _that this Court should re-examine to interfere with the same. The wholesome rule in regard to judicial interference in administrative decisions is that if the Government takes into consideration all relevant factors, eschews from considering irrelevant factors and acts_ B _reasonably within the parameters of the law, courts would keep off the same."_ 30. Reference may also be made to the decision of this Court in _N.D. Jayal v. Union of India_ (2004) 9 SCC 362 where this Court observed: C _"This Court cannot sit in judgment over the cutting edge of scientific analysis relating to the safety of any project. Experts in science may themselves· differ in their opinions while taking decisions on matters related to safety and_ D _allied aspects. The opposing vie.wpoints of the experts will also have to be given due consideration after full application of mind. When the Government or the authorities concerned after due consideration of all viewpoints and full application of mind took_ a _decision,_ E _then it is not appropriate for the court to interfere."_ · 31. Reliance by the appellant upon the report of the Committee is misplaced also for the reason that the same was ex parte. It is common ground that HR was never associated with the process of evaluation or verification if any conducted F by the Committee. In the absence of any such opportunity to the party whose GEC values were being test checked for their achievability, the report can hardly provide a sound basis for a writ court to upset a decision which the competent authority has taken after due deliberations by not one but four different G Committees including experts in the field. That apart, Mr. Parasaran fairly submitted that even the Government have not accepted the report submitted by the Committee so far. He urged that since the matter was pending in this Court, the Government has simply placed the report of the Committee in H H 854 SUPREME COURT REPORTS [2014] 2 S.C.R. A a sealed cover for the Court to decide as to what value has to be attached to it. That being the position, the preparation and submission of a report that does not even take the view point of the party affected by it into consideration can hardly provide to this Court a good reason to scuttle the entire process at this B stage when HR, the successful bidder, has already taken substantial steps in the direction of executing the works allotted to it. 32. Last but not the least, if the note submitted by the Director in the·MoUD is an indication of what the Committee C may have said, the difference in the GEC values pointed out in the report of the Director, may have led to CAF which was also an eligible bidder emerging as L-1 and not the appellant. In terms of cost of the project it would hardly make a sizable difference so as to justify a reversal of the steps that have D already been taken for execution of a project that is of utmost importance for the people living in the national capital execution whereof can brook no delay especially when the same is being financed by an agency from outside the country. E 33. In the result this appeal fails and is, hereby, dismissed with costs of Rs.5,00,000/- to be deposited within six weeks from today with the Supreme Court Advocates-on-Record Welfare Fund. R.P. Appeal dismissed.
End of Judgment Record
Browse All Supreme Court of India (2014) Decisions
2014-07-01

Duryodhan Rout v. State of Orissa

These appeals challenge a common judgment convicting Duryodhan Rout of rape and murder of a 10-year-old girl, Subhasini Bhoi. The trial court convicted him under IPC sections 376(f), 302, and 201 and sentenced him to death; on reference, the High Court remitted the death sentence for the 302 offence to life imprisonment while keeping the other sentences unchanged. The prosecution's case rested solely on circumstantial evidence. PW-1 and PW-2 saw the accused with the victim on a bicycle around 4 p.m. and returning alone about an hour later; PW-5 (father) and PW-6 (mother) testified that the child was taken on the pretext of talking on the phone. In custody, the accused confessed before PW-3 and PW-4, and under Section 27 of the Evidence Act the recovery of the body and the underwear was recorded; the autopsy by PW-9 indicated throttling and injuries consistent with rape. The chain of circumstances — last-seen with the victim, recovery of the corpse in the jungle, and the forensic findings — formed a robust basis for conviction. The central legal issue was whether sentences for multiple offences should run consecutively. The Court held that life imprisonment is the remainder of a convict's natural life, and the proviso to Section 31(2) Cr.P.C. prevents aggregation beyond fourteen years, thus consecutive sentences cannot be imposed where life imprisonment is one of the terms. Consequently, all IPC sentences should run concurrently; the death sentence for the 302 offence was replaced by life imprisonment, and the appeal was allowed in part.

2014-12-16

Nand Kishore v. State of Madhya Pradesh

This is a criminal original jurisdiction writ petition under Article 32 challenging the continued incarceration of a convict under Section 302 IPC, with the petitioner contending entitlement to the Juvenile Justice (Care and Protection of Children) Act, 2000 (JJC Act) protections on the ground that he was a juvenile at the time of the offence (born 14 April 1980; incident on 18 June 1997). The Court scrutinized documentary and oral evidence from the Juvenile Justice Board indicating the petitioner’s true date of birth and concluded that on the date of occurrence he was 17 years 2 months 4 days old, thereby satisfying the juvenile criteria. The judgment clarifies a central legal question: whether the protections and benefits under the JJC Act, enacted in 2000, can be extended to those convicted before its coming into force if they were juveniles at the time of the offence. Relying on earlier decisions such as Hariram v. State of Rajasthan and Ajay Kumar v. State of Madhya Pradesh (and others), the Court held that a person who had not completed 18 years on the date of offence is entitled to the Act’s benefits as if the provisions had always existed, effectively retroactively applying the protective regime. The petition was allowed; the petitioner is to be released forthwith, with bail bonds and sureties discharged, reflecting the Court’s protective stance for juveniles in criminal proceedings.

2014-04-24

Vishal Goyal & Ors. v. State of Karnataka & Ors.

This batch of writ petitions under Article 32 concerns admissions to Post Graduate Medical and Dental courses in government medical/dental colleges and the state quota in private colleges in Karnataka for the 2014-2015 academic year. The petitioners, who completed MBBS/BDS in Karnataka, challenged sub-clause (a) of clause 2.1 of two National Board of Examinations Information Bulletins (PGET-2014) which defined “Karnataka Origin” to permit admission only to those who satisfy certain criteria, effectively excluding many who studied in Karnataka institutions. They argued this violates Article 14 (equality before law and equal protection of laws) and undermines merit-based selection for postgraduate courses. They invoked Dr. Pradeep Jain & Others v. Union of India (1984) to contend that institutional preference may be permissible but must conform to equality; Magan Mehrotra v. Union of India (2003), Saurabh Chaudhri v. Union of India (2003), and Nikhil Himthani v. State of Uttarakhand (2013) were cited to support the continuing emphasis on merit and equality. The State countered that Article 371J allows reservation for the Hyderabad-Karnataka region and argued that the Pradeep Jain framework applies only to government or state-instrumentality institutions and not to private colleges. The Court held sub-clause (a) ultra vires Article 14, directed fresh Information Bulletins, and ordered admissions in accordance with the law on the basis of existing entrance test results, with the general counselling schedule from Dr. Fraz Naseem & Ors. not applying for 2014-2015 Karnataka admissions.

2014-08-21

SINGH RAM (D) THR. L.Rs. v. SHEO RAM & ORS.

This is a Supreme Court of India decision on the limit of time within which a usufructuary mortgagee can seek relief, and the corresponding equity of redemption for the mortgagor. The appellants challenged the Punjab and Haryana High Court Full Bench’s view that there is no fixed time for redemption in a usufructuary mortgage and that the right to seek redemption arises on payment/deposit of mortgage money, irrespective of the mortgage date. The HP High Court’s decision was later reversed by a larger bench of this Court in the context of reconciling conflicting precedents such as Sampuran Singh, Prabhakaran and Jayasingh Dhyanu Mhoprekar, Parichhan Mistry and Harbans etc., emphasizing that Section 62 of the Transfer of Property Act confers a special right on the usufructuary mortgagor to recover possession, which begins only when the mortgage money is paid out of rents and profits or when paid/deposited by the mortgagor. Article 61 of the Limitation Act governs the period for redeeming or recovering possession (30 years from accrual of the right, unless restricted). The Court reaffirms the principle ‘once a mortgage, always redeemable’ and rejects a blanket 30-year extinguishment rule for usufructuary mortgages, upholding the Full Bench view of the Punjab and Haryana High Court and dismissing the appeals. The decision emphasizes equity, statutory recognition under Section 62, and the distinctive treatment of usufructuary mortgages.