M/s. Shree Vishnu Constructions v. The Engineer in Chief Military Engineering Service & Ors.
Case Synopsis & Summary
This appeal arises from a dispute over an arbitration clause in an agreement dated 22.07.2010 for additions/alterations to the Senior Non-Commissioned Officers mess and repairs at the Air Force Academy, Hyderabad. The appellant submitted a revised final bill on 10.07.2012 and was paid the final amount on 29.04.2013, accompanied by a no-further-claim certificate. The appellant invoked arbitration by a notice dated 20.12.2013 and filed a Section 11(6) application for appointment of an arbitrator before the High Court on 27.04.2016. The High Court dismissed the petition, finding that the entire amount was settled and accord and satisfaction had occurred, negating the need for arbitration. The appellant contends that the Arbitration and Conciliation (Amendment) Act, 2015 introduced Section 11(6A), restricting judicial inquiry at Section 11(6) stage to the existence of an arbitration agreement, and bifurcating the regime under Section 26 into arbitral proceedings and court proceedings. It argues that the amended Act applies only to proceedings commenced on or after 23.10.2015, so the pre‑amendment regime should govern, given that arbitration was invoked in 2013. The respondents contend that the arbitral process began in 2013 and that the pre‑amendment regime applies. The Supreme Court ultimately held that the Amendment Act is prospective; it shall apply to arbitral proceedings commenced on or after the amendment and to court proceedings commenced on or after its date, and accordingly dismissed the appeal with no costs.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- M.R. Shah
- C. T. Ravikumar
- Judgment Date
- 2023-05-09
- Court Decision / Holding
- Appeal dismissed. The Court held that the Arbitration Amendment Act, 2015 is prospective and applies to arbitral proceedings commenced on or after the date of commencement and to court proceedings commenced on or after that date. Since the arbitration notice was issued in 2013, pre‑amendment law governs for Section 11(6) proceedings; ultimately, the High Court’s dismissal was upheld with no order as to costs.
- Final Disposition
- Appeal dismissed; no costs.
Parties to the Case
Appellants / Petitioners
- M/s. Shree Vishnu Constructions
Respondents
- The Engineer in Chief Military Engineering Service & Ors.
Legal Representation & Advocates
Counsels for Petitioners
- • Shri K. Parameshwar
Counsels for Respondents
- • Shri Padmesh Mishra
Provisions of Law Cited
Legal Doctrines & Maxims
- Every litigant has a vested right in substantive law but no such right exists in procedural law (Hitendra Vishnu Thakur v. State of Maharashtra)
- A procedural statute should not generally be applied retrospectively where the result would create new disabilities or obligations
- A statute which changes the procedure but also creates new rights and liabilities shall be construed to be prospective in operation
Submissions & Arguments
Contentions of Appellants / Petitioners
Appellants contended that the Amendment Act, 2015 introduced Section 11(6A) to confine the Court’s role at the Section 11 stage to the existence of an arbitration agreement, with issues like accord and satisfaction to be decided by the arbitrator. They argued Section 26 bifurcates arbitral proceedings from court proceedings and that Section 26(2) makes the Amendment Act applicable only to court proceedings commenced after the Amendment Act came into force; arbitration here commenced before 23.10.2015, so pre‑amendment law should apply. They relied on BCCI v Kochi Cricket and other decisions to support prospective application and the primacy of the pre‑amendment regime for Section 11(6).
Contentions of Respondents
Respondents argued that arbitration proceedings commenced in 2013 and the Section 11(6) application was filed in 2016, after the Amendment Act, 2015 came into force; thus the amended Act governs the proceedings under Section 11 and that accord and satisfaction issues are resolved in court/arbitral proceedings depending on the date of commencement. They contended that the pre‑amendment regime applies only to arbitration commenced prior to the amendment with respect to Sections 34/36, and that the court should follow the principles laid down in Parmar/Pradeep Vinod and related decisions.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (13)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Board of Control for Cricket in India (BCCI) v Kochi Cricket Private Ltd. | (2018) 6 SCC 287 | Positive | Provisions interpreted to be prospective; supports the view that the 2015 Amendment Act applies prospectively. |
| Mayawati Trading v. Pradyut Debbarman | (2019) 8 SCC 714 | Mentioned Only | Cited for the effect of 11(6A) but not a controlling authority on its own. |
| Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India | (2019) 15 SCC 131 | Positive | Applied to interpret the scope of amended Section 34 and its relation to post‑amendment applications. |
| Parmar Construction Company | (2019) 15 SCC 682 | Positive | Discussion on applicability of the Amendment Act to Section 11(6) proceedings; not held per incuriam. |
| Pradeep Vinod Construction Company | — | Positive | Followed Parmar on the Section 11(6) issue; supports pre‑amendment regime where applicable. |
| S.P. Singla Constructions Private Limited v State of Himachal Pradesh | (2019) 2 SCC 488 | Positive | Used to support interpretation that Amendment Act’s applicability to pre‑commencement proceedings can be limited by Section 21/Section 26. |
| Aravali Power Company Private Limited v Era Infra Engineering Limited | (2017) 15 SCC 32 | Distinguished | Not directly applicable to judicial arbitral proceedings; treated as not controlling. |
| Hitendra Vishnu Thakur v. State of Maharashtra | (1994) 4 SCC 602 | Positive | Principles on procedural/prospective application cited. |
| Ratna Infrastructure Projects Pvt. Ltd. v. Meja Urja Nigam (P) Ltd. | (2017) SCC OnLine Del 7808 | Distinguished | Delhi High Court decision distinguished for not applying in the present judicial context. |
| Hindustan Construction Company Limited v. Union of India | (2020) 17 SCC 324 | Positive | Affirms approach to application of Amendment Act to court proceedings. |
| Vedanta Limited v. Government of India | (2020) 10 SCC 1 | Positive | Followed the BCCI framework; supports prospective application to court proceedings. |
| Patel Engineering Limited v North Eastern Electric Power Corporation Limited | (2020) 7 SCC 167 | Positive | Three‑judge bench endorses BCCI approach in the related context. |
| Union of India v Parmar Construction Company | (2019) 15 SCC 682 | Mentioned Only | Cited in argument; not controlling for Section 11 in the instant matter. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/s. Shree Vishnu Constructions v. The Engineer in Chief Military Engineering Service & Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.