M/s Sai Baba Sales Pvt. Ltd. v Union of India & Ors (Civil Appeal Nos. 595 of 2021 and 5768 of 2021)

Case / Petition Number:
Civil Appeal Nos. 595 of 2021; 5768 of 2021

Case Synopsis & Summary

The two civil appeals challenge the National Green Tribunal’s OA judgment upholding a prohibition on further construction without an environment impact assessment (EIA) while protecting already erected structures based on an Environmental Clearance (EC) issued by the Pimpri Chinchwad Municipal Corporation (PCMC) under the 2016 MoEFCC notification regime. The core issue is whether the project proponent had a valid EC under the EIA notification dated 14 September 2006, given the regime changes effected by the 9 December 2016 notification and subsequent clarifications. The project initially sanctioned for 15,040 sq m (below the 20,000 sq m EC threshold) proceeded with construction; later, to expand to 49,012 sq m, it obtained a layout sanction and, under the 9 December 2016 regime, EC was to be granted by local authorities. The NGT’s 2020 order directed protection of the already completed structures but required future construction to have EC under the current regime. The Supreme Court held that the EC granted by PCMC on 28 November 2017, under the amended regime, was the operative EC for purposes of the ongoing project and protected pre-existing structures on legitimate-expectation grounds. It clarified that any further development must obtain fresh clearance under the then-applicable framework and disposed of the appeals without costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • R. Subhash Reddy
  • Hrishikesh Roy
Judgment Date
2021-11-26
Court Decision / Holding
Appeals disposed of. The four constructed buildings are to be treated as valid under the EC granted by the PCMC on 28 November 2017, under the then-applicable regime. Any further construction must be undertaken only after obtaining fresh clearance from the competent authority under the current framework. No orders on costs.
Final Disposition
Appeals disposed of without any order on costs.

Parties to the Case

Appellants / Petitioners

  • M/s Sai Baba Sales Pvt. Ltd.

Respondents

  • Union of India
  • State of Maharashtra
  • State Pollution Control Board
  • Pimpri-Chinchwad Municipal Corporation (PCMC)

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Huzefa Ahmadi (Senior Counsel)

Counsels for Respondents

  • • Ms. Aishwarya Bhati (ASG)
  • • Mr. Rahul Chitnis
  • • Mr. Mukesh Verma

Provisions of Law Cited

National Green Tribunal Act, 2010 - Section 22Environmental Impact Assessment Notification, 2006 (as amended)MoEFCC Notification dated 9 December 2016MoEFCC communications 7 July 2017; 14 November 2018; 15 November 2018

Legal Doctrines & Maxims

  • Doctrine of Legitimate Expectation
  • Regularity, Predictability and Certainty in Government’s dealings with the Public (De Smith’s Judicial Review)
  • Non-arbitrariness / Rule of Law

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicant contends that it had obtained the requisite EC framework through the 2016 regime via the local EC from PCMC, following prior layout sanction and development approvals obtained before the 9 December 2016 amendment. Since substantial construction had already commenced and the local EC was granted under the amended regime, the project should be protected as legitimate expectations and the already built structures should be permitted to stand with compliance to norms. The applicants seek to rely on the Committee’s findings favoring conformity with the local EC rather than re-opening completed work, while arguing that future construction must secure fresh clearance under the current regime.

Contentions of Respondents

The respondents argued that the EC granted by PCMC under the 9 December 2016 regime was legally invalid following the NGT’s later position striking down portions of the 2016 notification. They contended that construction without a valid EC should be penalized and that the project must adhere to the regime in force at the time of the application, with EC only being issued by SEIAA, and that the NGT’s directive to revisit the regime should apply retroactively to the EC already granted.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Goan Real Estate and Construction Ltd. v. Union of India(2010) 5 SCC 388PositiveCited to support the principle that legitimate expectation and regulatory stability should be considered in evaluating EC regimes and their impact on pre-existing structures.
Attorney General of Hong Kong v. Ng Yuen Shiu(1983) AC 629PositiveCited as authority on legitimate expectation and fair administrative action in regulatory changes.
Council of Civil Service Unions v. Minister for the Civil Service(1985) AC 374PositiveLocus classicus for legitimate expectation, cited to explain the contours of legitimate expectation in public decision-making.
Food Corporation of India v. Kamdhenu Cattle Feed Industries(1993) 1 SCC 71PositiveDefines the role of legitimate expectation as a factor requiring due consideration to avoid arbitrariness.
Sethi Auto Service Station v. Delhi Development Authority & Ors(2009) 1 SCC 180PositiveCited for elaboration on legitimate expectation and non-arbitrariness principles in decision-making.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,244 words•~15 min read

In The Court Record

M/s Sai Baba Sales Pvt. Ltd. v Union of India & Ors (Civil Appeal Nos. 595 of 2021 and 5768 of 2021)

## [REPORTABLE] IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ## CIVIL APPEAL NO. 595 OF 2021 M/S. SAI BABA SALES PVT. LTD. APPELLANT(S) ## VERSUS UNION OF INDIA & ORS. RESPONDENT(S) WITH CIVIL APPEAL NO. 5768 OF 2021 J U D G M E N T ## Hrishikesh Roy, J. **1.** Heard Mr. Huzefa Ahmadi, learned senior counsel appearing for the appellant in Civil Appeal No. 595/2021. Mr. Lonkar Nitin representing the Original Applicant before the National Green Tribunal. Ms. Signature Not Verified Digitally signed by Rajni Mukhi Aishwarya Bhati, learned Additional Solicitor General of Date: 2021.11.26 14:01:35 IST Reason: India appears for the Ministry of Environment & Forest. Page 1 of 18 The Government of Maharashtra and the State Pollution Control Board are represented by Mr. Rahul Chitnis and Mr. Mukesh Verma, learned counsel respectively. **2.** These two appeals are filed under Section 22 of the National Green Tribunal Act, 2010 (for short “the NGT Act”) assailing the judgment and final order dated 18.1.2021 in the OA No. 83/2019. Under the impugned judgment, the NGT held that further construction cannot be made without environment impact assessment, but protected the constructions already made by the appellant, M/s Sai Baba Sales Pvt. Ltd. (“Project Proponent”) on the basis of the Environmental Clearance (“EC” for short) issued by the Pimpri Chinchwad Municipal Corporation (“PCMC” for short) as per the notification dated 9.12.2016. The Original Applicant, on the other hand, is aggrieved by the decision of the NGT to protect the standing construction and limiting the impact of the impugned judgment on further construction to be made by the project proponent. **3.** The main issue that arises for consideration in these matters is whether the Project Proponent herein Page 2 of 18 possesses a validly granted Environmental Clearance (EC) under the Environmental Impact Assessment (EIA) notification dated 14.9.2006. The 2006 EIA notification provided that the projects above 20,000 sq. meter and below 1,50,000 sq. meter should obtain an EC from the State Environment Impact Assessment Authority (SEIAA) of the Ministry of Environment, Forest and Climate Change (MoEFCC). **4.** For deciding the issue, the necessary facts in brief are that the Project Proponent initially conceived a project of 15,040 sq. mtrs. (below the EC threshold limit of 20,000 sq. mtrs.) and it approached the PCMC for a lay out order which was a prerequisite, to obtain an EC from the SEIAA of the MoEFCC. The application was processed and the Building Permission Department of the PCMC granted the commencement certificate to the Project Proponent for an area of 15,040 sq. mtrs. and approved the plan under the sanction letter dated 14.5.2013. With such permission, the Project Proponent could construct the permitted structures, and since the built up area was less than the threshold limit of 20000 sq. mtrs., Page 3 of 18 the EC permission was not needed for the intended construction. **5.** The Project Proponent builder then applied and was granted additional FSI as it intended to expand the project to one with built up area of 49,012 sq. mtrs. and for this they approached the PCMC for a lay out order, which as noted earlier was essential to obtain an EC from the SEIAA of the Ministry of Environment, Forest and Climate Change (MoEFCC). The required approval was issued by the Corporation on 28.11.2016. **6.** Under the Ministry’s notification dated 9.12.2016, the EIA regime was altered to indicate that the EC could be obtained from the Environmental Cell of a local authority, such as the PCMC. The State of Maharashtra opted for the new regime and adopted the environmental condition stipulated in the MoEFCC notification dated 9.12.2016. This was followed by the communication of the MoEFCC on 7.7.2017 which clarified that separate environmental clearance is not required for projects upto 1,50,000 sq. mtrs. built up area in respect of municipal corporations in Pune and Konkan division. Page 4 of 18 **7.** The Project Proponent then filed an application for EC under the 2016 notification which was considered by the Environmental Cell of the PCMC which appraised the project, as contemplated in the notification dated 9.12.2016. The necessary permission for construction to the builder was issued on 28.11.2017, stipulating the environmental conditions for buildings and constructions and this permission was accorded as per the amended regime under the notification dated 9.12.2016 of the MoEFCC and consequential one dated 13.4.2017 of the Maharashtra Government. **8.** While the matter stood thus, the NGT while considering the challenge by certain applicants to the exemption from EC, in a batch matter, quashed certain portions of the MoEFCC notification dated 9.12.2016. The NGT in the analogous judgment dated 8.12.2017 in the OA No. 677/2016 _(Society for Protection of Environment and Biodiversity Vs. Union of India)_ and other cases, directed the MoEFCC to revisit its notification dated 9.12.2016 and to take appropriate steps to amend/rectify Page 5 of 18 certain clauses in the Ministry’s notification, in terms of the NGT’s judgment. **9.** Nearly two years after the Project Proponent secured construction permission on 8.12.2017 from the PCMC, the OA No. 83/2019 was filed by the Pune resident (respondent No. 10) with the allegation that the Project Proponent had made construction without obtaining any EC. In this proceeding the NGT constituted a three Member Committee comprising the SEIAA – Maharashtra, the State PCB and the Municipal Commissioner, Pune. The Committee, after spot verification, in its Report dated 18.8.2020 noted that construction of total built up area of 22930.17 sq. mtrs. is already completed for Building Nos. A,E,B,D and the Club House. Thereafter, the NGT considered the submission of the original applicant, who contended that while the authority to grant EC is SEIAA as per the EIA notification dated 14.9.2006, the EC for the project in question was granted by the PCMC. The NGT in its order on 17.11.2020, in the first round, opined that the constructions were irregular and Page 6 of 18 remedial measures were directed for the project in question. **10.** The above order of the NGT was challenged before this Court and the Project Proponent’s CA No. 3893/2020 was allowed on 11.12.2020 whereby, the NGT’s order was set aside and the matter was remitted back to the NGT to afford hearing to the appellants and to pass a fresh order. **11.** The case of the Project Proponent as can be seen from the pleadings was that he had initially commenced construction on 14.5.2013 with a sanction plan of 15040.05 sq. mtrs., which, being lesser than the threshold limit of 20,000 sq. mtrs, did not require a prior EC. Thereafter, for the proposed expansion of the project, for total constructed area of 49,012 sq. mtrs., the Project Proponent approached the concerned authority on 7.11.2016 for issuance of “ _Proposed Development Certificate_ ”, which is a prerequisite to apply for EC, and the said certificate was granted on 28.11.2016 for the purpose of obtaining the EC from the SEIAA. But at that stage, by virtue of the MoEFCC notification dated Page 7 of 18 9.12.2016, the concerned local authority was designated as the sanctioning authority for projects between 20,000 sq. mtrs. and 50,000 sq. mtrs. and accordingly under the changed regime the Project Proponent applied to PCMC on 10.7.2017 and was sanctioned EC by the competent local authority, on 28.11.2017. **12.** It is the further contention of the Project Proponent that when the NGT on 8.12.2017 had invalidated certain portions of the 2016 notification, it did not issue any order nullifying those ECs which were granted by the local authority under the altered regime. **13.** The original applicant on the other hand, contended that when the NGT struck down certain provisions of the MoEFCC’s 2016 notification, the 28.11.2017 EC granted by the Municipal Corporation, would not legitimize the construction and therefore the Project Proponent should be prevented from proceeding with the construction and also be penalized for the unauthorized construction. **14.** The NGT then observed that because of the invalidation of certain clauses in the 2016 Page 8 of 18 notification, the EC obtained from the PCMC is unacceptable and accordingly rendered a finding that the Project Proponent had failed to obtain the valid EC. The maintainability challenge of the OA on the ground of limitation was however rejected by observing that the cause of action arose only in 2017 when the builder allegedly exceeded the threshold limit of 20,000 sq. mtrs. Accordingly, the authorities were directed to take coercive action against the Project Proponent for construction done after 8.12.2017, when the NGT’s judgment was rendered in the OA No. 677/2016. However, even with such finding having regard to the regime that existed at the relevant time and adverting to the ratio in _Goan Real Estate and Construction Ltd. Vs. Union of India,[1]_ the NGT held that the construction already raised should be protected. However, further construction should be permitted only after securing the EC from the competent authority, under the current regime. **15** . The picture which emerges from the above discussion is that when the Project Proponent initially wanted to > 1 (2010) 5 SCC 388 Page 9 of 18 apply for the EC it had obtained the requisite layout sanction for applying to the SEIAA. As such, it was operating well within the applicable procedure, prior to the amendment. After grant of such sanction, while the construction was underway, the amendment came about on 9.12.2016 whereby, the local authority such as the Municipal Corporation was made the competent authority to grant EC. In the changed circumstances, the Project Proponent necessarily had to apply to the PCMC as during the interregnum before the NGT’s judgment on 8.12.2017, SEIAA was not the competent authority to consider application for EC. The Project Proponent was therefore, complying with the regime set out by the amended notification. It is apposite to note that the Committee appointed by the NGT, in its report dated 11.8.2020 had clearly indicated that when the Project Proponent had received the EC on 28.11.2017, the competent authority to issue the EC was the Environmental Cell of the PCMC. Thus, it is the discernible understanding as part of the NGT’s own expert Committee that the Project Proponent had obtained Page 10 of 18 the EC from the competent authority of the relevant time i.e. the PCMC. Interestingly, the constituted Committee also included a member of the SEIAA. **16.** Moreover, only after the earlier judgment of the NGT on 8.12.2017 in the OA No. 677/2016, the State of Maharashtra issued a clarification on 29.1.2018 directing that the Municipal authorities should not process pending applications. But neither the decision of the NGT nor of the Maharashtra Government categorically gave any guidance as to the implication on the EC obtained by the Project Proponent, on the strength of which, a substantial measure of construction was already made. It is also necessary to note that in the subsequent notification issued on 14.11.2018 and 15.11.2018 by the MoEFCC, the power to grant EC continued to vest in the local authority such as the PCMC, with the only change being that it is the municipality itself and not its Environmental Cell which is empowered to grant the EC. For the sake of completion, it may be recorded that the said Page 11 of 18 notifications of the MoEFCC is stayed by the Delhi High Court on 26.11.2018 in the WP(C) No. 12517/2018. **17.** It is important to bear in mind that the Committee constituted by the NGT to report on the building project did not underscore any major deviation but instead found that the Project Proponent had made substantial compliance by obtaining the EC from the competent local authority. Moreover the OA, neither before the NGT or this Court, ever contended that appraisal done by the PCMC’s Environmental Cell was defective or any different from one done by SEIAA. Both processes are also similarly structured. This may be the reason why the NGT in the impugned judgment itself protected the already made construction. However, the Project Proponent was restrained from making any further construction without obtaining clearance from the statutory EC and adhering to the environmental norms. **18.** The project of the appellant comprises six buildings of which three were constructed in full, and the super structure of the fourth building is completed and only the internal works remains to be done. In the fourth Page 12 of 18 building, 40 out of the 64 apartments have already been sold. In this context, it would be appropriate to advert to the submission of Ms. Aishwarya Bhati, the learned ASG who had clearly stated that at the relevant time, the competent authority to grant EC is the PCMC and not the SEIAA and therefore the internal works for the fourth constructed building, can be allowed to be completed. **19.** Considering the above circumstances, the NGT rightly protected the already erected buildings and this protection in our view, should not be impacted by the earlier judgment of the NGT on 8.12.2017 in the OA No. 677/2016 whereby certain portions of the MoEFCC’s 9.12.2016 notification were invalidated and direction was issued to the Ministry to revisit the said notification. Importantly, neither the NGT’s invalidation order nor the subsequent clarifications by the State of Maharashtra, have suggested any adverse action against the pre-existing structures. As the expert body exclusively occupying the environmental field, the NGT has assessed the factual circumstances to Page 13 of 18 consciously lean towards protecting the already constructed structures. Nothing more need be added on this aspect. It is also not necessary in this appeal to venture into the question of the retrospective implication of the invalidation of certain parts of the 2016 Notification for other project proponents, which may have gained their ECs in the interregnum. **20.** In situations of this nature, the Doctrine of _Legitimate Expectation_ is attracted. The principle of the rule of law as explained in _De Smith’s Judicial Review,_ such as, Regularity, Predictability and Certainty in Government’s dealings with the Public, must operate in the present matter. The Project Proponent can legitimately expect a certain degree of stability in the manner in which environmental regime is set and how the applications are processed. The actions of the authorities are expected to adhere to the prevalent norms only, without the element of uncertainty for the executed project. **21.** In the above context we may benefit by referring to the seminal case of _Attorney General of Hong Kong v. Ng_ Page 14 of 18 _Yuen Shiu[2]_ , where Lord Fraser speaking for the Privy ## Council, appositely observed thus, “… when a public authority has promised to follow a certain procedure, it is in the interest of good administration that it should act fairly and should implement its promise, so long as implementation does not interfere with its statutory duty.” **22.** This Court in _Sethi Auto Service Station vs Delhi Development Authority & Ors[3] ,_ speaking through Justice D.K. Jain, has cited other opinions and elucidated on the concept of _legitimate expectation_ , in the following manner, “24. The House of Lords in Council of Civil Service Unions & Ors. Vs. Minister for the Civil Service, a locus classicus on the subject, wherein for the first time an attempt was made to give a comprehensive definition to the principle of legitimate expectation. **Enunciating the basic principles relating to legitimate expectation, Lord Diplock observed that for a legitimate expectation to arise, the decision of the administrative authority must affect such person either** **==> picture [387 x 27] intentionally omitted <==** (b) **by depriving him of some benefit or advantage which either: (i) he has in the past been permitted by the decision maker to enjoy and which he can legitimately expect to be permitted to continue to do until some rational ground for withdrawing it has been communicated to him and he has been given an opportunity to comment thereon or** (ii) he has received assurance from the decisionmaker that they 2 (1983) 2 AC 629 : (1983) 2 WLR 735 3 (2009) 1 SCC 180 Page 15 of 18 will not be withdrawn without first giving him an opportunity of advancing reasons for contending that they should be withdrawn.” (emphasis supplied) **23.** The Doctrine of _Legitimate Expectation_ is further explained in _Food Corporation of India Vs. M/s Kamdhenu Cattle Feed Industries[4]_ where for a Three-Judge Bench of this Court Justice J.S. Verma observed thus: - "The mere reasonable or legitimate expectation of a citizen, in such a situation, may not by itself be a distinct enforceable right, but failure to consider and give due weight to it may render the decision arbitrary, and this is how the requirement of due consideration of a legitimate expectation forms part of the principle of non-arbitrariness, a necessary concomitant of the rule of law. Every legitimate expectation is a relevant factor requiring due consideration in a fair decision-making process. Whether the expectation of the claimant is reasonable or legitimate in the context is a question of fact in each case. Whenever the question arises, it is to be determined not according to the claimant's perception but in larger public interest wherein other more important considerations may outweigh what would otherwise have been the legitimate expectation of the claimant. A bona fide decision of the public authority reached in this manner would satisfy the requirement of non-arbitrariness and withstand judicial scrutiny. The doctrine of legitimate expectation gets assimilated in the rule of law and operates in our legal system in this manner and to this extent." **24.** The more compelling public interest might possibly diminish the degree of _legitimate expectation_ for a party but a balance has to be found. In the present 4 (1993) 1 SCC 71 Page 16 of 18 matter the appellant has acted on the EC and made substantial investments. They cannot be pushed to a precipice and be made to fall. Doing so would be inequitable particularly when, the appellant has scrupulously adhered to the applicable legal framework during the concerned period. Moreover, third-party interests have also cropped up in the interregnum. **25** . A Project Proponent is not expected to anticipate the changes in EC regimes, especially as a result of judicial interventions, and keep revisiting the sanctioned clearances by the competent authority or even raze down validly constructed structures. Neither can it be expected to knock the doors of an authority, not empowered at the relevant time, to process its applications. Such a scenario would render the process akin to a _Sisyphean task_ , eternally inconclusive and never ending. **26** . As seen, the NGT in the impugned judgment has protected the completed construction and, on this aspect, we deem it appropriate to endorse the same, by Page 17 of 18 accepting the submission of the appellant’s Counsel and the learned ASG. The four constructed buildings are resultantly to be treated to be under a valid EC with all legal consequences. It is, however, made clear that if any further construction is proposed by the appellant with the sanctioned layout, the same should not be done on the strength of the EC granted on 28.11.2017 by the PCMC. In other words, if the Project Proponent wishes to construct the remaining buildings, they must secure fresh clearance from the competent authority, as per the currently applicable framework. It is ordered accordingly. **27.** With the above order, the appeals are disposed of without any order on cost. ………………………………………………………J. [R. SUBHASH REDDY] ….…………………………………………………J. [HRISHIKESH ROY] NEW DELHI NOVEMBER 26, 2021 Page 18 of 18
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.