M/S Sai Baba Sales Pvt. Ltd. v. Union of India

Case / Petition Number:
Civil Appeal Nos. 595 of 2021 and 5768 of 2021
Neutral Citation:[2021] 11 S.C.R.

Case Synopsis & Summary

Two civil appeals challenge the National Green Tribunal's OA No. 83/2019 judgment protecting four constructed buildings while limiting further development pending fresh environmental clearance (EC). The Project Proponent Sai Baba Sales Pvt. Ltd. obtained initial permissions (layout sanction for 15,040 m2) under the pre-2016 regime, and, as construction progressed, sought EC for expansion. With the MoEFCC's 9 December 2016 notification, EC could be granted by the local authority (PCMC) rather than SEIAA, and PCMC granted EC on 28 November 2017. The NGT later questioned the validity of the 2016 notification, resulting in a directive to revisit the regime. The Supreme Court held that, considering the EC obtained from PCMC at the relevant time and the expert committee's findings, the EC stands for the built portion already completed; however, any further construction must obtain fresh clearance under the current framework. The judgment emphasizes legitimate expectation and the need for stability in environmental governance, balancing public interest and the developer's investments. It upheld the protection of completed structures and held that future construction must comply with the current regime. The appeals are disposed of without cost, while clarifying the pathway for future development.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • R. Subhash Reddy
  • Hrishikesh Roy
Judgment Date
2021-11-26
Court Decision / Holding
The Court held that the EC granted by the PCMC in 2017, for the expanded project, was valid for the completed constructions at the relevant time; the NGT's protection of the standing buildings is endorsed; any future construction must obtain fresh clearance under the current regime. The appeals are disposed of without cost.
Final Disposition
Appeals disposed of

Parties to the Case

Appellants / Petitioners

  • M/S Sai Baba Sales Pvt. Ltd.

Respondents

  • Union of India
  • Government of Maharashtra
  • State Pollution Control Board
  • Pimpri-Chinchwad Municipal Corporation

Legal Representation & Advocates

Counsels for Petitioners

  • • Huzefa Ahmadi
  • • Ninad Laud
  • • Saurabh Kulkarni
  • • Ivo. D. D’Costa
  • • Anshula Vijay Kumar Grover
  • • Nitin Lonkar
  • • Sonali Suryawanshi
  • • Shankey Agrawal

Counsels for Respondents

  • • Ms. Aishwarya Bhati
  • • Ms. Archana Pathak Dave
  • • Ms. Ruchi Kohli
  • • Sughosh Subramaniam
  • • Ms. Gurmeet Singh Makker
  • • Mr. Mukesh Verma
  • • Mr. Shashank Singh
  • • Mr. Rahul Chitnis
  • • Mr. Sachin Patil
  • • Mr. Aaditya S. Jadhav
  • • Mr. Geo E Joseph
  • • Mr. Anish R. Shah
  • • Mr. Shivaji M. Jadhav
  • • Ms. Qurratulain
  • • Mr. Brij Kishor Sah
  • • Ms. Damini Hajela
  • • Mr. Aditya S. Jadhav

Provisions of Law Cited

National Green Tribunal Act, 2010 (Section 22)Environment Impact Assessment (EIA) Notification, 2006MoEFCC Notification dated 9 December 2016MoEFCC Notifications dated 14 November 2018 and 15 November 2018

Legal Doctrines & Maxims

  • Doctrine of Legitimate Expectation
  • Rule of Law: Regularity, Predictability and Certainty in Government’s dealings with the Public
  • Sisyphean task (Sisyphean)
  • Judicial Review (as per De Smith)
  • Ng Yuen Shiu principle from Attorney General of Hong Kong v. Ng Yuen Shiu
  • Locus classicus concept from Council of Civil Service Unions v Minister for the Civil Service

Submissions & Arguments

Contentions of Appellants / Petitioners

The Project Proponent argued that the EC granted by PCMC under the 2016 notification was valid and that construction completed in 2017–2020 should be protected from retroactive invalidation, given substantial investments and legitimate expectation. It contended that the regime change in 2016-17 did not automatically invalidate ECs granted under the earlier regime, and that the NGT’s later directions should not undo accrued rights for the completed structures. The appellant relied on the expert committee’s finding that EC was issued by the competent local authority at the relevant time and urged a proportionate balancing of public interest with legitimate expectations.

Contentions of Respondents

The respondents argued that the 2016 MoEFCC notification was undermined by the NGT’s 8.12.2017 decision, and that ECs granted by the local authority under the amended regime cannot validate prior constructions without proper EC under the current regime. They urged strict compliance with environmental norms, urged penal action for any unauthorized construction, and pressed for fresh EC for any future development to ensure uniform application of the current regime and to safeguard the environment and public interest.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Goan Real Estate and Construction Ltd. v. Union of India(2010) 5 SCC 388Mentioned OnlyCited as background authority; not the central holding.
Food Corporation of India v. M/s Kamdhenu Cattle Feed Industries(1993) 1 SCC 71Mentioned OnlyCited to illustrate legitimate expectation and non-arbitrariness in decision-making.
Attorney General of Hong Kong v. Ng Yuen Shiu(1983) 2 AC 629 : (1983) 2 WLR 735Mentioned OnlyCited for the principle that public authorities should act fairly after promising to follow a procedure.
Judicial Review by De Smith—Mentioned OnlyReferential treatise cited in the context of judicial review principles.
Council of Civil Service Unions & Ors. v. Minister for the Civil Service—Mentioned OnlyCited as locus classicus on legitimate expectation.
Sethi Auto Service Station v. Delhi Development Authority & Ors(2009) 1 SCC 180PositiveCited to elucidate the concept of legitimate expectation and its weight in decision-making.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,896 words•~23 min read

In The Court Record

M/S Sai Baba Sales Pvt. Ltd. v. Union of India

284 SUPREME COURT REPORTS[2021] 11 S.C.R. 284 [2021] 11 S.C.R. A ## M/S SAI BABA SALES PVT. LTD. v. ## UNION OF INDIA (Civil Appeal No. 595 of 2021) B NOVEMBER 26, 2021 ## **[R. SUBHASH REDDY AND HRISHIKESH ROY, JJ]** - _Environmental Laws: Environmental clearance (EC) for_ - _building project – On facts, Project Proponent-construction project made substantial compliance by obtaining the EC from the competent_ - C _local authority – Subsequent changes in EC regimes – Effect of – Validity of the grant of EC to Project Proponent, challenged to – NGT held that further construction cannot be made without environment impact assessment, but protected the constructions already made by the appellant-Project Proponent on the basis of_ - D _the EC issued by the Pimpri Chinchwad Municipal Corporation as per the notification – On appeal, held: Project Proponent can legitimately expect a certain degree of stability in the manner in which environmental regime is set and how the applications are processed – Public interest might possibly diminish the degree of legitimate expectation for a party but a balance has to be found –_ - E _Project Proponent is not expected to anticipate the changes in EC regimes, especially as a result of judicial interventions, and keep revisiting the sanctioned clearances by the competent authority or even raze down validly constructed structures – Neither can it be expected to knock the doors of an authority, not empowered at the_ - F _relevant time, to process its applications – On facts, the appellant acted on the EC and made substantial investments – They adhered to the applicable legal framework during the concerned period, as such cannot be pushed to a precipice and be made to fall – Doing so would be inequitable – Moreover, third-party interests have also come up –Thus, the order passed by NGT protecting the completed_ - G _construction is endorsed and four constructed buildings are to be treated to be under a valid EC with all legal consequences – However, for any further construction proposed they must secure fresh clearance as required – Doctrine of legitimate expectation._ H 284 285 M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA ## **Disposing of the appeals, the Court** **HELD: 1.1 When the Project Proponent initially wanted to apply for the EC it had obtained the requisite layout sanction for applying to the SEIAA. As such, it was operating well within the applicable procedure, prior to the amendment. After grant of such sanction, while the construction was underway, the amendment came about on 9.12.2016 whereby, the local authority such as the Municipal Corporation was made the competent authority to grant EC. In the changed circumstances, the Project Proponent necessarily had to apply to the PCMC as during the interregnum before the NGT’s judgment on 8.12.2017, SEIAA was not the competent authority to consider application for EC. The Project Proponent was therefore, complying with the regime set out by the amended notification. It is apposite to note that the Committee appointed by the NGT, in its report dated 11.8.2020 had clearly indicated that when the Project Proponent had received the EC on 28.11.2017, the competent authority to issue the EC was the Environmental Cell of the PCMC. Thus, it is the discernible understanding as part of the NGT’s own expert Committee that the Project Proponent had obtained the EC from the competent authority of the relevant time-the PCMC. [Para 15][292-C-F]** **1.2 Moreover, only after the earlier judgment of the NGT on 8.12.2017 in the OA No. 677/2016, the State of Maharashtra issued a clarification on 29.1.2018 directing that the Municipal authorities should not process pending applications. But neither the decision of the NGT nor of the Maharashtra Government categorically gave any guidance as to the implication on the EC obtained by the Project Proponent, on the strength of which, a substantial measure of construction was already made. It is also necessary to note that in the subsequent notification issued on 14.11.2018 and 15.11.2018 by the MoEFCC, the power to grant EC continued to vest in the local authority such as the PCMC, with the only change being that it is the municipality itself and not its Environmental Cell which is empowered to grant the EC. The said notifications of the MoEFCC is stayed by the Delhi High Court on 26.11.2018 in the WP(C) No. 12517/2018. [Para 16][292G-H; 293-A-B]** A B C D E F G H 286 SUPREME COURT REPORTS [2021] 11 S.C.R. - A **1.3 The Committee constituted by the NGT to report on the building project did not underscore any major deviation but instead found that the Project Proponent had made substantial compliance by obtaining the EC from the competent local authority. Moreover the OA, neither before the NGT or this Court, ever contended that appraisal done by the PCMC’s** - B **Environmental Cell was defective or any different from one done by SEIAA. Both processes are also similarly structured. This may be the reason why the NGT in the impugned judgment itself protected the already made construction. However, the Project Proponent was restrained from making any further construction** - C **without obtaining clearance from the statutory EC and adhering to the environmental norms. [Para 17][293-C-E]** - **1.4 The NGT rightly protected the already erected buildings** - **and this protection in our view, should not be impacted by the earlier judgment of the NGT on 8.12.2017 in the OA No. 677/** - D **2016 whereby certain portions of the MoEFCC’s 9.12.2016 notification were invalidated and direction was issued to the Ministry to revisit the said notification. Importantly, neither the NGT’s invalidation order nor the subsequent clarifications by the State of Maharashtra, have suggested any adverse action against the pre-existing structures. As the expert body exclusively** - E **occupying the environmental field, the NGT has assessed the factual circumstances to consciously lean towards protecting the already constructed structures. Nothing more need be added on this aspect. It is also not necessary in this appeal to venture into the question of the retrospective implication of the invalidation** - F **of certain parts of the 2016 Notification for other project proponents, which may have gained their ECs in the interregnum. [Para 19][293-G-H; 294-A-B]** - **1.5 In situations of this nature, the Doctrine of Legitimate** - **Expectation is attracted. The principle of the rule of law such as,** - G **Regularity, Predictability and Certainty in Government’s dealings with the Public, must operate in the present matter. The Project Proponent can legitimately expect a certain degree of stability in the manner in which environmental regime is set and how the applications are processed. The actions of the authorities are** - H 287 M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA **expected to adhere to the prevalent norms only, without the element of uncertainty for the executed project. The more compelling public interest might possibly diminish the degree of legitimate expectation for a party but a balance has to be found. In the instant matter, appellant has acted on the EC and made substantial investments. They cannot be pushed to a precipice and be made to fall. Doing so would be inequitable particularly when, the appellant has scrupulously adhered to the applicable legal framework during the concerned period. Moreover, thirdparty interests have also cropped up in the interregnum. [Para 20, 24][294-B-D; 295-G-H; 296-A-B]** **1.6 A Project Proponent is not expected to anticipate the changes in EC regimes, especially as a result of judicial interventions, and keep revisiting the sanctioned clearances by the competent authority or even raze down validly constructed structures. Neither can it be expected to knock the doors of an authority, not empowered at the relevant time, to process its applications. Such a scenario would render the process akin to a Sisyphean task, eternally inconclusive and never ending. [Para 25][296-B-C]** **1.7 As seen, the NGT in the impugned judgment has protected the completed construction and, on this aspect, it is deemed appropriate to endorse the same. The four constructed buildings are resultantly to be treated to be under a valid EC with all legal consequences. It is, however, made clear that if any further construction is proposed by the appellant with the sanctioned layout, the same should not be done on the strength of the EC granted on 28.11.2017 by the PCMC. In other words, if the Project Proponent wishes to construct the remaining buildings, they must secure fresh clearance from the competent authority, as per the currently applicable framework. [Para 26][296-D-E]** _Goan Real Estate and Construction Ltd. v. Union of India_ **(2010) 5 SCC 388;** _Food Corporation of India v. M/s Kamdhenu Cattle Feed Industries_ **(1993) 1 SCC 71 – referred to.** A B C D E F G H 288 SUPREME COURT REPORTS [2021] 11 S.C.R. A _Attorney General of Hong Kong v. NgYuen Shiu_ **(1983) 2 AC 629 : (1983) 2 WLR 735 – referred to.** _Judicial Review_ **by De Smith – referred to.** ## **Case Law Reference** |B|**(2010) 5 SCC 388**|**referred to**|**Para 14**| |---|---|---|---| ||**(1993) 1 SCC 71**|**referred to**|**Para 22**| ||CIVIL APPELLATE|JURISDICTION: Civil Appeal No. 595 of|| ||2021.||| From the Judgment and Order dated 18.01.2021 of the National C Green Tribunal, Principal Bench, New Delhi in OA No. 83/2019(WZ). With Civil Appeal No. 5768 of 2021 Huzefa Ahmadi, Sr. Adv., Ninad Laud, Saurabh Kulkarni, Ivo. D D’Costa, Ms. Anshula Vijay Kumar Grover, Nitin Lonkar, Mrs. Sonali Suryawanshi, Shankey Agrawal, Advs. for the Appellant. Ms. Aishwarya Bhati, ASG, Ms. Archana Pathak Dave, Ms. Ruchi Kohli, Sughosh Subramaniam, Gurmeet Singh Makker, Mukesh Verma, Shashank Singh, Rahul Chitnis, Sachin Patil, Aaditya A. Pande, Geo E Joseph, Anish R. Shah, Shivaji M. Jadhav, Ms. Qurratulain, Brij Kishor Sah, Ms. Damini Hajela, Aditya S. Jadhav, Nitin Lonkar, Mrs. Sonali Suryawanshi, Shankey Agarwal, Advs. for the respondents. The Judgment of the Court was delivered by ## F ## **HRISHIKESH ROY, J.** 1. Heard Mr. Huzefa Ahmadi, learned senior counsel appearing for the appellant in Civil Appeal No. 595/2021. Mr. Lonkar Nitin representing the Original Applicant before the National Green Tribunal. Ms. Aishwarya Bhati, learned Additional Solicitor General of India appears for the Ministry of Environment & Forest. The Government of G Maharashtra and the State Pollution Control Board are represented by Mr. Rahul Chitnis and Mr. Mukesh Verma, learned counsel respectively. 2. These two appeals are filed under Section 22 of the National Green Tribunal Act, 2010 (for short “the NGT Act”) assailing the judgment and final order dated 18.1.2021 in the OA No. 83/2019. Under the H 289 M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA [HRISHIKESH ROY, J.] impugned judgment, the NGT held that further constructioncannot be A made withoutenvironment impact assessment, but protected the constructions already made by the appellant, M/s Sai Baba Sales Pvt. Ltd. (“Project Proponent”) on the basis of the Environmental Clearance (“EC” for short) issued by the Pimpri Chinchwad Municipal Corporation (“PCMC” for short) as per the notification dated 9.12.2016. The Original B Applicant, on the other hand, is aggrieved by the decision of the NGT to protect the standing construction and limiting the impact of the impugned judgment on further construction to be made by the project proponent. 3. The main issue that arises for consideration in these matters is whether the Project Proponent herein possesses a validly granted Environmental Clearance (EC) under the Environmental Impact Assessment (EIA) notification dated 14.9.2006. The 2006 EIA notification provided that the projects above 20,000 sq. meter and below 1,50,000 sq. meter should obtain an EC from the State Environment Impact Assessment Authority (SEIAA) of the Ministry of Environment, Forest and Climate Change (MoEFCC). 4. For deciding the issue, the necessary facts in brief are that the Project Proponent initially conceived a project of 15,040 sq. mtrs. (below the EC threshold limit of 20,000 sq. mtrs.) and it approached the PCMC for a lay out order which was a prerequisite, to obtain an EC from the SEIAA of the MoEFCC. The application was processed and the Building Permission Department of the PCMC granted the commencement certificate to the Project Proponent for an area of 15,040 sq. mtrs. and approved the plan under the sanction letter dated 14.5.2013. With such permission, the Project Proponent could construct the permitted structures, and since the built up area was less than the threshold limit of 20000 sq. mtrs., the EC permission was not needed for the intended construction. 5. The Project Proponent builder then applied and was granted additional FSI as it intended to expand the project to one with built up area of 49,012 sq. mtrs. and for this they approached the PCMC for a lay out order, which as noted earlier was essential to obtain an EC from the SEIAA of the Ministry of Environment, Forest and Climate Change (MoEFCC). The required approval was issued by the Corporation on 28.11.2016. C D E F G 6. Under the Ministry’s notification dated 9.12.2016, the EIA regime was altered to indicate that the EC could be obtained from the H 290 SUPREME COURT REPORTS [2021] 11 S.C.R. - A Environmental Cell of a local authority, such as the PCMC. The State of Maharashtra opted for the new regime and adopted the environmental condition stipulated in the MoEFCC notification dated 9.12.2016. This was followed by the communication of the MoEFCC on 7.7.2017 which clarified that separate environmental clearance is not required for projects upto 1,50,000 sq. mtrs. built up area in respect of municipal corporations - B in Pune and Konkan division. 7. The Project Proponent then filed an application for EC under the 2016 notification which was considered by the Environmental Cell of the PCMC which appraised the project, as contemplated in the notification dated 9.12.2016. The necessary permission for construction C to the builder was issued on 28.11.2017, stipulating the environmental conditions for buildings and constructions and this permission was accorded as per the amended regime under the notification dated 9.12.2016 of the MoEFCC and consequential one dated 13.4.2017 of the Maharashtra Government. - D 8. While the matter stood thus, the NGT while considering the challenge by certain applicants to the exemption from EC, in a batch matter, quashed certain portions of the MoEFCC notification dated 9.12.2016. The NGT in the analogous judgment dated 8.12.2017 in the OA No. 677/2016 _(Society for Protection of Environment and_ E _Biodiversity Vs. Union of India)_ and other cases, directed the MoEFCC to revisit its notification dated 9.12.2016 and to take appropriate steps to amend/rectify certain clauses in the Ministry’s notification, in terms of the NGT’s judgment. 9. Nearly two years after the Project Proponent secured F construction permission on 8.12.2017 from the PCMC, the OA No. 83/2019 was filed by the Pune resident (respondent No. 10) with the allegation that the Project Proponent had made construction without obtaining any EC. In this proceeding the NGT constituted a three Member Committee comprising the SEIAA – Maharashtra, the State PCB and the Municipal Commissioner, Pune. The Committee, after spot verification, G in its Report dated 18.8.2020 noted that construction of total built up area of 22930.17 sq. mtrs. is already completed for Building Nos. A, E, B, D and the Club House. Thereafter, the NGT considered the submission of the original applicant, who contended that while the authority to grant EC is SEIAA as per the EIA notification dated 14.9.2006, the EC for the H project in question was granted by the PCMC. The NGT in its order on 291 M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA [HRISHIKESH ROY, J.] 17.11.2020, in the first round, opined that the constructions were irregular A and remedial measures were directed for the project in question. 10. The above order of the NGT was challenged before this Court and the Project Proponent’s CA No. 3893/2020 was allowed on 11.12.2020 whereby, the NGT’s order was set aside and the matter was remitted back to the NGT to afford hearing to the appellants and to pass a fresh order. 11. The case of the Project Proponent as can be seen from the pleadings was that he had initially commenced construction on 14.5.2013 with a sanction plan of 15040.05 sq. mtrs., which, being lesser than the threshold limit of 20,000 sq. mtrs, did not require a prior EC. Thereafter, for the proposed expansion of the project, for total constructed area of 49,012 sq. mtrs., the Project Proponent approached the concerned authority on 7.11.2016 for issuance of “ _Proposed Development Certificate_ ”, which is a prerequisite to apply for EC, and the said certificate was granted on 28.11.2016 for the purpose of obtaining the EC from the SEIAA. But at that stage, by virtue of the MoEFCC notification dated 9.12.2016, the concerned local authority was designated as the sanctioning authority for projects between 20,000 sq. mtrs. and 50,000 sq. mtrs. and accordingly under the changed regime the Project Proponent applied to PCMC on 10.7.2017 and was sanctioned EC by the competent local authority, on 28.11.2017. B C D E 12. It is the further contention of the Project Proponent that when the NGT on 8.12.2017 had invalidated certain portions of the 2016 notification, it did not issue any order nullifying those ECs which were granted by the local authority under the altered regime. 13. The original applicant on the other hand, contended that when the NGT struck down certain provisions of the MoEFCC’s 2016 notification, the 28.11.2017 EC granted by the Municipal Corporation, would not legitimize the construction and therefore the Project Proponent should be prevented from proceeding with the construction and also be penalized for the unauthorized construction. 14. The NGT then observed that because of the invalidation of certain clauses in the 2016 notification, the EC obtained from the PCMC is unacceptable and accordingly rendered a finding that the Project Proponent had failed to obtain the valid EC. The maintainability challenge of the OA on the ground of limitation was however rejected by observing F G H 292 SUPREME COURT REPORTS [2021] 11 S.C.R. - A that the cause of action arose only in 2017 when the builder allegedly exceeded the threshold limit of 20,000 sq. mtrs. Accordingly, the authorities were directed to take coercive action against the Project Proponent for construction done after 8.12.2017, when the NGT’s judgment was rendered in the OA No. 677/2016. However, even with such finding having regard to the regime that existed at the relevant time and adverting - B to the ratio in _Goan Real Estate and Construction Ltd. Vs. Union of India,_[1] the NGT held that the construction already raised should be protected. However, further construction should be permitted only after securing the EC from the competent authority, under the current regime. 15. The picture which emerges from the above discussion is that C when the Project Proponent initially wanted to apply for the EC it had obtained the requisite layout sanction for applying to the SEIAA. As such, it was operating well within the applicable procedure, prior to the amendment. After grant of such sanction, while theconstruction was underway, the amendment came about on 9.12.2016 whereby, the local - D authority such as the Municipal Corporation was made the competent authority to grant EC. In the changed circumstances, the Project Proponent necessarily had to apply to the PCMC as during the interregnum before the NGT’s judgment on 8.12.2017, SEIAA was not the competent authority to consider application for EC. The Project Proponent was therefore, complying with the regime set out by the - E amended notification. It is apposite to note that the Committee appointed by the NGT, in its report dated 11.8.2020 had clearly indicated that when the Project Proponent had received the EC on 28.11.2017, the competent authority to issue the EC was the Environmental Cell of the PCMC. Thus, it is the discernible understanding as part of the NGT’s own expert - F Committee that the Project Proponent had obtained the EC from the competent authority of the relevant time i.e. the PCMC. Interestingly, the constituted Committee also included a member of the SEIAA. 16. Moreover, only after the earlier judgment of the NGT on 8.12.2017 in the OA No. 677/2016, the State of Maharashtra issued a G clarification on 29.1.2018 directing that the Municipal authorities should not process pending applications. But neither the decision of the NGT nor of the Maharashtra Government categorically gave any guidance as to the implication on the EC obtained by the Project Proponent, on the strength of which, a substantial measure of construction was already - 1 (2010) 5 SCC 388 - H 293 M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA [HRISHIKESH ROY, J.] made. It is also necessary to note that in the subsequent notification A issued on 14.11.2018 and 15.11.2018 by the MoEFCC, the power to grant EC continued to vest in the local authority such as the PCMC, with the only change being that it is the municipality itself and not its Environmental Cell which is empowered to grant the EC. For the sake of completion, it may be recorded that the said notifications of the B MoEFCC is stayed by the Delhi High Court on 26.11.2018 in the WP(C) No. 12517/2018. 17. It is important to bear in mind that the Committee constituted by the NGT to report on the building project did not underscore any major deviation but instead found that the Project Proponent had made substantial compliance by obtaining the EC from the competent local authority. Moreover the OA, neither before the NGT or this Court, ever contended that appraisal done by the PCMC’s Environmental Cell was defective or any different from one done by SEIAA. Both processes are also similarly structured. This may be the reason why the NGT in the impugned judgment itself protected the already made construction. However, the Project Proponent was restrained from making any further construction without obtaining clearance from the statutory EC and adhering to the environmental norms. 18. The project of the appellant comprises six buildings of which three were constructed in full, and the super structure of the fourth building is completed and only the internal works remains to be done. In the fourth building, 40 out of the 64 apartments have already been sold. In this context, it would be appropriate to advert to the submission of Ms. Aishwarya Bhati, the learned ASG who had clearly stated that at the relevant time, the competent authority to grant EC is the PCMC and not the SEIAA and therefore the internal works for the fourth constructed building, can be allowed to be completed. 19. Considering the above circumstances, the NGT rightly protected the already erected buildings and this protection in our view, should not be impacted by the earlier judgment of the NGT on 8.12.2017 in the OA No. 677/2016 whereby certain portions of the MoEFCC’s 9.12.2016 notification were invalidated and direction was issued to the Ministry to revisit the said notification. Importantly, neither the NGT’s invalidation order nor the subsequent clarifications by the State of Maharashtra, have suggested any adverse action against the pre-existing structures. As the expert body exclusively occupying the environmental C D E F G H 294 SUPREME COURT REPORTS [2021] 11 S.C.R. - A field, the NGT has assessed the factual circumstances to consciously lean towards protecting the already constructed structures. Nothing more need be added on this aspect. It is also not necessary in this appeal to venture into the question of the retrospective implication of the invalidation of certain parts of the 2016 Notification for other project proponents, which may have gained their ECs in the interregnum. B 20. In situations of this nature, the Doctrine of _Legitimate Expectation_ is attracted. The principle of the rule of law as explained in _De Smith’s Judicial Review,_ such as, Regularity, Predictability and Certainty in Government’s dealings with the Public, must operate in the present matter. The Project Proponent can legitimately expect a certain C degree of stability in the manner in which environmental regime is set and how the applications are processed. The actions of the authorities are expected to adhere to the prevalent norms only, without the element of uncertainty for the executed project. 21. In the above context we may benefit by referring to the seminal D case of _Attorney General of Hong Kong v. Ng Yuen Shiu_[2] , where Lord Fraser speaking for the Privy Council, appositely observed thus, “… when a public authority has promised to follow a certain procedure, it is in the interest of good administration that it should act fairly and should implement its promise, so long as E implementation does not interfere with its statutory duty.” 22. This Court in _Sethi Auto Service Station vs Delhi Development Authority & Ors_[3] _,_ speaking through Justice D.K. Jain, has cited other opinions and elucidated on the concept of _legitimate expectation_ , in the following manner, F “24. The House of Lords in Council of Civil Service Unions & Ors. Vs. Minister for the Civil Service, a locus classicus on the subject, wherein for the first time an attempt was made to give a comprehensive definition to the principle of legitimate expectation. **Enunciating the basic principles relating to legitimate** G **expectation, Lord Diplock observed that for a legitimate expectation to arise, the decision of the administrative authority must affect such person either** 2 (1983) 2 AC 629 : (1983) 2 WLR 735 H 3 (2009) 1 SCC 180 M/S SAI BABA SALES PVT. LTD. v. UNION OF INDIA 295 [HRISHIKESH ROY, J.] (a) **** **** **** **** **** A (b) **by depriving him of some benefit or advantage which either: (i) he has in the past been permitted by the decision maker to enjoy and which he can legitimately expect to be permitted to continue to do until some rational ground for withdrawing it has been communicated to him and he has been given an opportunity to comment thereon or** (ii) he has received assurance from the decisionmaker that they will not be withdrawn without first giving him an opportunity of advancing reasons for contending that they should be withdrawn.” (emphasis supplied) B C 23. The Doctrine of _Legitimate Expectation_ is further explained in _Food Corporation of India Vs. M/s Kamdhenu Cattle Feed Industries_[4] where for a Three-Judge Bench of this Court Justice J.S. Verma observed thus: - “The mere reasonable or legitimate expectation of a citizen, in such a situation, may not by itself be a distinct enforceable right, but failure to consider and give due weight to it may render the decision arbitrary, and this is how the requirement of due consideration of a legitimate expectation forms part of the principle of non-arbitrariness, a necessary concomitant of the rule of law. Every legitimate expectation is a relevant factor requiring due consideration in a fair decision-making process. Whether the expectation of the claimant is reasonable or legitimate in the context is a question of fact in each case. Whenever the question arises, it is to be determined not according to the claimant’s perception but in larger public interest wherein other more important considerations may outweigh what would otherwise have been the legitimate expectation of the claimant. A bona fide decision of the public authority reached in this manner would satisfy the requirement of non-arbitrariness and withstand judicial scrutiny. The doctrine of legitimate expectation gets assimilated in the rule of law and operates in our legal system in this manner and to this extent.” D E F G 24. The more compelling public interest might possibly diminish the degree of _legitimate expectation_ for a party but a balance has to be 4 (1993) 1 SCC 71 H 296 SUPREME COURT REPORTS [2021] 11 S.C.R. - A found. In the present matter the appellant has acted on the EC and made substantial investments. They cannot be pushed to a precipice and be made to fall. Doing so would be inequitable particularly when, the appellant has scrupulously adhered to the applicable legal framework during the concerned period. Moreover, third-party interests have also cropped up in the interregnum. - B 25. A Project Proponent is not expected to anticipate the changes in EC regimes, especially as a result of judicial interventions, and keep revisiting the sanctioned clearances by the competent authority or even raze down validly constructed structures. Neither can it be expected to knock the doors of an authority, not empowered at the relevant time, to C process its applications. Such a scenario would render the process akin to a _Sisyphean task_ , eternally inconclusive and never ending. 26. As seen, the NGT in the impugned judgment has protected the completed construction and, on this aspect, we deem it appropriate to endorse the same, by accepting the submission of the appellant’s D Counsel and the learned ASG. The four constructed buildings are resultantly to be treated to be under a valid EC with all legal consequences. It is, however, made clear that if any further construction is proposed by the appellant with the sanctioned layout, the same should not be done on the strength of the EC granted on 28.11.2017 by the PCMC. In other E words, if the Project Proponent wishes to construct the remaining buildings, they must secure fresh clearance from the competent authority, as per the currently applicable framework. It is ordered accordingly. 27. With the above order, the appeals are disposed of without any order on cost. F Nidhi Jain Appeals disposed of. G H
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.