M/S Rubek Balloons Pvt. Ltd. v. P.K. Ramachandran and Justice K. John Mathew
Case Synopsis & Summary
This is an Arbitration Request (AR No. 37 of 2007) filed in the Kerala High Court by M/S Rubek Balloons Pvt. Ltd., seeking appointment of an independent and impartial arbitrator under section 11(5) read with the arbitration clause (Annexure A1/A2) to adjudicate disputes arising from civil works for constructing the petitioner’s factory building. The petitioner contends that disputes arose after the respondent contractor rendered defective work and demanded dues; it challenges the appointment of Justice K. John Mathew as the sole arbitrator, arguing that the arbitration clause requires a panel of three names (Annexure A9) and that the employer was obligated to forward a panel within 30 days of notice, failing which the appointment must be from the panel. The applicant produced multiple Annexures (A3–A8, A9–A11) detailing notices, counterclaims, and discussions toward settlement, including a 20.07.07 meeting and 10.08.07 forwarding of a three-name panel. The respondent defended the appointment of K. John Mathew as consistent with the agreement, asserting the clause permits selection from a submitted panel after due process, and invoked 11(5) (and later 11(6) after amendment). The learned Judge, while upholding arbitration’s validity, ultimately appointed another retired judge (Smt. K.K. Usha) to avoid prejudice, and held the Arbitration Request “stands allowed,” directing reference and an early award, without addressing merits. The decision emphasizes expediency and the parties’ arbitration agreement, while not deciding the underlying contentions on their merits.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- Pius C. KuriaKose
- Judgment Date
- 2007-11-23
- Court Decision / Holding
- The Arbitration Request is allowed. The Court recognizes a valid arbitration agreement and appoints another retired judge of the Kerala High Court, Hon’ble Justice Smt. K.K. Usha (retired Chief Justice of this Court), as arbitrator for settlement of all disputes, directing her to enter on reference and pass an award at the earliest. The court clarifies that its judgment does not decide the merits of the contentions or the legality/correctness of the initial appointment of Justice K. John Mathew, but serves as a governing precedent in similar situations. No costs are awarded.
- Final Disposition
- Arbitration Request allowed; appointment of an arbitrator (Smt. K.K. Usha) appointed for settlement; no costs.
Parties to the Case
Appellants / Petitioners
- M/S Rubek Balloons Pvt. Ltd., represented by its Managing Director, K. Thulasidharan Nair
Respondents
- P.K. Ramachandran, Engineering Contractor, Deepa Mandir, Karuvelippadi, Cochin-682 005
- Mr. Justice K. John Mathew, Former Judge, Kattapurath, Veekshanam Road, Ernakulam North, Cochin-682 018
Legal Representation & Advocates
Counsels for Petitioners
- • Sri P.V. Madhavan Nambiar
- • Sri M.A. Khadirkunju
Counsels for Respondents
- • Sri K.L. Varghese
- • Smt. SANTHA VARGHESE
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioner contends that significant disputes arose from the contract for construction of the factory building. Arbitration is invoked under Annexure A2/A1 clauses. The key grievance is that the appointment of Justice K. John Mathew as arbitrator deviates from the procedure: the agreement requires a panel of three names (Annexure A9) and selection should occur within 30 days of notice. The petitioner argues that Annexure A10 and related letters show non-compliance with the arbitration mechanism, amounting to an improper appointment. They contend that Section 11(5) vested in the Chief Justice or designated authority should be used to appoint a sole arbitrator from the panel, and that the respondent’s attempt to appoint a different arbitrator violates the agreement. They pr ovide Annexures A8–A11 to show attempts at amicable settlement (A7–A8) and the panel submission (A9) and the supposed disregard (A10). The court is urged to stay proceedings pending decision on the arbitration request and to appoint an arbitrator from the agreed panel.
Contentions of Respondents
The respondents submit that a valid arbitration agreement exists and the clause (Clause 43 of Annexure A2) requires the employer to forward a panel of three names within 30 days so the contractor can choose one as sole arbitrator and communicate it within another 30 days. They argue that after disputes arose, notices Ext.R1(a) and Ext.R1(b) were sent; because there was no response, the employer appointed Justice K. John Mathew under para 4 of the arbitration clause, a retired judge of the court. They claim the appointment was in consonance with the agreement and that the arbitrator has already entered on reference (Annexure R1(c)). After amendments (11(6)), the petitioner invoked Section 11(6). They contend the court should not interfere and that the appointment should stand to avoid delay, and that the arbitration should proceed with the invoked arbitrator or with a new one if necessary.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Datar Switchgears Ltd. v. Tata Finance Ltd. | (2000) 8 SCC 151 | Mentioned Only | Cited by counsel as supportive authority; the judgment itself does not explicitly adopt or distinguish this precedent in its ultimate ruling. |
| You One Engg. & Construction Co. Ltd v. National Highways Authority of India | (2006) 4 SCC 372 | Mentioned Only | Cited during argument to challenge invocation conditions under 11(6); the judgment does not adopt or distinguish this precedent in delivering its order. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/S Rubek Balloons Pvt. Ltd. v. P.K. Ramachandran and Justice K. John Mathew
Related Decisions & Precedents from High Court of Kerala (2007)
Godavari Leasing and Finance Ltd. v. M. M. Baby
This is a Civil Revision Petition (CRP 606 of 2005) before the High Court of Kerala, challenging the order of a Sub Court at Thodupuzha in O.S. No. 52 of 2003. The case arises from a hire-purchase agreement under which Godavari Leasing and Finance Ltd. financed a car used as a taxi by M. M. Baby. After disputes over charges and alleged forcible repossession, the plaintiff filed for settlement of accounts, declaration and injunction. The main issue is the forum for dispute resolution: whether Calcutta should have exclusive jurisdiction under Clause 22 of the hire-purchase agreement, or whether Thodupuzha (or Ernakulam) has jurisdiction. The trial court held that Calcutta had exclusive jurisdiction. The appellate court reversed, holding that the agreement did not establish Calcutta as the exclusive forum since it was not executed there nor were payments or actions tied to Calcutta; evidence suggested the vehicle was seized at Thodupuzha, the contract was executed at Thodupuzha, and the stamping and receipts were from Ernakulam and Kochi. The court discussed Economic Transport Organisation v. United India Insurance Co. (1986 KLT 220) to analyse ouster clauses and stressed that exclusive jurisdiction clauses must be clear and mutually accepted. The present order clarifies that the findings relate only to jurisdiction and preserves the right to seek transfer to another forum; the revision petition is disposed of accordingly. The judge also notes that the appellate and revision judgments should not preclude seeking transfer to Ernakulam, if desired.
Palakkad Plantation and General Workers Union (H.M.S.) v Nelliyampathy Tea Produce Company Limited
The High Court of Kerala at Ernakulam, in a writ petition (WP(C) 14475/2004), upheld an Industrial Tribunal Palakkad award (ID No.56/2001 dated 27.10.2003) dismissing two workers for theft following a domestic enquiry. The core issue was whether the dismissal was justifiable after a preliminary finding that the enquiry was conducted validly and with adequate evidence. The Tribunal had found the charges proven and the punishment proportionate, and the Union challenged the award on three grounds: (i) non-payment of subsistence allowance during the enquiry, (ii) non-disclosure of certain documents to the workers, and (iii) reliance on statements made by the workers to the police, which the Union argued should be inadmissible. The management contended that the workers were temporary employees who were not suspended, documents were supplied in advance and allowed for perusal, and that domestic enquiries are not bound by the Rules of Evidence Act; it also invoked a Supreme Court decision (Kuldip Singh v. State of Punjab) to justify reliance on police statements. The High Court accepted the Tribunal’s reasoning on subsistence allowance and document disclosure, held that non-supply did not prejudice the workers, and ruled that statements to the police are admissible in domestic enquiries. Consequently, the writ petition was dismissed and the award upheld.
PepsiCo India Holdings Pvt. Ltd. v. State of Kerala & Others
The Kerala High Court heard WP(C).No.3115 of 2007, challenging the Deputy Commissioner (General)’s Ext.P24 denial of sales tax exemption under SRO 1729/93 as amended by SRO 1092/99 and SRO 295/2000. PepsiCo had planned a soft drink plant at Kanjikode, Palakkad, and claimed eligibility for exemptions under a state tax incentive scheme intended to attract investments. The scheme provides a two-tier process: eligibility is certified by the Director of Industries (and KSIDC/KFC where applicable), and the exemption order is issued by the Deputy Commissioner of Commercial Taxes. The amendments restricted exemptions to units that commenced production before 1.1.2000 or had taken “effective steps” prior to that date. PepsiCo argued that the Director’s Ext.R1(a) eligibility certificate fixed its entitlement and that Ext.P24, which rejected exemption after eligibility, was ultra vires as it re-examined eligibility. The court reviewed Ext.P2 and Ext.P3 (earlier Kerala judgments) and concluded that the Deputy Commissioner has the power to determine exemption in light of the eligibility certificate, and that the Director’s certificate does not automatically confer exemption. It held that PepsiCo’s manufacturing activities were within the notification’s scope and upheld Ext.P24, but with a finding that the unit’s activities constituted manufacturing. The writ petition was dismissed, with Ext.P24 sustained subject to the court’s finding on manufacturing. The decision clarifies jurisdictional roles among Director, KSIDC/KFC and the Deputy Commissioner under the SRO regime.
Kurungottil Ebrayi and others v. Palathil Moidu and others
This is a Civil Revision Petition (CRP No. 677/1994) from the Kerala High Court, heard by Justice Pius C. Kurianose, arising under Section 87(7) of the Land Reforms Act. The petitioners, who are assessees under ceiling laws, challenge an order of the Taluk Land Board (TLB) dated 28.07.1992 directing them to surrender 4.27 acres of land because the same extent of land could not be located as originally noted, and to surrender an equivalent area from their other lands due to alleged misclassification and survey errors (R.S.Nos.59/2 misrecorded as 59/3C; 32/2 misrecorded as 34/5.6). Respondents include two claimants who asserted independent rights and sought relief under Section 85(8), which the TLB allowed, prompting the petition. The court notes that while Mathew Mathai v. State of Kerala suggested a favorable view toward reopening under Section 85(8), Ayyappan Pillai v. Taluk Land Board clarifies that decisions under the original order that affect claims under Section 85(8 must be set aside. The judge ultimately finds fault with the TLB’s handling, sets aside the impugned order, and directs a fresh determination of liability with opportunity for the petitioners to file an option statement if needed. The decision emphasizes correct survey references, re-evaluation of liability, and the need to consider new rights created by respondents before finalizing surrender obligations.