Supreme Court of IndiaSupreme Court · 2024Division BenchAppeals partly allowed.

M/s Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.

Case / Petition Number:
Civil Appeal No. 8985 of 2013
Neutral Citation:[2024] 7 S.C.R. 1129

Case Synopsis & Summary

This Supreme Court judgment addresses whether a Build-Operate-Transfer (BOT) concession agreement, under which tolls are collected in exchange for the lessee constructing roads and bridges, is a lease or a license, and the applicable stamp duty provisions. Following amendments in Madhya Pradesh, proviso (c) to Clause (C) of Entry 33 in Schedule 1-A of the Indian Stamp Act (as amended by MP Act 12 of 2002) prescribed a 2% stamp duty on the amount likely to be spent by the lessee under a concession agreement; previously, the state had clarified that such BOT agreements would incur no stamp duty and would be executed on Rs.100 stamp paper. The Madhya Pradesh High Court held that the BOT concession was a lease under Section 105 of the Transfer of Property Act, 1882 and Section 2(16) of the Indian Stamp Act, 1899, and upheld the 2002 amendment. The appellant contended that prior executive assurances created legitimate expectations and that promissory estoppel barred such legislative action; the High Court dismissed these arguments. The Supreme Court upheld the lease finding and the validity of the 2002 proviso, holding that legitimate expectation and promissory estoppel do not bar legislative amendments made in larger public interest. The Court directed recalculation of stamp duty on the amount spent by the lessee and partial relief by refund or additional payment as applicable, while partly allowing the appeals with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Vikram Nath
  • Ahsanuddin Amanullah
Judgment Date
2024-07-19
Court Decision / Holding
Appeals partly allowed. Stamp duty is payable at 2% on the amount spent by the lessee under BOT concessions. The Collector (Stamps) is to recalculate the demand; if excess has been paid, refunds to be issued; if there is a deficit, to be paid within two months. No costs.
Final Disposition
Appeals partly allowed.

Parties to the Case

Appellants / Petitioners

  • M/s Rewa Tollway P. Ltd.

Respondents

  • The State of Madhya Pradesh
  • Madhya Pradesh Rajya Setu Nirman Nigam Ltd. (MPRSNN)
  • Others (as defined in the Civil Appeals)

Legal Representation & Advocates

Counsels for Petitioners

  • • Prafulla Kumar Behera
  • • S. S. Nehra
  • • Vikrant Nehra
  • • Ms. Sundari Rawat
  • • Kunal Verma
  • • Mrs. Yugandhara Pawar Jha
  • • Ms. Lavanya Dhawan
  • • Shivraj Pawar
  • • Ritik Gupta
  • • Sanjay Kapur
  • • Arjun Bhatia
  • • B. K. Satija

Counsels for Respondents

  • • Saurabh Mishra
  • • A.A.G.
  • • Sunny Choudhary
  • • Ms. Aarushi Singh
  • • Ashiesh Kumar

Provisions of Law Cited

Transfer of Property Act, 1882 – Section 105 (lease)Indian Stamp Act, 1899 – Section 2(16) (definition of lease)Indian Stamp (M.P.) Act, 2002 – proviso (c) to Clause (C) of Entry 33 of Schedule 1-A (stamp duty rate)Entry-22 of Schedule 1-A (stamp duty on conveyances)Indian Stamp Act, 1899 – Section 48 and 48-B (deficit stamp duty)Indian Toll (MP) Amendment Act, 1972 (amendments relevant to BOT tolls)General Clauses Act, 1897 – Section 3(26) (definition of immovable property)MP Amendment Act 2002 (Schedule 1-A Entry 33)Constitutional references to Article 14 (ultra vires challenges)Constitutional provisions on legislative competence

Legal Doctrines & Maxims

  • Legitimate expectation
  • Promissory estoppel
  • No estoppel against the legislature / no enforceable right against legislative action
  • Doctrine that a prior executive decision may be withdrawn in the larger public interest
  • Judicial restraint in reviewing executive policy changes unless arbitrary or in public interest

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that prior executive clarifications (01.07.2002 and 21.07.2002) and subsequent 2002 amendment indicated that BOT concession agreements in Madhya Pradesh would not bear 2% stamp duty and would be executed on Rs.100 stamp paper. They maintained that legitimate expectations and promissory estoppel barred the state from levying 2% stamp duty. They contended that the Concession Agreement was not a lease but at best a license, and that the project’s 50% cost attributed to the lessee meant stamp duty could not be levied on the entire project cost. They also argued that the 2002 amendment was ultra vires, and that the 2008 revision reversed the 2002 policy (thus invalidating the levy).

Contentions of Respondents

The respondents contended that the Concession Agreement satisfies the definition of lease under Section 105 TP Act and Section 2(16) IS Act, and that stamp duty at 2% on the amount spent by the lessee is correctly determined by proviso (c) to Clause (C) of Entry 33, Schedule 1-A of the IS Act as amended by MP Act 12 of 2002. They argued the legislature has competence to alter policy in the public interest, and that promissory estoppel/legitimate expectation cannot override statute or legislative action. They relied on decisions like Associated Hotels, Navjyoti, Nasiruddin, Uttarakhand, and Hero Motocorp to support the broad interpretation of lease, and the principle that legislative power prevails over executive representations.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (14)

Case NameCitationTreatmentExplanation
State of Uttarakhand and Ors. v. Harpal Singh Rawat(2011) 4 SCC 575Mentioned OnlyCited as part of the case law landscape but not centrally relied upon to reject or accept the primary issues.
Nasiruddin and another v. State of Uttar Pradesh Thr. Secretary and Ors.[2017] 12 SCR 1073 : (2018) 1 SCC 754PositiveCited for the expanded understanding of lease under Stamp Act (Paragraph 17 reproduction) supporting broad lease interpretation.
Union of India & Ors. v. Hindustan Development Corporation & Ors.[1993] 3 SCR 128 : (1993) 3 SCC 499PositiveReferenced for principle that legitimate expectation cannot override legislative action; used to frame doctrine in policy changes.
Ram Pravesh Singh & Ors. v. State of Bihar & Ors.[2006] Suppl. 6 SCR 512 : (2006) 8 SCC 381PositiveUsed to define legitimate expectation as a procedural safeguard rather than enforceable right.
P.T.R. Exports (Madras) Pvt. Ltd. v. Union of India & Ors.[1996] Suppl. 2 SCR 662 : (1996) 5 SCC 268PositiveExplains limited role of legitimate expectation in policy changes.
M/s Hero Motocorp Ltd. v. Union of India[2022] 13 SCR 592 : (2023) 1 SCC 386PositiveUsed to support principle that there can be no promissory estoppel against the legislature.
Navjyoti Co-op. Group Housing Society v. Union of India[1992] Supp. 1 SCR 709Mentioned OnlyCited by appellant; not adopted by the Court in the final reasoning.
Food Corporation of India v. Kamdhenu Cattle Feed Industries[1992] Supp. 2 SCR 322Mentioned OnlyCited by appellant; not central to the Court’s final holding.
The State of Jharkhand and Ors. v. Brahmputra Metallies Ltd. Ranchi and Anr.[2020] 14 SCR 45PositiveUsed to support a broad lease interpretation in some contexts.
State of Bihar and Ors. v. Shyama Nandan Mishra[2022] 11 SCR 1136PositiveUsed to reinforce conclusions on legitimate expectations and admin actions.
State of Gujarat and another v. Raman Lal Keshav Lal Soni and Ors.[1983] 2 SCR 287Mentioned OnlyCited in argument but not adopted as controlling authority.
B.S. Yadav and Ors. etc. v. State of Haryana and Ors. Etc.[1981] 1 SCR 1024Mentioned OnlyCited in general context; not centrally relied upon by Court.
Kunnathat Thathunni Moopil Nair v. The State of Kerala and another[1961] 3 SCR 77DistinguishedExplicitly held inapplicable to the facts.
Associated Hotels of India Ltd. v. R.N. Kapoor[1960] 1 SCR 368 : AIR 1959 SC 1262Mentioned OnlyCited as part of jurisprudence; not the decisive authority here.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,823 words•~32 min read

In The Court Record

M/s Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.

[2024] 7 S.C.R. 1129 : 2024 INSC 539 ## **M/s Rewa Tollway P. Ltd.** **v.** ## **The State of Madhya Pradesh & Ors.** (Civil Appeal No. 8985 of 2013) 19 July 2024 **[Vikram Nath* and Ahsanuddin Amanullah, JJ.]** ## **Issue for Consideration** In view of the subsequent change of policy by the state legislature in light of larger public interest, the appellants were required to pay stamp duty on the Concession Agreement executed under the Build, Operate & Transfer (BOT) Scheme. Plea of the appellants that in view of the previous executive decision that the agreement would not require stamp duty, but was to be executed only on stamp paper of Rs.100/-, the appellants entered into the agreement with legitimate expectation that no stamp duty was required to be paid. Whether the appellants had any enforceable legal right in light of the previous policy and executive action which was subsequently changed in light of larger public interest; whether the Concession Agreement was a lease or a bond or a license; when the stamp duty was payable on the amount spent by the lessee, whether the demand raised on the whole amount was unjustified. ## **Headnotes[†]** **Legitimate expectation – Promissory estoppel – When not applicable – Transfer of Property Act, 1882 – Indian Stamp Act, 1899 – Indian Stamp (M.P.) Act, 2002 – High Court held that the Concession Agreement was a lease as defined u/s.105 of the TP Act as also u/s.2(16) of the IS Act and also rejected the challenge made by the appellants to the validity of the amendment made in proviso (c) to Clause (C) of Article 33 of Schedule 1(A) as amended by the Indian Stamp (M.P.) Act, 2002 – Correctness:** **Held:** Concession Agreement was a lease – Definition of lease as given under the IS Act covers any instrument by which tolls of any description are let and also u/s.105 of the TP Act, all the ingredients of a lease are fulfilled – No infirmity in the judgment of * Author [2024] 7 S.C.R. 1130 ## **Digital Supreme Court Reports** the High Court warranting any interference – Validity of the M.P. Act No.12 of 2002 inserting the proviso (c) to Clause(C) to Entry 33 of Schedule 1-A of the IS Act, upheld – It is only a statutory provision as to what would be the rate of stamp duty payable on lease deeds of a particular type – But for the insertion of the proviso which was challenged, the stamp duty payable on the lease would be 8% of the market value as provided to be charged on the conveyance under Entry-22 of Schedule 1-A – By inserting the proviso, the stamp duty chargeable on a lease under BOT Project for tolls/bridges, construction of roads etc. would be 2% of the amount spent by the lessee – In fact, insertion of this proviso reduced the rate of stamp duty to be charged to 2% instead of 8% and that too on the amount to be spent by the lessee – Principle of promissory estoppel cannot be invoked against the exercise of legislative power – A prior executive decision does not bar the State legislature from enacting a law or framing any policy contrary to or in conflict with the previous executive decision in furtherance of larger public interest – Law laid down by the legislature would not be hit by principle of promissory estoppel or legitimate expectation because earlier the executive expressed its view differently – If the previous executive decision is withdrawn, modified or amended in exercise of legislative power in larger public interest, then the earlier promise upon which the party acts, cannot be enforced as a right and neither can the authorities be estopped from withdrawing its promise, as such an expectation does not give any enforceable right to the party – Appellants did not have any enforceable legal right in light of the previous law or policy and executive action, which was subsequently changed by the state legislature in light of larger public interest Thus, principles of legitimate expectation and promissory estoppel are not applicable – Stamp duty would be chargeable @ 2% on the amount likely to be spent under the agreement by the lessee – Lessee had no liability to pay any stamp duty on the amount not spent by the lessee but by the lessor or any other stakeholder – The amount spent by the lessee as per the agreement generally was 50% of the total cost of the project – Once, the stamp duty was payable on the amount spent by the lessee, the demand raised on the whole amount would be unjustified – Demand set aside to that extent – Revenue Officer/Collector (Stamps) to re-calculate the same and raise the demand accordingly. [Paras 18, 19, 24, 25, 27, 28, 32, 34] [2024] 7 S.C.R.  1131 ## **M/S Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.** ## **Legitimate expectation – Promissory estoppel – Principles of – Discussed.** ## **Case Law Cited** _State of Uttarakhand and Ors. v. Harpal Singh Rawat_ **(2011) 4 SCC 575;** _Nasiruddin and another v. State of Uttar Pradesh Thr. Secretary and Ors._ **[2017] 12 SCR 1073 : (2018) 1 SCC 754;** _Union of India & Ors. v. Hindustan Development Corporation & Ors._ **[1993] 3 SCR 128 : (1993) 3 SCC 499;** _Ram Pravesh Singh & Ors. v. State of Bihar & Ors._ **[2006] Suppl. 6 SCR 512 : (2006) 8 SCC 381;** _P.T.R. Exports (Madras) Pvt. Ltd. v. Union of India & Ors._ **[1996] Suppl. 2 SCR 662 : (1996) 5 SCC 268;** _M/s Hero Motocorp Ltd. v. Union of India_ **[2022] 13 SCR 592 : (2023) 1 SCC 386 – relied on.** _Navjyoti Co-op. Group Housing Society v. Union of India_ **[1992] Supp. 1 SCR 709;** _Food Corporation of India v. Kamdhenu Cattle Feed Industries_ **[1992] Supp. 2 SCR 322;** _The State of Jharkhand and Ors. v. Brahmputra Metallies Ltd. Ranchi and Anr._ **[2020] 14 SCR 45;** _State of Bihar and Ors. v. Shyama Nandan Mishra_ **[2022] 11 SCR 1136;** _State of Gujarat and another v. Raman Lal Keshav Lal Soni and Ors._ **[1983] 2 SCR 287;** _B.S. Yadav and Ors. etc. v. State of Haryana and Ors. Etc._ **[1981] 1 SCR 1024;** _Kunnathat Thathunni Moopil Nair v. The State of Kerala and another_ **[1961] 3 SCR 77 – held inapplicable.** _Associated Hotels of India Ltd. v. R.N. Kapoor_ **[1960] 1 SCR 368 : AIR 1959 SC 1262 – referred to.** ## **List of Acts** Transfer of Property Act, 1882; Indian Stamp Act, 1899; Indian Stamp (M.P.) Act, 2002. ## **List of Keywords** Concession Agreement; Subsequent change of policy/law; Previous law or policy subsequently changed; Stamp duty; Lease deeds; Bond; License; Legitimate expectation; Promissory estoppel; Previous policy; Executive decision; Tolls/bridges; Roads; Executive action subsequently changed in light of larger public interest; Stamp duty payable on lease deeds; Recovery of deficit stamp duty; Recovery notice. [2024] 7 S.C.R. 1132 ## **Digital Supreme Court Reports** ## **Case Arising From** CIVIL APPELLATE JURISDICTION: Civil Appeal No. 8985 of 2013 From the Judgment and Order dated 11.02.2010 of the High Court of M.P. at Jabalpur in WP No. 2219 of 2004 ## With Civil Appeal Nos. 8989, 8986, 8990, 8988, 8987, 8991, 8992, 8993, 8995, 8996 and 8994 of 2013 ## **Appearances for Parties** Prafulla Kumar Behera, S. S. Nehra, Vikrant Nehra, Ms. Sundari Rawat, Kunal Verma, Mrs. Yugandhara Pawar Jha, Ms. Lavanya Dhawan, Shivraj Pawar, Ritik Gupta, Sanjay Kapur, Arjun Bhatia, B. K. Satija, Advs. for the Appellant. Saurabh Mishra, A.A.G., Sunny Choudhary, Ms. Aarushi Singh, Ashiesh Kumar, Advs. for the Respondents. ## **Judgment / Order of the Supreme Court** ## **Judgment** ## **Vikram Nath, J.** 1. By the impugned judgment and order dated 11.02.2010, the High Court of Madhya Pradesh at Jabalpur decided a group of twelve petitions wherein the question involved was whether a transaction where the right to collect tolls is given in lieu of the amount spent by the Concessionaire in the construction of roads, bridges etc. under the Build, Operate & Transfer (BOT) Scheme amounts to a “lease” as contemplated under Section 105 of the Transfer of Property Act, 1882[1] and Section 2(16) of the Indian Stamp Act, 1899.[2] Further challenge made in the said writ petitions was with regard to the validity of the amendment made in proviso (c) to Clause (C) of Article 33 of Schedule 1(A) as amended by the Indian Stamp (M.P.) Act, 2002, and a further prayer was made to declare Section 48 and 48(B) of IS Act, 1899, as amended by M.P. Act 24 of 1990 as _ultra vires_ . > 2 IS Act 1 TP Act [2024] 7 S.C.R.  1133 ## **M/S Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.** 2. The Division Bench of the High Court, after considering the submissions and the material on record came to the conclusion that the writ petitions were without any merit and accordingly dismissed the same. Aggrieved by the same, these twelve appeals have been preferred. 3. For the sake of convenience, we are referring to the facts of Civil Appeal No.8985 of 2013, which are briefly stated hereunder: - (i) Madhya Pradesh Rajya Setu Nirman Nigam Ltd.,[3] (respondent no.3) is a Company incorporated and registered under the Companies Act, 1956. The State of Madhya Pradesh, vide order dated 01.02.2001, authorized MPRSNN for reconstruction, strengthening, widening and rehabilitation of a section of road on Satna-Maihar-Parasimod-Umaria Road Project to be executed through Concession on Build, Operate and Transfer Scheme. - (ii) MPRSNN, vide Advertisement dated 22.04.2002, invited tenders against the aforesaid project pursuant to which the bid of the appellant was accepted. On 8[th] August, 2002, Letter of Acceptance was issued by the MPRSNN to the appellant for execution of the Concession Agreement within 30 days. - (iii) The IS Act was amended in the State of Madhya Pradesh vide Amendment Act No.12 of 2002 and proviso (c) to Clause(C) was inserted to Entry No.33 of Schedule-1(A), which provided that there shall be levy of stamp duty @ 2% on the amount likely to be spent on the project, on the agreement to lease and right to collect the toll is given. The State of Madhya Pradesh notified the said amendment on 12.08.2002. - (iv) A Concession Agreement was signed on 15.09.2002 on a stamp paper of Rs.100 between MPRSNN and the appellant. A show cause notice dated 26.03.2004 was issued to the appellant intimating that the matter between State of M.P. and the Rewa Tollway Private Ltd. would be listed for hearing on 29.03.2004 before the Collector of Stamps, Bhopal and the appellant was required to produce the original copy of the agreement dated 15.09.2002. The appellant filed a detailed reply dated 25.04.2004 stating that the agreement executed was a 3 MPRSNN [2024] 7 S.C.R. 1134 ## **Digital Supreme Court Reports** Concession Agreement and, as such, it cannot be treated as a lease but as a license at best. The Collector (Stamps), Bhopal vide order dated 30.04.2004 passed an order exercising power under Section 48-B of the IS Act directing recovery of deficit stamp duty amounting to Rs.1,08,00,000/-(Rupees one crore eight lakhs) said to be payable on the Concession Agreement dated 15.09.2002. Thereafter, a recovery notice was issued on 29.05.2004 by the Collector (Stamps), Bhopal to deposit the aforesaid amount within seven days of the receipt of the said recovery notice. - (v) On 6[th] June, 2004, the appellant challenged the order dated 30.04.2004 by way of a writ petition under Article 226 of the Constitution which was registered as Writ Petition No.2219 of 2004. The High Court vide order dated 03.08.2004 granted interim stay of recovery of any amount pursuant to the impugned order dated 30.04.2004. The High Court, vide judgment and order dated 11.02.2010, dismissed the said writ petition along with eleven other matters and upheld the demand raised by the Collector of Stamps by the order dated 30.04.2004. - (vi) Aggrieved by the impugned judgment of the High Court, the appellant preferred the instant appeal with connected matters before this Court on 3[rd] May, 2010, in which notices were issued on 14[th] May, 2010 and, thereafter, interim order was passed on 7[th] January, 2011. Later on, vide order dated 13.09.2013, this Court granted leave and further directed the interim stay granted earlier to continue. 4. We have heard Shri Dushyant Dave, learned Senior Counsel appearing for the appellants in nine (9) appeals and other learned counsels appearing for the appellants in the other three (3) appeals and Shri Saurabh Mishra, learned Additional Advocate General for the State of Madhya Pradesh on behalf of the respondents. 5. Before we proceed further with the submissions, it would be relevant to refer to three other dates which have been referred to by Shri Dave in support of his submissions on legitimate expectation and promissory estoppel. According to Shri Dave, after the tender was invited vide Advertisement dated 22[nd] April, 2002, the Chief Secretary issued a Clarification dated 01.07.2002 with respect to the agreements executed under BOT Scheme stating that stamp duty would not [2024] 7 S.C.R.  1135 ## **M/S Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.** be payable on such agreements in the State of Madhya Pradesh also and further reiterating that in order to avoid any doubts to be raised in future, it is necessary to clarify that no stamp duty shall be payable on the agreements being executed under BOT Scheme. A further clarification was issued vide letter dated 21.07.2002 by the Chief Secretary of the State with respect to the Resolution dated 01.07.2002, that no stamp duty would be levied on BOT Projects in future and such agreements would be signed on stamp paper of Rs.100/-. Shri Dave further referred to the Notification of the State Government dated 10[th] March, 2008 whereby the stamp duty on toll was reduced from 2% to Rs.100 i.e. the position which existed prior to the Amendment of 2002 and as clarified in the notification and the letters of 1[st] July of 2002 and 21[st] July, 2002. It was, thus, submitted that the charge of 2% stamp duty was only applicable in the State of Madhya Pradesh between August, 2002 till March, 2008 and, thereafter, again all such Concession Agreements under BOT Scheme are to be executed on stamp paper of Rs.100. It was throughout the intention of the State of Madhya Pradesh to not charge stamp duty @ 2% and treat the Concession Agreement under BOT Scheme to be a license but unfortunately for the period referred to above, it was treated as a lease and the appellants are the victims of this period, whereas all subsequent Concession Agreements under BOT Scheme executed after 10[th] March, 2008 are exempt from such stamp duty. 6. Further continuing his submissions Mr. Dave, learned Senior Counsel submitted that in view of the Clarification dated 01.07.2002 and subsequent circulation vide letter dated 21.07.2002 throughout the State, once it was clarified that the Concession Agreements under the BOT Projects would be executed on stamp paper of Rs.100/-, the appellants entered into the agreement with the same impression and having calculated their project cost and also their tenders without factoring in 2% stamp duty, had legitimate expectation that the agreement would not require stamp duty @ 2% of the value, but was to be executed only on stamp paper of Rs.100/-. The subsequent demand was contrary to the legitimate expectations of the appellants and, therefore, liable to be set aside. 7. It was next submitted that the Circular of the Chief Secretary dated 1[st] July, 2002 and its subsequent circulation vide letter dated 21[st] July, 2002, estopped the State Government from amending the IS [2024] 7 S.C.R. 1136 ## **Digital Supreme Court Reports** Act and, further raising the demand @ 2% treating the Concession Agreement to be a lease, the same would be hit by principle of promissory estoppel. The State was estopped from demanding such stamp duty by treating the Concession Agreement to be a lease. 8. In support of his submissions, Shri Dave has placed reliance upon the following judgments: - **(1) Navjyoti Co-op. Group Housing Society Vs. Union of India;[4]** - **(2) Food Corporation of India Vs. Kamdhenu Cattle Feed Industries;[5]** - **(3) The State of Jharkhand and Ors. Vs. Brahmputra Metallies Ltd. Ranchi and Anr.;[6]** - **(4) State of Bihar and Ors. Vs. Shyama Nandan Mishra;[7]** - **(5) M/S Hero Moto Corp Ltd. Vs. Union of India and Ors.;[8]** 9. Shri Dave, learned Senior Counsel next submitted that the insertion of proviso (c) to Clause(C) under Article 33 of Schedule 1-A by the 2002 Amendment Act was _ultra vires_ as it violates the mandate of Article 14 of the Constitution of India. It was submitted that the said amendment was illegal, arbitrary and bad in law as it nullified the promise made by the Chief Secretary, vide Circular dated 01.07.2002, and has taken away the vested right of the appellants of not factoring in 2% stamp duty and ultimately resulting into a demand of a huge amount of Rs.1,08,00,000/- (Rupees one crore eight lakhs) approximately. In support of his submission, he has relied upon the following two judgments: - **(1) State of Gujarat and another Vs. Raman Lal Keshav Lal Soni and Ors.;[9]** - **(2) B.S. Yadav and Ors. etc. Vs. State of Haryana and Ors. Etc.;[10]** > 4 [1992] Supp. 1 SCR 709 : (1992) Supp.1 SCR 709 > 5 [1992] Supp. 2 SCR 322 : (1992) Supp.2 SCR 322 > 6 [2020] 14 SCR 45 : (2020) 14 SCR 45 - 7 [2022] 11 SCR 1136 : (2022) 11 SCR 1136 > 8 [2022] 13 SCR 592 > 9 [1983] 2 SCR 287 : (1983) 2 SCR 287 - 10 [1981] 1 SCR 1024 : (1981) 1 SCR 1024 [2024] 7 S.C.R.  1137 ## **M/S Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.** 10. The next point raised by Shri Dave is that the aforesaid amendment was _ultra vires_ , inasmuch as, the State had no legislative competence to bring in this amendment. Further, it was submitted that it was a colourable and excessive legislation and was a fraud on the Constitution of India, inasmuch as, the State itself in 2008 withdrew the Amendment of 2002. In support of his submission, he has relied upon the following judgment: - **(1) Kunnathat Thathunni Moopil Nair Vs. The State of Kerala and another;[11]** 11. The next submission of Shri Dave is that the Concession Agreement dated 15.09.2002 is not an instrument of lease and, as such, the demand of 2% stamp duty was totally uncalled for and illegal. According to him, the ownership of the project land has not been transferred by the State to the MPRSNN and, as such, MPRSNN could not transfer any ownership or interest to the appellants. The Concession Agreement was on the concept of public, profit, partnership (PPP mode). He has further elaborated his submissions by referring to Section 105 of the TP Act. According to him, in a lease, the following three ingredients must pre-exist: - (1) There is a transfer of a right to enjoy such property. - (2) It is made for a fixed time, express or implied or in perpetuity. - (3) There has to be consideration of a price paid or promised. 12. According to Shri Dave, learned Senior Counsel for the appellants, lease means transfer of interest in the property to enjoy the property whereas, license means transfer of property but no interest in the property. According to him, in the present case, there was no transfer of interest in the property, as such, it would not fall within the definition of lease. He has further referred to various clauses of the Concession Agreement in support of his submission. 13. It was next submitted that MPRSNN is a 50% partner in the construction of the project which indicates that the Concession Agreement is a mutual contract and, as such, would not levy 2% stamp duty as imposed by the impugned orders. According to him, out of a total project cost, 50% was to be paid by the MPRSNN. 11 [1961] 3 SCR 77 : (1961) 3 SCR 77 [2024] 7 S.C.R. 1138 ## **Digital Supreme Court Reports** According to him, respondent no.3, MPRSNN being a 50% partner in the entire road project meant that the appellant and respondent no.3 are equal stake holders and, as such, the unilateral imposition of 2% stamp duty of the entire project cost on the appellant was illegal and unwarranted. He has further criticised the judgment of the Collector (Stamps), Bhopal whereby he held that the total project cost was Rs.110 crores whereas actually it was 54 crores, out of which, MPRSNN (respondent no.3) had granted subsidy and invested Rs.29.10 crores and the remaining Rs.24.90 crores, was invested by the appellant. As such, even if he was liable to pay 2% stamp duty, the amount would be much less, approximately Rs.48 lakhs and odd and not Rs.1.08 crores, which was 2% stamp duty on the entire project cost. 14. The last argument raised is that once the IS Act had been re-amended on 10[th] March, 2008, the earlier Amendment of 2002 should be held to be illegal and arbitrary. On such submissions, Shri Dave, learned senior counsel urged the Court to allow the appeal and set aside the impugned orders imposing deficiency in stamp duty of Rs.1.08 crores. 15. On the other hand, Shri Saurabh Mishra, learned Additional Advocate General for the State of Madhya Pradesh representing all the three respondents including ‘MPRSNN’ submitted that the High Court had dealt with all the above arguments in great detail and had rejected them for good reasons based on statutory provisions as also the law on the point. It did not suffer from any infirmity, much less any perversity warranting interference by this Court. 16. According to Shri Mishra, all the ingredients of a document constituting a lease as defined under the TP Act were existing in the Concession Agreements under the BOT Scheme. He has also referred to various clauses of the Concession Agreement to show that possession was actually transferred to the appellants in order to recover the toll, the period of such possession was defined to be fifteen years. It was for a consideration which was also mentioned in the agreement. Therefore, all the three ingredients were fulfilled and, as such, the Collector (Stamps), Bhopal and the High Court rightly held the Concession Agreements to be a lease. He also referred to definition of ‘lease’ under the IS Act, as laid down in Section 2(16), which includes any instrument by which tolls of any description are let. He also referred to the definition of ‘immovable property’ as defined under Section [2024] 7 S.C.R.  1139 ## **M/S Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.** 3(26) of the General Clauses Act, 1897, which would include land, benefits to arise out of land, and things attached to the earth, or permanently fastened to anything attached to the earth. He further referred to various findings recorded by the High Court. He further placed reliance upon three judgments of this Court:- - **(1) Associated Hotels of India Ltd. Vs. R.N. Kapoor;[12]** - **(2) State of Uttarakhand and Ors. Vs. Harpal Singh Rawat;[13]** - **(3) Nasiruddin and another Vs. State of Uttar Pradesh Thr. Secretary and Ors.;[14]** 17. Shri Mishra, further referred to the various provisions of the Indian Tolls (MP) Amendment Act, 1972. Insofar as to the challenge of the amendments as being _ultra vires_ is concerned, Shri Mishra submitted that the insertion of proviso (c) to Clause(C) to Entry-33, is only for determining the rate of charging stamp duty and, as such, the challenge was totally irrelevant. The Concession Agreement is a lease as defined under Section 105 of the TP Act as also under Section 2(16) of the IS Act and, therefore, would be chargeable to stamp duty, for which rate is provided under Schedule 1-A. It was further submitted that the submission relating to Promissory Estoppel and Legitimate Expectation are unwarranted and without any merit, inasmuch as, prior to the execution of the concession agreement, the amendment had been brought in. The communication by the Chief Secretary cannot have any overriding effect over the statutory amendments brought in by the State legislature. It is also submitted that there can be no Legitimate Expectation or application of Promissory Estoppel against statute. It is also submitted that the State was fully competent to carry out the amendments. It was next submitted that as the 2002 amendment had been reversed in 2008, cannot by itself draw any kind of presumption that 2002 amendment was illegal. It was submitted that the appeals lack merit and are liable to be dismissed. 18. Having considered the submissions advanced and having perused the material on record, we have no hesitation in holding that the judgment > 12 [1960] 1 SCR 368 : AIR 1959 SC 1262 13 (2011) 4 SCC 575 > 14 [2017] 12 SCR 1073 : (2018) 1 SCC 754 [2024] 7 S.C.R. 1140 ## **Digital Supreme Court Reports** of the High Court impugned in these appeals does not require any interference. We do not find any infirmity, much less any perversity warranting any interference by this Court. The High Court has dealt with all aspects of the matter considering not only the stipulations in the Concession Agreement but has also dealt with in detail with the respective arguments advanced by the petitioners before the High Court (the appellants herein) at the same time referring to the statutory provisions, the constitutional provisions as also the caselaws relied upon by the counsel for the parties. However, there is one aspect of the matter which requires clarification which we shall deal with at the end of this judgment. 19. The arguments made on behalf of the appellants relating to the vires of inserting the proviso (c) to Clause (C) to Entry 33 of Schedule 1-A of the IS Act, 1899 by the M.P. Amendment of 2002 have no merits as it neither defines the word ‘lease’ nor does it in any way interfere with the definition of ‘lease’ in any manner, either by expanding or restricting its interpretation. It is only a statutory provision as to what would be the rate of stamp duty payable on lease deeds of a particular type. But for the insertion of the proviso which is sought to be challenged, the stamp duty payable on the lease would be 8% of the market value as provided to be charged on the conveyance under Entry-22 of Schedule 1-A. By inserting the proviso, the stamp duty chargeable on a lease under BOT Project for tolls/bridges, construction of roads etc. would be 2% of the amount spent by the lessee. In fact, insertion of this proviso reduced the rate of stamp duty to be charged to 2% instead of 8% and that too on the amount to be spent by the lessee. 20. The doctrine of legitimate expectation has been discussed and elucidated upon in several judgment by this Court. The doctrine provides a framework for judicial review of executive actions, policy changes, and legislative decisions. In **Union of India & Ors. v. Hindustan Development Corporation & Ors.,[15]** this Court emphasized that legitimate expectation primarily grants an applicant the right to a fair hearing before a decision that negates a promise or withdraws an undertaking from which an expectation of certain outcome or treatment arises. It does not, however, create an absolute 15 [1993] 3 SCR 128 : (1993) 3 SCC 499 [2024] 7 S.C.R.  1141 ## **M/S Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.** right to the expected outcome. The protection of legitimate expectation is subject to overriding public interest, which means that even if an individual’s expectation is reasonable and based on a past practice or representation by the executive or legislature, it can be denied if justified by a significant public necessity. The Court also highlighted that in matters of policy change, the judiciary typically refrains from interfering, unless the decision is arbitrary, unreasonable, or not in public interest. 21. The judgment in **Ram Pravesh Singh & Ors. v. State of Bihar & Ors.[16]** defines legitimate expectation as an expectation of a benefit, relief, or remedy that arises from a promise or established practice through administrative, executive or legislative action. This expectation must be reasonable, logical, and valid; but it in no way vests any enforceable legal right. The doctrine does not elevate legitimate expectation to the level of a right enforceable by law. Instead, it is a procedural concept that demands fairness in administrative action. When an expectation is deemed legitimate, it may entitle the individual to a chance to show cause before the expectation is denied or to receive an explanation for the denial. However, legitimate expectation does not always result in relief, particularly when public interest, policy changes, or other valid reasons justify the deviation from the expected course of action. 22. The decision in **P.T.R. Exports (Madras) Pvt. Ltd. v. Union of India & Ors.[17]** further clarifies the limited role of legitimate expectation in the context of policy changes and legislative actions. This Court observed that the government retains the authority to revise policies in response to changing circumstances, such as potential foreign markets and the need to earn foreign exchange. Thus, the doctrine of legitimate expectation does not constrain the government from altering its policies, provided the changes are made in public interest and not through an abuse of power. The judiciary affords considerable leeway to the executive and legislature in matters of economic policy, recognizing their prerogative to prioritize different economic factors. Consequently, previous policies do not bind the government indefinitely; new policies can be adopted, if deemed > 16 [2006] Suppl. 6 SCR 512 : (2006) 8 SCC 381 17 [1996] Suppl. 2 SCR 662 : (1996) 5 SCC 268 [2024] 7 S.C.R. 1142 ## **Digital Supreme Court Reports** necessary, for the public good. This underscores the principle that while legitimate expectation warrants fair treatment, it does not preclude the government’s flexibility in policy-making. 23. Therefore, the doctrine of legitimate expectation serves only as a procedural safeguard ensuring fairness in administrative decisions and policy changes. It grants the expectant party the right to a fair hearing and an explanation but does not guarantee the realization of the expected benefit. The government’s authority to revise policies in public interest remains paramount, with the judiciary intervening only in cases of arbitrariness, unreasonableness, or lack of public interest. This balanced approach ensures that while individuals can expect consistent treatment based on past practices or promises, the government retains the flexibility to respond to evolving needs and priorities. 24. On the doctrine of promissory estoppel, since it is an equitable doctrine, it only comes into play when equity requires a party be estopped from withdrawing its promise. It has been well settled by this Court in several judgments that the principle of promissory estoppel cannot be invoked against the exercise of legislative power. In order to avoid burden on the present judgment, we are relying on the observations made by this Court in a recent judgment dealing with the doctrine of promissory estoppel. The Bench in _**Hero Motocorp Ltd vs Union of India**_ **,[18]** while relying upon other judgments of this Court in this regard, observed thus (SCC pp. 414-415, para 68) - _“68. A common thread in all these judgments that could be noticed is that all these judgments consistently hold that there can be no estoppel against the legislature in the exercise of its legislative functions. The Constitution Bench in the case of M. Ramanatha Pillai (supra) has approved the view in American Jurisprudence that the doctrine of estoppel will not be applied against the State in its governmental, public or sovereign capacity. It further held that the only exception with regard to applicability of the doctrine of estoppel is where it is necessary to prevent fraud or manifest injustice. The analysis of all the judgments of this Court on the issue would reveal_ 18 [2022] 13 SCR 592 : (2023) 1 SCC 386 [2024] 7 S.C.R.  1143 ## **M/S Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.** _that it is a consistent view of this Court, reiterated again in Godfrey Philips India Ltd. (supra), that there can be no promissory estoppel against the legislature in the exercise of its legislative functions.”_ 25. In light of the observations made by this Court in the above cited judgments and several others, it is an evident position of law that a prior executive decision does not bar the State legislature from enacting a law or framing any policy contrary to or in conflict with the previous executive decision in furtherance of larger public interest. Nor can it be canvassed that the law laid down by the legislature would be hit by principle of promissory estoppel or legitimate expectation because earlier the executive had expressed its view differently. 26. Promissory estoppel or legitimate expectation can be dealt with on the same status of the executive decision when the prior as well as the subsequent decisions are both taken by the same or similarly placed authorities. Where the executive takes a decision based upon which a party acts and, later on, the executive withdraws that decision to the detriment of the party acting upon the earlier decision, it can be said to be estopped from withdrawing its promise or depriving the party from its legitimate expectation of what had been promised. 27. In situations, such as the one before us, if the previous executive decision is withdrawn, modified or amended in any manner in exercise of legislative power in larger public interest, then the earlier promise upon which the party acts, cannot be enforced as a right and neither can the authorities be estopped from withdrawing its promise, as such an expectation does not give any enforceable right to the party. Applying the above discussion to the present facts, it is evident that the principles of legitimate expectation and promissory estoppel would not apply here, as the appellants cannot be said to have any enforceable legal right in light of the previous law or policy and executive action, which was subsequently changed by the state legislature in light of larger public interest. Thus, the submissions advanced on behalf of the appellants relating to the challenge to the M.P. Act No.12 of 2002 inserting the proviso (c) to Clause(C) to Entry 33 of Schedule 1-A of the IS Act has to be rejected. None of the case-laws relied upon on behalf of the appellants come to the rescue of the appellants and have no application in the facts and circumstances of the present case. [2024] 7 S.C.R. 1144 ## **Digital Supreme Court Reports** 28. Now coming to the next submission on behalf of the appellants with regard to the question as to whether the Concession Agreement is a lease or a bond or a license. The definition of lease as given under the IS Act clearly covers any instrument by which tolls of any description are let and also under Section 105 of the TP Act, all the ingredients of a lease are fulfilled. In the present case, we need not reiterate and repeat the same reasoning and findings as given by the High Court in great detail after considering the various clauses of the Concession Agreement. We uphold the finding of the High Court to be clearly justified and based upon a clear understanding of the terms of the concession agreement. We do not find any perversity at all in the reasoning given by the High Court to uphold the Concession Agreement to be a lease. 29. After the judgment of the High Court which is of the year 2010, two further judgments have been delivered by this Court regarding interpretation of a lease, which have been relied upon by Shri Mishra on behalf of the respondents. Out of the three judgments relied upon by Shri Mishra, the judgment in the case of **Associated Hotels of India Ltd. (supra)** has already been considered by the High Court. Further, the judgments in the case of **State of Uttarakhand and others (supra)** and in the case of **Nasiruddin and another (supra)** further reiterated the view taken by **Associated Hotel of India Ltd. (supra)** . Paragraph 17 in the case of **Nasiruddin and another (supra)** is reproduced hereunder: - _“17. The expression “lease” under the Stamp Act has a wider meaning as compared to its original meaning contained in Section 105 of the Transfer of Property Act (for short “the TP Act”). If “lease” under Section 2(16) of the Stamp Act includes therein four specified categories of documents set out in sub-clauses (a) to (d), we do not find any such inclusion in Section 105 of the Transfer of Property Act. It is for this reason, we are of the view that the definition of “lease” for the purpose of the Stamp Act is extensive in nature. It is also clear from the use of the expression and includes also “in Section 2(16) of the Stamp Act. So by fiction, “any instrument by which tolls of any description are let “is considered as “lease” for the purpose of payment of stamp duty under the Stamp Act.”_ [2024] 7 S.C.R.  1145 ## **M/S Rewa Tollway P. Ltd. v. The State of Madhya Pradesh & Ors.** 30. Thus, the view taken by the High Court further stands fortified by the above two judgments and the view that we are taking. 31. The only issue which requires to be considered afresh is with respect to determination of the amount spent under the agreement by the lessee. For the said purpose, we reproduce proviso(c) to Clause (C) of the proviso inserted in 2002: _“(c) an agreement to lease where the right to collect tolls is given_ _**in lieu of the amount spent by the lesse** e in construction of roads, bridge etc. under the Build, Operate and Transfer (B.O.T.) scheme, shall be chargeable at the rate of two percent_ _**on the amount likely to be spent under the agreement by the lessee.** ”_ 32. From a clear reading of the above proviso (c) to Clause (C), the stamp duty would be chargeable @ 2% on the amount likely to be spent under the agreement by the lessee. Thus, the lessee has no liability to pay any stamp duty on the amount not spent by the lessee but by the lessor or any other stake-holder. The amount spent by the lessee as per the agreement generally was 50% of the total cost of the project. 33. In the case of **Rewa Tollway** , **[19]** the total cost of the project was Rs.54 crores, out of which, approximately 50 % would be that of the lessee and 50% to be funded by the lessor i.e. MPRSNN, respondent no.3. However, further reading of the Concession Agreement reflects that the amount to be spent by the lessee was not exactly 50% but is slightly different figure. At some places, it is mentioned as Rs.24.10 crores and in other places a different amount is mentioned. We are not entering into this issue of what is the amount spent but we require that this be determined by the Collector (Stamps) / Revenue Officer of the concerned district. 34. Once, the stamp duty is payable on the amount spent by the lessee, the demand raised on the whole amount would be unjustified, as such, to the above extent, the demand needs to be set aside with a further direction to the Revenue Officer/Collector (Stamps) of the district concerned to re-calculate the same as observed above and, accordingly, raise the demand. In case, the appellants have deposited 19 Civil Appeal No. 8985 of 2013 [2024] 7 S.C.R. 1146 ## **Digital Supreme Court Reports** the demand raised on the entire project cost then the amount lying in excess with the State would be refunded to them. However, in case of any deficit in stamp duty having not been deposited, the appellants would deposit the same within two months of the fresh demand being raised by the Revenue Officer/Collector (Stamps) of the district concerned. The Collector (Stamps)/Revenue Officer is further directed to calculate the said amount in each of the cases individually and communicate the same to the appellants within a period of two months from today and where the amount is lying in excess with the State, the same shall be refunded within a period of two months of such determination. 35. The appeals stand partly allowed as above. No costs. _Result of the case:_ Appeals partly allowed. - _†Headnotes prepared by:_ Divya Pandey
End of Judgment Record
Browse All Supreme Court of India (2024) Decisions
2024-04-09

Kizhakke Vattakandiyil Madhavan (Dead) Thr. Lrs. v. Thiyyurkunnath Meethal Janaki and Ors

This appeal concerns partition of a family property in Eravattur, Kozhikode, governed by pre-1956 Mitakshara succession. Madhavan died before 1910; his widow Chiruthey remarried Neelakandan, triggering Section 2 of the Hindu Widow’s Remarriage Act, 1856, which extinguishes a widow’s rights in her deceased husband’s property on remarriage. Chiruthey’s second marriage, and a sequence of instruments dated 1910–1925—back-to-back deeds creating a lease in favour of Cheriyamma and her son (Exhibits A-20 and A-1) and an assignment (Exhibit A-2)—formed the basis for Chandu (the plaintiff) and Sankaran’s successors-in-interest to seek partition in OS 157/1985. The Trial Court granted partition to the plaintiff; the First Appellate Court dismissed; the Kerala High Court restored the Trial Court’s decree. The Supreme Court, however, allowed the appeal. It held that on remarriage the widow’s title over Madhavan’s property stood lapsed under Section 2; yet the back-to-back deeds involved Nangeli (Madhavan’s mother) and Sankaran, who retained an interest. Exhibit A-20 was treated as a valid conveyance, but Chiruthey’s own title did not survive; the lease purportedly created by A-1 could not extend beyond its 12-year term. Consequently, the plaintiff’s claim for partition could not be sustained, and the appeal was allowed with the trial/decree of the lower courts set aside.

2024-10-04

Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Limited & Others

Banshidhar Construction Private Limited (the appellant) challenged Bharat Coking Coal Limited’s tender for a mega project to salvage, develop, and operate a coal mine under a revenue-sharing arrangement for 25 years. The tender NIT dated 16.08.2023 imposed stringent eligibility criteria, including Clause 10 requiring financial capacity documentation and a Power of Attorney for signing bids. The appellant contended that its Power of Attorney (dated 07.11.2023 and notarised 14.11.2023) was valid, and its bid documents were uploaded before the last submission date (01.12.2023). Technical bids opened on 04.12.2023, yet the appellant was declared technically disqualified on 06.05.2024 on grounds that it did not meet Clause 10. Meanwhile, Respondent No.8 was declared technically qualified and later found to be the successful bidder after financial bids were opened on 07.05.2024, despite non-compliance with the “mandatory” Clause 10 documents, including delayed Audited Balance Sheets. The High Court dismissed the writ petition. The Supreme Court, while acknowledging limited review in mega-project tenders, held that public authorities must act with fairness, transparency, and without arbitrariness or malafides. It held that the Power of Attorney requirement was satisfied and that accepting the non-compliant Respondent No.8 while rejecting the appellant was arbitrary. The Court set aside the impugned decision and permitted a fresh tender process in accordance with law, reaffirming that Article 14 requires equal treatment and non-arbitrariness in public procurement.

2024-03-21

Union of India v. M/s Indian Oil Corporation Ltd.

This Supreme Court judgment concerns an appeal by the Union of India challenging a batch of Allahabad High Court orders that directed refunds to IOCL for a difference of approx. 110 km in freight charges on the Baad–Hisar route. IOCL had been charged on the basis of a distance of 444 km under the old Local Distance Table; following Railway Ministry circulars in 2004 and 2005 rationalizing the rounding-off of chargeable distance, the distance was reduced to 333.18–334 km in practice. IOCL issued notices under Section 106 of the Railways Act, 1989 (formerly Section 78-B of the Railways Act, 1890) seeking refunds of the alleged overcharge, and 122 consignments were paid at the old distance before the authorities corrected the distance. The Railway Claims Tribunal dismissed most claims as time-barred, while the Allahabad High Court allowed IOCL’s appeals, holding that the original 444 km charge was an “illegal charge” rather than an overcharge, and thus protected by equity. The Union of India challenged this, arguing that Section 106(3) only covers refunds of overcharges and not illegal charges; that the change in distance stemmed from policy rationalization and circulars, not an erroneous charge. The Court distinguishes Hindustan Petroleum, clarifies the overcharge/illegal charge distinction, and ultimately holds that the 444 km distance was illegal. As a result, the Union’s appeals are dismissed, and IOCL’s refunds for the difference would be payable to IOCL. The matter underscores the nuanced interplay between statutory time limits, chargeable distance, and the nature of the charge in refund claims.

2024-07-23

Gene Campaign & Anr. v. Union of India & Ors.

This is a batch of writ petitions initiated in 2004–2005 addressing the environmental and regulatory treatment of GM crops, specifically the environmental release of transgenic mustard DMH-11 (Dhara Mustard Hybrid-11). The Supreme Court examined whether GEAC’s 18.10.2022 conditional approval and the 25.10.2022 decision were legally sound, whether they violated Article 21 (right to a safe environment) and whether the precautionary principle was properly applied. The court undertook a comprehensive review of the regulatory framework under the Environment Protection Act, 1986 and the 1989 Rules, as well as the Technical Expert Committee (TEC) reports and Parliamentary Standing Committee recommendations. A key feature is the dual opinions: Justice Nagarathna (with Justice Karol concurring but delivering a separate opinion) upheld a robust judicial review of executive policy in GM regulation and found serious irregularities in the decision-making process, quashing the impugned approvals and directing a national policy on GM crops, greater public transparency, and safe-guarded field testing. Justice Karol, in a separate opinion, while endorsing the need for precaution, cautioned against an outright ban on HT crops and emphasized policy matters be left to the legislature. The judgment thus emphasizes environmental rule of law, public trust, intergenerational equity, and a precautionary approach, while mandating further regulatory reform and public participation.