High CourtSingle JudgeAppeals allowed

M/S RAVEECHEE AND CO. v. UNION OF INDIA

Case / Petition Number:Civil Appeal Nos. 5964-5965 of 2018

Case Details & Bench

Court
High Court
Hon'ble Judges
  • S. A. Bobde
  • L. Nageswara Rao
Judgment Date
2018-07-03
Court Decision / Holding
Appeals are allowed. The High Court’s judgment setting aside the arbitrators’ order on Claim No. 12 is set aside, and the arbitral award is restored, including pendente lite interest on damages from 26.09.1988 to 23.03.2001.
Final Disposition
Appeals allowed

Parties to the Case

Appellants / Petitioners

  • M/s Raveechee and Co.

Respondents

  • Union of India

Legal Representation & Advocates

Counsels for Petitioners

  • • K. V. Viswanathan
  • • Mohit Paul
  • • Ayush Agrawal
  • • Anugram Niraj Ekka
  • • Vikarant Singh Baloria

Counsels for Respondents

  • • Vikramjit Banerjee
  • • A. K. Panda
  • • A. K. Srivastav
  • • Ms. Sushma Verma
  • • Ayush Anand
  • • Shubhandu Anand
  • • Raj Bahadur
  • • Bharat Sood
  • • Shreekant N. Terdal

Case Synopsis & Summary

These Civil Appeals arise from a contract dated 02.06.1981 for quarrying, loading and stacking ballast material, where disputes led to arbitration. The Arbitral Tribunal awarded Rs. 76,43,800 on claims 1-12, with Claim No. 12 focusing on interest pendente lite on damages excluding security deposits, amounting to Rs. 44,92,800 from 26.09.1988 to 22.03.2001. The Gujarat High Court partially allowed the Union of India’s appeal and quashed the arbitrators’ order on Claim No.12, effectively denying pendente lite interest. The core question is whether Clause 16(3) of the General Clauses Contract (GCC) restricted the arbitrator’s power to award pendente lite interest. Clause 16(3) provides that no interest is payable on earnest money, security deposits, or amounts payable under the contract, but it does not expressly bar pendente lite interest on damages arising during lis. The Supreme Court held that pendente lite interest arises from being kept out of money due to arbitration and is determined in the course of lis, not as a contractual payment. An arbitrator has inherent power to award such interest unless a clear, specific bar exists. The judgment traces supportive authority from Irrigation Deptt. v. G.C. Roy, Board of Trustees v. Engineers-De-Space Age, Madnani Construction, Sayeed Ahmed, and Ambica Construction, and restores the arbitral award for Claim No. 12. Appeals are allowed.

Provisions of Law Cited

Arbitration Act, 1940Clause 16(3) of General Clauses Contract (GCC)Clause 16(1) of GCCSection 17 of the Arbitration Act, 1940

Legal Doctrines & Maxims

  • Power to do equity
  • Bar to award pendente lite must be clear and specific (ouster)
  • Arbitrator's inherent power to award pendente lite unless barred
  • Interest pendente lite arises from being kept out of money due to pendency of arbitration

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contend that Clause 16(3) of GCC excludes only interest on earnest money, security deposits, or amounts payable under the contract. It does not bar pendente lite interest on damages determined in lis. The arbitrators awarded pendente lite interest on damages (Rs. 44,92,800) for the period 26.09.1988 to 22.03.2001. Clause 16(3) is not an express bar to pendente lite; it relates to specific categories of interest and cannot bind the arbitrator in respect of unascertained damages discovered during lis. This position is supported by Irrigation Deptt. v. G.C. Roy, Board of Trustees v. Engineers-De-Space Age, Madnani Construction, Sayeed Ahmed, and Ambica Construction, which collectively establish the arbitrator’s power to award pendente lite interest absent an explicit bar. The High Court’s reasoning on the GCC clause is flawed, and the award should be restored as a permissible exercise of the arbitrator’s discretion.

Contentions of Respondents

Clause 16(3) is an express bar contained in the GCC: no interest will be payable on the earnest money, security deposits, or amounts payable under the contract. Pendente lite interest on damages is not contractually due; it arises from the lis and is not payable under the contract terms. The GCC clauses bind the parties and, by extension, the arbitrator; therefore, the arbitrator could not award pendente lite interest. The High Court’s interpretation was correct in holding that Clause 16(3) barred such interest, and the arbitral award to pay pendente lite interest was improper.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Irrigation Deptt., State of Orissa v. G.C Roy[1991] 3 Suppl. SCR 417; (1992) 1 SCC 508PositiveHeld that arbitrator has the power to award pendente lite interest where there is no express bar.
Board of Trustee for the Port of Calcutta v. Engineers-De-Space Age[1995] 6 Suppl.SCR 327; (1996) 1 SCC 516PositiveFollowed Irrigation Dept; acknowledged arbitrator’s power to award pendente lite.
Madnani Construction Corporation Pvt. Ltd. v. Union of India and Ors.[2009] 16 SCR 216; (2010) 1 SCC 549PositiveAffirmed arbitrator’s power to award pendente lite.
Sayeed Ahmed & Co v. State of Uttar Pradesh and Ors.[2009] 12 SCC 26PositiveCited in context of pendente lite power and related principles.
Superintending Engineer and Ors. v. B. Subba Reddy[1999] 2 SCR 880; (1999) 4 SCC 423PositiveNoted for distinction between pre-reference interest and pendente lite; supports the general proposition that pendente lite can be awarded.
Ambica Construction v. Union of India(2017) 14 SCC 323PositiveHeld that the bar to pendente lite must be explicit; GCC clause did not automatically bar pendente lite; supports arbitrator’s power.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against M/S RAVEECHEE AND CO. v. UNION OF INDIA and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

138 SUPREME COURT REPORTS[2018] 5 S.C.R. 138 [2018] 5 S.C.R. A ## M/S RAVEECHEE AND CO. v. ## UNION OF INDIA (Civil Appeal Nos. 5964-65 of 2018) B ## JULY 03, 2018 ## **[S. A. BOBDE AND L. NAGESWARA RAO, JJ.]** - _Arbitration Act, 1940 – Interest pendente lite – Award of –_ - _Power of the arbitrator – Award of mining contract to appellant – Dispute between parties – Award of interest pendente lite on damages_ - C _excluding the security deposits, from the date of commencement of the arbitral proceedings to the date of award – High Court set aside the award in so far as the order of pendente lite interest – On appeal, held: Liability to pay interest pendente lite arises because the claimant has been found entitled to the damages and has been kept_ - D _out from those dues due to the pendency of the arbitration-pendente lite – Thus, the liability for interest pendente lite does not arise from any term of the contract, or during the terms of the contract, but in the course of determination by the Arbitrators of the losses or damages that are due to the claimant – When a dispute is referred to for adjudication to an arbitrator, a contract clause excluding_ - E _interest upon the earnest money and security deposit, that is binding on the parties cannot be extended to bind an Arbitrator – Arbitrator has power to award interest pendente lite where justified – Thus, judgment of the High Court is set aside – Order of interest pendente lite restored._ ## F **Allowing the appeals, the Court** **HELD: 1.1 The Arbitrators have awarded amounts to the claimant on account of the losses suffered by them for various reasons, mainly due to the ban on mining. These amounts are not awarded on account of any payment due under the contract** G **but are awarded on losses determined in the course of arbitration or the ‘lis’. A claimant becomes entitled to interest not as compensation for any damage done but for being kept out of the money due to him. Obviously, in a case of unascertained damages such as this, the question of interest would arise upon the** H 138 M/S RAVEECHEE AND CO. v. UNION OF INDIA 139 **ascertainment of the damages in the course of the lis. Such** A **damages could attract interest pendente lite for the period from the commencement of the arbitration to the award. Thus, the liability for interest pendente lite does not arise from any term of the contract, or during the terms of the contract, but in the course of determination by the Arbitrators of the losses or damages that** B **are due to the claimant. Specifically, the liability to pay interest pendente lite arises because the claimant has been found entitled to the damages and has been kept out from those dues due to the pendency of the arbitration i.e. pendente lite. [Para 11][143D-G]** **1.2 The Arbitrators rightly awarded interest pendente lite for the period from 26.09.1988 to 23.03.2001 which is the date of the award, on the amounts found due to the claimant. Undoubtedly, such a power must be considered inherent in an Arbitrator who also exercises the power to do equity, unless the agreement expressly bars an Arbitrator from awarding interest pendente lite. An agreement which bars interest is essentially an agreement that the parties will not claim interest on specified amounts. It does not bar an Arbitrator, who is never a party to the agreement from awarding it. The instant case must be decided on the general rule that an arbitrator has the power to award interest unless specifically barred from awarding it; and the bar must be clear and specific. [Para 12][143-H; 144-A-C]** **1.3 When a dispute is referred to for adjudication to an arbitrator, a term of such a nature as contained in the Clause 16(3) of General Clauses Contract, that is binding on the parties cannot be extended to bind an Arbitrator. The Arbitrator has power to award interest pendente lite where justified. Therefore, the judgment of the High Court is set aside and the award passed by the Arbitral Tribunal is restored. [Para 18][146-B]** _Irrigation Deptt., State of Orissa v. G.C Roy_ **[1991] 3 Suppl. SCR 417: (1992) 1 SCC 508;** _Board of Trustee for the Port of Calcutta v_ . _Engineers-De-Space Age_ **[1995] 6 Suppl. SCR 327 : (1996) 1 SCC 516;** _Madnani Construction Corporation Pvt. Ltd. v. Union of India and Ors._ **[2009] 16 SCR 216 : (2010) 1 SCC 549[;]** _Sayeed Ahmed_ & _Co v. State of Uttar Pradesh and Ors._ C D E F G H 140 SUPREME COURT REPORTS [2018] 5 S.C.R. A **[2009] 10 SCR 841: (2009) 12 SCC 26;** _Superintending Engineer and Ors. v. B. Subba Reddy_ **[1999] 2 SCR 880 : (1999) 4 SCC 423;** _Union of India v. Ambica Construction_ **[2016] 2 SCR 810 : (2016) 6 SCC 36;** _Ambica Constructions v. Union of India_ **(2017) 14 SCC 323 - referred to.** B ## **Case Law Reference** C |**[1991]**|**3 Suppl. SCR 417**|**referred to**|**Para 13**| |---|---|---|---| |**[1995]**|**6 Suppl.SCR 327**|**referred to**|**Para 14**| |**[2009]**|**16 SCR 216**|**referred to**|**Para 14**| |**[2009]**|**10 SCR 841**|**referred to**|**Para 15**| |**[1999]**|**2 SCR 880**|**referred to**|**Para 16**| |**(2017)**|**14 SCC 323**|**referred to**|**Para 17**| D CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 5964-5965 of 2018. From the Judgment and Order dated 23.07.2015 and 05.11.2015 of the High Court of Gujarat at Ahmedabad in FA No. 189 of 2005 and Misc. Civil Application No. 3178 of 2015 respectively E K. V. Viswanathan, Sr. Adv., Mohit Paul, Ayush Agrawal, Anugram Niraj Ekka, Vikarant Singh Baloria, Advs. for the Appellant. Vikramjit Banerjee, ASG, A. K. Panda, Sr. Adv., A. K. Srivastav, Ms. Sushma Verma, Ayush Anand, Shubhandu Anand, Raj Bahadur, Bharat Sood, Shreekant N. Terdal, Advs. for the Respondent. F The Judgment of the Court was delivered by **S. A. BOBDE, J.** 1. Leave granted. 2. These Civil Appeals arise out of the final judgment and order of Gujarat High Court dated 23.07.2015 in F.A No 189 of 2005 and the G final judgment and order dated 5.11.2015 in MCA No 3178 of 2015 in F.A No 189 of 2005. The High Court partly allowed the appeal of the Respondent- Union of India and quashed Order of the Arbitrators and set aside the amount awarded by them in respect of Claim No 12. The Arbitrators, under Claim No. 12 awarded interest pendente lite at 12% on the award of Rs. 30 lacs excluding security deposits amounting to H M/S RAVEECHEE AND CO. v. UNION OF INDIA [S. A. BOBDE, J.] 141 Rs. 44,92,800/- per annum from 26.09.1988 to 22.03.2001. Further, the A High Court dismissed the review application filed by the appellant. 3. The appellant – M/s Raveechee and Co. and the respondentUnion of India entered into a contract dated 02.06.1981 for quarrying, stacking and loading stone ballast, broken stone aggregate, rubble etc. from the Western Railway quarry at Udvada at an estimated cost of Rs. 55,81,000/-. Thereafter, disputes arose between the parties due to which the appellant called upon the General Manager, Western Railway to appoint Arbitrators in order to settle the dispute. The Arbitration proceedings commenced on 26.09.1988 and the award was passed on 22.03.2001. 4. The Arbitral Tribunal comprising of Shri N.K. Gupta, Chief Engineer (C&S) and Shri R.K. Sinha, Director, Finance, KRCL, awarded a total of Rs. 76,43,800/- as against the claim of Rs. 1,34,87,044/- raised by the appellant. An award for the Claim Nos. 1-12 raised by the appellant was made. The present dispute relates to the amount awarded under Claim No. 12 i.e. Interest. The Arbitrators awarded the appellant interest pendente lite at 12% on the award for damages excluding security deposits amounting to Rs. 44,92,800/- from 26.09.1988 to 22.03.2001. 5. The appellant thereafter filed a Civil Miscellaneous Application No.22 of 2001 along with the award dated 22.03.2001 in the Civil Court. The award was made a rule of the Court by an order dated 29.07.2004 under Section 17 of the Arbitration Act of 1940 (hereinafter referred to as ‘the Act’) by the Civil Court. The respondent challenged the order of the Civil Court dated 29.07.2004 in appeal. The High Court partly allowed the appeal and set aside the order of Arbitrators qua Claim No.12 under which the Arbitrators had awarded Rs. 44,92,800/- as interest pendente lite. The Arbitrators awarded amounts in favour of the appellant as follows: Claim No.1 – Rs. 12 lacs, Claim No.3 – Rs. 8 lacs and Claim No. 5 – Rs. 10 lacs and interest on the total amount of damages (i.e. Rs. 12 lacs + Rs. 8 lacs + Rs. 10 lacs = Rs. 30 lacs) excluding the amount of security deposits. Thus, interest on Rs. 30 lacs from 26.09.1988 to 23.03.2001 at 12 % amounting to Rs. 44,92,800/-. 6. The appellant, aggrieved by the High Court’s judgment and order dated 23.07.2015 filed a review application before the High Court. The High Court dismissed the review application vide judgment and order dated 05.11.2015. The present SLPs are filed against the High Court judgments and orders dated 23.07.2015 & 05.11.2015 passed by the High Court. B C D E F G H 142 SUPREME COURT REPORTS [2018] 5 S.C.R. A 7. The question that arises for determination before this Court is: Whether Clause 16(3) (reproduced hereafter) of the General Contract Clauses (hereinafter referred to as “GCC”) restricted the power of the arbitrator to award interest pendente lite? 8. In the present case, the Arbitral Tribunal giving effect to the B purport of Clause 16(3) did not award any interest on security deposits. The clause in terms states that no interest will be payable on earnest money, security deposits or on any amounts payable to the contractor under the contract. - The Arbitrators in their award have relied on Clause 16(3) of - C the contract to deny interest on the security deposit. The Arbitrators held that what was intended under Clause 16(3) barred the grant of interest on earnest money, security deposit and amounts payable to the appellant, it does not in any way bar grant of interest pendente lite. 9. Clause 16(1) and 16(3), which are relevant, read as follows: - D _“16(1):- The earnest money deposited by the contractor with his tender will be retained by the Railways as part of security for the due and faithful fulfillment of the contract by the contractor. The balance to make up the security deposit, the rates for which are given below, may be deposited by the_ - E _contractor in cash or in the form of Government Securities or may be recovered by percentage deduction from the contractor’s ‘on account’ bills._ _Provide also that in case of defaulting contractor the Railway may retain any amount due for payment to the contractor on_ F _the pending ‘on account bills’ so that the amounts so retained may not exceed 10% of the total value of the contract._ _“16(3):- No interest will be payable upon the earnest money and the security deposit or amounts payable to the Contractor under the Contract, but Government Securities deposited in_ G _terms of sub clause (1) of this clause will be payable with interest accrued thereon.”_ 10. On behalf of the Union of India, it is contended that the Arbitrators by reason of Clause 16(3) could not have awarded interest H M/S RAVEECHEE AND CO. v. UNION OF INDIA [S. A. BOBDE, J.] 143 pendente lite. This contention is incorrect. _Ex facie_ the clause does not A deal with interest pendente lite. In terms, the clause only bars interest upon earnest money and security deposits or amounts payable to the contractor under the contract. The above mentioned amounts are amounts which in a sense belong to the contractor. They are amounts voluntarily deposited with the other contracting party in order to be refunded or B forfeited depending on performance of the contract. As such they are not amounts of which the contractor is deprived the use of against his wishes, so as to attract interest. It is not the case of the Government before us that interest has been awarded to the contractor under any of the three heads. Neither does any question of interest payable on Government security arise in the present case. The contention put forth by the Government is that the above clause in the agreement bars the Arbitrators from awarding interest pendete lite. On a plain reading we find that there is no such bar. 11. In fact, the Arbitrators have awarded amounts to the claimant on account of the losses suffered by them for various reasons, mainly due to the ban on mining. These amounts are not awarded on account of any payment due under the contract but are awarded on losses determined in the course of arbitration or the ‘lis’. A claimant becomes entitled to interest not as compensation for any damage done but for being kept out of the money due to him. Obviously, in a case of unascertained damages such as this, the question of interest would arise upon the ascertainment of the damages in the course of the lis. Such damages could attract interest pendente lite for the period from the commencement of the arbitration to the award. Thus, the liability for interest pendente lite does not arise from any term of the contract, or during the terms of the contract, but in the course of determination by the Arbitrators of the losses or damages that are due to the claimant. Specifically, the liability to pay interest pendente lite arises because the claimant has been found entitled to the damages and has been kept out from those dues due to the pendency of the arbitration i.e. pendente lite. 12. We are, therefore, of the view that the Arbitrators rightly awarded interest pendente lite for the period from 26.09.1988 to 23.03.2001 which is the date of the award, on the amounts found due to the claimant. Undoubtedly, such a power must be considered inherent in C D E F G H 144 SUPREME COURT REPORTS [2018] 5 S.C.R. - A an Arbitrator who also exercises the power to do equity, unless the agreement expressly bars an Arbitrator from awarding interest pendente lite. An agreement which bars interest is essentially an agreement that the parties will not claim interest on specified amounts. It does not bar an Arbitrator, who is never a party to the agreement from awarding it. B We are not called upon, in this case, to decide whether parties can agree that they will not claim interest pendente lite even in respect of unascertained damages determined in the course of arbitration. The present case must be decided on the general rule that an arbitrator has the power to award interest unless specifically barred from awarding it; and the bar must be clear and specific. C 13. In _Irrigation Deptt., State of Orissa v. G.C Roy[1]_ this Court thoroughly considered the question of power of the arbitrator to award interest pendente lite and held that when the agreement between the parties does not prohibit grant of interest and where the party claims interest and that dispute has been referred to an arbitrator, then the D arbitrator does have the power to award interest pendente lite. 14. Subsequently, this Court in the cases of _Board of Trustee for the Port of Calcutta v_ . _Engineers-De-Space Age[2]_ and _Madnani Construction Corporation Pvt. Ltd. v. Union of India and Ors._[3] held that according to the view taken in the case of Irrigation _Deptt., State_ E _of Orissa_ (supra), the arbitrator does have the power to award interest pendente lite. The Court observed that it essentially depends upon the ouster in each clause, which means that unless there is an express bar that provides that the arbitrator cannot award interest pendente lite, the grant of interest pendente lite will predominantly be based on the arbitrator’s discretion to award the same. F 15. In _Sayeed Ahmed_ & _Co v. State of Uttar Pradesh and Ors._[4] _,_ this Court referred to the decision in _Superintending Engineer and Ors. v. B. Subba Reddy_[5] and observed thus: _“11. Two more decisions dealing with cases arising under the_ G _Arbitration Act, 1940 require to be noticed. In Superintending Engineer v. B. Subba Reddy (1999) 4 SCC 423 this Court_ 1 (1992) 1 SCC 508 2 (1996) 1 SCC 516 3 (2010) 1 SCC 549 4 (2009) 12 SCC 26 H 5 (1999) 4 SCC 423 M/S RAVEECHEE AND CO. v. UNION OF INDIA [S. A. BOBDE, J.] 145 _held that interest for pre-reference period can be awarded_ A _only if there was an agreement to that effect or if it was allowable under the Interest Act, 1978. Therefore, claim for interest for pre-reference period, which is barred as per the agreement or under the Interest Act, 1978 could not be allowed. This Court however held that the Arbitrator can_ B _award interest pendente lite and future interest.”_ 16. A three Judge Bench of this Court in the case of _Union of India v. Ambica Construction_[6] held that the power of an arbitrator to grant pendente lite interest will depend upon several factors such as; phraseology used in the agreement clauses conferring power relating to arbitration, nature of claim and dispute referred to arbitrator, and on what items power to award interest has been taken away and for which period. The Court observed: _“34. Thus our answer to the reference is that if contract expressly bars award of interest pendente lite, the same cannot be awarded by the Arbitrator. And that the bar to award interest on delayed payment by itself will not be readily inferred as express bar to award interest pendente lite by the Arbitral Tribunal, as ouster of power of the arbitrator has to be considered on various relevant aspects referred to in the decisions of this Court , it would be for the Division Bench to consider the case on merits.”_ 17. Further, this Court considered an identical clause in the contract in the case of _Ambica Constructions v. Union of India_[7] , wherein it observed that the Clause of the GCC did not bar the arbitrator from awarding interest pendente lite and affirmed the award passed by the arbitrator. The three Judge Bench of this Court held that the contention raised by the Union of India based on the Clause of the GCC that the arbitrator could not award interest pendente lite was not a valid contention and the arbitrator was completely justified in granting interest pendente lite. C D E F G Relying on the three Judge Bench judgment in _Union of India v. Ambica Construction_ (supra) and in _Irrigation Deptt., State of Orissa_ (supra), this Court held that the bar to award interest on the amounts 6 (2016) 6 SCC 36 7 (2017) 14 SCC 323 H 146 SUPREME COURT REPORTS [2018] 5 S.C.R. - A payable under the contract would not be sufficient to deny the payment of interest pendente lite. 18. Thus when a dispute is referred to for adjudication to an Arbitrator, a term of such a nature as contained in the Clause 16(3) of GCC, that is binding on the parties cannot be extended to bind an B Arbitrator. The Arbitrator has the power to award interest pendente lite where justified. We, therefore, set aside the judgment of the High Court and restore the award passed by the Arbitral Tribunal in respect of Claim No. 12. 19. Appeals are allowed accordingly. C Nidhi Jain Appeals allowed. D E F G H