Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1997Division BenchAppeal disposed of.

M/S. RAAG RANG AND ANR. v. THE GENERAL MANAGER, DELHI TELEPHONES AND ORS.

Case / Petition Number:
Civil Appeal No. 3660 of 1986
Neutral Citation:[1997] 3 S.C.R. 566

Case Synopsis & Summary

Under Civil Appeal No. 3660 of 1986, the appellants challenge a Delhi Telephones bill dispute under the Telegraph Act, 1885, section 11-A. The appellants claim they paid Rs. 5,370.35, plus reconnection charges of Rs. 50, but the threat of disconnection remains. The relevant correspondence includes Annexure-E (paper book, page 36) stating a payment in the first week of May 1979, which the GMT office records do not reflect; further, a letter dated 8.11.85 references a discussion about the dues for telephone No. 386056 and recalls the appellants’ visit to Sh. K.K. Trikha, Area Manager (Central), on 28.8.85 regarding payment. Investigations by the GMT office conclude that payment did not appear in the bonds. The core disputed question is the fact of payment; since the payment status is unresolved, the court cannot satisfactorily decide the dispute. Consequently, it holds that arbitration under Section 11-A of the Telegraphs Act is available to adjudicate the dispute. The appellants may either pay the bill or submit an application to the competent authority for adjudication, and once such an application is made, an appropriate decision may be taken. Until then, the interim stay granted by this Court continues. The appeal is disposed of with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • D.P. Wadhwa
Judgment Date
1997-04-03
Court Decision / Holding
Appeal disposed of. No costs. Interim stay to continue. The appellants shall make payment or file an application under Section 11-A of the Telegraphs Act within 30 days from today; appropriate orders will be made on such application.
Final Disposition
Appeal disposed of.

Parties to the Case

Appellants / Petitioners

  • M/S. RAAG RANG AND ANR.

Respondents

  • The General Manager, Delhi Telephones and Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • Mukul Mudgal

Counsels for Respondents

  • • Ms. Bharati Anand (NP)

Provisions of Law Cited

Telegraph Act, 1885: Section 11-A

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that they had paid Rs. 5,370.35 together with reconnection charges, and that the matter of payment is disputed; they submitted that the court should exercise its arbitration under Section 11-A to determine the dispute, since a factual dispute existed about whether the payment was made.

Contentions of Respondents

The respondents argued payment records do not show the payment; the bill remains due; the court cannot decide the dispute on facts; the remedy lies in Section 11-A arbitration.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•467 words•~3 min read

In The Court Record

M/S. RAAG RANG AND ANR. v. THE GENERAL MANAGER, DELHI TELEPHONES AND ORS.

A _J_ ## M/S. RAAG RANG AND ANR. ## _v._ THE GENERAL MANAGER, DELHI TELEPHONES AND ORS. APRIL 3, 1997 B ## [K. RAMASWAMY AND D.P: WADHWA, JJ.] _Telegraph Act, 1885: Section 11-A._ _Telephone--Payme11t due against-Disputed question off act whether payment has been made or not-Held cowt cannot satisfactorily decide the_ C _dispute--Altemative arbitration under section 11-A of the Telegraphs Act is available for adjudication of the dispute-It is open to the appellants either to make payment of the bill or submit an application to the competent auth01ity to ·adjudicate the dispute and on such application being made appropriate decision would be taken._ D CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3660 of 1986. From the Judgment and Order dated 14.4.86 of the Delhi High Court in C.W.P. No. 750of1986. Mukul Mudgal for the Appellants. Ms. Bharati Anand (NP) for the Respondents. The following Order of the Court was delivered : F The appellants claim that they have paid a sum of Rs. 5,370.35 together with reconnection charges of Rs. 50, nonetheless, there is a thn;at of disconnection to the appellant. In the letter, Annexure-E at page 36 of the paper book, it is stated as under : "Please refer to this letter of even No. dated 8.11.85 regarding payment of telephone dues pertaining to telephone No. 386056. G You may please recall your visit to Sh. K.K. Trikha Area Manager (Central) on 28.8.85 in connection with payment of the dues against telephone No. 386056. During the discussion you have H 565 [1997] 3 S.C.R. SUPREME COURT REPORTS 566 ## A intimated that the payment of the said bills were made in the 1st week of May, 79. Investigations have been made by GMT office and records have been thoroughly checked. Payment of bills in question detailed below do not appear in the bonds of GMT office. B You are therefore again requested to arrange payment of the following bills and furnish payment particulars within 10 days from the date of issue of this letter;" In view of this letter, the primary disputed question is of fact, viz., whether or not payment has been made. Under these circumstances, we C cannot satisfactorily decide the dispute. Alternative arbitration under Section 11-A of the Telegraphs Act is available for adjudication of the dispute. It is open to the appellants either to make payment of the bill or submit an application to the competent authority to adjudicate the dispute and on such application being mode appropriate decision would be taken. Until then, the interim stay granted by this Court would continue. The appellants D shall make payment of an application, as the case may be, within 30 days from today, subject to such objections that may be raised. The appeal is accordingly disposed of. No costs. T.N.A. Appeal disposed of.
End of Judgment Record
Browse All Supreme Court of India (1997) Decisions
1997-12-17

Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.

This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.

1997-11-18

National Insurance Co. Ltd. v. Santro Devi and Ors.

National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.

1997-02-03

JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.

This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.

1997-07-07

Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.

Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.