M/S. ORIENTAL STRUCTURAL ENGINEERS PVT. LTD. v. STATE OF KERALA

Case / Petition Number:
Arb. Appeal No. 32 of 2007
Neutral Citation::null

Case Synopsis & Summary

The Kerala High Court, in Arb. Appeal No. 32 of 2007, reviews disputes arising from a highway upgradation contract between Oriental Structural Engineers Pvt. Ltd. (contractor/applicant) and the State of Kerala (employer/respondent). The dispute centers on three claims arising from the arbitral award under the Arbitration Agreement and GCC: (i) payment of interest on overdue sums, (ii) reimbursement of land-cost incurred for Engineers’ office accommodation, and (iii) Excise Duty exemption certificates for project materials (HSD, lubricants, tyres, etc.). The Arbitral Tribunal, in a majority award, allowed all three claims. The DRB had previously recommended resolution, and the State challenged the award before the Court below. The State argued that the Appendix to Bid disclosed interest rates only for foreign currency (LIBOR + 2%), leaving local-currency rates blank, implying no grant of interest for the local currency; and that the Excise Duty exemption depended on a Government notification, not on a contractual right. The Court discussed reliance on Oil & Natural Gas Corp. v. Saw Pipes (AIR 2003 SC 2629) to justify interference under Section 34 of the Arbitration Act and distinguished Secretary, Irrigation Dept. v. G.C. Roy (1992) on pendente lite interest. Ultimately, it held that the arbitral award on interest in local currency and on exemption certificates contradicted the contract terms, allowed interference, and dismissed the appeal, while upholding the land-cost aspect. The result preserves the arbitral award only on the land-cost claim and reverses the others.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • P. R. Raman
  • P. R. Ramachandra Menon
Judgment Date
2009-09-17
Court Decision / Holding
Appeal dismissed; no relief to the appellant on the disputed interest (local currency) and Excise Duty exemption claims; the award on land-cost for Engineer’s office remains unaffected.
Final Disposition
Appeal dismissed

Parties to the Case

Appellants / Petitioners

  • M/S. ORIENTAL STRUCTURAL ENGINEERS PVT. LTD.

Respondents

  • State of Kerala, represented by Chief Engineer, Projects, KSTP-III, PWD, Thiruvananthapuram-2

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. K.L. Varghese
  • • Smt. Santha Varghese

Counsels for Respondents

  • • Government Pleader Adv. Mr. K.V. Manoj Kumar

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 19Arbitration and Conciliation Act, 1996 - Section 34

Legal Doctrines & Maxims

  • Pendente lite (doctrine related to arbitration awards on interest)
  • Waiver by conduct

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the rate of interest for the local currency portion (76%) was to be determined as per the Appendix to Bid; the blank in the local-currency column does not amount to waiver and cannot override the express contractual provision that interest is payable at the rate stated in the Appendix. Ext. R1 (14.07.2004) allegedly shows no obligation to pay interest, and Ext. C72 (3.08.2004) is claimed as a ‘gesture of goodwill’ rather than a waiver; coercion of Ext. R1 is not proven. The DRB recommendation and the Arbitral Award on the Excise Duty exemption are argued to be not contractual rights and not anchored in the contract terms; the 1995 notification cannot create a binding contractual entitlement to exemption. The appellant urges that the arbitration award remain in force only to the extent of the land-cost claim and that interference with the other two claims was proper under Section 34.

Contentions of Respondents

The respondent State contends that the contract and COPA terms require interest to be paid strictly at the rate stated in the Appendix to Bid, with foreign currency details specified and local-currency rates effectively implied to be governed by the blank column; thus the local-currency interest claim is unsupported. The Excise Duty exemption certificate claim is not part of the contract and the 1995 notification cannot create a contractual entitlement; absence of a clause in the contract to issue such certificates justifies the lower court’s decision. The Arbitral Tribunal’s award, being inconsistent with the contract, is subject to interference under Section 34; reliance on Roy is misplaced since the contract here contains explicit terms. The DRB recommendation cannot override express contractual terms, and the appeal should be dismissed with the award’s land-cost aspect surviving.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd.AIR 2003 SC 2629PositiveCited to justify the power of the court under Section 34 to interfere with an arbitral award when it contravenes substantive law or the contract terms.
Secretary, Irrigation Department, Government of Orissa and others v. G.C. Roy1992 (1) SCC 508DistinguishedCited and distinguished; used to argue that Roy’s reasoning on pendente lite interest does not apply due to contract-specific terms in the instant case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,910 words•~18 min read

In The Court Record

M/S. ORIENTAL STRUCTURAL ENGINEERS PVT. LTD. v. STATE OF KERALA

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE P.R. RAMAN & THE HONOURABLE MR. JUSTICE P.R. RAMACHANDRA MENON THURSDAY, THE 17TH SEPTEMBER 2009 / 26TH BHADRA 1931 **Arb.Appeal .No. 32 of 2007** **----------------------** OPARB.291/2005 of VI ADDL.DISTRICT COURT, ERNAKULAM .................... ## APPELLANT/RESPONDENT/CLAIMANT/CONTRACTOR: ---------------------------------------------------------- M/S. ORIENTAL STRUCTURAL ENGINEERS PVT. LTD., 21, COMMERCIAL COMPLEX, MALCHA MARG DIPLOMATIC ENCLAVE, NEW DELHI-110 021 (THRIKALATHOOR P.O., THRIKALATHOOR-683 557, MUVATTUPUZHA). BY ADV. SRI.K.L.VARGHESE SMT.SANTHA VARGHESE ## RESPONDENT/PETITIONER/RESPONDENT/EMPLOYER: ----------------------------------------------------------- STATE OF KERALA, REPRESENTED BY CHIEF ENGINEER, PROJECTS,KSTP-III, PWD, THIRUVANANTHAPURAM-2. BY GOVERNMENT PLEADER ADV. MR. K.V. MANOJ KUMAR. THIS ARBITRATION APPEAL HAVING BEEN FINALLY HEARD ON 17/09/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## **P.R. RAMAN & P.R. RAMACHANDRA MENON, JJ.** ........................................................................ **ARBITRATION APPEAL NO. 32 OF 2007** ......................................................................... Dated this the 17[th] September, 2009 ## **J U D G M E N T** ## Ramachandra Menon, J: Whether the rights and liabilities arising out of a contract are to be adjudged on the basis of the express terms of the contract as pursued by the court below or on the basis of the deemed circumstances as pursued by the Arbitral Tribunal, is the crucial issue involved herein. Reliance is also placed by either side, on the decision rendered by the Apex Court in _**Oil**_ ## _**& Natural Gas Corporation Ltd. vs. SAW Pipes Ltd.**_ **[AIR 2003 SC 2629].** 2. With regard to the sequence of events, the appellant was awarded the work of upgradation of the State Highway from Muvattupuzha-Thodupuzha and Muvattupuzha-Angamali. After completing all the formalities, the work was being pursued. During the course of execution of the work, disputes arose between the parties; which, by virtue of clause 67.4 of the General conditions of Contract (GCC) forming part of the Arbitration Agreement, had to be settled in Arbitration. The appellant raised three claims viz., **2** ## **ARBITRATION APPEAL NO. 32 OF 2007** (i) payment of interest at the prevailing market rates upon unpaid sums/belated payments (ii) Payment of cost of land purchased for Engineers’ office accommodation and transferred to the respondent by regd: conveyance and (iii) issuance of Excise Duty exemption certificates for HSD (High speed Diesel), Lubricants, Tyres etc. and for reimbursement for non-issuance of such certificates. 3. With regard to the 1[st] claim, as per the terms of the contract, the payment had to be effected in the course of execution of the work on the basis of the IPC (Interim Payment Certificate) within 42 days of preferring the claim. It was stipulated in the terms of the agreement that, _in the event of failure of the employer to make payment within the time stated, the employer shall pay to the contractor interest compounded monthly at the rates stated in 'Appendix to Bid' upon sums unpaid from the date upon which the same should have been paid, in the currencies in which the payments are due._ It was also stipulated in the agreement that the payments to an extent of 24% had to be effected in 'Foreign currency' and 76% in 'Local currency'. The said claim, more particularly involving ‘Local currency’ was resisted **3** ## **ARBITRATION APPEAL NO. 32 OF 2007** from the part of the respondent/State, stating that no rate was shown in the ‘Appendix to Bid’ and as such, by virtue of the specific clause and the “instructions to the bidders” issued in this regard, no interest was liable to be paid under any circumstances. “Appendix to Bid” (a copy of which was placed before this Court for perusal) shows that in respect of Column with regard to the payment of ‘Foreign currency’, the rate of interest was quoted as _“LIBOR ” (London Inter Bank on lending Rate)+ 2% ,_ whereas in respect of Column for the ‘Local currency’, the rate was left blank. The case of the appellant is that it was only an omission, intending to have it claimed later in the due course and that it could never be deemed as waived. 4. The second claim was in respect of non-payment of cost of the land procured by the appellant for providing office accommodation to the Engineers in connection with the work. However, in view of subsequent turn of events, answering the said issue in favour of the appellant and further since no challenge has been raised by the respondent/State in respect of the finding rendered by the Arbitral Tribunal, it has become final and this issue does not form the subject matter of the present Appeal. 5. The third claim put up by the appellant was that, by virtue **ARBITRATION APPEAL NO. 32 OF 2007** **4** of the notification bearing No. 108/95-CE dated 28.08.1995, the appellant was entitled for the benefit of exemption from Excise Duty in respect of the “goods required for the project” and that denial of issuance of necessary certificate in respect of HSD, Lubricants, Tyres etc., that too, after allowing the claim for exemption in respect of Cement, Steel, Bitumen etc, has resulted in much loss and hardships; which in turn was sought to be compensated by way of reimbursement. 6. Since the claims put up by the appellant were not positively considered, the matter was taken up before the ‘Dispute Review Board’ (DRB) for the first time, as provided in the Arbitration Agreement. It is the case of the appellant that, though the DRB had made necessary recommendation on 02.04.2004, the same was not complied with, from the part of the respondent, which led to arbitration before the Arbitral Tribunal consisting of three members. The Arbitral Tribunal passed an award in favour of the appellant by a majority decision allowing all the three claims; aggrieved of which, the respondent/State preferred the O.P. (Arbitration) before the Court below. After appreciating the facts and circumstances, the 'second claim' with regard to the cost/ compensation for the land was sustained by the Arbitration Court, **5** ## **ARBITRATION APPEAL NO. 32 OF 2007** whereas the findings and reasoning given by the Arbitral Tribunal on the 'first' and 'third' claims were set aside, which has led to the present Appeal. 7. With regard to the 'first claim', on interest, the contention put forth by the appellant is mainly that non-showing of rate of interest in the 'Appendix to Bid' is not fatal, so as to deny the claim. Reliance is placed on the decision rendered by the Apex Court in _**Secretary, Irrigation Department, Government of Orissa and others Vs. G.C. Roy [1992 (1) SCC 508 (at 532)]**_ as well. The said contention is sought to be resisted from the part of the respondent stating that the terms of the Bid are very much clear as specified under clause 60.8(b) of the Conditions of Particular Application (COPA in short), which, as extracted in paragraph 13 of the impugned order, reads as follows: _“In the event of the failure of the employer to make payment within the times stated, the Employer shall pay to the contractor interest compounded monthly at the rate (s) stated in the Appendix to Bid upon on sums unpaid from the date upon which the same should have been paid in the currencies in which the payments are due. The provisions of this Subclause are without prejudice to the contractor's_ **ARBITRATION APPEAL NO. 32 OF 2007** **6** ## _entitlement under Clause 69 or otherwise”._ Referring to the factual position, it has been held by the Court below in paragraph 15 that in the 'Appendix to Bid', in respect of the rate of interest upon unpaid sum in ‘Foreign currency’ as well as in ‘Local currency’, the rate of interest was shown only in respect of ‘Foreign currency’ (24% of the due amount); whereas in the case of ‘Local currency’, it was left blank. In the said circumstances, the Court below observed that there was a conscious decision on the part of the appellant, while submitting the tender, that the party did not intend to claim any interest in respect of the ‘Local currency’ (76% of the due amount). Reference is also made to Ext. R1 letter issued by the appellant confirming that there was no provision for interest on delayed payment and that the appellant would not claim any interest in future. That apart, the appellant had also issued Ext. C72, stating that their commitment for not to claim any interest on the said ‘ ’ amount was to be treated as purely a gesture of goodwill . Accordingly, a finding was rendered by the Court below that the party had chosen to waive the claim for interest in respect of the due amount to be paid in ‘Local currency’, even though the **ARBITRATION APPEAL NO. 32 OF 2007** **7** agreement provided for interest on belated payment. 8. The appellant has got a case that Ext. R1 was got executed under coercion. The learned Counsel for the appellant also submits that the contents of Ext.C72 are very much qualified, by referring to the particular payment effected under Ext.R1 and that it cannot be taken to connect with the further/subsequent payments. After considering the facts and figures, the Court below held that absolutely no evidence was adduced to substantiate the factum of coercion, particularly when the burden was on the shoulders of the party who raised the said contention. It is also observed in paragraph 15 of the impugned verdict that Ext. R1 is dated 14.07.2004 and it was thereafter that, the claimant issued Ext. C72 which is dated 3.08.2004; wherein there is no retraction of Ext. R1 or as to any element of coercion. It was accordingly, that the Court below arrived at a finding in the succeeding paragraph that the said document was executed on ‘free will’ and that the bidder was very much liable to fill up the rate of interest in the place provided in the ‘Appendix to Bid’ and having not chosen to do so, it had to be presumed that the party had chosen to waive the same. The reference made by the appellant to Section 19 of the Arbitration and Conciliation Act, 1996 to contend that the **ARBITRATION APPEAL NO. 32 OF 2007** **8** Arbitral Tribunal is not bound by the CPC or the Evidence Act is rather wrong and misconceived. True, the mandate under Section 19 is very clear. But it doesn’t mean that the Arbitral Tribunal can resort to any arbitrary exercise or arrive at a finding on astrological assumptions; which otherwise will be wrong and perverse in all respects. 9. The explanation offered from the part of the appellant, that non showing of the rate of interest in respect of ‘Local currency’ was to have it claimed in the due course, does not appear to be palatable to this Court; more so, when the liability to pay interest was undertaken at the rate to be shown in the ‘Appendix to Bid’ and further when the appellant, with proper application of mind, had shown the rate in the relevant column only in respect of the 'Foreign currency'. It is probable, that the work was awarded to the appellant, also taking note of the fact that the bidder had chosen to waive the right to claim interest for belated payment in respect of the ‘Local currency’, which actually constituted the Lion’s share (76%). It is also possible that some other bidders would have been there, who might have quoted appropriate rate of interest in respect of ‘Local currency’, while **9** ## **ARBITRATION APPEAL NO. 32 OF 2007** leaving the column blank with regard to ‘Foreign currency’, or sometimes, there might be some bidders who would have quoted a very lower rate in toto. After considering the relevant aspects, the work was awarded in favour of the appellant, presumably also for the reason that the appellant’s, bid was a better deal, having left the column blank with respect to the rate of interest for belated ‘ ’ payment upon the unpaid sum involving Local currency . 10. The reliance placed by the appellant on the decision rendered by the Hon'ble Supreme Court in _**Secretary, Irrigation**_ ## _**Department, Government of Orissa and others Vs. G.C. Roy**_ _**[1992 (1) SCC 508]**_ as to the power of the Arbitrator to award interest does not support the case of the appellant in any manner. In the said case, the issue considered was, whether the Arbitrator was having power to award interest 'pendente lite', when the Arbitration Agreement did not contain any such clause. Observing that the Arbitration Agreement did not contain any clause prohibiting payment of interest and that there was nothing contrary to the intention of the parties, the Apex Court held that in the absence of any clause for interest, the Arbitrator was very well within his jurisdiction and competence in awarding interest 'pendente lite'. Unlike this, in the instant case, as already **ARBITRATION APPEAL NO. 32 OF 2007** ## **10** mentioned hereinbefore, there is a provision in the Arbitration Agreement to pay interest in a specific/prescribed manner, making it clear that it shall be at the rate as shown by the bidder in the 'Appendix to bid'. Since the appellant/bidder chose to quote the rate of interest only in respect of the amount payable in 'Foreign currency' (24%), while leaving out the Column blank in respect of the rate of interest with regard to the quantum payable in 'Local currency' (76%); the parties are very much governed by the above specific terms of the contract. In the said circumstances, we are not satisfied with the case put forth by the appellant with regard to claim No.1, and the appellant is not expected to take a 'U' turn, after winning the bid. The finding and reasoning given by the Court below are very much proper and no interference is called for. 11. With regard to the remaining claim, i.e., regarding the benefit of exemption from Excise Duty by issuing necessary certificate, it has been held by the Court below in paragraph No.24 as follows; _“Admittedly, there is no term or provision in the_ _contract for issue of Excise Duty Exemption Certificate as per this notification. Counsel appearing for respondents has not brought to_ ## **ARBITRATION APPEAL NO. 32 OF 2007** ## **11** _my notice any such provision in the contract or usage of trade to issue Excise Duty Exemption Certificate as claimed. The conditions for issue of Excise Duty Exemption Certificate as stated in the notification in Ext.C41 are not complied with.”_ The learned Counsel for the appellant submits that the right to have the said benefit arises from the notification dated 28.08.1995, which was marked before the Arbitral Tribunal as Ext.C41. It is the case of the respondent that the necessity or occasion for issuance of any such certificate on the basis of the 'notification' does not spring out from the terms of the contract and as such, there could not have been any such recommendation or direction, as given by the DRB (Dispute Review Board) or the Arbitral Tribunal, which hence was rightly intercepted by the Court below. 12. The case projected by the appellant in the appeal appears to be more based on the fact that the respondent has already issued necessary certificates in respect of Cement, Steel, Bitumen etc., whereas no such certificate has been chosen to be issued with respect to HSD, Lubricants and Tyres, which are also stated as very much ‘required for the project’. The learned counsel for the appellant submits that the words used in the notification do **ARBITRATION APPEAL NO. 32 OF 2007** ## **12** not mean that the materials should have been actually consumed and that the exemption is meant in respect of the goods which were actually ‘required for the project’ and hence that, on liberal interpretation, HSD, Lubricants, Tyres etc also would fall within the purview of the notification. 13. Obviously, the above notification was issued in the year 1995 and is not with respect to the project in hand, though it may be applicable to other cases as well. The procedure for issuance of the relevant certificates is prescribed in the notification itself; which stipulates that the manufacturer has to comply with the requirements as specified therein and necessary certificate has to be produced before clearance of such goods. Of course, duty is cast upon the State Government, if such project has been approved for implementation by the State Government and on such an event, it has to be certified by the Principal Secretary or Secretary (Finance), as the case may be, in the concerned State, by stating that the said goods are required for execution of the project. But issuance of certificate stands entirely on a different pedestal and while issuing such certificate, the State Government has to act in a different capacity. 14. In the instant case, after considering the actual nature, **ARBITRATION APPEAL NO. 32 OF 2007** ## **13** scope and requirement of the project, the State Government has issued necessary certificates in respect of Cement, Steel, Bitumen etc., while declining to issue such certificate in respect of HSD, Lubricants and Tyres. If the appellant is aggrieved of the same, the remedy is stated as elsewhere; mainly for the reason that it does not form part of the contract. It has been observed by the Court below that there is no provision in the contract with reference to the said notification or as to the liability of the respondent in this regard; thus leading to the inference which is impugned in this appeal. 15. Absolutely, no material has been produced from the part of the appellant to show that the observation made by the Court below that there is no clause in the Agreement with regard to the liability to issue any such certificate for exemption is wrong or perverse. No reference is made to any of the terms of the contract, but for placing reliance solely on the ‘notification’ and the instance of issuing such certificates in respect of Cement, Steel and Bitumen. This shows that the finding and reasoning given by the Court below as to the absence of such clause in the contract stand fortified and in the absence of any specific term in the contract, no benefit could have been extended by the Arbitral Tribunal, directing **14** ## **ARBITRATION APPEAL NO. 32 OF 2007** the respondent to reimburse the amount in respect of the Excise Duty, which otherwise could have been covered by such certificates. The finding and reasoning given by the Court below are perfectly within the four walls of law and are not assailable under any circumstances. 16. In the course of arguments, the learned Counsel for the appellant, referring to the mandate under clause 67.1 of ‘COPA’ submits that the recommendation of the DRB was effected on 02.04.2004 and that, since the respondent did not convey their dissatisfaction with the recommendation stating that they were to pursue further remedy by way of ‘arbitration’ within the stipulated time of ‘14 days’; it had become final on 16.04.2004. The learned Counsel further submits that this issue was specifically raised before the Arbitral Tribunal and was dealt with in paragraph No. 3.1 of the Arbitral Award. However, the same is stated as not considered by the Court below, while passing the impugned Order. The relevant portion of clause 67.1 of ‘COPA’ reads as follows: “ _If the Board has issued a Recommendation to the Employer and the Contractor within the said 56 days and no_ ## **ARBITRATION APPEAL NO. 32 OF 2007** ## **15** _notice of intention to commence arbitration as to such dispute has been given by either the Employer or the Contractor within 14 days after the parties received such Recommendation from the Board, the Recommendation shall become final and binding upon the Employer and the Contractor._ _Whether or not it has become final and binding upon the Employer and the Contractor, a Recommendation shall be admissible as evidence in any subsequent dispute resolution procedure including any arbitration or litigation having any relation_ _to the dispute to which the Recommendation relates._ _All Recommendations which have become final and binding shall be implemented by the parties forthwith such implementation to include any relevant action of the Engineer.”_ As per the above clause, the crucial date is not the date of recommendation, but the date of receipt of such recommendation from the Board. The contention of the appellant was only that the **ARBITRATION APPEAL NO. 32 OF 2007** **16** matter had become final on 16.04.2004, since the date of recommendation of DRB was 02.04.2004. Absolutely no case was pleaded to the effect that the recommendation was conveyed to the Government on a ‘particular date’ and that the intention of the Government was not communicated, despite the expiry of 14 days from the date of receipt of such recommendation. It is also brought to light from paragraph No.3.1 of the Arbitral Award that the DRB in their meeting on 12.06.2004 recorded that the recommendation of the DRB had been submitted by the Engineer to the Government for acceptance. Obviously, in the absence of any specific plea, as to the date of receipt of the recommendation by the Government and the expiry of the prescribed time, the Arbitral Tribunal could not have considered the same and for this reason, there is no finding in this regard as well. This being the position, the contention of the appellant that the matter has already become final, since the respondent had not acted in tune with the stipulation in clause 67.1 of ‘COPA’, does not hold any water at all. It is also relevant to note that the award was passed by the Arbitral Tribunal ‘on majority’ and the dissenting member has given sufficient and proper reasons with regard to the various aspects on which the dissent was recorded; which appears to be **ARBITRATION APPEAL NO. 32 OF 2007** **17** correct and sustainable. 17. The only remaining question to be answered is whether the Arbitration Court was justified in having interfered with the finding of the Arbitrary Tribunal in respect of the claims No.1 and 3 (interest and Excise Duty exemption) invoking the power under Section 34 of the Arbitration and Conciliation Act, 1996. The law has been laid down by the Apex Court in crystal clear terms in the decision in _**ONGC Ltd., Saw Pipes Ltd**_ . ([2003] 5 SCC 705 = [AIR 2003 SC 2629],. It has been held that if the award is contrary to the substantive provisions of law or against the terms of the contract which would be patently illegal, it could be interfered with under Section 34 of the Act. Viewed in the above background, the award passed by the Arbitrary Tribunal directing to pay interest in respect of the belated payments/unpaid amounts involving local currency as well as the direction to reimburse the amount because of non-issuance of exemption certificate pertaining to Excise Duty in respect of HSD, Lubricants and Tyres placing reliance on the relevant notifications issued by the Government of India in this regard were rather contrary to the specific terms of the contract and beyond the scope of arbitration. This being the position, interference made by the Court below rejecting the claims in this ## **ARBITRATION APPEAL NO. 32 OF 2007** ## **18** regard is perfectly in order and it is very much within the four walls of the law. In the above facts and circumstances, the matter requires no interference. The appeal fails and it is dismissed accordingly. **P.R. RAMAN, JUDGE** **P.R. RAMACHANDRA MENON, JUDGE.** lk
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.