M/s. Oriental Structural Engineers Pvt. Ltd. v. State of Kerala

Case / Petition Number:
Civil Appeal No. 3454 of 2011

Case Synopsis & Summary

This Civil Appeal arose from disputes over payment under a contract for upgrading two stretches of the Kerala State highway. The agreement provided for interim and final payments with interest on delayed sums and contemplated payments in both foreign and local currencies. A Disputes Review Board gave a majority award directing interest on the local-currency component for delayed payments; one member dissented. The State of Kerala challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, and the Arbitration Court and Kerala High Court set aside or limited the award on the ground that the contract’s appendix to bid left the local-currency rate blank, effectively reading as “zero” interest and, alternatively, that the claim had been waived by communications from the claimants. The Supreme Court, in a Division Bench, allowed the appeal in part, holding that omission to fill the blank did not negate the contractual right to interest and that the interest provision was within the contract’s terms. While affirming the Tribunal’s entitlement to interest, it fixed the rate at 8% simple per annum for the local-currency component, holding the prior rate (1% per month with further charges) excessive. The decision also clarifies the law on patent illegality, waiver, and the correct application of contract terms in arbitration under the 1996 Act.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Aniruddha Bose
  • Surya Kant
Judgment Date
2021-04-22
Court Decision / Holding
The appeal is allowed in the above terms.
Final Disposition
Appeal allowed in part; Tribunal’s award directing interest on the local currency component remains but the rate is fixed at 8% simple interest per annum; other aspects of the Kerala High Court’s decision are not restored; no costs.

Parties to the Case

Appellants / Petitioners

  • M/s. Oriental Structural Engineers Pvt. Ltd.

Respondents

  • State of Kerala

Provisions of Law Cited

Arbitration and Conciliation Act, 1996Section 34, Arbitration and Conciliation Act, 1996Section 31(7)(a), Arbitration and Conciliation Act, 1996Section 28(3), Arbitration Act (as referenced under 1996 Act)Arbitration Act, 1940

Legal Doctrines & Maxims

  • Patent illegality doctrine (as refined under Saw Pipes)
  • Public Policy test for arbitral awards
  • Right to compensation for deprivation of use of money (interest) – GC Roy principle
  • Arbitrator to decide in accordance with the terms of the contract (28(3)) and not rewrite the contract
  • Interest as a compensatory measure rather than merely punitive
  • Waiver concepts in contract and their limits
  • Active exclusion or nullification cannot be inferred from silence in contract terms

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the contract itself provided for interest on delayed payments under Clause 60.8 and within the Appendix to Bid; their claim for interest on the local-currency component was thus contractual and not waived by the two communications dated 14 July 2004 and 3 August 2004, which pertained to IPC‑1 and were limited in scope. The blank space in the Appendix to Bid could not be read as an express cancellation of the right to interest; waiver, if any, must be intentional and unequivocal. The Tribunal’s majority award was within the contract’s terms and was based on the principle from GC Roy that deprivation of the use of money entitles compensation; the High Court’s contrary view rewrote the contract. While the rate of interest could be fixed by reference to market standards, the rate used (1% per month with other charges) was excessive and should be set at 8% simple interest per annum as a just and equitable rate consistent with the contract and relevant precedents (e.g., Bright Power, Saw Pipes). The Court should not adopt a strict zero-interest reading merely because the Appendix to Bid was left blank, as this would undermine the contract’s clear inclusion of an interest provision.

Contentions of Respondents

The respondents argued that the local-currency interest clause was effectively negated by the blank space in the Appendix to Bid, which they contended created a term that there would be no interest on delayed payments in local currency. They asserted waiver, evidenced by two letters from the appellants, restricting or relinquishing any claim for interest, and argued that the contract must be interpreted in light of these communications. Relying on the Saw Pipes standard for patent illegality and public policy, they contended that the Tribunal exceeded its remit by imposing an interest regime not clearly specified in the contract, and that the High Court correctly set aside the award. They further asserted that the rate of interest should be limited by the contract’s terms, and that the Tribunal’s 8% rate was unjustified beyond what the contract provides, particularly since the 60.8 clause lacks a fixed rate for local-currency payments. They invoked the 1940 Act precedents and urged a conservative approach to awarding interest under Section 34.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Secretary, Irrigation Department, Government of Orissa & Ors. v. G.C. Roy(1992) 1 SCC 508PositiveCited to support the principle that deprivation of use of money warrants compensation and to frame the patent illegality/public policy inquiry.
Oil Natural Gas Corp. Ltd. v. Saw Pipes Ltd.(2003) 5 SCC 705PositiveUsed as the guiding authority for patent illegality and the public-policy framework governing arbitral awards.
Associate Builders v. Delhi Development Authority(2015) 3 SCC 49PositiveCited for the interpretation that arbitral awards must be consistent with the contract terms (Section 28(3) discussion) and not contravene the contract.
Reliance Cellulose Products Ltd. v. ONGC Ltd.(2018) 9 SCC 266DistinguishedDistinguished on the ground that it involved a different Act (Arbitration Act, 1940) and different contexts (pendente lite) than the 1996 Act scenario here.
Union of India v. Bright Power Projects (India) (P) Ltd.(2015) 9 SCC 695PositiveCited to affirm that, unless agreed otherwise, an arbitral tribunal may award interest at a reasonable rate from the date of the cause of action to the date of award.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,563 words•~21 min read

In The Court Record

M/s. Oriental Structural Engineers Pvt. Ltd. v. State of Kerala

## **REPORTABLE** IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ## **CIVIL APPEAL NO. 3454 OF 2011** ## **M/s. Oriental Structural Engineers Pvt. Ltd. ...Appellant(s)** ## **Versus** ## **State of Kerala** ## **…Respondent(s)** ## **J U D G M E N T** ## **ANIRUDDHA BOSE, J.** The appellants were awarded a contract by the State of Kerala for upgradation of a State Highway for two stretches, from Muvattupuzha­Thodupuzha and Muvattupuzha–Angamaly. The agreement in this regard was executed on 7[th] November, 2002. This appeal originates from disputes on certain issues arising between the parties primarily relating to making payment to the appellants under certain heads. In the present proceeding, Signature Not Verified however, the only point of dispute on which arguments have been Digitally signed by DEEPAK SINGH Date: 2021.04.22 18:26:01 IST Reason: advanced before us is over entitlement of the appellants to receive interest on delayed payment on the subject­heads, which were to 1 be paid by the employer in local currency as per the stipulations in the said agreement. The agreement had provision for resolution of disputes by a Disputes Review Board (DRB) which was to make recommendations at the first instance. If the recommendations were not acceptable to any of the parties, such disagreeing party was required to give notice to commence arbitration within a specified time and thereafter the dispute was to be settled through arbitration. So far as the controversies out of which this appeal arises are concerned, disputes on three counts arose between the parties, which could not be resolved at the stage of DRB recommendations. Those disputes were referred to a three­ member Arbitral Tribunal (the ‘Tribunal’ in short). We have already referred to the scope of controversy involved in this appeal. This controversy shall be henceforth referred to in this judgment as dispute on delayed payment. We shall address that issue only in this judgment. **2.** The Tribunal passed the award in favour of the appellants on this point and interest was directed to be paid on delayed payment in relation to local currency component payable under the agreement. This was, however, a majority award and not a unanimous one as one of the members of the Tribunal gave a 2 dissenting view. In the succeeding paragraphs of this judgment, whenever we refer to the expression ‘award’, it shall mean the majority award only. The award of the Tribunal was assailed by the State of Kerala before the District Court at Ernakulam (the Arbitration Court) by taking out an application under Section 34 of the Arbitration and Conciliation Act, 1996 (the1996 Act). This application was allowed in part. Award of the Tribunal in favour of the appellants on the point of interest on delayed payment was set aside. The Arbitration Court also adjudicated upon two other points, but as these points have not been urged before us, we do not consider it necessary to deal with them here in this judgment. The decision of the Arbitration Court was sustained in appeal by a Division Bench of the Kerala High Court. This appeal is against the said Bench decision of the High Court delivered on 17[th] September, 2009. The appellants want the award of the Tribunal allowing their claim for interest on delayed payment to be restored. **3.** Entitlement of the contractor to interest was provided for in sub­clause 60.8 of the agreement on delayed interim payment. This clause has been reproduced in page 38 of the paperbook and reads:­ 3 - “ Time of Payment and Interest - (a) The amount due to the Contractor under any Interim Payment Certificate issued by the Engineer pursuant to this Clause or to any other term of the Contract shall subject to Clauses be paid by the Employer to the Contractor as follows. (i) (A) In the case of Interim Payment Certificates within 42 days after the Contractor’s monthly statement has been submitted to the Engineer for certification pursuant to sub­clause 60.1. Provided that if the Engineer’s Interim Certificate has not yet been issued within said 42 days, the Employer shall pay the amount shown in the Contractor’s monthly statement and that any discrepancy shall be added to or deducted from the next payment to the Contractor and (B) in the case of any monthly statement submitted by the Contractor at a time when the Bank’s loan or credit (from which part of the payment to the Contractor are being made) is suspended within 14 days after such monthly statement is submitted. Provided that if the Engineer’s Interim Certificate has not yet been issued within said 14 days the Employer shall pay the amount shown in the Contractor’s monthly statement and that any discrepancy shall be added to or deducted from the next payment to the Contractor. (ii) (A) In the case of the Final Payment Certificate pursuant to Sub­clause 60.13 within 84 days after the Final statement and written discharge have been submitted to the Engineer for certification and (B) In the case of the Final Statement submitted by the Contractor at a time when the Bank’s loan or credit from which part of the payments to the Contractor are being made is suspended or for which payment under (ii) (A) becomes due after 63 days of the date of notification of the suspension notice payment will be made within 63 days after the date of notification of the suspension pursuant to Sub Clause 69.6(d) provided that if the Engineer’s Final Payment Certificate has not been issued within 4 the said 63 days, the Employer shall pay the undisputed amounts shown in the Final Statement. (b) In the event of the failure of the Employer to make payments within the time stated the Employer shall pay to the Contractor interest compounded monthly at the rate(s) stated in the Appendix to Bid upon all sums unpaid from the date upon which the same should have been paid in the currencies in which the payment are due. The provisions of the Sub Clause are without prejudice to the Contractor’s entitlement under Clause 69 or otherwise.” ## **4.** The relevant provision of the appendix to the bid, the content of which came for interpretation before the Tribunal and thereafter before the two judicial fora stipulated:­ ## “ANNEXURE- P-3 Kerala State Transport Project Volume III Section 6: Appendix to Bid Page 7.8 Origin of materials 60.3(a) (v) item Origin Currency And Plants 60.3 (d) Plant, USA Machinery & Germany, or Spares any other US Dollars Bitumen & Iran, Thermoplastic Singapore or US Dollars Paint any other ## _Bidder to complete_ **Rates of Interest upon 60.8** ________ percent of payments in local **Unpaid Sums** currency. For other countries, refer to the table below. Currency (as per Sub­Clause 60.1) London Inter­Bank On­ Lending Rate (LIBOR) Plus 2 percent USS ­do­ The above of interest for foreign currencies shall be supplied by the Bidder, and these rates are subject to clarification/negotiation before ” 5 formalizing the Contract. **5.** In their bid document, the appellants had left the space for recording the rate of interest for payment to be made in local currency blank. The agreement contemplated payment to the contractor in foreign currency as also in local currency. So far as payment by foreign currency was concerned, as would be evident from the appendix to the bid quoted in the preceding paragraph, the London Interbank On­lending Rate (LIBOR) plus two per cent was the specified norm. It was on this basis the State’s stand has been that the rate of interest on delayed payment (as contemplated in Clause 60.8) in local currency had to be treated as “zero” or “nil”. It has also been the position of the State, referring to certain communications made by the appellants that there was waiver of the claim of interest by the appellants. In the award, the Tribunal had repelled the argument of the State that the words “zero” or “nil” could be read into the said column of the “appendix to bid”. Relying on the Constitution Bench judgment of this Court in the case of **Secretary, Irrigation Department, Government of Orissa & Ors. vs. G.C. Roy** [(1992) 1 SCC 508], 6 the Tribunal held that a person deprived of the use of money to which he is legitimately entitled has a right to be compensated and such compensation may be called interest, compensation or damages. Two documents originating from the appellants in the form of written communications were relied upon by the State before the Tribunal to contend that claim for interest, in any event, stood waived by claimants on delayed payment of the sum which was to be made in local currency. First of these two documents was a letter of the appellant dated 14[th] July, 2004 (Exhibit R­1 before the Tribunal) and the next was another written communication dated 3[rd] August, 2004 (Exhibit C­72 before the Tribunal). The first letter issued by the appellants addressed to the Chief Executive Officer, Kerala State Transport Project reads :­ “Dear Madam, As discussed on the above subject we confirm that there is no provision of interest on delayed payment in the Contract and hence interest will not be claimed.” **(quoted verbatim)** **6.** The next communication dated 3[rd] August, 2004 was addressed to the same officer of the respondents. The text of this communication is:­ 7 ## “Dear Sir, We wish to invite your kind attention to the issue of release of payment against IPC­1 General Items as recommended by DRB. As a pre­condition for release of the said payment, we were made to issue the above referred letter dated 14.7.2004. Our commitment not to claim any interest on the said amount released by you be treated purely as a goodwill gesture so that our future payments are released to us without any delay. The said letter is restricted to the subject claim/item only.” ## **(quoted verbatim)** **7** . Before the Tribunal, the appellants had taken a point that the said letter of 14[th] July, 2004 was issued under coercion or duress. Their second plea on this count was that the content of the first letter was restricted to release of withheld amount recommended by the Review Board in respect of Interim Payment Certificate­I (IPC­I). The Tribunal accepted the stand of the appellants (claimants before it). It was, inter­alia, observed in the award:­ “The essential element of waiver is intentional relinquishment of known right. The claimant has stated that the said letter was given by them under coercion. This holds goods in view of the fact and circumstances of the case. It is also noted that the said letter dated 14.7.04 (ext. R1) is not even mentioned in the defence statement dated 29.1.05. Nor has this issue been raised before the DRB. So the 8 argument of the respondent that the letter dated 14.7.04 (ext. R1) is a waiver of the rights of the claimant does not stand. The fact that this letter was issued at the time of receiving payment in respect of IPC. I suggests that this was given under coercion. The waiver does not apply to the instant case. This is corroborated by the fact that the claimant has been continually agitating for the payment of interest before and after the issuance of the said letter. As discussed earlier, payment of interest on unpaid sums was due under the terms of the contract and under the law. The recommendation of the DRB made after due deliberations and discussions with the parties has relevance in the matter.” ## **(quoted verbatim)** The Tribunal directed interest on delayed payment in paragraphs 1.6 to 1.8 of the award. Extract from the award these would later in this containing paragraphs appear judgment. **8** . The majority view of the Tribunal was that the contract itself provided for payment of interest with regard to local currency and foreign currency. The plea of the appellants has been that there was no waiver and in any event the communication of 14[th] July, 2004 followed by that of 3[rd] August, 2004 related to IPC­I only. This stand had been broadly accepted by the Tribunal. The 9 Tribunal had also accepted the appellants/claimants’ stand that there was no waiver on claim of interest in respect of all sums due for which Interim Payment Certificates had been issued. The Tribunal’s finding on that aspect was buttressed by the fact that the appellants/claimants had continued to raise demand for interest subsequent to the issue of those two communications. These were essentially findings on facts. **9** . The Arbitration Court and the Appellate Court in sustaining the State’s application for setting aside the award were of the view that the contract could not be construed to contain provisions for interest on delay in payment with regard to the local currency component contained in the agreement, as the appellants did not fill up the blank space with the rate of interest. Opinion of the Appellate Bench was that in the event it was intention of the claimants to retain their entitlement to interest on delayed payment under that head, they ought to have had filled in the blank space in the “appendix to bid”. Another facet of the High Court’s reasoning was that the respondents might have had been persuaded to accept the appellants’ bid on the basis that the appellants would claim no interest on delayed payment in such 10 situation, as this factor could have made their bid more competitive. **10.** This appeal, in substance, is an extension of a proceeding under Section 34 of the 1996 Act. To go into the question of legality of the decisions made by the two judicial fora, we need to test first if the grounds of challenge to the award met the test laid down by this Court in the case of **Oil Natural Gas Corporation Ltd. vs. Saw Pipes Ltd.** [(2003) 5 SCC 705]. Contention of the respondents has been that the Arbitral Tribunal’s order stood vitiated under the “patent illegality” principle spelt out in that judgment. This principle came under the broad heading of “Public Policy” test, applying which an arbitral award could be set aside. What would constitute patent illegality has been elaborated by this Court in a later judgment, **Associate Builders vs. Delhi Development Authority** [(2015) 3 SCC 49]. An award would be invalidated, as per this authority, if the same was in contravention of substantive law of the country or contravention of the “Arbitration Act itself”. In paragraph 42.3 of the Report (in the case of **Associate Builders** ), it has been held:­ 11 “42.3 (c) Equally, the third subhead of patent illegality is really a contravention of Section 28(3) of the Arbitration Act, which reads as under: ## **“28. Rules applicable to substance of dispute.** ­(1)­(2)* * * (3) In all cases, the Arbitral Tribunal shall decide in accordance with the terms of the contract and shall take into account the usages of the trade applicable to the transaction.” This last contravention must be understood with a caveat. An Arbitral Tribunal must decide in accordance with the terms of the contract, but if an arbitrator construes a term of the contract in a reasonable manner, it will not mean that the award can be set aside on this ground. Construction of the terms of a contract is primarily for an arbitrator to decide unless the arbitrator construes the contract in such a way that it could be said to be something that no fair­minded or reasonable person could do.” **11.** The High Court in the appeal concurred with the Arbitration Court and concluded that omission to include the rate of interest in the bid document, the “appendix to bid” to be specific, had resulted in creation of contractual term that there would not be any claim for interest on delayed payment (as per Clause 60.8) so far as payment in local currency component contained in the agreement is concerned. In our opinion, however, the 12 interference with the award by the Arbitration Court on this ground was unwarranted. The underlying reasoning of the Appellate Court and earlier, the Arbitration Court on this point is that the Tribunal went beyond the contractual term in awarding interest. The case of **G.C. Roy** (supra) and a later decision of this Court, **Reliance Cellulose Products Ltd. vs. ONGC Ltd.** [(2018) 9 SCC 266], were relied upon before us by the appellants to sustain the Tribunal’s findings. These decisions are sought to be distinguished on behalf of the respondents on the ground that the former decision related to interest pendente lite and both these cases were under the Arbitration Act, 1940. Under the said statute, an arbitrator had power or jurisdiction to grant pre­ reference interest under the Interest Act, 1978 as also pendente lite and future interest. Such jurisdiction stood curbed only if express terms of the contract precluded payment of interest. Referring to another authority, the **Union of India vs. Bright Power Projects (India) (P) Ltd.** [(2015) 9 SCC 695], this Court highlighted the position of law on grant of interest under Section 31(7) of the 1996 Act. In the case of **Bright Power Projects** (supra), it has been opined by this Court that unless otherwise 13 agreed by the parties, the Arbitral Tribunal can award interest at reasonable rate for a period commencing from that date when the cause of action arises till the date of the award. In the dispute which forms the subject­matter of this appeal, being the agreement, there was no specific exclusion of payment of interest on delayed payment in relation to the local currency component. **12** . On the other hand, the specific term of the agreement entered into by and between the parties provided for payment of interest on delayed payment as terms of the contract. What was not specifically agreed upon was the rate at which such interest would be paid. The blank space in the “appendix to the bid”, in our opinion, cannot be construed as cancellation of the clause providing for payment of interest of delayed release of funds. We do not think the Appellate Court or the Arbitration Court was right in adopting the approach that by not specifying the blank space provided for filling in the interest rate. We are of the view that to come to such an inference, active exclusion of payment of interest under that head was to have been necessary incorporated in the agreement. Though the case of **G.C. Roy** (supra) was delivered in a dispute to which the 1940 Act was 14 applicable, the Constitution Bench of this Court has laid down certain general proposition or principle on the aspect of grant of interest. This general proposition was referred to by the Tribunal. It has been held in paragraph 43.1 of the Report (in the case of ## **G.C. Roy** ):­ “43. The question still remains whether arbitrator has the power to award interest pendent lite, and if so on what principle. We must reiterate that we are dealing with the situation where the agreement does not provide for grant of such interest nor does it prohibit such grant. In other words, we are dealing with a case where the agreement is silent as to award of interest. On a conspectus of aforementioned decisions, the following principles emerge: (i) A person deprived of the use of money to which he is legitimately entitled has a right to be compensated for the deprivation, call it by any name. It may be called interest, compensation or damages. This basic consideration is as valid for the period the dispute is pending before the arbitrator as it is for the period prior to the arbitrator entering upon the reference. This is the principle of Section 34, Civil Procedure Code and there is no reason or principle to hold otherwise in the case of arbitrator.....” **13.** The underlying principle guiding award of interest is that interest payment is essentially compensatory in nature. But as we have already observed, in the case before us, interest on delayed payment formed part of the contract itself. The 15 agreement did not contain any express exclusion clause on payment of interest on delayed payment whether on component of payment in foreign currency or local currency. We accept the reasoning of the Tribunal on the basis of which it rejected the respondents’ plea of waiver. This was a finding of fact on appreciation of materials placed before the Tribunal. One of the reasons behind the decisions of the Appellate Court and Arbitration Court was that the appellants, while bidding, had given up their claims for interest. In substance, the respondents’ assertion is that the Tribunal went beyond the contractual terms, and the said two fora sought to invoke the principle of law contained in the third sub­head of the “patent illegality” principle elaborated in the case of **Associate Builders** (supra). **14.** The Appeal Court accepted reasoning of the Arbitration Court that the blank portion in the appendix to the bid would imply “zero” or “nil”. This reasoning, in our opinion, is flawed and such an interpretation of the agreement would actually be contrary to and beyond the terms of the contract. The Tribunal in this case had already come to a factual finding on appreciation of evidence that there was no such implication. Such an exercise on the part of the Arbitration Court and the Appellate Court would 16 constitute rewriting the contract, which is impermissible. The Tribunal rejected the plea of waiver and we have reproduced its reasoning on that point. We cannot hold such reasoning to be perverse or improbable in the factual background of the present case. The Tribunal in this case could have had awarded interest as a compensatory or equitable measure, as there was no clause providing for exclusion or ouster of interest payment on delayed payment. The Tribunal determined the rate thereof in sub­ paragraphs 1.6 to 1.8 of the award. This part of the award specifies:­ “1.6 It is, therefore, held that the Claimants are entitled to interest on the amount as due under any IPCs issued by the Engineer or failing which, on the amounts as shown in the Claimants monthly statements submitted to the Engineer for certification and when were not paid or had been withheld by the Respondents and such interest shall be paid by the Respondents for the period as 42 days after the claimants’ respective monthly statements had been submitted to the Engineer for certification to the date of payment thereof in full. The arbitral tribunal further holds that on the unpaid sums and for the period of delay in the payment thereof as stated hereinabove, the Respondents shall pay to the claimants interest at the rate of 1% per month compounded monthly such rate being representative of the prevalent rate of access to money that the claimants were deprived of. 1.7 The Arbitral Tribunal therefore directs that the Respondents shall pay to the claimants interest on the unpaid sum of Rs. 17 2,15,72,150/­ for the period of the due dates of payment till the actual dates of full payment of such amount at the rate stated in para 1.6 above in respect of IPCs No. 2 & IPC No. 4. 1.8 The Respondents shall further pay to the claimants such interest on the unpaid sums in respect of other IPCs No. 5 to 14 issued by the Engineer or the Claimants monthly statements submitted to the Engineer for certification for the period from the due dates of payment till the actual dates of full payment at the rate as stated in hereinabove. The respondents are also directed to pay further interest at the rate of 12% per annum on the interest amount determined pursuant to para 1.7 and 1.8 hereinabove from such dates of payment of the principal amount to the date of award.” **15** . The Appellate Court’s rationale that such blank interest column might have had resulted in acceptance of the bid of the appellants as their bid could have been more competitive on the assumption that the other bidders might have had pressed for interest in that column is not acceptable to us. We do not find any material from which such a conclusion could be reached. No material has been shown to us from which it can be inferred that omission to fill in the blank space gave the appellants some kind of competitive edge in the bid process. We also do not know if other bidders had left the space blank or filled the same with 18 specified rate. The Arbitration Court’s view, sustained by the High Court is tainted with an element of speculation on this point. **16** . We do not find any flaw in the reasoning of the Arbitral Tribunal that the contract did not prohibit the award of interest in respect of delayed payment in local currency component specified therein. This being the position, in our opinion, the contrary view expressed by the Arbitration Court in a proceeding under Section 34 of the Act, which view was upheld by the Appellate forum, breaches the permissible boundaries for encroaching upon an award as laid down in **Saw Pipes** case (supra). **17.** In our opinion, the view taken by the Tribunal on consideration of the contract was both reasonable and possible view. We, however, are of the opinion that the rate at which interest has been directed to be paid as contained in paragraphs 1.6 and 1.8 of the award, which we have reproduced above, are rather excessive. As the agreement is silent on the point of rate of interest but provides for payment of interest on delayed payment, the Tribunal’s exercise of fixing the rate should have been on the basis of applying the principle laid down in 19 paragraph 43.1. in the case of **G.C. Roy** (supra). The said principle is applicable in a proceeding under the 1996 Act as well. This principle has been broadly incorporated in Section 31(7) (a) of the 1996 Act. The only difference between the situation contemplated in the aforesaid provision and the facts of this case is that the agreement involved is not silent on interest entitlement of the appellants on delayed payment but the agreement contains provision for such payment. Only the rate at which interest would be payable remained unspecified. In our view, simple interest at the rate of 8% would be just and equitable on the sum left unpaid, calculated otherwise on the basis of sub­paragraphs 1.6. to 1.8 of the award. We, accordingly, set aside the judgment of the Division Bench of the High Court of Kerala impugned in this appeal on the point of entitlement of the appellants to receive interest on delayed payment in relation to local currency component of the contract. As a consequence, judgment of the Sixth Additional District Judge, Ernakulam, shall also stand invalidated. The award of the Tribunal shall stand sustained so far as direction to pay interest on delayed payment of the local currency component of the agreement is concerned, but the rate of interest on the sum shall be computed in the manner 20 prescribed in paragraphs 1.6, 1.7 and 1.8 and shall be at 8% simple interest per annum. **18** . The appeal is allowed in the above terms. **19.** There shall be no order as to costs. **.................................J.** **(SURYA KANT)** **...............................J. (ANIRUDDHA BOSE)** **NEW DELHI APRIL 22, 2021** 21
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.