M/s Om Gurusai Construction Company vs M/s V.N. Reddy & Ors.
Case Synopsis & Summary
This Supreme Court Civil Appeal arises from a tender dispute relating to the award of work for construction of land development works (Part-I) of Gadegaon main minor offtaking at Wardha. After the lowest bid (L1) was declared on 12.03.2021, Clause 2.22.0(ix) of the tender conditions required the additional performance security to be furnished within two working days. Given 13.03.2021 was a Saturday and 14.03.2021 a Sunday, and a nationwide bank strike on 15–16.03.2021, the appellant submitted the security on 17.03.2021. The tendering authority accepted it and issued a work order on 07.05.2021. The first respondent challenged the award, arguing the two‑day limit could not be relaxed and that acceptance of the security beyond the period breached the tender terms. The High Court (Nagpur Bench) held the clause mandatory, non‑relaxable, and that the security could not be accepted late. The Supreme Court reversed, emphasizing that in exceptional circumstances like holidays and bank strikes, the core object of the clause could still be met (deposit made at earliest feasible time). Relying on maxims such as lex non cogit ad impossibilia and supportive precedents, the Court held no mala fide or arbitrariness and directed dismissal of the writ petition with the appeal allowed, overturning the High Court’s order and upholding the tender award.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- K. V. Viswanathan
- Judgment Date
- 2023-08-23
- Court Decision / Holding
- The appeal is allowed. The High Court’s impugned judgment is set aside; Writ Petition No. 1787 of 2021 stands dismissed. The tender award to the appellant is upheld, and no order as to costs.
- Final Disposition
- Appeal allowed; High Court order set aside; Writ Petition dismissed; Tender award upheld; No costs ordered.
Parties to the Case
Appellants / Petitioners
- M/s Om Gurusai Construction Company
Respondents
- M/s V.N. Reddy & Ors.
Legal Representation & Advocates
Counsels for Petitioners
- • Amit K. Pathak
Counsels for Respondents
- • Prashant Shrikant Kenjale
- • Uday B. Dube
Provisions of Law Cited
Legal Doctrines & Maxims
- lex non cogit ad impossibilia
Submissions & Arguments
Contentions of Appellants / Petitioners
The two‑day submission window for additional security could not be treated as rigid to deny a bid where circumstances made compliance practically impossible—holidays and bank strikes delayed deposit; the object of the clause was to secure performance, not require an impossible standard. The appellant contended the bank strike 15–16 March and non‑operational banks on those dates justified submission on 17 March and that the tendering authority reasonably interpreted the clause, consistent with the maxim lex non cogit ad impossibilia and supportive jurisprudence.
Contentions of Respondents
The clause 2.22.0(ix) was mandatory and non‑relaxable; timely submission of additional security was a condition of eligibility. Deposits made after the specified two days could not be accepted, and accepting for 17 March (the third working day) breached the tender terms. The High Court rightly held the clause as essential and non‑relaxable and erred in reversing the tender decision.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (13)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Mahanth Ram Das vs. Ganga Das | [1961] 3 SCR 763 | Positive | Cited for guiding principle on procedural orders and time extensions within litigation, illustrating that such orders are not absolute and can adapt to circumstances. |
| Raj Kumar Dey and Others vs. Tarapada Dey and Others | (1987) 4 SCC 398 | Positive | Uses the lex non cogit ad impossibilia maxim to justify not compelling impossibilities in legal obligations. |
| HUDA and Another vs. Dr. Babeswar Kanhar and Another | (2005) 1 SCC 191 | Positive | Applied to justify applying general principles to ensure justice when statutory provisions do not strictly cover every scenario. |
| Rosali V. vs TAICO Bank and Others | (2009) 17 SCC 690 | Positive | Discusses interpreting immediacy/necessity of deposits under time-bound requirements during extenuating circumstances. |
| Dakshayani vs. Branch Manager, Indian Overseas Bank | AIR 1998 Kant 114 | Positive | Supportive precedent on interpreting the word ‘immediately’ and permissible extensions in exceptional situations. |
| Savithramma case | ILR 1973 Kant 1277 | Positive | Used to illustrate handling of acts impossible to perform on the stated day due to practical impediments. |
| Jagdish Mandal vs. State of Orissa and Others | (2007) 14 SCC 517 | Positive | Caution against judicial interference in tender/contractual matters where impropriety or prejudice is not shown. |
| Afcons Infrastructure Limited vs Nagpur Metro Rail Corporation Limited and Another | (2016) 16 SCC 818 | Positive | Supports deference to the employer’s interpretation of tender documents in absence of mala fides. |
| Uflex Limited Vs. Government of Tamil Nadu and Others | (2022) 1 SCC 165 | Positive | Affirms consideration of practical realities in contract/tender adjudications. |
| Vidarbha Irrigation Development Corporation and Others vs Anoj Kumar Agarwala and Others | (2020) 17 SCC 577 | Distinguished | Distinguished on facts; not applicable to the present case’s circumstance. |
| Tata Cellular Vs Union of India | (1994) 6 SCC 651 | Mentioned Only | Cited but not relied upon for the key reasoning of the present decision. |
| Savithramma case | ILR 1973 Kant 1277 | Positive | See above; cited in supporting interpretation of timing. |
| Jagdish Mandal vs State of Orissa and Others | (2007) 14 SCC 517 | Positive | As above; emphasized restraint in judicial review of tender decisions. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/s Om Gurusai Construction Company vs M/s V.N. Reddy & Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.