M/S N.V. International vs The State of Assam & Ors.

Case / Petition Number:
Civil Appeal No. 9244 of 2019 (Arising out of SLP (C) No. 23808/2019)

Case Synopsis & Summary

This Supreme Court judgement deals with the challenge to an arbitral award dated 19 December 2006, rendered by Justice K.N. Saikia. A challenge under Section 34 of the Arbitration and Conciliation Act, 1996, was rejected by the District Judge, Kamrup, Gauhati on 30 May 2016. An appeal under Section 37 of the 1996 Act was filed in March 2017, but the delay amounted to 189 days beyond the 90-day period prescribed under Article 116 of the Limitation Act for filing such an appeal. The Division Bench did not condone this delay for want of a sufficient cause. The appellant’s counsel argued that unlike Section 34, Section 37 does not exclude Section 5 of the Limitation Act, so even after 90 days a condonation application under Section 5 should be considered on its own merits, not by the length of delay alone. The respondent supported the judgment below, contending that 189 days delay would subvert the object of speedy resolution of disputes referred to arbitration. The Court cites Union of India v Varindera Constructions Ltd., noting a near-identical fact pattern where such appeals were allowed, but distinguishes this case on the facts. Relying on Lachmeshwar Prasad Shukul and Others, the Court reiterates that appellate proceedings are a continuation of the original proceeding and that the overall aim is dispatch. Consequently, the delay beyond 120 days is not condoned, and the appeal is dismissed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • R.F. Nariman
  • S. Ravindra Bhat
Judgment Date
2019-12-06
Court Decision / Holding
The Special Leave Petitions stand disposed of. The appeal is dismissed.
Final Disposition
Appeal dismissed

Parties to the Case

Appellants / Petitioners

  • M/s N.V. International

Respondents

  • The State of Assam
  • Others

Legal Representation & Advocates

Counsels for Petitioners

  • • Parthiv K. Goswami

Counsels for Respondents

  • • Shuvodeep Roy

Provisions of Law Cited

Section 34 of the Arbitration and Conciliation Act, 1996Section 37 of the Arbitration and Conciliation Act, 1996Article 116 of the Limitation ActSection 5 of the Limitation Act

Legal Doctrines & Maxims

  • Appellate proceedings are a continuation of the original proceeding (Lachmeshwar Prasad Shukul and Others)
  • Object of speedy resolution of arbitral disputes
  • Despatch/dispatch objective of the 1996 Act

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that Section 37 does not exclude Section 5 of the Limitation Act; thus, even if the 90-day period elapses, a condonation application under Section 5 should be decided on its merits, irrespective of delay length. The argument relies on a broader interpretation of limitation in Section 37 to ensure meritorious disputes are heard, particularly where the arbitral process aims for timely resolution. Reference is made to precedents allowing equitable consideration of delays and the overarching objective of effective arbitration.

Contentions of Respondents

The respondents submit that the object of speedy dispute resolution requires strict adherence to time limits. A delay of 189 days defeats the purpose of arbitration and cannot be condoned. They cite the Division Bench 2013 decision that treated delays beyond 120 days as untenable and caution that allowing extensions would undermine the statutory scheme and its dispatch objective, even while acknowledging related precedents like Varindera Constructions.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Lachmeshwar Prasad Shukul and Others v. Keshwar Lal Chaudhuri and OthersAIR 1941 Federal Court 5PositiveCited to support the view that appellate proceedings are a continuation of the original proceedings and to emphasize the dispatch objective of arbitration proceedings.
Union of India v Varindera Construction Ltd.SLP (C) No. 23155/2013; Civil Appeal Nos. 3994-3995 of 2018DistinguishedCited as an authority with near-identical facts where the appeal was allowed, but this case is distinguished on the facts due to a delay exceeding 120 days and the Division Bench’s earlier finding; thus not applied in the present case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•792 words•~4 min read

In The Court Record

M/S N.V. International vs The State of Assam & Ors.

1 **REPORTABLE** ## **IN THE SUPREME COURT OF INDIA** ## **CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NO. 9244 OF 2019 (Arising out of SLP (C) No. 23808/2019)** **M/S N.V. INTERNATIONAL Appellant(s)** **VERSUS** **THE STATE OF ASSAM & ORS. Respondent(s)** **J U D G M E N T** **R.F. Nariman, J.** - **1) Leave granted.** **2) On the facts of the present case, an Arbitral Award dated 19.12.2006 was made by Justice K.N. Saikia, retired Judge of this Court. From this, a Section 34 petition was filed and rejected by the District Judge, Kamrup, Gauhati on 30.05.2016. An appeal under Section 37 of the Arbitration and Conciliation Act, 1996 was filed from this order in March, 2017, that is after a delay of 189 days from the 90 days that were given under Article 116 of the Limitation Act for filing such appeal. By the impugned judgment dated 24.06.2019, this delay was, on facts, not condoned as no sufficient cause was made out.** **3) Mr. Parthiv K. Goswami, learned advocate on behalf of the appellant has argued before us that unlike Section 34, Section 37 does not exclude Section 5 of the Limitation Act, as a result of which even if the 90 day period is over, if a** Signature Not Verified Digitally signed by R NATARAJANDate: 2019.12.10 **condonation application is made under Section 5 of the** 17:12:28 IST Reason: **Limitation Act, it should be considered on its own merits notwithstanding the length of delay. Mr. Shuvodeep Roy,** 2 **learned counsel for the respondent supported the judgment under appeal, stating that 189 days cannot be condoned as the object of speedy resolution of disputes referred to arbitration would be subverted.** **4) Having heard learned counsel for both sides, we may observe that the matter is no longer res integra. In SLP (C) No. 23155/2013 [** _**Union of India**_ **vs.** _**Varindera Const. Ltd.**_ **, this Court, by its judgment and order dated 17.09.2018 held thus:** **“Heard the learned Counsel appearing for the parties.** **By a judgment dated 19.04.2018 in Civil Appeal Nos. 3994-3995 of 2018 [** _**Union of India**_ **vs.** _**M/s Varindera Constructions Ltd. Etc.**_ **], this Court has in near identical facts and circumstances allowed the appeal of the Union of India in a proceeding arising from an Arbitral Award.** **Ordinarily, we would have applied the said judgment to this case as well. However, we find that the impugned Division Bench judgment dated 10.04.2013 has dismissed the appeal filed by the Union of India on the ground of delay. The delay was found to be 142 days in filing the appeal and 103 days in refiling the appeal. One of the important points made by the Division Bench is that, apart from the fact that there is no sufficient cause made out in the grounds of delay, since a Section 34 application has to be filed within a maximum period of 120 days including the grace period of 30 days, an appeal filed from the self-same proceeding under Section 37 should be covered by the same drill.** **Given the fact that an appellate proceeding is a continuation of the original proceeding, as has been held in** _**Lachmeshwar Prasad Shukul and Others**_ **vs.** _**Keshwar Lal Chaudhuri and Others,**_ **AIR 1941 Federal Court 5, and repeatedly followed by our judgments, we feel that any delay beyond 120 days in the filing of an appeal under Section 37 from an application being either dismissed or allowed under Section 34 of the Arbitration and Conciliation Act, 1996 should not be allowed as it will defeat the overall statutory purpose of arbitration proceedings being decided with utmost** 3 ## **despatch.** **In this view of the matter, since even the original appeal was filed with a delay period of 142 days, we are not inclined to entertain these Special Leave Petitions on the facts of this particular case.** **The Special Leave Petitions stand disposed of accordingly.** **Pending applications, if any, also stand disposed of.”** **5) We may only add that what we have done in the aforesaid judgment is to add to the period of 90 days, which is provided by statute for filing of appeals under Section 37 of the Arbitration Act, a grace period of 30 days under Section 5 of the Limitation Act by following** _**Lachmeshwar Prasad Shukul and Others (supra),**_ **as also having regard to the object of speedy resolution of all arbitral disputes which was uppermost in the minds of the framers of the 1996 Act, and which has been strengthened from time to time by amendments made thereto. The present delay being beyond 120 days is not liable, therefore, to be condoned.** **6) Accordingly, the appeal is dismissed.** **.......................... J. (ROHINTON FALI NARIMAN)** **.......................... J.** **(S. RAVINDRA BHAT)** **New Delhi; December 06, 2019.**
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.