M/S NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING CORP. LTD. & ANR.

Case / Petition Number:
Civil Appeal No. 6296 of 2016
Neutral Citation:[2016] 5 S.C.R. 69

Case Synopsis & Summary

This Supreme Court judgment concerns a dispute between two government-owned enterprises: Northern Coalfield Ltd. (appellant) and Heavy Engineering Corporation Ltd. (respondent) arising from two contracts for a Coal Handling Plant at Bina. Each contract contained an arbitration clause and both sets of claims were resolved through the Government’s Permanent Machinery of Arbitration (PMA), an administrative mechanism outside the traditional Arbitration Act regime. Two PMA awards dated 28.02.1997 favored the respective parties, which were challenged before the Law Secretary (Department of Legal Affairs) under the in-house mechanism. During this period, Rampur Engineering Company Ltd. (Respondent No.2) filed a suit in the Delhi High Court seeking to restrain enforcement of the awards and challenging contract breaches (notably sub-letting without consent). The appellant argued that despite the PMA mechanism, the suit should proceed since there was no privity issue and a COD clearance was not a prerequisite for filing; the High Court held that COD permission was required and rejected the plaint. The Constitution Bench of this Court has since held that the COD mechanism is obsolete and its clearance cannot be insisted upon at this stage. The Court allowed the appeal, set aside the High Court’s order, and directed that all disputes between the two corporations be referred to a sole arbitrator (Hon’ble Justice K.G. Balakrishnan) under the Arbitration and Conciliation Act, 1996, with Civil Suit OS 1709/2000 disposed of accordingly. The parties are to appear on 22 August 2016 for further directions.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • T. S. Thakur, CJI
  • R. Banumathi, J
Judgment Date
2016-07-13
Court Decision / Holding
We allow this appeal and set aside the judgment and order of the High Court. All disputes relating to the contracts executed between Northern Coalfield Ltd. and Heavy Engineering Corp. Ltd. shall stand referred for adjudication to Hon’ble Mr. Justice K. G. Balakrishnan, Former Chief Justice of India, who is appointed as Sole Arbitrator to adjudicate all claims and counter‑claims. Civil Suit No. 1709/2000 shall stand disposed of in terms of this order. The parties shall appear before the Arbitrator on 22 August 2016 for further directions. The Arbitrator shall determine his own fee. No costs.
Final Disposition
Appeal allowed; High Court’s order set aside; disputes referred to a sole arbitrator under the Arbitration and Conciliation Act, 1996; Civil Suit disposed.

Parties to the Case

Appellants / Petitioners

  • M/S Northern Coalfield Ltd.

Respondents

  • Heavy Engineering Corporation Ltd.
  • Rampur Engineering Company Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • P. S. Patwalia, ASG
  • • Anup Sachthey
  • • Ms. Anjali Chauhan

Counsels for Respondents

  • • Ranjit Kumar, SG
  • • Binu Tamta
  • • Dhruv Tamta
  • • Ms. Nikita Shrivastava

Provisions of Law Cited

Arbitration Act, 1940Arbitration and Conciliation Act, 1996Code of Civil Procedure, 1908 (Order 7, Rule 11(d))

Legal Doctrines & Maxims

  • Remedies on the administrative side cannot substitute legal remedies available under the law.
  • No estoppel against seeking redress in accordance with law.
  • Arbitral awards outside the statutory framework of arbitration are not legally enforceable in a court of law.
  • Where COD clearance is no longer in force (COD abolished), it cannot be insisted upon to bar litigation at this stage.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that the High Court erred in treating the PMA award or the mechanism as governed by the arbitration statutes. The object of PMA was to resolve inter‑se disputes between PSUs, and its process, being administrative, cannot bar access to the ordinary courts when a party seeks a lawful adjudication. The absence of COD clearance could not be a fatal defect for instituting suit, especially since COD had been dissolved and the Court had recalled prior directives. The appellant sought reference to a sole arbitrator under the Arbitration and Conciliation Act, 1996 for all outstanding disputes to avoid protracted litigation and the impracticality of enforcing a non‑statutory award. The suit, filed to vindicate breach of Clause 3, should not be struck down merely because the parties resorted to PMA. The appellant also urged deletion of Rampur Engineering Co. Ltd. from the array to focus on the contract‑to‑contract dispute between the two corporations.

Contentions of Respondents

The respondents argued that the special in‑house mechanism for disputes between government undertakings was designed to avoid Court litigation and that the absence of COD clearance would block proceedings pending clearance. They contended that PMA awards, though outside the statutory arbitration regime, were efficacious in resolving inter‑corporate disputes, and a civil action to set aside such awards would defeat the very purpose of the COD/CoD scheme and the PMA. They urged the Court to uphold the High Court’s view that the suit was not maintainable without COD clearance and to proceed with the PMA mechanism’s remedies, rather than direct adjudication in a civil court.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (7)

Case NameCitationTreatmentExplanation
Electronics Corporation of India Ltd. v. Union of India2011 (3) SCC 404PositiveCited for recall of COD/CoD directives and to support the proposition that COD regime had flaws and directions were recalled.
Oil and Natural Gas Commission v. Collector of Central Excise2004 (6) SCC 437OverruledEarlier COD clearance requirement; held to be superseded by later recall of COD directives.
Oil and Natural Gas Commission v. Collector of Central Excise1995 Supp (4) SCC 541Mentioned OnlyHistorical reference in the COD regime; used for context rather than binding authority.
Oil and Natural Gas Corporation Ltd. v. City and Industrial Development Corp., Maharashtra and Ors.2007 (7) SCC 39PositiveCites the sequence of COD creation and committee formation; supports administrative dispute resolution approach.
Commissioner of Income Tax, Delhi‑VI v. Oriental Insurance Co. Ltd.2008 (9) SCC 349PositiveClarified time frames for COD clearance are not rigid, aiding the view that litigation can proceed with some timely coordination.
Commissioner of Central Excise v Bharat Petroleum Corp. Ltd.2010 (13) SCC 42PositiveEmphasized expeditious handling of COD matters; reinforces the functioning and role of COD/CoD regimes.
Electronics Corporation of India Ltd. v. Union of India2011 (2) SCR 971PositiveReferenced again to emphasize recall and reform of COD/CoD regime; foundational to the present decision.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•8,840 words•~41 min read

In The Court Record

M/S NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING CORP. LTD. & ANR.

[2016) 5 S.C.R. 69 # _MIS._ NORTHERN COALFIELD LTD. A v. HEAVY ENGINEERING CORP. LTD. & ANR. (Civil Appeal No. 6296of2016) JULY 13, 2016 B [T.S. **THAKUR, CJI AND R. BANUMATHI, J.]** _Government Corporations: Government contracts_ - _Redressal of commercial disputes between public sector enterprises_ inter se _as well as between the public sector enterprises and the Government departments_ - _Procedure for settlement of disputes_ - _In the instant case,_ di~pute _arose between two govern111ent owned corporations_ - _Referred to resolution in terms of the 'permanent in-house administrative machinery' set up by the Govern11ient_ - _Arbitra/ award_ - _Aggrieved by the award, appellant filed Suit_ - _Defendant claimed that suit was barred in view of the existence of specially prescribed procedure for resolving disputes and in the light of said procedure, neither party to the dispute was entitled to take recourse to proceedings in any court without permission of the Co111111ittee on_ - _Disputes (COD) High Court rejected the plaint accepting the plea of defendant_ - _On appeal, held: In ONGC case, it was held that permission of COD was necessary to proceed with the suit_ - _However, COD stood dissolved and the orders directing constitution of COD is reversed and, therefore, requirement of clearance of COD should not be insisted upon at this stage_ - _In view thereof. there is no question of either obtaining or insisting upon any clearance from the same_ - _Therefore, orders passed by High Court rejecting the plaint on the ground that the same was not preceded by permission from COD is unsustainable_ - _Right of the appellant to de111and such an adjudication cannot be denied si111ply because it happens to be a Govern111ent owned company for even when the appellant is a govern111ent company, it has its legal character as an entity separate from the Govern111ent_ - _Just because it had resorted to the permanent procedure or taken part in the proceedings there can be no estoppel against its seeking redress in accordance with law_ - _Matter referred to sole arbitrator for adjudication of all outstanding disputes between the two corporations._ c **D** E F G **H** 69 70 [2016] 5 S.C.R. SUPREME COURT REPORTS ------ ## Allowing the appeal, ~he Court A HELD: 1. Commercial disputes between public sector enterprises _inter se_ as well as between the public sector enterprises and the Government departments were in the ordinary course settled through arbrtration by Government B Officers or good offices of empowered government agencies like Bureau of Public Enterprises. Department of Legal Affairs however submitted a note dated 8 .. May, 1987 on the subject which was considered by a Committee of Secretaries in its meeting held on 26'h June, 1987. The Committee of Secretaries suggested that a permanent machinery for arbitration should be c set up in the Department of Public Enterprises to settle all commercial disputes between PSE _inter se_ and between PSE and Government department excluding disputes concerning income tax, customs and excise. The Committee also suggested that there should be a contractual clause binding the parties to the D commercial contracts to refer all their disputes for settlement to the Permanent Machinery of Arbitrators. The Committee of .. Secretaries proposed that Bureau of Public Enterprises should bring a note for consideration of the Cabinet in that regard which note was prepared and upon submission to the Cabinet was approved in its meeting held on 24'h February, 1989. The Cabinet E decision envisaged that all Public Sector Enterprises include a contractual clause in their future and current commercial contracts regarding settlement of disputes by arbitration by resorting to Permanent Machinery of Arbitration and that administrative Ministries shall issue necessary directives to the PSEs under F the relevant clause of the Articles of Association. The directives and draft outline of procedure to be .followed by the Permanent Machinery of Arbitrators in the Bureau of Public Enterprises was accordingly issued in terms of DPE D.O. No. 15(9)/86-BPE(Fin) dated 29'h March, 1989. The procedure for settlement_ of disputes so devised was however outside the framework of the Arbitration G ·Act, 1940 which then held the field. iPara 14] [78-G-H; 79-A-E) B c D E 2 .. The disputes between t~e appellant and respondents were referred for settlement in terms of the Permanent Machinery for Arbitration as early as in the year 1993/1994_, As on the date of the said reference the Committee on Disputes was already set H 71 _MIS._ NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING CORP. LTD. & ANR. up but no, permission for a reference was taken. That the Arbitrator made an award under the Permanent Machinery of Arbitration which was questioned in appeals before the Law Secretary who made some alterations in the same; The award so made was not accepted by' the appellants. The appellant filed a suit challenging the arbitral award in which the appellant claimed a declaration that the, contracts were rendered null and void on account of the breach of Clause 3 thereof. The appellant also sought a declaration that the respondent company was not entitled to claim any relief under the said contract nor was respondent No.2 entitled to do so and that the so called arbitral award was vitiated on the face of record hence liable to be set aside. That such a suit could be filed but could not be proceeded with till such time the COD granted permission is also beyond dispute as on the date of the institution of the suit the direction of this Court in ONGC group of cases still held the field. Such permission could be obtained within 30 days which was not sacrosanct but the institution of the suit itself could not be faulted as a litigant was in terms of the direction of this Court entitled to institute the proceedings to save limitation. The High Court has, all the same, rejected the plaint on the ground that permission from COD was . not obtained. In doing so the High Court obviously understood the direction of this Court to mean as though absence of such permission was a fatal defect which it was not. What was restrained was further progress in the suit till such time permission from the COD was obtained. However, the requirement of the clearance of COD should not be insisted upon at this stage, because COD stands abrogated/dissolved and the orders directing constitution of such a Committee is reversed. Since there is no COD at present there is no question of either obtaining or insisting upon any clearance from the same. Therefore, the orders passed by the High Court rejecting the plaint on the ground that the same was not preceded or accompanied by permission from COD is unsustainable. [Paras 23, 24) (88-D-H; 89-A-E) A B c D E F G 3. An arbitral award under the Permanent Machinery of Arbitration may give quietus to the controversy if the same is accepted by the parties to the dispute. In cases, however, a party does not accept the award, as is the position in the case at hand, H 72 [2016] 5 S.C.R. SUPREME COURT REPORTS - A the arbitral award may not put an end to the controversy. Such an award being outside the framework of the law governing arbitration will not be legally enforceable in a court of law. [Para 25] (89-F-H] 4. Remedies which are available to the Government on the B administrative side cannot substitute remedies that are available to a losing party according to the law of the land. The appellant has lost before the arbitrators in terms of the Permanent Machinery of Arbitration and is stoutly disputing its liability on several grounds. The dispute regarding liability of the appellant under the contract, therefore, continues to loom large so long as c it is not resolved finally and effectually in accordance with law. No such effective adjudication recognized by law has so far taken place. That being so, the right of the appellant to demand such an adjudication cannot be denied simply because it happens to be a Government owned company for even when the appellant is a D government company, it has its legal character as an entity separate from the Government. Just because it had resorted to the permanent procedure or taken part in the proceedings there can be no estoppel against its seeking redress in accordance with law. That is precisely what it did when it filed a suit for declaration that the award was bad for a variety of reasons and E also that the contract stood annulled on account of the breach committed by the respondents. The matter is referred· to sole arbitrator for adjudication of all outstanding disputes between the two corporations especially because the alternative to such arbitration is a long drawn expensive and cumbersome trial of F the suit filed by the appellant before a civil court and the difficulties that beset the execution of an award made under a non-statutory administrative mechanism [Paras 25, 27) [90-B-E; 91-A-B) - _Electronics Corporation of India Ltd. v. Union of India_ (2011) 3 SCC 404 : 2011 (2) SCR 971; _Oil and_ - G _Natural Gas Commission v. Collector of Central Excise_ (2004) 6 SCC 437; _Oil and Natural Gas Commission and Am: v. Collector of Central Excise_ 1995 Supp (4) SCC 541; _Oil and Natural Gas Corporation Ltd. v. City and Indus!. Dev. Corpn., Maharashtra and Ors._ (2007) 7 SCC 39 : 2007 (8) SCR 429; _Commissioner of Income_ - H M/S. NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING 73 CORP. LTD. & ANR. _Tax, Delhi-VI v. Oriental Insurance Co. Ltd._ (2008) 9 SCC 349; _Co111111issioner of Central Excise v. Bharat Petroleum Corp. Ltd._ (2010) 13 SCC 42; _Electronics Corporation of India Ltd. v. Union of India_ (2011) 3 SCC 404 : 2011 (2) SCR 971 - referred to. ## Case Law Reference A B |Case|CaseLawReference||B| |---|---|---|---| |2011 (2)SCR971|referred to|Para11|| |(2004) 6sec437|referred to|Para11, 16|| |1995 Supp (4) SCC 541 referred to||Para15|| |2007 (8)SCR429|referred to|Para17|c| |(2008) 9sec349|referred to|Para17|| |(2010)13sec42|referredto|Para18|| |2011 (2)SCR971|referredto|Para19|| D CIVJL APPELLATE JURISDICTION: Civil Appeal No. 6296 of2016. From the Judgment and Order dated 07 .08.2008 of the High Court of Delhi at New Delhi in RFA (OS) No. 50 of 2007. P. S. Patwalia, ASG, Anip Sachthey, Ms. Anjali Chauhan, Advs. for the Appellant. E Ranjit Kumar, SG, Binu Tamta, Dhruv Tamta, Ms. Nikita Shrivastava, Advs. for the Respondents. The Judgment of the Court was delivered by F T.S. THAKUR, CJI. I. Leave granted. 2. This is yet another case that brings to fore a sad state of affairs when it comes to resolving disputes between two Government owned corporations. What adds to the enigma of apathy towards realism in official circles is the fact that the respondent-corporation has with considerable tenacity opposed the move aimed at a quick and effective resolution of the conflict and resultant quietus to the controversy by a reference of the disputes to arbitration in terms of the Arbitration and Conciliation Act, 1996. G H 74 (2016] _5_ S.C.R. SUPREME COURT REPORTS A The Facts: 3. Appellant - Northern Coalfield Ltd. issued a tender for construction of a Coal Handling Plant at Bina sometime in May, 1984. The construction work was meant to be carried out under two contracts: _viz._ (I) a Contract for works and services and (2) a Contract for B equipment and spares. Both these contracts were awarded to the respondent- Heavy Energy Corporation Ltd. which is also a Government of India company. The contracts contained a Clause that provided for adjudication of disputes between the parties by way of arbitration. Disputes having actually arisen in relation to the two contracts, the same were referred for resolution in terms of the "permanent in-house c administrative machinery" set up by the Government. Claims and counter claims were made by the two corporations against each other which finally culminated in the making of two awards both dated 28.02.1997 under which respondent No. I was held entitled to a sum of Rs.16,87 ,61,981.11/-, while the appellant was awarded Rs.56,05,000/-. D Both the parties were, however, dissatisfied with the awards which they challenged in appeals filed before the Law Secretary, Department of Legal Affairs, Ministry of Law and Justice in terms of the in-house mechanism provided by the Gov.ernment. While Appeal No.67 of 1998 · filed before the Law Secretary pertained to the contract for supply of equipment, Appeal No.64 of I 999 pertained to the contract for execution E of works and services. 4. During the pendency of the appeals aforementioned respondent No.2 - _Mis._ Rampur Engineering Company Ltd. filed Suit No.450 of 1999 before the High Court of Delhi against the two corporations in which the said respondent prayed for an injunction restraining respondent F No. I from settling the disputes with the appellant. The appellant's case is that it came to know about the role of Respondent No.2 in the execution of contracts only after the filing of the said suit in which by an interim order, the High Court restrained the parties from implementing any award made by the appellate authority. The appellant's further case is that G respondent No.1 had, contrary to Clause 3 o'f the Terms of Contracts executed with the appellant, sublet the contracts in favour of responcjent No.2 without prior consent of the former and that the said arrangement was of no legal consequence nor did it create any legal relationship between the appellant and the sub-contractor. H 5. Appeal No.64 of I 999, arising out of the contract for works M/S. NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING 75 · CORP. LTD. & ANR. [T.S. THAKUR, CJ!] and services came to be disposed of first, wherein the appellate authority made an award on 13.11.1999 holding that a sum of Rs.15,84,50,000/- ' apart from Rs.3.73 crores due as interest was recoverable from the ' appellant. Appeal No.67of1998 filed by the first respondent was disposed of by the appellate authority on 01.12.1999 remanding the matter back to the Arbitrator for reconsideration. Aggrieved by the awards made by the Arbitrator and the appellate authority, the appellant-herein filed Civil Suit No.1709 of2000 before the High Court of Delhi in which it claimed a declaration to the effect that respondent No. I had committed a breach of Clause 3 of the terms of the Contracts executed between the two Corporations by sub-letting the contract to respondent No.2 thereby rendering the contracts between the appellants and the first respondents null and void. The appellant further prayed for a declaration to the effect that respondent No. l was not entitled to claim any relief under those contracts nor was respondent No.2 entitled to do so. The SQ called Arbitral award passed by the appellate authority was according to the appellant illegal and vitiated by errors apparent-On the face of the: record, hence, liable to be set aside. 6. The learned Single Judge of the High Court by an interim order dated 4.08.2000 passed in the suit restrained the implementation/execution of awards passed by the Appellate Authority. The appellant's case is that it was at that stage that the defendant-respondents herein moved an application under Order 7, Rule 11 (d) of the Code of Civil Procedure, 1908 (for short, "the CPC") praying for rejection of the plaint in the suit filed by the appellant. The defendant claimed that the suit was barred in view of the existence of a specially prescribed procedure for resolving disputes in arbitration proceedings between the two Government corporations. It was contended that in the light of the said procedure, neither party to the dispute was entitled to take recourse to proceedings in any Court without the permission of the Committee on Disputes. 7. The appellant opposed the prayer for rejection of the plaint _inter a/ia_ on the ground that no permission to file a suit or other proceedings was required as the subject dispute also involved respondent No.2 who was not a party to the arbitration agreement or the proceedings. By an order dated 10.07.2007 a learned Single Judge of the High Court allowed the application filed by the defendants-respondents and rejected the plaint filed by the appellant. The learned Single Judge held that the arbitral award made pursuant to the proceedings conducted in terms of A B c D E F G H 76 [2016] 5 S.C.R. SUPREME COURT REPORTS - A the special mechanism could not be set aside in a suit. The learned Single Judge also held that there was no privity of contract between the appellant-corporation and respondent No.2 and that the suit between the two public sector undertakings could not be filed without Glearance from the Committee on Disputes. 8 c 8. Aggrieved by the order passed by the Single Judge of High Court, the appellant filed RFA (OS) No.50 of 2007 before a Division Bench of the High Court of Delhi. The Division Bench has by an order dated 07 .08.2008 dismissed the said appeal and affirmed the rejection of the plaint by the learned Single Judge primarily on the ground that since the special procedure prescribed by the Government for adjudication of disputes between Government Corporations having been effectuated and resorted to by the parties in terms of the judgments of this Court in _ONGC s Cases,_ the appellant was not entitled to seek a declaration that the awards so made were illegal or liable to be set aside. 9. The High Court observed: D - D _"Before us, the appellant, which is admittedly a government undertaking, is claiming that the first respondent, also a government undertaking, has violated and breached a contract between them. In particular, Clause 3 of the said contract is stated to have been breached. Respondent No.J, of course, says_ - E _that 110 such breach has occurred. This then, is the dispute merely because the appellant feels that the breach committed by the first respondent has benefited a third party, will not change the nature of the dispute from being one between the appellant and Respondent_ - F _No.l, i.e., the two contracting parties. Since both of them are government undertakings, therefore, the_ - _·permanent machinery provided for resolving disputes between public sector undertakings ought to have been followed._ " - _By the impugned order, the learned Single Judge has_ - G _examined the question whether the appellant is entitled to seek a declaration that the appellant awards are illegal and liable to be set aside by way of a suit or whether the same is barred by any law. The learned Single Judge has held that the arbitral award cannot_ H M/~). NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING CORP. LTD. & ANR. [T.S. THAKUR, CJI] 77 _be set aside in a suit. It was further held that an arbitral award cannot be set aside in a suit. It was further held that once the parties have subjected themselves to permanent machinery for redressal of dispute between public sector undertakings. then the mechanism prescribed therein should be followed and, therefore, the suit in question could not have been filed without clearance of the Committee of Disputes. By merely noting the contention of the appellant that the root of the dispute is violation of Clause 3 of the terms of the contracts, it cannot be said that the learned Single Judge has decided disputed question of facts. It has merely taken note of the_ appellant~ _own case in stating that the key players are the two public sector undertakings which have entered into the contract in question with each other, and therefore, the special procedure prescribed for such disputes should have been followed._ Consequent!;~ _the learned Single Judge rightly held that the plaint was liable to be rejected, inter alia, for that reason."_ A B c D 10. The present appeal calls in question the correctness of the above judgments and orders. E I I .Appearing on behalfofthe appellant, Mr. P.S. Patwalia, learned senior counsel argued that the view taken by the High Court was legally unsustainable. It was submitted that the High Court has proceeded on the assumption as though the award made by the Arbitrator under the special procedure prescribed by the Government is an arbitral award within the comprehension of the Arbitration Act, 1940 or Arbitration and Conciliation Act, 1966. He urged that the High Court had overlooked the genesis of the administrative arrangement, in as much as the object behind the setting up of the special procedure for resolution of disputes between Government corporations was not meant to prescribe a mechanism recognized by the old or the new Arbitration Act nor was the special procedure meant to be a substitute for a proper adjudication under the said two enactments. It was contended that in as much as the Arbitrator under the special procedure had determined the issue referred to him to the prejudice of the appellant company, it was open to the latter to assail the adjudication in a proper civil action which action was not F G H 78 [2016) 5 S.C.R. SUPREME COURT REPORTS - A barred by any law nor could the same be thrown out merely because a purely administrative procedure for a possible amicable resolution of the conflict had been adopted no matter without the sanction of law. It was urged that the mechanism provided for under the decisions of this Court in ONGC matters was in any case _11011-est_ the same having been scrapped by the Constitution Bench of this __ Court in· _Electronics_ - B _Corporation of India Ltd. v. Union of India, (2011) 3 SCC 404._ Reliance was also placed by Mr. Patwalia upon the decision of this Court in _Oil and Natural Gas Commission v. Collector of Central Excise, (2004) 6 SCC 43 7_ to urge that no suit filed by the parties to the dispute and covered by the administrative machinery could be dismissed - c as untenable. All that could be done was to give to the plaintiff an opportunity to obtain permission of the Committee on Disputes to proceed with the same. 12. On behalf of the respondent, Mr. Ranjit Kumar, learned Solicitor General strenuously argued that High Court was justified in rejecting the - D plaint as the very purpose of providing a special mechanism for adjudication of the disputes would be defeated if any such adjudication could be questioned in any civil action as was sought to be done by the appellant-herein. It was contended ~y Shri Kumar that the arbitral proceedings conducted by the Arbitrator under the special mechanism may be outside the statutory framework of the two enactments, yet the - E efficacy of the adjudication could not be doubted. He urged that ·even when the adjudication by the Arbitrator under the special mechanism did not tantamount to a decree enforceable in a Court of law, the fact that both the corporations were owned by the Government was sufficient by itself to facilitate recovery of the amount payable to one by the other - F and thereby effectuate the execution of the award by way of administrative action. 13. We have given our anxious consideration to the submissions made at the Bar. Before we deal with the contentions urged at the Bar, we need to advert to the historical backdrop in which the special G mechanism came to be prescribed by the Government. 14. Commercial disputes between public sector enterprises _inter_ seas well as between the public sector enterprises and the Government departments were in the ordinary course settled through arbitration by Government Officers or good offices of empowered government agencies H like Bureau of Public Enterprises. Department oflegal affairs however _MIS._ NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING 79 CORP. LTD. & ANR. [T.S. THAKUR, CJI] A submitted a note dated 8[1] h May, 1987 on the subject which was considered A by a Committee of Secretaries in its meeting held on 26[1] h June, 1987. The Committee of Secretaries suggested that a permanent machinery for arbitration should be set up in the Department of Public Enterprises to settle all commercial disputes between PSE _inter se_ and between PSE and Government department excluding disputes concerning income B tax, customs and excise. The Committee also suggested that there should be a contractual clause binding the parties to the commercial contracts to refer all their disputes for settlement to the Permanent Machinery of Arbitrators. The Committee of Secretaries proposed that Bureau of Public Enterprises should bring a note for consideration of the Cabinet in that regard which note was prepared and upon submission to the Cabinet c was approved in its meeting held on 24'h February, 1989. The Cabinet decision envisaged that all Public Sector Enterprises include a contractual clause in their future and current commercial contracts regarding settlement of disputes by arbitration by resorting to Permanent Machinery of Arbitration and that administrative Ministries shall issue necessary D directives to the PSEs under the relevant clause of the Articles of Association. The directives and draft outline of procedure to be followed by the Permanent Machinery of Arbitrators in the Bureau of Public Enterprises was accordingly issued in terms of OPE 0.0. No. 15(9)/ 86-BPE(Fin) dated 29[1] h March, 1989. The procedure for settlement of disputes so devised was however outside the framework of the Arbitration E Act, 1940 which then held the field. This is evident from Para 2 of the draft outline of the procedure which reads as under: c D _"2. The Arbitration Act, 1940 (JO of 1940) shall not be applicable to the arbitration under this clause. The award of the sole arbitrator shall be binding upon the parties to the dispute. Provided, however, any party aggrieved by such award may make a jilrlher reference for setting aside or revision of the award to the Law Secretary, Department of Legal Affairs, Ministry of Law & Justice, Government of India. Upon such further reference, the dispute shall be decided by the Law Secretary or the Special Secretary/ Additional Secretary when so authorised by the Law Secretary, whose decision shall bind the parties finally and conclusively._ " F G H 80 [2016] 5 S.C.R. SUPREME COURT REPORTS 15. While the Permanent Machinery of Arbitration was put in place in terms of the above order and while instructions to the public sector undertakings and public sector enterprises to take resort to the said procedure also remained in force, instances of public sector undertakings resorting to legal proceedings instead of complying with those instructions came to the notice of this Court in _Oil mu/ N(ltUr(I/_ B _G"s Commission (Ind Anr. v. Collector of Ce11tral Excise 1995 Supp (4) sec 541_ in which this C:ourt taking note of such legal proceedings at considerable public expense resulting in waste of valuable Court time directed Government of India to set up a Committee consisting of representatives from-the Ministry of Industry and Commerce, Bureau c of Public Enterprises and the Ministry of Law to monitor disputes _inter se_ Public Sector Undertakings and with the Government to ensure that no litigation came to the Courts and Tribunals without the matter having being first examined by the Committee for grant or refusal of clearance for litigation. This Court made it obligatory for every Court and every Tribunal where such a dispute is raised to demand a clearance from the D Committee in case it has not been so pleaded, and also directed that in the absence of such a clearance the proceedings would not be carried forward. It was pursuant to the said directions that a Committee of Disputes headed by the Cabinet Secretary was constituted by the Government oflndia in terms of Cabinet Secretariat OM No.53/3/6/91E Cabinet dated 31" December, 1991. B c D 16. More than a decade after the setting up of the Committee aforementioned this Court in _Oil mul N"tur(lf G"s Commissio11 v. Collector of Ce11tral Excise, (2004) 6 SCC 437_ clarified the previous order to say that in the absence of a clearance from the Committee, the F Courts would not proceed with the case but a suit could be instituted by a Public Sector Undertaking to save limitation. This Court observed: - _'"4. There are some doubts and proble111s that have arisen in the working out of these arrangements which require to be clarified and so111e crease ironed out. Some doubts_ - G _persist as to the precise i111port and i111plications of the words and "recourse to litigation should be avoided". It is clear that order of this court is not to effect that_ - _nor can that be done- so far as Union oUndia and its statutory corporations are concerned. the statutory re111edles are effaced. Indeed. the purpose of the_ H M/S. NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING CORP. LTD. & ANR. [T.S. THAKUR, CJI] 81 _Constitution of the High Power Committee was not to take awav those remedies._ A ## _Xxx_ _5. Accordinglv. there. should be no bar to the lodgment of an a{2,peal or petition either by the Union oflndia or the Public Sector Undertakings bef(ire any court or tribunal so as to save limitation. But. before such filing every endeavor should be made to have the clearance of the High Power Committee._ B _Xxx_ c _6. Wherever appeals. petitions etc. are filed without the clearance of the High Power Committee. so as to save limitation. the appellant or the petitioner as the case may be, shall within a month from such filing. refer the matter to the High Power Committee with prior notice to the Designated Authority in Cabinet Secretariat of Government of lnaia authorised to receive notices in that behalf Sri. K. T.S. Tulsi, learned Additional Solicitor General, stated that in order to coordinate these references of the High Power Committee the Government proposes to nominate the Under Secretary (Coordination) in the Cabinet Secretariat as the nodal authority to coordinate these references. The reference shall be deemed to have been made and become effective only after a notice of the reference is lodged with the said nodal authority. The reference shall be deemed to be valid if made in the case of the Union of India by its Secretary, Ministry of Finance Department of Revenue, and in the case of Public Sector Undertakings by its Chairman, Managing Director or chief Executive, as the case may be. It is only after such reference to the High Power Committee is made in the manner indicated that the operation of the order or proceedings under challenge shall be suspended till the High Power Committee resolves the dispute or gives clearance to the litigation. If the High Power Committee is unable to resolve the matter for reasons to be recorded by it. it_ D E F G H 82 [2016] 5 S.C.R. SUPREME COURT REPORTS A ## _shall grant clearance [or the litigation."_ (emphasis supplied) 17. In _Oil and Natural Gas Corporation Ltd. v. City and Imlust. Dev. Corpn., Maliaraslttra and Ors._ (2007) 7 SCC 39 this Cou11 ordered the constitution of another Committee to look into the disputes between Central Government and State Government entities. Then came _Commissioner of Income Tax, De/Iii-VI v. Oriental Insurance Co. Ltd._ (2008) 9 SCC 349 in which this Court while clarifying its earlier order in _Oil and Natural Gas Commission v. Collector of Central Excise,_ (2004) 6 SCC 437 observed that there was no rigid time frame prescribed by the Court and that merely because there was some delay in approaching the Committee did not mean that the action was illegal. The following passage is in this regard apposite: B c - _"JO. It needs to be emphasized that there was actually no rigid time frame indicated by this Court. The_ - D _emphasis on one month '.s ti111e was to show urgency needed. Merely because there is some delay in approaching the Co111111ittee that does not make the action illegal. The Committee is required tu deal with the matter expeditiously so that there is no unnecessary backlog of appeals which ultimately 111ay not be pursued._ - E _Jn that sense, it is i111perative that the concerned authorities take urgent action otherwise the intended objective would be frustrated. There is 110 scope for lethargy. It is to be tested by the Court as to whether there was any indifference and lethargy and in_ - F _appropriate cases refuse to interfere. Jn these cases factual position is not that. Therefore, we set aside the order of the High Court in each case and direct consideration of the question of desirability to proceed in the matter before it on receipt of the report from the concerned Committee._ D E ## G ## _Xxx_ H _J 2. It is to be noted that where vermission has bee11 grallled by the Committee there is 110 impediment on the Court to examine the matter and take a decision on merits. But where there is no belated approach as noted_ _MIS._ NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING 83 CORP. LTD. & ANR. [T.S. THAKUR, CJ!] A _above, the matter has. to be decided. Court has to decide whether because of unexplained delay and lethargic action it would decline to entertain the matters. That would depend on the (actual scenario in each case. and no straight jacket formula can be adopted."_ (emphasis supplied) 18. In _Commissioner of Central Excise v. Bltarat Petroleum Corp. Ltd._ (2010) 13 SCC 42, this Court, held that working of the ·coo had failed as numerous difficulties had been experienced by the COD which were expressed in the Cabinet Secretary's letter dated 9[1] h March, 2010. This Court observed "./. _Jn our experience, the working of the COD has failed. Numerous difficulties are experienced by the COD which are expressed in the letter of the Cabinet Secretary, dated 9th March, 2010. Apart from the said letter, we .find in numerous matters concerning public sector companies that different views are expressed by COD which results not only in delay in filing of matters but also results into further litigation. In the circumstances, we find merit in the submission advanced before us by learned Attorney General that time has come to revisit the orders passed by the three Judge Bench of this Court ilf Jhe case of Oil & Natural Gas Commission v. Collector of Central Excise (supra)."_ 19. The matter was accordingly referred to a larger bench to reconsider the earlier decisions directing constitution of the COD. The matter was eventually heard and decided by a Five Judge Bench of this Court in _Electronics Corpomtio11 of India Ltd. v. Union of India, (2011) 3 SCC 404._ This Court after noticing various flaws in the working of the Committee ofDisputes ordered recall ofits previous orders passed by it in the following words: _"6 ...... By Order dated 11.9.1991, reported in 1992 Supp (2) SCC 432 (ONGC and Am: v. CCE), this Court noted that "Public Sector Undertakings of Central Government and the Union of India should not fight their litigations in Court". Consequently, the Cabinet Secretary, Government of India was "called upon to_ B c D E F G H 84 [2016] 5 S.C.R. SUPREME COURT REPORTS A **B** c D E F G H _handle the matter personally"._ 7. _This was followed by the order dated 11.10.1991 in_ _**ONGC-11** case (supra) where this Court directed the Government of India "to set up a Committee consisting of representatives from the Ministry of Industry, Bureau of Public Enterprises and Ministry of Law, to monitor disputes between Ministry and Ministry of Government of India, Ministry and public sector undertakings of the Government of India and public sector undertakings betWeen themselves, to ensure that no litigation comes to Court or to a Tribunal without the matter having been first examined by the Committee and its clearance for litigation"._ _8. Thereafter, in_ _**ONGC-lll** case (supra), this Court directed that in the absence of clearance from the "Committee of Secretaries" (CoS), any legal proceeding will not be proceeded with. This was subject to the rider that appeals and petitions filed without such clearance could be filed to save limitation. It was, however, directed that the needful should be done within one month from such filing, failing which the matter would not be proceeded with. By another order dated 20. 7.2007 (ONGC-IVth case) this Court extended the concept of Dispute Resolution by High-Powered Committee to amicably resolve the disputes involving the State Governments and their Instrumentalities._ _9. The idea behind setting up of this Committee, initially, called a "High-Powered Committee" (HPC), later on called as "Committee of Secretaries" (CoS) and finally termed as "Committee on Disputes." (CoD) was to ensure that resources of the State are not frittered away in inter se litigations between entities of the State, which could be best resolved, by an empowered CoD. The machinery contemplated was only to ensure that no litigation comes ·to Court without the parties having had an opportunity of conciliation before an in-house committee. [see: para 3 of'the order dated 7.1.1994 (supra)} Whilst the principle and the object behind the aforestated Orders_ M/S. NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING 85 CORP. LTD. & ANR. [T.S. THAKUR, CJI] _is unexceptionable and laudatory, experience has shown that despite best e[forts of the CoD. the mechanism has 'not achieved the results for which it was constituted and has in fact led to delays in litigation. We have already given two examples hereinabove. They indicate that on same set of facts. clearance is given in one case and refused in the other. This has led a PSU to institute a SLP in this Court on the ground of discrimination. We need not multiply such illustrations. The mechanism was set up with a laudatory object. However. the mechanism has led to delay in filing of civil appeals causing loss of revenue. For example, in many cases of exemptions, the Industry Department gives exemption, while the same is denied by the Revenue Department. Similarly, with the enactment of regulatory lmvs in several cases there could be overlapping of jurisdictions between, let us say, SEB1 and insurance regulators. Civil appeals lie to this Court. Stakes in such cases are huge. One cannot possibly expect timely clearance by CoD. In such cases, grant of clearance to one and not to the other may result in generation of more and more litigation. The mechanisnl has outlived its utiliiy. Jn the changed scenario indicated above, we are of the view that time has come under the above circumstances to recall the directions of this Court in its various Orders reported as 1995 Supp (4) SCC 541 dated 11.10.1991. {ii) (2004) 6 sec 437 dated 7.1.1994 and (iii) (2007)_ 7 _sec 39 dated 20. 7.2007._ A B c D E F _10. In the circumstances, we hereby recall the following Orders reported in:_ _(i) 1995 Supp (4) SCC 541 dated 11.10.1991_ _(ii) (2004) 6 sec 437 dated 7.1,1994_ _(iii) (2007)_ 7 _sec 39 dated 20. 7.2007"_ G (emphasis supplied) 20. The Government of India had, in the intervening period, consolidated into a single set of guidelines the Permanent Machinery of Arbitration for settlement of commercial disputes and the directives issued by this Ccrnrt regarding constitution of Committee on Disputes in terms H 86 [2016] 5 S.C.R. SUPREME COURT REPORTS - A of a circular issued by the Department of Pub I ic Enterprises vi de order No. OPE O.M. No.DPE/4(10)/2001-PMA-GL-1 dated 22"d January, 2004 which inter alia provided for creation of Permanent Machinery of Arbitrators (PMA), stated the need for creation of such a machinery, indicated the entitlement of departments/ PSEs, CPSC, banks etc. to take resort to the said machinery, fixed monetary limits, stipulated fees - B payable towards arbitration, provided for an appeal against the award and also provided for clearance from the Committee on Disputes. The instructions issued to PSES, CPSEs, banks etc. stipulated the incorporation of a clause in current and future contracts/ agreements which specifically excluded the application of Arbitration and Conciliation - c Act, 1996 to arbitrations conducted under the Permanent Machinery of Arbitration. The arbitration clause recommended for inclusion in the current and future contracts/ agreement was to be in the following words: - _"In the event of any dispute or difference relating to the interpretation and application of the provisions of_ - D _the contracts, such dispute or difference shall be referred by either party for Arbitration to the sole Arbitrator in the Department of Public Enterprises to be nominated by the Secretary to the Government of India in-charge of the Department of Public Enterprises. The Arbitration and Conciliation Act, 1996 shall not be_ - E _applicable to arbitration under this clause. The airard of the Arbitrator shall be binding upon the parties to the dispute, provided, however, any party aggrieved by such award may make a further reference for setting aside or revision of the award to the Law Secretary,_ - F _Department of Legal Affairs, Ministry of Laiv & Justice, Government of India. Upon such reference the di5pute shall be decided by the Law Secretary or the Special Secretary/Additional Secretary, when so authorized by the Law Secretary, whose decision shall bind the Parties finally and conclusively. The Parties lo the dispute will_ - G _share equally the cost of arbitration as intimated by the Arbitrator":_ _(emphasis supplied)_ 21 . Reference may also be made to Office Memorandum dated H _MIS._ NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING 87 CORP. LTD. & ANR. [T.S. THAKUR, CJI] 12[1] h June, 2013 issued by the Government oflndia, Ministry oflndustries and Public Enterprises, Department of Public Enterprises revising the guidelines further and deleting from the earlier guidelines Para 13 that required clearance from the Committee of Disputes. _A_ 22. The net effect of the above can be summarized as under: - (i) The Permanent Machinery of Arbitration was put in place as early as in March, 1989, even before _ONGC II_ was decided on 11 '" October, 1991. - (ii) The Permanent Machinery of Arbitration was outside the statutory provision then regulating arbitrations in this country namely Arbitration Act, 1940 ( 10of1940). - (iii) The award made in terms of the Permanent Machinery of Arbitration being outside the provisions of the Arbitration Act, 1940 would not constitute an award under the said legislation and would therefore neither be amenable to be set aside under the said statute nor be made a rule of the court to be enforceable as a decree lawfully passed against the judgment debtor. - (iv) The Committee on disputes set up under the orders of this Court in the series of orders passed in ONGC cases did not prevent filing of a suit or proceedings by one PSE/PSU against another or by one Government depatiment against another. The only restriction was that even when such suit or proceedings was instituted the same shall not be proceeded with till such time the Committee on Disputes granted permission to the paiiy approaching the Court. B c D E F - (v) The time limit fixed for obtaining such permission was also only directory and did not render the suit and/ or proceedings illegal if pennission was not produced within the stipulated period. - (vi) The Committee on Disputes was required to grant permission for instituting or pursing the proceedings. If the High Power Committee (COD) was unable to resolve the dispute for reasons to be recorded by it, it was required to grant clearance for litigation. - (vii) The Committee on Disputes experience was found to G H 88 [2016] 5 S.C.R. SUPREME COURT REPORTS A be unsatisfactory and the directives issued by the Court regarding its constitution and matters incidental thereto were recalled by the Constitution Bench of this Court thereby removing the impediment which was placed upon the Court's/Tribunal's powers to proceed with the suit/ legal proceedings. The Department of Public Enterprises B has subsequent to the recal I of the orders in the ONGC line of cases modified its guidelines deleting the requirements for a COD clearance for resorting to the Permanent Machinery of Arbitration and; - (viii) The Permanent Machinery of Arbitration was and - c continues to be outside the purview of Arbitration Act, 1940 now replaced by Arbitration and Conciliation Act, 1996. 23. Let us now see the case at hand in the light of the above propositions. It is true that the disputes between the appellant and D respondents were referred for settlement in terms of the Permanent Machinery for Arbitration as early as in the year 1993/1994. It is also not in dispute that as on the date of the said reference the Committee on Disputes was already set up but no permission for a reference was taken. That the Arbitrator made an award under the Permanent Machinery of Arbitration which was questioned in appeals before the E Law Secretary who made some alterations in the same is also admitted. That the award so made has not been accepted by tfie-appel lants is also common ground in as much as the appellant has filed a suit challenging an arbitral award in Civil Suit No.1709 of 2000 in which the appellant claimed a declaration that the contracts were rendered null and void on F account on the breach of Clause 3 thereof. The appellant also sought a declaration that the respondent company was not entitled to claim any relief under the said contract nor was respondent No.2 entitled to do so and that the so called arbitral award was vitiated on the face of record hence liable to be set aside. That such a suit could be filed but could not be proceeded with till such time the COD granted permission is also G beyond dispute as on the date of the institution of the suit the direction of this Court in ONGC group of cases still held the field. Such permission could be obtained within 30 days which was not sacrosanct but the institution of the suit itself could not be faulted as a litigant was in terms of the direction of this Court entitled to institute the proceedings to save H limitation. The High Court has, all the same, rejected the plaint on the _MIS._ NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING CORP. LTD. & ANR. [T.S. J:HAKUR, CJ!] 89 ground that permission from COD was not obtained. In doing so the High Court obviously understood the direction of this Court to mean as though absence of such permission was a fatal defect which it was not. The orders of this Court to which we have made a reference earlier unequivocally make it clear that filing of the suit in itself was not barred. What was restrained was further progress in the suit till such time permission from the COD was obtained. In as much as the High Court considered the absence of permission from COD to be a mandatory legal requirement for the institution of the suit it committed a mistake. No such legal requirement could be read into the judgment of this Court nor has any such requirement been pointed out by Mr. Ranjit Kumar, learned Solicitor General appearing before us. 24. The question then is whether the requirement of the clearance of COD could be insisted upon even at this stage. Our answer is in the negative. We say so because COD stands abrogated/dissolved and the orders directing constitution of such a Committee reversed. Since there is no COD at present there is no question of either obtaining or insisting upon any clearance from the same. The upshot of the above discussion is that the orders passed by the High Court rejecting the plaint on the ground that the same was not preceded or accompanied by permission from COD is unsustainable, are hence, liable to be set aside. 25. That brings us to the question whether we ought to remand the matter back to the Civil Court for adjudication and ifthat were not a desirable course of action whether adjudication of the matters in dispute by way of arbitration would be a better option. It was argued by Mr. Ranjit Kumar, learned Solicitor General that the respondent has an award in its favour made in terms of the Permanent Machinery of Arbitration and that so long as that award stands there is no need for any fresh or further arbitration on the claims already adjudicated upon under the said mechanism. The argument appears to be attractive at first blush but does not survive a closer scrutiny. That is so because an arbitral award under the Permanent Machinery of Arbitration may give quietus to the controversy if the same is accepted by the parties to the dispute. In cases, however, a party does not accept the award, as is the position in the case at hand, the arbitral award may not put an end to the controversy. Such an award being outside the framework of the law governing arbitration will not be legally enforceable in a court oflaw. In fairness to Mr. Ranj it Kumar, learned Additional Solicitor General, we must mention A B c D E F G H 90 [2016] 5 S.C.R. SUPREME COURT REPORTS - A that he did not dispute that the award made by the arbitrator under the Permanent Machinery of Arbitration was outside the statute regulating arbitration in this country and was not, therefore, executable in law. What he argued was that since both sides to the disputes were government corporations the Government could adopt administrative mechanism for recovering the amount held payable to the respondent. That does not, in - B our opinion, answer the question. Remedies which are available to the Government on the administrative side cannot substitute remedies that are available to a losing party according to the law of the land. The appellant has lost before the arbitrators in terms of the Permanent Machinery of Arbitration and is stoutly disputing its liability on several - c grounds. The dispute regarding liability of the appellant under the contract, therefore, continues to loom large so long as it is not resolved finally and effectually in accordance with law. No such effective adjudication recognized by law has so far taken place. That being so, the right of the appellant to demand such an adjudication cannot be denied simply because it happens to be a Government owned company for even when - D the appellant is a government company, it has its legal character as an entity separate from the Government. Just because it had resorted to the pennanent procedure or taken part in the proceedings there can be no estoppel against its seeking redress in accordance with law. That is precisely what it did when it filed a suit for declaration that the award - E was bad for a variety of reasons and also that the contract stood annulled on account of the breach committed by the respondents. 26. Having said that, Mr. Patwalia made a candid statement after instructions that the appellant would have no difficulty in having all the claims and counter-claims of the appellants and the respondentF corporation referred to adjudication in accordance with law to a sole arbitrator to be nominated by this Court. To facilitate such a reference Mr. Patwalia has on instructions sought deletion of respondent No.2 from the array ofrespondents which prayer we see no reason to decline especially because the dispute is between the two corporations which alone ought to be referred to adjudication in accordance with law. G Respondent No.2 shall accordingly stand deleted from the array of pa11ies. 27. Mr. Ranj it Kumar was, however, somewhat diffident in making a concession that the claim could be referred for a fresh round of arbitration in accordance with provisions of Arbitration and Conciliation H M/S. NORTHERN COALFIELD LTD. v. HEAVY ENGINEERING CORP. LTD. & ANR. [T.S. THAKUR, CJI] 91 Act, 1996. That diffidence does not prevent us from making a suitable order of reference to a sole arbitrator for adjudication of all outstanding disputes between the two corporations especially because the alternative to such arbitration is a long drawn expensive and cumbersome trial of the suit filed by the appellant before a civil court and the difficulties that beset the execution of an award made under a non-statutory administrative mechanism. Both these courses are unattractive with no prospects of an early fruition even after the parties have fought each other for nearly twenty years. 28. In the result we allow this appeal and set aside the judgment and order passed by the High Court. We further direct that all disputes relating _to_ and arising out of the contracts executed between the appellant company and the respondent corporation shall stand referred for adjudication to Hon'ble Mr. Justice K.G. Balakrishnan, Former Chief Justice of this Court, who is hereby appointed as Sole Arbitrator to adjudicate upon all claims and counter claims which the parties may choose to file before him. Civil Suit(OS) No.1709/2000 shall also stand disposed of in terms of this order. The pa11ies shall appear before the Arbitrator on 22"d of August, 2016 for further directions. The Arbitrator shall be free to determine his own fee. No costs. A B c D Dcvika Gujral l\pp<'al allowctl. E
End of Judgment Record
Browse All Supreme Court of India (2016) Decisions
2016-03-16

Union of India v. Mis. Ambica Construction

This judgment addresses whether an arbitrator can award pendente lite interest when a contract expressly bars such interest, within the framework of Indian arbitration law. The Union of India approached this dispute after two arbitrators failed to publish an award and after a long procedural history in the Calcutta High Court and various SLPs. The core issue is whether pendente lite interest can be awarded where the contract contains explicit clauses barring such interest, and how this interacts with the implied terms of arbitration under the Arbitration Act, 1940 and, for post-1996 matters, the Arbitration and Conciliation Act, 1996. The Court traces a lineage of decisions (GC Roy; NC Budharaj; Sayeed Ahmed; Harish Chandra; Balimela; Engineers-De-Space-Age; Tehri Hydro) and clarifies that while arbitrators are generally creatures of the contract, their power to award pendente lite interest is bounded by express contractual bars. It concludes that no pendente lite interest can be awarded if the contract expressly prohibits it. The judgment also recognizes Tehri Hydro’s reasoning and clarifies the status of earlier decisions, holding certain observations as overruled or limited prospectively. The result is that the High Court and the award are to be modified to reflect the absence of pendente lite interest, with a reference answered and no costs awarded.”

2016-08-29

Madhya Pradesh State Road Transport Corporation v. Manoj Kumar & Anr.

This is a civil appeal challenging the voluntary retirement scheme (VRS) introduced by the Madhya Pradesh State Road Transport Corporation (MPSRTC) to downsize its workforce as the company faced losses and declining business. The scheme opened on July 1, 2005 and closed on August 1, 2005, with employees permitted to submit their option for voluntary retirement (VRS) within that window. The scheme included a clause stating that once an employee’s option was submitted it could not ordinarily be withdrawn, yet the scheme was a funded, time-bound arrangement requiring the employer to create a fund and to lay out a process for acceptance and settlement. In October 2006, the Corporation issued an amendment extending the period to October 28, 2006, prompting questions whether this extension created a new scheme or was merely an extension of the original. Several employees who had submitted applications sought withdrawal after August 1, 2005, and in some cases after the extension, while the Corporation accepted their VRS applications and disbursed terminal dues. The High Court of Madhya Pradesh upheld the employees’ right to withdraw within the relevant periods, but the Supreme Court concluded that VRS schemes, being contractual and funded, are invitations to offer governed by the Indian Contract Act, and withdrawals are permissible only within the valid period; the extension does not automatically grant a right to withdraw beyond the original window. The Court accordingly set aside some reinstatement orders and disposed of the appeals in favor of the Corporation in most respects.

2016-07-01

Mahipal Singh Rana, Advocate v. State of Uttar Pradesh

The appeal arises from a High Court of Allahabad judgment (Criminal Contempt Petition No.16 of 2004) finding the appellant, an advocate, guilty of criminal contempt for intimidating and berating a Civil Judge, Etah, on two dates (16 April 2003 and 13 May 2003). The Allahabad High Court sentenced him to two months’ simple imprisonment and imposed a fine, with a direction to Bar Council authorities to consider disciplinary action for professional misconduct. On admission to this Supreme Court, the matter was referred to a larger bench to decide whether a case of criminal contempt by a lawyer could also implicate professional misconduct beyond the contempt regime, and whether the Court could exercise suo motu jurisdiction under the Advocates Act if Bar Councils fail to act. The Court examined the separation of powers between contempt proceedings and Bar Council disciplinary processes, the scope of Article 142/129, and the ability to regulate appearance in courts (including the right to practice vs. the right to appear). It held that contempt conviction was justified and upheld the High Court’s finding, but set aside the imprisonment sentence due to the appellant’s advanced age. It sustained a two-year enrollment suspension under Section 24A of the Advocates Act and directed the Bar Councils to suspend the licence for an additional five years, with further appearance restrictions until the contemnor purges himself of contempt. The judgment emphasizes reform of regulatory mechanisms governing the legal profession and the State Bar Councils’ failings in acting on earlier notices.

2016-03-10

CHARANJIT KAUR v. BIKRAM SINGH & ANR.

Charanjit Kaur, wife of Bikram Singh, faced dowry-related harassment under sections 498A and 406 IPC. The trial court convicted the husband and imposed a one-year RI for each offence, with the sentences to run concurrently and a fine of Rs. 1,000/- with default imprisonment. The wife appealed against the conviction and also sought enhancement of punishment; the husband cross-appealed. The mother-in-law was acquitted; the father-in-law had died. The Sessions Court at Kapurthala modified the sentence by permitting the husband to deposit Rs. 2,50,000 payable to the appellant within one month, so that he could obtain the benefit of probation under Section 4(1) of the Probation of Offenders Act, 1958. The wife’s revision before the High Court of Punjab & Haryana at Chandigarh was dismissed in a summary manner, reportedly influenced by the deposit. The Supreme Court, noting the summary disposal and the deposit-driven rationale, held that the impugned order required setting aside so that the matter could be re-heard on merits. It directed remand to the High Court for a fresh decision strictly in accordance with law, without entering into the merits of rival submissions in this order. The decision was delivered by a Single Judge, Justice Shiva Kirti Singh, on March 10, 2016.