M/S. MITRA GUHA BUILDERS (INDIA) COMPANY vs OIL AND NATURAL GAS CORPORATION LIMITED
Case Synopsis & Summary
This Supreme Court Civil Appeals arise from two related arbitrations under ONGC’s contract for construction work at Noida (two separate agreements: DHL/Civil/NOIDA/6/94 and DHL/Civil/NOIDA/5/94). The Arbitrator awarded some claims in both arbitration cases but disallowed liquidated damages and related interest, directing that the withheld amounts be adjusted against the final bills. ONGC challenged these awards under Section 34 of the Arbitration and Conciliation Act, 1996, which the Single Judge initially upheld, but the Delhi High Court, in a Division Bench, reversed, holding that the levy of liquidated damages is an “excepted matter” under Clause 2 read with Clause 25 of the contract and thus not arbitrable, and set aside the Arbitrator’s findings. The matter then went to the Supreme Court. The Constitution of the bench—R. Banumathi, J., with A.S. Bopanna, J. and Hrishikesh Roy, J.—held that Clause 2 creates a complete machinery for determining liability for delay and empowers a final decision by the Superintending Engineer, which is outside arbitration; the appeals were dismissed, upholding the High Court’s view. The Court directed the amount already deposited to be paid to ONGC with applicable adjustments and interest, while ensuring reconciliation of final accounts. The decision clarifies the interplay between excepted matters and arbitration clauses in government contracts and reaffirms that finality provisions may bar arbitration when the contract assigns a named adjudicator.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- R. Banumathi, J.
- A.S. Bopanna, J.
- Hrishikesh Roy, J.
- Judgment Date
- 2019-11-08
- Court Decision / Holding
- The appeals are dismissed.
- Final Disposition
- Appeals dismissed; No order as to cost.
Parties to the Case
Appellants / Petitioners
- M/S. Mitra Guha Builders (India) Company
Respondents
- Oil and Natural Gas Corporation Limited (ONGC)
Legal Representation & Advocates
Counsels for Petitioners
- • Mr. Bipin Prabhat (counsel for the appellant)
Counsels for Respondents
- • Mr. K.M. Natraj, Additional Solicitor General, assisted by Mr. Akshay Amritanshu (counsel)
Provisions of Law Cited
Legal Doctrines & Maxims
- Finality of administrative decisions under a contract (finality clause)
- Excepted matters doctrine (as per Food Corporation of India v. Sreekanth Transport)
- Arbitrability of disputes under arbitration clause 25 when contract designates a specific adjudicator
- Vishwanath Sood v. Union of India and Another (1989) 1 SCC 657 (ratio applied to non-arbitrability of certain decisions)
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant argued that Clause 25 of the contract provides for arbitration of disputes arising under the contract and that the levy of liquidated damages under Clause 2 is not an excepted matter. Clause 2 furnishes a complete mechanism for determination of delay liability, with the Superintending Engineer’s decision being final. The Division Bench erred in treating the levy as an excepted matter; the arbitrator’s jurisdiction should extend to disputes regarding liquidated damages, and the petition under Section 34 should not have been used to challenge an otherwise final contractual determination.
Contentions of Respondents
ONGC contended that Clause 2 creates a final and non-arbitrable determination by the Superintending Engineer as to liquidated damages, an “excepted matter” not subject to arbitration under Clause 25. The Superintending Engineer’s decision is a final, binding determination on compensation for delay and is outside the purview of arbitration. The High Court correctly reversed the Arbitrator’s award in this respect, and BSNL/Food Corporation precedents support the non-arbitrability of such excepted matters.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (4)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Vishwanath Sood v. Union of India and Another | (1989) 1 SCC 657 | Positive | Cited to support the proposition that the question of awarding compensation under clause 2 is outside the purview of the arbitrator and the finality is a matter determined by an official designated in the contract. |
| Food Corporation of India v. Sreekanth Transport | (1999) 4 SCC 491 | Positive | Used to illustrate the concept of ‘excepted matters’ where the contract designates a named adjudicator; the decision of that adjudicator is final and not arbitrable. |
| Bharat Sanchar Nigam Limited and Motorola India (P) Ltd. | (2009) 2 SCC 337 | Distinguished | The present case is distinguished on the facts; BSNL dealt with a different contractual framework where the clause there did not confer finality on liquidated damages—hence not applicable here. |
| Food Corporation of India v. Sreekanth Transport (referred again) | (1999) 4 SCC 491 | Mentioned Only | Referenced in the discussion on excepted matters to anchor the principle, but the later Kerala case clarified the non-applicability more directly. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/S. MITRA GUHA BUILDERS (INDIA) COMPANY vs OIL AND NATURAL GAS CORPORATION LIMITED
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.