M/s Mar Basil Granites and Metals v. Kerala State Electricity Board and Ors.
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- Raja Vijayaraghavan V
- Judgment Date
- 2023-03-07
- Court Decision / Holding
- This writ petition is disposed of. The petitioner is relegated to the statutory remedy under Section 127 of the Electricity Act, with permission to file an appeal before the Kerala State Electricity Board Appellate Authority within four weeks from the date of the order. Coercive proceedings against the petitioner are deferred for four weeks.
- Final Disposition
- Writ petition disposed of; petitioner relegated to statutory remedy under Section 127; four-week window to file an appeal; coercive proceedings deferred for four weeks.
Parties to the Case
Appellants / Petitioners
- M/s Mar Basil Granites and Metals
Respondents
- Kerala State Electricity Board
- The Deputy Chief Engineer, Kerala State Electricity Board Electrical Circle, Thodupuzha
- The Executive Engineer, Electrical Division, Kattappana
- The Assistant Executive Engineer, Electrical Sub Division, Nedumkandom
- The Assistant Engineer, Electrical Sub Division, Udumanchola
- The Sub Engineer, Electrical Sub Division, Udumanchola
Legal Representation & Advocates
Counsels for Petitioners
- • LAL K. JOSEPH
- • T.A. LUXY
- • P. MURALEEDHARAN (THURAVOOR)
- • SURESH SUKUMAR
- • P.K. SEALEM
- • ANZIL SALIM
Counsels for Respondents
- • Sri Riji Rajendran SC
Case Synopsis & Summary
Mar Basil Granites and Metals, a partnership engaged in mining and quarrying, approached this Court seeking to quash Ext. P4 final order under Section 126 of the Electricity Act, 2003, which imposed a penalty of Rs. 17,07,648 for unauthorized connected load. The petitioner contends that it had a High Tension connection with a sanctioned load of 145 KW and a contract demand of 150 KVA under HT1A tariff. An Anti-Power Theft Squad inspection on 14.12.2022 revealed an additional 59 KW load beyond the sanctioned level, leading to provisional assessment (Ext. P2) and a subsequent objection (Ext. P3). The final order (Ext. P4) was issued by the 4th respondent. The petitioner argues that energization approval had been granted and the actual connected load was below sanctioned load; further, the penalty should be based on demand charges for a High Tension consumer, not merely the connected load. The respondents pressed that the remedy lies in Section 127 of the Electricity Act (appeal) and relied on Regulation 99 of the Supply Code; they also invoked precedents including Seetaram Rice Mill (Southco) and Thomas Joseph to justify penalties and tariff interpretation. The Court ultimately held that exhaustion of statutory remedies is required and disposed of the petition, directing the petitioner to pursue a Section 127 appeal before the State Electricity Board Appellate Authority within four weeks, with coercive proceedings deferred for four weeks.
Provisions of Law Cited
Legal Doctrines & Maxims
- Exhaustion of statutory remedies before invoking writ jurisdiction (rule of policy, convenience and discretion)
- When a right is created by a statute, the remedy prescribed by that statute should be pursued before invoking discretionary writ powers
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioner contends the final assessment under Section 126 was not justified as the sanctioned load was higher than calculated; energization approval had been granted and the actual connected load was within sanctioned limits; the penalty should be based on demand charges for HT consumers, not merely the connected load; the calculation used for the percentile load was incorrect and inconsistent with Contract Demand and HT tariff provisions. They also argue that an extraneous extension of supply without a supplementary agreement should not lead to a penalty based solely on apparent over-consumption.
Contentions of Respondents
The respondents submit that the petitioner must exhaust statutory remedies under Section 127 before challenging the order in writ, citing Seetaram Rice Mill and Radha Krishan Industries to support exhaustion and Regulation 99 of the Supply Code for enhanced load/demand. They further argue that tariff principles (including fixed and energy charges) justify penalties when unauthorized use is detected, and rely on Thomas Joseph to interpret tariff-based penalties.
Cited Precedents (3)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Executive Engineer, Southern Electricity Supply Company of Orissa Limited (Southco), and Another v. Sri Seetaram Rice Mill | (2012) 2 SCC 108 | Positive | Court relied on Seetaram Rice Mill to emphasize exhaustion of statutory remedies (appeal under Section 127) before invoking writ jurisdiction. |
| Radha Krishan Industries v. State of Himachal Pradesh | AIR 2021 SC 2144 | Positive | Cited to support the principle that rights created by statute require pursuing the statutory remedy before discretionary writ relief. |
| Electricity Board and Ors. v. Thomas Joseph and Ors. | 2022 SCC Online SC 1737 | Positive | Cited for tariff interpretation, clarifying that tariff comprises fixed charges and energy charges and penalties may correspond to the tariff for unauthorized use. |
Diagnostic Tool
Does this judgment govern your specific facts?