M/S Laxmi Continental Construction Co. v. State of U.P. & Anr.
Case Synopsis & Summary
The dispute concerns an arbitration clause (Clause 52) in a contract between M/S Laxmi Continental Construction Co. (claimant) and the State of Uttar Pradesh ( respondent). An officer of the rank of Superintending Engineer or higher, appointed by the Chief Engineer as the Sole Arbitrator, conducted the arbitration. The agreement provides that the arbitration shall be conducted under the Indian Arbitration Act, 1940, and that the arbitrator’s mandate would ordinarily continue until the proceedings conclude, with the award being final. The Sole Arbitrator entered references in 1992 and, despite several adjournments and the retirement of the arbitrator in 1995, extended periods to complete the arbitration. A Civil Judge extended time by 1997, and an award was passed on 08.01.1998 in favor of the claimant. The respondents challenged the award, and the High Court, in 2007, quashed it and set aside the Civil Judge’s order, citing misconduct by continuing arbitration after retirement. The Supreme Court held that Clause 52 contemplates appointment of a sole arbitrator who remains in office until the arbitration is concluded, and retirement does not ipso facto terminate the mandate. State amendments to Section 4 of the Arbitration Act do not render continuation improper. The appeal is allowed, the High Court’s judgment is quashed, the award and the Rule of Court restored, and no costs are awarded."
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- M. R. Shah
- A. S. Bopanna
- Judgment Date
- 2021-09-20
- Court Decision / Holding
- Appeal allowed. The impugned High Court judgment dated 19.06.2007 is quashed and set aside. The award dated 08.01.1998 and the Civil Judge’s 20.04.2001 order making the award Rule of the Court are restored. No order as to costs.
- Final Disposition
- Appeal allowed; award restored; no order as to costs.
Parties to the Case
Appellants / Petitioners
- M/S Laxmi Continental Construction Co.
Respondents
- State of U.P.
- ANR.
Legal Representation & Advocates
Counsels for Petitioners
- • Mukesh Kumar Sharma
Counsels for Respondents
- • Ravindra Raizada
- • Rajeev Kumar Dubey
- • Ashiwan Mishra
- • Anurag Tiwari
- • Ms. Vaidhruti Mishra
- • Kamlendra Mishra
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contends that Clause 52 of the contract provides for the Chief Engineer to nominate a Sole Arbitrator from three eligible officers of the rank of Superintending Engineer or higher. Once appointed, the Sole Arbitrator continues until the arbitration concludes, unless disqualified under the Arbitration Act, 1940. The clause does not envisage termination of the arbitrator’s mandate upon retirement. The Civil Judge’s extension of time for 30 days and the award dated 08.01.1998 were lawful. The High Court’s finding that retirement amounted to misconduct is unsustainable, as the Civil Judge’s order granting extension had achieved finality. The State Amendment to Section 4 of the Arbitration Act is inapplicable here. Precedents such as Himalayan Construction Co. are relied upon to support continuation after retirement. The appeal seeks restoration of the award and the Court’s Rule, with no costs.
Contentions of Respondents
The respondents argue that once the arbitrator retires, his mandate terminates; the clause does not authorize continuation post-retirement, and the retired officer cannot continue as Sole Arbitrator. They contend that continuing after retirement constitutes misconduct and that the High Court correctly quashed the award and set aside the Civil Judge’s order. They rely on the State Amendment to Section 4 to argue vacancy rules, but contend it is not applicable since the arbitrator did not become incapable of acting. The respondents maintain that the Civil Judge’s extension (11.12.1997) and the subsequent award were illegitimate, and the appeal should be dismissed.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (3)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Himalayan Construction Co. v. Executive Engineer, Irrigation Division, J&K and Anr. | (2001) 9 SCC 359 | Positive | This decision is relied upon to support the proposition that the mandate of a designated arbitrator may continue post-retirement and that retirement does not automatically terminate the arbitrator's mandate. |
| Prasun Roy v. Calcutta Metropolitan Development Authority and Anr. | (1987) 4 SCC 217 | Mentioned Only | Cited in the judgment but not relied upon for the core reasoning; used for reference. |
| N. Chellappan v. Secretary, Kerala State Electricity Board and Anr. | (1975) 1 SCC 289 | Mentioned Only | Cited in discussion, but not essential to the decision; treated as a reference. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/S Laxmi Continental Construction Co. v. State of U.P. & Anr.
Related Decisions & Precedents from Supreme Court of India (2021)
HARI OM @ HERO v. STATE OF U.P.
This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.
INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL
This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.
Hasmat Ali v. Amina Bibi & ORS.
This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.
Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.
This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.