Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2022Division BenchAppeals dismissed

M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS

Case / Petition Number:
Civil Appeal No. 180 of 2022; Civil Appeal No. 268 of 2022
Neutral Citation:[2022] 2 S.C.R. 411

Case Synopsis & Summary

Two related Civil Appeals under Section 23 of the Consumer Protection Act, 1986 arise from complaints by allottees of IREO's SKYON project, Gurgaon, alleging failure to hand over a ready‑to‑use apartment and demanding either delivery in compliance with the Apartment Buyers Agreement (ABA) within six months of the petition or, failing that, refund with interest. The National Consumer Disputes Redressal Commission (NCDRC) found evidence of payment by the allottee and that the allottee would be a consumer under COPRA because the developer did not prove business activity of the buyer. It ordered a refund of Rs 2,23,91,480 with simple interest at 10.25% per annum and observed that amenities promised were not provided. Interim orders directed possession but the appellant could not deliver owing to a reduced workforce at the site; emails from September 2018 supported the conclusion that completion could not be achieved in the target time. The Supreme Court held that the appellant was not in a position to comply with the interim order, and the NCDRC's refund direction could not be faulted. Relying on Siddharth Vasisht and Shamshul Hoda Khan, it held the 42‑month possession period begins from the Fire NOC date (25 September 2013) with a 180‑day grace, ending around 24 September 2017; even then, possession could not be handed over. The Court affirmed refunds with interest and noted breach of promised amenities, distinguishing Abhishek Khanna. The appeals were dismissed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Dr. Dhananjaya Y. Chandrachud
  • Bela M. Trivedi
Judgment Date
2022-01-21
Court Decision / Holding
Appeals dismissed
Final Disposition
Appeals dismissed

Parties to the Case

Appellants / Petitioners

  • M/S IREO PRIVATE LIMITED

Respondents

  • ALOKE ANAND AND OTHERS

Legal Representation & Advocates

Counsels for Petitioners

  • • Ankur Saigal
  • • E. C. Agrawala

Counsels for Respondents

  • • Ms. Nina R. Nariman
  • • Aditya Parolia
  • • Piyush Singh
  • • Nithin C Chandaran
  • • Akshay Srivastava
  • • Sumbul Ismail
  • • Rajesh Kumar
  • • Gaurav Goel
  • • Vaibhav Gaggar
  • • Ms. Sumedha Dan
  • • Utkarss Tiwari
  • • Pai Amit

Provisions of Law Cited

Consumer Protection Act, 1986, Section 23Consumer Protection Act, 1986, Section 2(1)(d)Real Estate (Regulation and Development) Act, 2016Haryana Fire Service Act, 2009

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that under Clause 13.3 of the Apartment Buyers Agreement (ABA) the 42‑month period for handing over possession began from the date of Building Plan approval, with a 180‑day grace, or, alternatively, from the Fire NOC date; citing Abhishek Khanna (three‑judge bench) and IREO Grace Realtech, the period should start from the Fire NOC. It argues possession was offered within the contractual window and the main prayer was possession, with refund only in the alternative if possession could not be delivered; hence there is no basis for a refund.

Contentions of Respondents

The respondents relied on interim orders directing possession upon payment of dues; the appellant’s September 2018 email indicated inability to complete, owing to workforce shortages; construction began before Fire NOC, and the project saw delays in delivery of amenities and possession. They urged that the primary relief was possession and not a refund, and that the delay justified compensation under COPRA and the relevant contractual terms; they also highlighted the NCDRC’s findings on consumer status and breach of promised amenities.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
IREO Grace Realtech Private Limited v. Abhishek Khanna and Others(2021) 3 SCC 241DistinguishedCourt distinguished this decision; facts/foundation differ; the present case applies a Fire NOC‑based timeline instead of starting from building plan approval, following Siddharth Vasisht/Shamshul Hoda Khan line.
Siddharth Vasisht v. IREO Pvt. Ltd. and Ors.Consumer Case No 1062 of 2018; Civil Appeal (Diary) No. 21634 of 2020PositiveRelied upon to uphold that the period for delivery begins from Fire NOC and to reject the appellant’s construction‑from‑pre‑Fire NOC argument.
Shamshul Hoda Khan v. IREO Victory Valley Pvt. Ltd. and Anr.Consumer Case No 2110 of 2016PositivePart of the line of precedents considered in determining the starting point for calculating the possession period; used to support Siddharth Vasisht’s logic.
Abhishek Khanna v. IREO Grace Realtech Private Limited and Others(supra)DistinguishedPresent Court distinguished this three‑judge decision on the facts; held that the present case is distinguishable.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,536 words•~26 min read

In The Court Record

M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS

411 [2022] 2 S.C.R. 411 M/S IREO PRIVATE LIMITED A v. ALOKE ANAND AND OTHERS (Civil Appeal No 180 of 2022) JANUARY 21, 2022 B ## **[DR. DHANANJAYA Y CHANDRACHUD AND BELA M TRIVEDI, JJ.]** _Consumer Protection Act, 1986: Housing – Apartment Buyers Agreement – Apartment not handed over in time by developer – Allottee filed consumer complaint seeking a direction to the developer to provide the apartment, compliant with all the requirements mentioned in the ABA, within six months of the complaint, i.e., by 3 November 2017 – Along with this, the allottee sought compensation for delayed possession, calculated at the rate of 18 per cent p.a. on the amount deposited with the developer from the date on which actual possession was to be delivered (March 2015) and in case developer failed to deliver the possession of the apartment within six months, refund of the principal amount of Rs 2,23,91,480, with interest at 18 per cent p.a. from the date the amount was paid by the allottee to the developer– Inspite of interim direction of NCDRC to handover possession, the same was not given – On 17 May 2018, allottee filed IA bringing on record several photographs showing that the apartment was not ready and was not in a habitable condition – On 25 September 2018, developer sent email that due to limited work force, the finishing work was slow – By impugned judgment, the NCDRC held that the developer did not contest that an amount of Rs 2,23,91,480 was paid by the allottee – It then noted that the allottee would be considered as a consumer within the meaning of s.2(1)(d) of the Act since the developer had not brought on record anything to prove that the allottee was indulging in the business of buying/selling apartments – NCDRC ordered a refund of Rs 2,23,91,480 with simple interest at the rate of 10.25 per cent per annum, which it noted was the rate of interest payable under the Real Estate (Regulation and Development) Act 2016 in Haryana in respect of cases where refund is made to flat buyers due to the delay of the developer in handing over possession – Hence instant appeal – Held: It is apparent that the developer was_ C D E F G H 411 412 SUPREME COURT REPORTS [2022] 2 S.C.R. - A _not in a position to comply with the interim order of the NCDRC for the handing over of possession – Though the interim direction was issued on 16 February 2018, the email of the developer dated 25 September 2018 indicated that possession could not be handed over due to the absence of an adequate work force at the site – Thus, it is evident that the developer was not in a position to hand over_ - B _possession of the apartment even after the interim order – In this backdrop, the order of the NCDRC for the grant of refund at the appropriate rate of interest cannot be faulted – In another set of appeals, the finding of fact recorded by the NCDRC in its impugned judgment dated 22 November 2021 was that the amenities which_ - C _were promised by the developerwere not provided in the Project and the apartment – In view of the matter, the direction for the refund of the amount paid together with interest, cannot be faulted – The developer made a solemn representation to the flat buyer of the amenities which would be provided in the flat and the Project – A breach of this representation is actionable at law._ - D ## **Dismissing the appeals, the Court** **HELD: 1. In the present case, since the Fire NOC was only granted on 25 September 2013, the period for delivery of possession of the apartment (the forty-two months period, along** E **with the 180 days’ grace period) would end on 24 September 2017. The appellant issued a notice of possession to the first respondent on 25 September 2017. However, even if this submission of the appellant is accepted, it is apparent that the appellant was not in a position to comply with the interim order of the NCDRC for the handing over of possession. Though the** F **interim direction was issued on 16 February 2018, the email of the appellant dated 25 September 2018 indicates that possession could not be handed over due to the absence of an adequate work force at the site. Thus, it is evident that the appellant was not in a position to hand over possession of the apartment even after** G **the interim order. In this backdrop, the order of the NCDRC for the grant of refund at the appropriate rate of interest cannot be faulted. [Paras 20, 21][423-G-H; 424-A-C]** _IREO Grace Realtech Private Limitedv.Abhishek Khanna and Others_ **(2021) 3 SCC 241 – distinguished.** H 413 M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS **2.1 In Civil Appeal No 268 of 2022, the first respondent was allotted an apartment in Tower D of the Project. The ABA was signed on 6 September 2013. The appellant issued a notice of possession on 6 September 2016. The first respondent filed a consumer complaint before the NCDRC on 14 February 2017 seeking a refund of the amount paid with interest at 18 per cent per annum or the possession of the apartment, if the appellant was willing to complete the apartment in accordance with the specifications in the ABA in a time bound manner and not charge any further amount over and above the sale consideration. By its judgment dated 22 November 2021, which takes note of the decision of this Court in Abhishek Khanna, the NCDRC directed the appellant to refund the principal amount to the first respondent with interest at the rate of 10.25 per cent per annum. [Para 23][424-D-F]** **2.2 The finding of fact which has been recorded by the NCDRC in its impugned judgment dated 22 November 2021 is that the amenities which were promised by the appellant have not been provided in the Project and the apartment. In the course of discussion, the NCDRC has, in fact, tabulated the amenities which were to be but have not been provided. In this view of the matter, the direction for the refund of the amount paid together with interest, cannot be faulted. The appellant made a solemn representation to the flat buyer of the amenities which would be provided in the flat and the Project. A breach of this representation is actionable at law. [Para 25][424-G-H; 425-A-B]** _Siddharth Vasisht v. lREO Pvt. Ltd. and Ors._ **Consumer Case No 1062 of 2018;** _Shamshul Hoda Khan v. IREO Victory Valley Pvt. Ltd. and Anr._ **Consumer Case No 2110 of 2016 – referred to.** ## **Case Law Reference** **(2021) 3 SCC 241 distinguished** **Para 16** A B C D E F G H 414 SUPREME COURT REPORTS [2022] 2 S.C.R. A CIVIL APPELLATE JURISDICTION: Civil Appeal No. 180 of 2022. From the Judgment and Order dated 01.11.2021 of the National Consumer Disputes Redressal Commission, New Delhi in Consumer Complaint No.1277 of 2017. B With Civil Appeal No. 268 of 2022. Ankur Saigal, E. C. Agrawala, Advs. for the Appellant. Ms. Nina R. Nariman, Aditya Parolia, Piyush Singh, Nithin C Chandaran, Akshay Srivastava, Sumbul Ismail, Rajesh Kumar, Gaurav Goel, Vaibhav Gaggar, Ms. Sumedha Dan, Utkarss Tiwari, Pai Amit, Advs. for the Respondents. The Judgment of the Court was delivered by ## D ## **DR. DHANANJAYA Y CHANDRACHUD, J.** 1. The appeals under Section 23 of the Consumer Protection Act 1986[1] arise from the decision of the National Consumer Disputes Redressal Commission[2] on complaints which were instituted against the appellant by the allotees of its housing project called ‘SKYON’, located E at Golf Course Extension Road in Sector 60 of Gurgaon, Haryana[3] . The appellant advertised that the Project offered state of the art facilities such as home automation devices, Wi-Fi and high-end video door security systems in each apartment. 2. The Building Plans for the Project were approved by the F Directorate of Town and Country Planning, Haryana[4] on 27 September 2011, subject to certain terms and conditions to be fulfilled by the appellant. Thereafter, on 31 July 2012, the State Environment Impact Assessment Authority, Haryana granted an Environment Clearance for the Project. 3. The appellant submitted an application to the Commissioner, G Municipal Corporation, Gurgaon[5] , for approval of the Fire Fighting - 1 “ **COPRA** ” - 2 “ **NCDRC** ” - 3 “ **Project** ” 4 “ **TCP Haryana** ” - H 5 “ **CMC Gurgaon”** 415 M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS [DR. DHANANJAYA Y CHANDRACHUD, J.] Scheme for the Project on 16 January 2012. The CMC Gurgaon granted the approval on 25 September 2013[6] . 4. On 26 August 2016, the Occupation Certificate was issued by the Director General of TCP Haryana in respect of Tower D of the Project. Further, on 14 September 2017, the Occupation Certificate was issued in respect of Tower B of the Project. A B 5. Other than these common facts in relation to the Project, the appeals arise from separate complaints and have distinct facts. However, they raise a common issue. Hence, we shall set out the facts of the lead appeal (Civil Appeal No 180 of 2022) in detail. 6. In Civil Appeal No 180 of 2022, the first respondent filed a booking application for an apartment in the Project on 22 December 2010. An amount of Rs 15,00,000 was paid as booking amount by a cheque dated 14 October 2010. C 7. The appellant issued a letter offering allotment to the first respondent on 14 January 2011, by which the appellant allotted an D apartment having a tentative super area of 2809 sq ft, bearing No B3203, Floor 31 in Tower B of the Project. The appellant and the first respondent entered into an Apartment Buyers Agreement[7] on 14 February 2012. 8. Due to the apartment not being handed over in time by the appellant, the first respondent filed a consumer complaint[8] before the E NCDRC on 3 May 2017. The reliefs claimed in the complaint were as follows: “i. Direct the Opposite Parties to handover possession of Unit to the Complainant, complete in all respects and in conformity with the Allotment Letter and Apartment Buyers’ Agreement, with all additional facilities and as per quality standards promised and execute all necessary and required documents in respect of the said apartment in favour of the Complainant within 6 months of this petition being filed before this Hon’ble Commission or as directed by this Commission; F G ii. Direct the Opposite Parties for an immediate 100% refund of the total principal amount of Rs. 2,23,91,480/- (Rupees Two Crore > 6 “ **Fire NOC** ” > 7 “ **ABA”** > 8 Consumer Complaint No 1277 of 2017 H 416 SUPREME COURT REPORTS [2022] 2 S.C.R. A Twenty Three Lakh Ninety One Thousand Four Hundred and Eighty Only) paid by the Complainant, along with a penal interest of 18% per annum from the date of the receipt of the payments made to the Opposite Parties, in case the Opposite Parties cannot deliver or fail to deliver the absolute, complete and final physical possession of the flat within a period of 6 months of this petition B being filed before this Hon’ble Commission or as directed by this Hon’ble Commission; - A iii. Direct the Opposite Parties to pay a delayed possession compensation equal to interest @ 18% per annum on the amount deposited by the Complainant with the opposite Parties, with effect C from March 2015 i.e. date when possession was promised, till the date of actual possession is handed over by the Opposite Parties along with all necessary documents and common areas and facilities as promised during the initial booking made by the Complainant; - […]” - D - From the prayers, it is clear that the first respondent sought a - direction to the appellant to provide the apartment, compliant with all the requirements mentioned in the ABA, within six months of the complaint, _i.e._ , by 3 November 2017. In relation to this prayer, the first respondent also filed an interim application[9] before the NCDRC seeking a direction - E to the appellant for the delivery of possession of the apartment. Along with this, the first respondent sought compensation for delayed possession, calculated at the rate of 18 per cent per annum on the amount deposited with the appellant from the date on which actual possession was to be delivered (March 2015). However, if the appellant failed to deliver the - F possession of the apartment within six months, the first respondent sought the refund of the principal amount of Rs 2,23,91,480, with interest at 18 per cent per annum from the date the amount was paid by the first respondent to the appellant. 9. The appellant issued a notice to claim possession to the first G respondent on 25 September 2017. On 16 February 2018, the NCDRC passed an interim order, _inter alia_ , in relation to the interim application: - “Arguments on IA No. 17613 of 2017 filed by the complainant heard. By this application, complainant is seeking direction to the - H 9 IA No 17613 of 2017 417 M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS [DR. DHANANJAYA Y CHANDRACHUD, J.] opposite parties to deliver possession of the allotted apartment being unit no. SY-B-32-03. Learned counsel for the complainant submits that he is ready and willing to take possession of the flat if found in fit condition and he is also ready and willing to pay the payment raised by the opposite party subject to the decision in this complaint. Learned counsel for the opposite party has no objection if interim order is passed as stated by learned counsel for the complainant. In view of the above, application is disposed of with the direction that opposite parties shall deliver possession of the allotted apartment to the complainant on payment of demanded dues by the complainant within one month of the date of payment. It is made clear that this order is subject to final outcome of the complaint. Counsel for the opposite parties state that in view of the interim order passed today on the application of complainant, he does not press his IA No. 2661 and 2662 of 2018.” 10. On 17 May 2018, the first respondent filed another interim application bringing on record several photographs showing that the apartment was not complete and was not in a habitable condition. In response to an email from the first respondent, the appellant sent the following email on 25 September 2018: “We have noted the content if your email and wish to apprise you that due to limited workforce, the finishing work is slow at the site. We expect the same to resume in full force in near future and thereafter, we may look at completing the work at the earliest for the handover.” Thus, it is clear the apartment which had been offered for possession by the appellant was not complete in all respects nor was it in a habitable condition. 11. By its judgment dated 1 November 2021, the NCDRC held that the appellant did not contest that an amount of Rs 2,23,91,480 had been paid by the first respondent. It then noted that the first respondent would be considered as a consumer within the meaning of Section 2(1)(d) of COPRA since the appellant had not brought on record anything to prove that the first respondent was indulging in the business of buying/selling apartments. On merits, the NCDRC relied on a A B C D E F G H 418 SUPREME COURT REPORTS [2022] 2 S.C.R. - A decision rendered by it on 6 December 2019 in relation to the appellant’s Project ( **Siddharth Vasisht** v. **lREO Pvt. Ltd. and Ors[10]** ), which was upheld by this Court on 11 December 2020[11] . The NCDRC thus ordered a refund of Rs 2,23,91,480 with simple interest at the rate of 10.25 per cent per annum, which it noted was the rate of interest payable under the Real Estate (Regulation and Development) Act 2016 in - B Haryana in respect of cases where refund is made to flat buyers due to the delay of the developer in handing over possession. 12. In **Siddharth Vasisht** (supra), relying on its previous decision in **Shamshul Hoda Khan** v. **IREO Victory Valley Pvt. Ltd. and Anr.[12]** , the NCDRC had rejected the appellant’s argument that the calculation C of the period for the delivery of possession of the apartment under Clause 13.3 of the ABA would only start from the date the Fire NOC was granted. In **Shamshul Hoda Khan** (supra), the NCDRC had rejected the developer’s submission by noting that the Haryana Fire Service Act 2009[13] did not prohibit the commencement of construction on a housing D project after Building Approval was sanctioned and pending a Fire NOC if the Building Approval did not contain such a condition and, in any case, the appellant had commenced construction on the housing project before it received the Fire NOC. Similarly, in **Siddharth Vasisht** (supra), the NCDRC also noted that the appellant had commenced construction E on the Project before it received the Fire NOC. 13. This Court rejected the appeal against the decision in **Siddharth Vasisht** (supra) by relying on its earlier order dated 3 May 2019[14] rejecting the appeal against **Shamshul Hoda Khan** (supra). This Court has thereafter rejected a review petition[15] against its order rejecting the F appeal against the decision in **Shamshul Hoda Khan** (supra) by an order dated 15 October 2019, where it noted that the NCDRC had correctly pointed out that since the appellant began construction before the Fire NOC was granted, it could not argue that the period for delivery of possession should start only from the date the Fire NOC was granted. This Court held: G 10 Consumer Case No 1062 of 2018 11 Civil Appeal (Diary) No 21634 of 2020 12 Consumer Case No 2110 of 2016, decided on 17 January 2019 > 13 “ **HFS Act** ” 14 Civil Appeal No 4801 of 2019 - H 15 Review Petition (Civil) No 2339 of 2019 419 M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS [DR. DHANANJAYA Y CHANDRACHUD, J.] “Delay in filing the review petition is condoned. The principal submission raised in the review petition is on the basis of Section 15(1) of the Haryana Fire Service Act, 2009. It is submitted that the construction of a building could only begin after the Fire Scheme was approved by the concerned authority and as the Fire Safety Scheme in the present case was approved on 28.10.2013 the period ought to be reckoned from that date. A B The submission was dealt with by the National Commission and the relevant portion from para 10 was as under: “It is an admitted position that the opposite party had been raising demand based upon the stage of construction even prior to 28.10.2013 when the first fire safety clearance came to be issued. The payment plan agreed between the parties envisaged payment of the 3[rd] instalment on commencement of excavation, 4[th] on casting of basement roof slab and the 5[th] on casting of ground floor roof slab. The 6[th] instalment was payable on casting of 3[rd] floor roof slab. It is an admitted position that even the 4[th] instalment which was payable on casting of basement roof slab was demanded on 5.2.2013. The 5[th] and 6[th] instalments were demanded on 21.3.2013 and 18.9.2013 respectively. Admittedly, the fire safety clearance had not been received by that time.” C D E In view of the circumstances on record this Court refused to interfere and dismissed the civil appeal. We have gone through the review petition and do not find any substance in the submissions raised therein. This review petition is, therefore, dismissed.” F 14. In the present appeal, Mr Ankur Saigal, learned Counsel appearing on behalf of the appellant, has submitted that: - (i) Clause 13.3 of the ABA stipulates that possession would be handed over within forty-two months after the preconditions were fulfilled, and there was a grace period of 180 days. It has been submitted that the Building Plan sanctioned on 27 September 2011 contained a requirement of a Fire NOC, and the Fire NOC was received only on 25 September 2013. Hence, the contractual date for handing over possession, including the 180 days’ grace period, would G H 420 SUPREME COURT REPORTS [2022] 2 S.C.R. - A - B be 24 September 2017. In this context, reliance has been placed on the communication of the appellant dated 25 September 2017 making an offer of possession; - (ii) In view of the judgment of this Court dated 11 January 2021 in **IREO Grace Realtech Private Limited** v. **Abhishek Khanna and Others[16]** , the period for delivery of possession begins only from the date the Fire NOC is granted; and - (iii) A direction for refund together with interest was not warranted because the relief sought in the consumer complaint before the NCDRC was possession of the flat - C and the prayer for refund was set up in the alternate, in the event that possession could not be offered. Since the appellant offered possession within the contractual period, there is no valid basis to order a refund. 15. Opposing these submissions, Ms Nina R Nariman, learned D Counsel appearing on behalf of the first respondent, submitted that: - (i) The first respondent moved an interim application before the NCDRC seeking a direction for the delivery of possession. On 16 February 2018, the NCDRC disposed it off with a direction to the appellant to deliver possession - E upon the payment of the outstanding dues, within a month of the date of payment; - (ii) On 25 September 2018, nearly seven months after the interim order of the NCDRC, the appellant addressed an email, _inter alia_ , stating that _“…due to limited workforce,_ - F _the finishing work is slow at the site_ ”. The appellant’s email stated that it expected “ _the same to resume in full force in near future and thereafter…may look at completing the work at the earliest for the handover_ ”. In view of the above email, the appellant was not in a position to hand over possession even as on 25 September - G 2018; and - (iii) The construction of the Project started even before the issuance of the Fire NOC, as is apparent from the fact that letters of demand were addressed to the first respondent - H 16 (2021) 3 SCC 241 421 M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS [DR. DHANANJAYA Y CHANDRACHUD, J.] commensurate with the casting of slabs on 18 February A 2013, 27 May 2013 and 3 December 2013. Hence, the plea that the period for the delivery of possession of the apartment commenced only from the date of the Fire NOC is not tenable. 16. The primary relief which was sought by the appellant before the NCDRC was the handing over of possession of the flat allotted under the ABA. The _bona fides_ of the first respondent are apparent from the fact that interim application was moved before the NCDRC for handing over possession. In other words, consistent with the plea in the complaint, the first respondent sought possession in the first instance. An interim order was passed on 16 February 2018 directing the appellant to hand over possession. 17. The core submission of the appellant is that the date for handing over possession would be 24 September 2017, having regard to the provisions of Clause 13.3 of the ABA. Clause 13.3 provided as follows: “13.3 Subject to Force Majeure, as defined herein and further subject to the Allottee having complied with all its obligations under the terms and conditions of this Agreement and not being in default of any provision(s) of this Agreement including but not limited to the timely payment of all dues and charges including the total Sale Consideration, registration charges, stamp duty and other charges and also subject to the Allottee having complied with all formalities or documentation as prescribed by the Company, the Company proposes to hand over the possession of the said Apartment to the Allottee within a period of 42 (forty two) months from the date of approval of the Building Plans and/or fulfillment of the preconditions imposed thereunder (‘Commitment Period’). The Allottee further agrees and understands that the Company shall additionally be entitled to a period of 180 days (‘Grace Period’), after the expiry of the said Commitment Period to allow for unforeseen delays in obtaining the Occupation Certificate etc., from the DTCP under the Act, in respect of SKYON Project.” 18. According to the appellant, in terms of the above clause, the date by when the offer of possession could be made would be 24 September 2017. This submission runs contrary to the orders of this Court dismissing the appeals against NCDRC’s decisions in **Shamshul Hoda Khan** (supra) and **Siddharth Vasisht** (supra), both of which are B C D E F G H 422 SUPREME COURT REPORTS [2022] 2 S.C.R. - A of two-judge Benches. However, in support of this proposition, the appellant has placed reliance on the decision of this Court in **Abhishek Khanna** (supra), which is a decision by a three-judge Bench. 19. In **Abhishek Khanna** (supra), which was in relation to another housing project of the appellant, one of the issues before this Court was: - B - “22.1. (i) Determination of the date from which the 42 months period for handing over possession is to be calculated under Clause 13.3, whether it would be from the date of issuance of the fire NOC as contended by the developer; or, from the date of sanction of the building plans, as contended by the apartment buyers.” - C After analysing the provisions of the HFS Act, Clause 13.3 of the ABA (which contained the same condition as the ABA in this case, that the period for delivery of possession would commence from the “ _date of approval of the Building Plans and/or fulfillment of the preconditions imposed thereunder_ ”), and Clauses 3 and 17(iv) of the D sanctioned Building Approval (which are identical to Clauses 3[17] and 17(v)[18] of the sanctioned Building Approval in the present case), the Court held that the period for delivery of possession would only commence from the date the Fire NOC was granted. This Court held: - E 17 “3. FIRE SAFETY: […] On receipt of the above request the Commissioner, Municipal Corporation, Gurgaon after satisfying himself that the entire fire protection measures proposed for the above buildings are as per NBC and other Fire Safety Bye Laws, and would issue a NOC from Fire safety and means of escape/access point of view. This clearance/NOC from Fire Authority shall be submitted in this office along with a set of plans duly signed by the F Commissioner, Municipal Corporation, Gurgaon within a period of 90 days from the date of issuance of sanction of building plans. Further, it is also made clear that no permission for occupancy of the building shall be issued by Commissioner, Municipal Corporation, Gurgaon unless he is satisfied that adequate firefighting measures have been installed by you and suitable external firefighting infrastructure has been created at Gurgaon, by Municipal Corporation, Gurgaon. A clearance to this effect shall be obtained from the Commissioner, Municipal Corporation, Gurgaon before grant of G occupation certificate by the Director General.” 18 “17. GENERAL:- […] (v) That the colonizer shall obtain the clearance/NOC as per the provisions of the Notification No. S.O. 1533 (E) Dated 14.09.2006 issued by Ministry of Environment and Forest, Government of India before starting the construction/execution of H development works at site.” ## M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS 423 [DR. DHANANJAYA Y CHANDRACHUD, J.] “25.7. The environmental clearance granted by the Ministry of A Environment & Forest Government of Haryana on 12-12-2013 required the developer to submit a copy of the fire safety plan approved by the Fire Department, before commencing construction of the project. General Condition (vi) under Part B of the environmental clearance stipulated that the developer shall obtain B all other statutory clearances, including the approval from the Fire Department, prior to construction of the project. Clause (vi) provides that: “(vi) All other statutory clearance such as the approvals for storage of diesel from Chief Controller of Explosive, Fire Department, Civil Aviation Department, Forest Conservation Act, 1980 and Wild Life (Protection) Act, 1972, Forest Act, 1927, PLPA 1900, etc. _shall be obtained as applicable by project proponents from the respective authorities prior to construction of the project_ .” (emphasis supplied) 25.8. We are of the view that it was a mandatory requirement under the Haryana Fire Service Act, 2009 to obtain the fire NOC before commencement of construction activity. This requirement is stipulated in the sanctioned building plans, as also in the environment clearance. C D E 25.9. The 42 months’ period in Clause 13.3 of the Agreement for handing over possession of the apartments would be required to be computed from the date on which fire NOC was issued, and not from the date of the building plans being sanctioned.” F Based on this, the Court held[19] that allottees who had been offered possession and in respect of whose apartments the Occupation Certificate had been issued, were bound to take possession (after having been paid compensation for the delay in offering possession) and could not terminate the ABA. However, it is important to note that the Court found that the construction in respect of their apartments was complete. G 20. In the present case, since the Fire NOC was only granted on 25 September 2013, the period for delivery of possession of the apartment (the forty-two months period, along with the 180 days’ grace period) > 19 Paragraph 44 H 424 SUPREME COURT REPORTS [2022] 2 S.C.R. - A would end on 24 September 2017. The appellant issued a notice of possession to the first respondent on 25 September 2017. 21. However, even if this submission of the appellant is accepted, it is apparent that the appellant was not in a position to comply with the interim order of the NCDRC for the handing over of possession. Though B the interim direction was issued on 16 February 2018, the email of the appellant dated 25 September 2018 indicates that possession could not be handed over due to the absence of an adequate work force at the site. Thus, it is evident that the appellant was not in a position to hand over possession of the apartment even after the interim order. In this backdrop, the order of the NCDRC for the grant of refund at the C appropriate rate of interest cannot be faulted. 22. For the above reasons, we affirm the judgment of the NCDRC, since the position in the present case is distinguishable from the facts before this Court in **Abhishek Khanna** (supra). - D 23. In Civil Appeal No 268 of 2022, the first respondent was allotted an apartment in Tower D of the Project. The ABA was signed on 6 September 2013. The appellant issued a notice of possession on 6 September 2016. The first respondent filed a consumer complaint[20] before the NCDRC on 14 February 2017 seeking a refund of the amount paid with interest at 18 per cent per annum or the possession of the apartment, - E if the appellant was willing to complete the apartment in accordance with the specifications in the ABA in a time bound manner and not charge any further amount over and above the sale consideration. By its judgment dated 22 November 2021, which takes note of the decision of this Court in **Abhishek Khanna** (supra), the NCDRC directed the appellant to - F refund the principal amount to the first respondent with interest at the rate of 10.25 per cent per annum. 24. We have heard Mr Ankur Saigal, learned Counsel for the appellant and Mr. Vaibhav Gaggar, learned Counsel for the respondent. 25. The finding of fact which has been recorded by the NCDRC G in its impugned judgment dated 22 November 2021 is that the amenities which were promised by the appellant have not been provided in the Project and the apartment. In the course of discussion, the NCDRC has, in fact, tabulated the amenities which were to be but have not been - H 20 Consumer Case No 417 of 2017 M/S IREO PRIVATE LIMITED v. ALOKE ANAND AND OTHERS 425 [DR. DHANANJAYA Y CHANDRACHUD, J.] provided. In this view of the matter, the direction for the refund of the A amount paid together with interest, cannot be faulted. The appellant made a solemn representation to the flat buyer of the amenities which would be provided in the flat and the Project. A breach of this representation is actionable at law. 26. The appeals are accordingly dismissed. B 27. Pending applications, if any, stand disposed of. Devika Gujral Appeals dismissed. C D E F G H
End of Judgment Record
Browse All Supreme Court of India (2022) Decisions
2022-12-09

MOHD. SABEER @ SHABIR HUSSAIN v. RM, U. P. STATE ROAD TRANSPORT CORP.

The appellant, Mohd. Sabeer (also known as Shabir Hussain), a scrap dealer, was a passenger in a UP State Road Transport Corporation bus when the driver rashly and negligently drove the vehicle, causing a collision near Ghaziabad in 2009. He sustained grave injuries including an amputation of the right lower limb and other bodily injuries. The Motor Accident Claims Tribunal (MACT) awarded Rs. 15,76,465 with interest; the High Court of Delhi enhanced the amount to Rs. 16,70,932. The Disability Certificate recorded 70% permanent disability. The High Court had treated the claimant’s functional disability as 35%, relying on post‑accident income reflected in IT returns, and erred in not adequately recognizing the impact on earning capacity of a self‑employed person who cannot drive. The Supreme Court held that the appellant’s functional disability should be treated as 60% for loss of future earning capacity and that permanent disablement warrants consideration of future prospects in addition to future income. It invoked National Insurance Co. v. Pranay Sethi to apply a 40% addition for future prospects, and directed compensation for prosthetic limb purchase and maintenance, as well as enhanced non‑pecuniary damages. The final award was increased to Rs. 38,70,120 with 9% interest from the date of application, and the appeals were allowed, emphasizing liberal, holistic justice to restore the claimant to his pre‑accident position in light of socio‑economic factors.

2022-01-25

Intercontinental Hotels Group (India) Pvt. Ltd. & ANR. v. Waterline Hotels Pvt. Ltd.

Intercontinental Hotels Group (India) Pvt. Ltd. & Anr. v Waterline Hotels Pvt. Ltd. is a Supreme Court decision addressing appointment of a sole arbitrator under Section 11(6) read with Section 11(12)(a) of the Arbitration and Conciliation Act, 1996, in a dispute arising from a Hotel Management Agreement (HMA) for renovating the Holiday Inn & Suites Bengaluru, Whitefield. The petitioners allege breach by Waterline Hotels, including non-payment of incentive management fee and related charges, culminating in Waterline’s email termination of the HMA on 12 October 2018 after rebranding the hotel as Miraya. The petitioners invoked arbitration; Waterline challenged the enforceability of the arbitration clause on the ground that the HMA is an unstamped instrument under the Karnataka Stamp Act. A Karnataka High Court ad‑interim relief was granted in 2018, but the Supreme Court’s judgment focuses on the scope of judicial interference at the pre‑appointment stage. The Court reiterates a pro‑arbitration stance, noting that arbitrability/validity are generally matters for the arbitrators, with a narrow exception to cut deadwood or to refer for authoritative settlement where necessary, invoking Vidya Drolia. It also analyzes stamp duty, observing that stamp duty has been paid (albeit disputed) and that the question of the correct stamp duty may be resolved later, not as a precondition to appointing an arbitrator. Consequently, the Court appoints Justice A. V. Chandrashekara as a sole arbitrator, directs SIAC to proceed under its rules, and allows the petition in terms stated, while leaving stamp duty issues for arbitration to determine later.

2022-02-01

The State of Sikkim v. Jasbir Singh & ANR

This appeal by the State of Sikkim challenges a High Court judgment upholding a Sessions Judge’s order directing a written notice to the Army’s commanding officer to transfer the case to a court-martial. The case concerns concurrent jurisdiction between a court-martial and an ordinary criminal court under the Army Act for an offence allegedly committed by Lance Naik Jasbir Singh during active service in Sikkim, with the FIR under IPC 302 and related charges. The High Court held that the procedure under Sections 125/126 Army Act, the 1978 Rules (Rules 3-5) and CrPC Rule 475 had not been observed and that the Army authorities had exercised their discretion to prefer a court-martial; thus, the court-martial alone would have jurisdiction. The Supreme Court, however, held that the offence falls into a category with concurrent jurisdiction under Sections 69 and 70 of the Army Act, and that where there is concurrent jurisdiction, the first instance discretion to choose the forum lies with the designated officer under Section 125. In the present case there was no decision by the designated officer to institute proceedings before a court-martial, and the sequence of events showed significant cooperation with the CrPC process. Consequently, the Sessions Judge’s competence to proceed in the criminal court was not in error, the High Court’s order is set aside, and the respondent-accused is to be transferred to civil custody to face trial in the criminal court. The appeal is allowed.

2022-07-22

Hemant Kumar Verma & Ors. v. Employees State Insurance Corporation & Ors.

This writ petition concerns whether junior resident doctors in ESIC-run medical colleges should be eligible for the 50% in-service reservation for postgraduate medical courses, a benefit presently available to Insurance Medical Officers Grade-II (IMO-II) recruited through competitive selection. ESIC recruits IMO-II and provides a 50% in-service quota for PG seats; however junior residents, who complete MBBS under bond and serve as part of ESIC's residency scheme, are not deemed in-service doctors. The petitioners argued parity with IMO-II because their qualifications, duties, and work environment are similar, and urged the Court to treat them as in-service to extend the 50% reservation to their batch. ESIC contends that junior residents are contractual, bond-based appointees governed by the ESIC Residency Scheme; IMO-II is a permanent post governed by the ESIC Staff and Condition of Service Regulations 1959; the bond reduction in 2020 and the 2018/2020 memoranda cannot convert junior residents into in-service doctors. The Court relies on precedents establishing institutional preference in PG admissions—Saurabh Chaudri v. Union of India, Yatin Kuma Jasubahi v. State of Gujarat, and Pradeep Jain v. Union of India — to acknowledge the legitimacy of institutional preference, but ultimately holds that junior residents and regular ESIC doctors are distinct categories and the in-service quota cannot be equitably extended to junior residents. The petition is dismissed.