Tenetowl LogoTenetowl
Landmark CasesDivision BenchCivil appeal allowed; impugned High Court judgm...

M/S Interstate Construction vs National Projects Construction Corporation Ltd.

Case / Petition Number:
Civil Appeal No. 3461 of 2025

Case Synopsis & Summary

This civil appeal challenges a Division Bench Delhi High Court decision that set aside directions in the arbitral award regarding interest computed under paragraph 58 of the 2020 award for the Ramagundam Super Thermal Power Project. The arbitral tribunal allowed several heads of claim and awarded interest across pre-reference, pendente lite, and future periods, though the High Court in 2021 partly set aside the future-interest portion, holding the rate beyond 9% p.a. unsustainable. The Division Bench in 2023 then set aside the arbitral tribunal’s directions that interest be calculated on the sum including the interest already awarded (i.e., interest on interest). The Supreme Court, by a two-judge bench, reconsiders Section 31(7) of the 1996 Act, holding that the statute contemplates two main periods for interest but permits the first period to be subdivided with varying rates and even inclusion of interest on interest, subject to contract, statutory provisions, and appropriate limits. It accords weight to Pam Developments, clarifying that pre-reference, pendente lite, and post-award interest are well-settled and that the tribunal may determine the rates for sub-periods. The Court thus allows the appeal, sets aside the High Court’s directions, and restores the position in line with the statutory framework on interest in arbitral awards.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Abhay S. Oka, J.
  • Ujjal Bhuyan, J.
Judgment Date
2025-05-15
Court Decision / Holding
Civil appeal is allowed. The impugned judgment dated 01.08.2023 of the Division Bench is set aside; the appeal is allowed and the arbitral award’s treatment of interest stands in accordance with the statutory framework on Section 31(7). The Court clarifies the interpretive approach to periods of interest and remands no further. Each party bears its own costs.
Final Disposition
Civil appeal allowed; impugned High Court judgment set aside

Parties to the Case

Appellants / Petitioners

  • M/S Interstate Construction

Respondents

  • National Projects Construction Corporation Ltd.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 – Section 34Arbitration and Conciliation Act, 1996 – Section 37Arbitration and Conciliation Act, 1996 – Section 14Arbitration and Conciliation Act, 1996 – Section 15Arbitration and Conciliation Act, 1996 – Section 31(7)(a)Arbitration and Conciliation Act, 1996 – Section 31(7)(b)Interest Act, 1978 – Section 3Arbitration Act, 1940 (historical reference)

Legal Doctrines & Maxims

  • No compound interest is permissible
  • Sum awarded includes principal and interest; post-award interest may be on interest amount
  • Two-period framework under Section 31(7) and its flexibility to divide the first period into sub-periods with different rates

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the arbitral tribunal had statutory power to award interest on the total sum including interest components; Section 31(7) permits the first period (pre-award) and the second period (post-award); the first period can be subdivided, and interest may be computed on the principal and interest components within that period, including interest on interest in appropriate circumstances. The challenge to the Division Bench concerns only the directions in paragraph 58(b) to award interest on the enhanced sum; no challenge to the rate for pre-reference or pendente lite periods is raised.

Contentions of Respondents

The respondent contends that the two main periods under Section 31(7) should be read rigidly as pre-award (including pre-reference and pendente lite) and post-award; awarding interest on interest (compound interest) is impermissible unless expressly authorized; laches during the 01.01.2009 to 31.12.2016 period justifies limiting or excluding interest; the Division Bench correctly struck down the arbitral tribunal’s direction to compute interest on the sum including prior interest.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (8)

Case NameCitationTreatmentExplanation
Sayeed Ahmed and Company Vs. State of Uttar Pradesh(2009) 12 SCC 26DistinguishedDivision Bench’s reading of Sayeed Ahmed as limiting to two periods is not accepted; the Supreme Court clarifies that Section 31(7) allows a nuanced subdivision of the first period.
Pam Developments Private Limited Vs. State of West Bengal(2024) 10 SCC 715PositiveCited to support that the power to award pre-reference, pendente lite, and post-award interest is well-settled.
Hyder Consulting (UK) Ltd. Vs. Governor, State of Orissa(2015) 2 SCC 189PositiveSupports inclusion of interest (and post-award interest on interest) in the sum; later authority overruled Arora’s narrower view on interest on interest.
S.L. Arora Vs. State of Haryana(2010) 3 SCC 690OverruledHyder Consulting later overruled this decision regarding interest on interest.
UHL Power Company Ltd. Vs. State of Himachal Pradesh(2022) 9 SCC 286PositiveAffirms Hyder’s approach that post-award interest can be on interest amount.
Delhi Airport Metro Express Private Ltd. Vs. Delhi Metro Rail Corporation(2022) 4 SCC 116PositiveReiterates the Hyder-based understanding on post-award interest.
Morgan Securities and Credits Pvt. Ltd. Vs. Videocon Industries Limited(2023) 1 SCC 602PositiveFollows Hyder’s principle on interest on interest post-award.
S.A. Builders Ltd. Vs. Delhi Development Authority—PositiveSupports the interpretation that the sum awarded includes interest and underscores post-award interest considerations.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,183 words•~29 min read

In The Court Record

M/S Interstate Construction vs National Projects Construction Corporation Ltd.

2025 INSC 699 **==> picture [68 x 68] intentionally omitted <==** ## **REPORTABLE** # **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 3461 OF 2025** ## **M/S. INTERSTATE CONSTRUCTION APPELLANT(S)** # **VERSUS** **NATIONAL PROJECTS CONSTRUCTION CORPORATION LTD. RESPONDENT(S)** ## **J U D G M E N T** ## **UJJAL BHUYAN, J.** This appeal by special leave is directed against the judgment and order dated 01.08.2023 passed by the Division Bench of the High Court of Delhi in FAO (OS) (Comm) No.175 of 2021. Signature Not Verified Digitally signed byASHISH KONDLE 2. It may be mentioned that by the aforesaid judgment Date: 2025.05.15 13:35:47 IST Reason: and order dated 01.08.2023 (impugned judgment), Division Bench of the High Court of Delhi (High Court) allowed the appeal of National Projects Construction Corporation Limited, (NPCC) or the respondent hereinafter, filed under Section 37 of the Arbitration and Conciliation Act, 1996 (briefly ‘the 1996 Act’ hereinafter) setting aside that part of the judgment and order dated 02.08.2021 passed by a learned Single Judge of the High Court under Section 34 of the 1996 Act upholding the directions contained in paragraph 58(b) of the award dated 28.10.2020 as well as setting aside the directions of the arbitral tribunal as contained in paragraph 58(b) of the said award. 3. Relevant facts may be briefly noted. 4. Respondent had engaged the services of the appellant for executing a contract relating to Ramagundam Super Thermal Power Project, Ramagundam, District Karimnagar in the then composite State of Andhra Pradesh. In this regard, two separate work orders were issued: - (i) Work order No.917344/838 dated 19.06.1984 in respect of the work _excavation of foundation package work-II 3 X 500 MW of National Thermal Power_ 2 _Corporation Limited, Ramagundam Super Thermal Power Project;_ - (ii) Work Order No. 917344/2382 in respect of the work _foundation package work, stage-II, at Ramagundam Super Thermal Power Project;_ 5. Thereafter, contract agreement was entered into between the parties. As per clause 4 of the conditions of contract read with clause 15 of the special conditions attached to the work orders, all the disputes and differences between the parties were to be settled by way of arbitration. 6. It is stated that appellant had completed the contract work in the year 1987. Respondent had paid the appellant the contractual dues after withholding certain sums on account of recoveries. Appellant disputed such recoveries. Additionally, appellant also raised certain claims which were not accepted by the respondent. 7. In view of such disputes and differences, appellant invoked the arbitration clause by issuing notice dated 17.05.1993. 3 8. Respondent did not take immediate steps for appointment of an arbitrator. After considerable delay, by communication dated 07.10.1997, respondent appointed Shri Shivamoy Ghosh, Additional General Manager, NPCC, Madras Sector, Chennai as the sole arbitrator to arbitrate on the subject dispute. 9. Appellant filed statement of claims before the learned arbitrator on 20.01.1998 claiming an aggregate amount of Rs.4,46,29,404.00 along with _pendente lite_ and future interest at the rate of 24 percent per annum till final realization of the amount. 10. Appellant sought for a direction from the learned arbitrator to the respondent to supply various documents related to the dispute. However, learned arbitrator only permitted the appellant an opportunity to inspect the documents and did not issue any direction to the respondent for supply of copies. 11. Aggrieved thereby, appellant filed a petition under Section 14 of the 1996 Act before the High Court seeking 4 termination of the mandate of the learned arbitrator and for appointment of a new arbitrator in his place. This petition was registered as OMP No. 214/2002. By order dated 11.10.2004, learned Single Judge terminated the mandate of Shri Shivamoy Ghosh and appointed Shri A.S. Chandhiok, Sr. Advocate, as the sole arbitrator. 12. Respondent challenged the said order of the learned Single Judge dated 11.10.2004 before the Division Bench of the High Court in FAO (OS) No.241/2004. By order dated 02.02.2005, Division Bench appointed Shri L.R. Gupta, retired Director General of CPWD as the sole arbitrator. 13. Before Shri L.R. Gupta, the learned arbitrator, respondent while filing its reply to the statement of claims filed by the appellant, also challenged the authority of one Shri Jagdish Raj Yadav to file the claim on behalf of the appellant. In this regard an application dated 23.02.2007 was filed before the learned arbitrator. Learned arbitrator dismissed the said application _vide_ the order dated 03.08.2007. 5 14. The said order dated 03.08.2007 was challenged by the respondent before the learned Single Judge of the High Court by filing a petition under Section 34 of the 1996 Act, being OMP No.537/2007. 15. It may be mentioned that Shri L.R. Gupta resigned as the sole arbitrator on 23.06.2008. 16. _Vide_ order dated 30.01.2007, learned Single Judge disposed of the petition filed under Section 34 of the 1996 Act bearing OMP No.537/2007. 17. Appellant filed a petition under Section 15 of the 1996 Act before the High Court being OMP (T) (Comm) No. 30/2018 seeking appointment of an arbitrator in place of Shri L.R. Gupta who had resigned. The said petition was disposed of by the learned Single Judge of the High Court _vide_ order dated 31.05.2018 reconstituting the arbitral tribunal by appointing Mr. Justice R.C. Jain, a former Judge of the High Court, as the sole arbitrator to arbitrate on the disputes between the parties. 6 18. New arbitrator held the first hearing on 03.05.2019 and finally pronounced the award on 28.10.2020. While the arbitral tribunal allowed the claims of the appellant under several heads, we are concerned with the contentious part of the award relating to payment of interest (claim No. 7) contained in paragraph 58 of the award. Relevant portion contained in paragraph 58 of the award reads as under: 58. *** *** *** *** In a nutshell the claimant is held entitled to interest as under: a) Pre-reference / past period interest: @ 18% per annum on a sum of Rs.34,43,490.61 w.e.f. July 1987 up-till 19.01.1998. b) _Pendente lite_ interest: i) @ 12% per annum w.e.f. 20.01.1998 uptill 31.12.2008 on the total amount (i.e. principal amount + the amount of interest on the pre-reference/past period). ii) @ 12% per annum w.e.f. 01.01.2017 till the date of award on the total amount (i.e. principal amount + the amount of interest for the pre-reference period and for the period from 20.01.1998 till 31.12.2008). c) Future interest: 7 @ 18% per annum from the date of the award till the date of payment on the total amount (i.e. principal amount + amount of interest on the pre-reference/past period+ amount of interest _pendente lite_ ). 19. Respondent filed a petition under Section 34 of the 1996 Act before the Single Bench of the High Court for setting aside the award dated 28.10.2020. The same was registered as OMP (Comm) No. 78/2021. By the judgment and order dated 02.08.2021, learned Single Judge partly allowed the petition by setting aside the award with regard to future interest at the rate exceeding 9 percent per annum from the date of the award till the date of payment. 20. Aggrieved by the judgment and order dated 02.08.2021 passed by the learned Single Judge, respondent preferred an appeal under Section 37 of the 1996 Act before the Division Bench of the High Court which was registered as FAO (OS) (Comm) No. 175/2021. In the appeal, learned senior counsel for the respondent (which was the appellant before the Division Bench) clarified that the challenge would be restricted to the directions issued by the arbitral tribunal insofar the issue 8 of interest was concerned. This was further clarified by submitting that the challenge was not with respect to the rate of interest or award of interest for the pre-reference/past period. Grievance highlighted was against the directions contained in sub-paragraph (b)(i) of paragraph 58 to the extent of the arbitral tribunal stipulating that interest for the period mentioned therein would be leviable not merely on the principal amount as awarded but upon the said amount inclusive of the amount of interest relating to the pre-reference/past period. Likewise, arbitral tribunal awarded interest on identical terms in subparagraph (b)(ii) of paragraph 58 which was objected to. Division Bench of the High Court _vide_ the judgment and order dated 01.08.2023 (impugned judgment) allowed the appeal by setting aside the directions contained in paragraph 58(b). 21. Aggrieved thereby, appellant filed the related SLP (C) No.23235/2023 before this Court. By order dated 19.10.2023, this Court issued notice. In the hearing held on 25.02.2025, leave was granted. 9 22. Though there is no challenge by either parties to the award on merit, challenge of the respondent being confined only to the interest part, nonetheless, to have a complete picture, it would be appropriate to mention the claims of the appellant and the corresponding amounts awarded by the arbitral tribunal. The following statement in tabular form will throw light on the amounts claimed by the appellant and the amounts awarded by the arbitral tribunal under sixteen heads of claim. The tabular ## statement is as under: |Claim<br>No.|Particulars|Amount<br>Claimed|Amount<br>Awarded| |---|---|---|---| |(a)|Escalation at 10% for work<br>order 48/4|Rs.20,71,322.0<br>0|Rs.20,71,322<br>.00| |(b)|Escalation at 10% for work<br>order 47/11|Rs.1,84,418. 77|Rs.1,84,418.<br>77| |(c)|Refund of panel recovery of<br>steel taking 5% of scrap<br>wastage in place of 3%<br>wastage: -<br>I) Steel difference<br>II) M.S. Found Steel<br>III) 12 Dia M.S.<br>IV) Structural Steel<br>V) Steel Plates<br>VI) Scrap made in labour<br>rates|<br>Rs.1,75, 132.00<br>Rs. 1,806.42<br>Rs. 68,750.00<br>Rs. 2,513.28<br>Rs. 2,649.84<br>Rs.12,000.00|| ||Total|Rs.2,62,850.70|Rs.1,82,463.<br>70| |d)|Unreasonable recoveries:-<br>i) Cribes<br>ii) Shutter plates|Rs. 3,747.75<br>Rs. 38,322.65|| 10 ||iii) B.F.P. Hire charges for<br>shutter plates<br>iv) B.F.P. Hire charges for<br>shutter plates<br>v) Refund of 28%<br>overhead supply for metal<br>vi) Dozer recovery for work<br>order No. 48/4<br>vii) Cubes failure<br>(never given in writing of any<br>cube failure of any member)<br>viii) Chain pulley<br>block (not with us)<br>ix) Clamps (already<br>returned)<br>x) Pipes (already<br>returned)|Rs. 15,776.31<br>Rs. 64,521.00<br>Rs. 60,833.00<br>Rs. 10,676.00<br>Rs. 34,701.92<br>Rs. 8,000.00<br>Rs. 14,990.00<br>Rs. 89,353.00|| |---|---|---|---| ||Total|Rs.3,40,921.63|Rs.60,833.00| |e)|Work order by other agencies<br>but not in our scope like<br>plastering etc.|Rs.84,447.00|Rs.84,447.00| |f)|Held amounts:-<br>i) Amount held on account<br>of grouting T.G.<br>ii) Amount held on account<br>of grouting C.E.P.<br>iii) Staging held amount of<br>T.G.<br>iv) Work order No. 48/4<br>withheld amount<br>v) Work Order No. 47/11<br>withheld amount<br>vi) Work Order No. 48/4<br>shutter plates held<br>vii) Curing held amount<br>48/4<br>viii) Work order No.48/4<br>E.S.P.<br>rectification<br>held<br>amount<br>ix) Work order No.48/4<br>T.G. held amount for final<br>shape.|Rs.3,95,000.00<br>Rs.20,000.00<br>Rs.3,09,203.14<br>Rs.43,000.00<br>Rs.51,803.00<br>Rs.23,000.00<br>Rs.3,000.00<br>Rs.10,000.00<br>Rs.5,000.00|| ||Total|Rs.8,60,004.14|Rs.8,60,004.<br>14| 11 |g)|Balance payable in bills<br>i) Payable in bills 47/11<br>ii) S.D. 47/11 total balance<br>iii) Work order No. 48/4<br>money payableinbills|Rs.64,376.76<br>Rs.2,02,870.00<br>Rs.84,000.00|| |---|---|---|---| ||Total|Rs.3,51,246.76|| |h)|Differenceinexcavation|Rs.1,31,464.00|| |i)|Booking of C.E.P. in package-<br>IV as agreed by E.D.S.R.<br>differences|Rs.17,690.00|| |j)|Claims of not allotting quarry<br>as agreed byE.D.S.R.|Rs.2,66,000.00|| |k)|1200 M3 of stone aggregate<br>from<br>Karim<br>Nagar<br>for<br>rate differences of Rs. 70/-<br>M3<br>extra<br>and<br>the<br>claim<br>was agreed by EDSR referred<br>to our letter ISC/ Claims/1<br>Dt.14.10.89 paraIII.|<br> <br> <br>Rs.13,40,000.0<br>0|| |l)|Idle<br>labour<br>charges<br>refer<br>our letter ISC/Claims/1 dt.<br>14.10.89, para IV|<br>Rs.4,81,000.00|| |m)|2% interest rate difference on<br>mobilization advance.|Rs.50,000.00|| |n)|Interest on delayed release of<br>S.D. refer para 9 of our letter<br>ISC/Claims/1dt. 14.10.89.|Rs.2,40,000.00|| |o)|Mental<br>anguishes,<br>torture<br>and loss of social status<br>suffered refer Letter No. ISC/<br>Claims/1 dt. 14.10.89 para<br>II.|Rs.60,00,000.0<br>0|| |p)|Addl. 24% interest for 10.5<br>years w.e.f. July 1987 upto<br>Dec.1997.|Rs.3,19,57,039.<br>0|| ||Total|Rs.4,46,38,404.<br>00|Rs.34,43,490<br>.61| 23. We have already extracted the nature of interest payment provided in the award dated 28.10.2020. However, for 12 ready reference, interest awarded to the appellant by the arbitral tribunal may once again be noted which is as under: (a) Pre-reference/past period interest at the rate of 18% per annum on the sum of Rs. 34,43,490.61 with effect from July 1987 uptill 19.01.1998. (b) _Pendente lite_ interest at the rate of 12% per annum with effect from 20.01.1998 uptill 31.12.2008 on the total amount (that is, principal amount plus the amount of interest for the prereference/past period). (c) _Pendente lite_ interest at the rate of 12% per annum with effect from 01.01.2017 till the date of the award on the total amount (that is, principal amount plus the amount of interest on the prereference period and for the period from 20.01.1998 till 31.12.2008). (d) Future interest at the rate of 18% per annum from the date of the award till the date of payment on the total amount (that is, principal amount added to the amount of interest for the prereference/past period and interest _pendente lite_ ). 23.1. While holding that appellant was entitled to award of interest for the pre-reference period i.e. from the date on which the cause of action arose till filing of the claim before the arbitral 13 tribunal as well as for the _pendente lite_ period and also for the future period, arbitral tribunal agreed with the respondent that no interest should be awarded to the appellant for the period when there was absolute laches on the part of the appellant. Arbitral tribunal held that for the period from 01.01.2009 till 31.12.2016, that is for a period of about eight years, there was complete laches on the part of the appellant. Therefore, the arbitral tribunal declared that appellant would not be entitled to any interest for the aforesaid period. 24. Respondent filed a petition under Section 34 of the 1996 Act before the High Court impugning the arbitral award dated 28.10.2020. _Vide_ the judgment and order dated 02.08.2021, learned Single Judge upheld the claims awarded by the arbitral tribunal. On the question of interest, learned Single Judge framed the question as to whether interest awarded by the arbitral tribunal was exorbitant and unsustainable. Learned Single Judge held that arbitral tribunal’s decision to award pre-reference interest at the rate of 18 percent per annum did not warrant any interference. As 14 regards _pendente lite_ interest, learned Single Judge while noting that arbitral tribunal had awarded 12 percent interest per annum for the period from 20.01.1998 till 31.12.2008 and again from 01.01.2017 till 28.10.2020, justified the decision of the arbitral tribunal not to award interest for the period from 01.01.2009 to 31.12.2016 as during this period the appellant was remiss and did not pursue its claim before the arbitral tribunal diligently. On the rate of interest, learned Single Judge held that interest at the rate of 12 percent per annum could not by any stretch be considered to be exorbitant or unreasonable but held that 18 percent future interest from the date of the award till the date of payment granted by the arbitral tribunal was _ex facie_ erroneous as according to learned Single Judge the interest rate should have been 2 percent higher than the current rate of interest prevalent on the date of the award. Therefore, this portion of the award was set aside by the learned Single Judge; instead learned Single Judge awarded future interest holding that it could not have been in excess of 9 percent per annum. Therefore, learned Single Judge partly 15 allowed the petition under Section 34 of the 1996 Act to the extent of setting aside the award of future interest at a rate exceeding 9 percent per annum from the date of the award till the date of payment. 25. This brings us to the impugned judgment and order dated 01.08.2023. We have already noted about the limited nature of challenge made by the respondent during the hearing of the appeal filed under Section 37 of the 1996 Act. Learned senior counsel appearing for the respondent clarified that the challenge to the award stood restricted to the directions issued by the arbitral tribunal insofar the issue of interest was concerned. He clarified that the challenge was not with respect to either the rate at which interest was awarded or the grant of interest for the pre-reference/past period. The grievance was confined to the directions contained in paragraph 58(b)(i) of the award and the similar nature of interest in paragraph 58(b)(ii) inasmuch as the arbitral tribunal proceeded to award interest on identical terms: on the principal amount plus the amount of interest for the pre-reference/past period. Division Bench 16 referred to Section 31(7)(a) and (b) of the 1996 Act as well as placed reliance on the decision of this Court in _Sayeed Ahmed and Company Vs. State of Uttar Pradesh[1]_ and came to the following two conclusions: i) Section 31(7) recognizes only two periods for which interest may be awarded. The two periods are, firstly from the date on which the cause of action arose till passing of the award and secondly from the date of the award till actual payment. Therefore, the distinction between prereference/past period and _pendente lite_ period no longer existed. The period from the date of cause of action i.e. July, 1987 till the date of the award dated 28.10.2020 would constitute the period contemplated under Section 31(7)(a) of the 1996 Act. The period commencing from the date of award till payment would be the second period within the meaning of Section 31(7)(b) of the 1996 Act. Therefore, the arbitral tribunal committed an illegality in awarding interest for three periods: pre-reference/past periods, _pendente lite_ and for the future period. ii) Arbitral tribunal committed further illegality in forging the principal amount with interest as would be evident from paragraph 58(b) of the award. Interest awarded for the pre-reference period as well as for the _pendente lite_ period have been subjected to further levy > 1 (2009) 12 SCC 26 17 of interest for the said periods by adding the interest amount with the principal amount awarded. This amounted to levying compound interest which is impermissible. Accordingly, the directions contained in paragraph 58(b) were set aside by the Division Bench. 26. In our considered view, the reasonings given by the Division Bench are fallacious. We say so for the reasons mentioned hereunder. 27. Section 31 of the 1996 Act is the relevant provision. It deals with the form and contents of arbitral award. Section 31 has eight sub-sections. Sub-section (7) is central to the debate and after the amendment with retrospective effect from 23.10.2015 read as under: ## **31. Form and contents of arbitral award -** (7)( _a_ ) Unless otherwise agreed by the parties, where and in so far as an arbitral award is for the payment of money, the arbitral tribunal may include in the **sum** for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on 18 which the cause of action arose and the date on which the award is made. ( _b_ ) A **sum** directed to be paid by an arbitral award shall, unless the award otherwise directs, carry interest at the rate of two per cent higher than the current rate of interest prevalent on the date of award, from the date of award to the date of payment. 27.1. Before substitution and prior to 23.10.2015, clause ## (b) of sub-section (7) of Section 31 stood thus: (b) A **sum** directed to be paid by an arbitral award shall, unless the award otherwise directs, carry interest at the rate of eighteen per centum per annum from the date of the award to the date of payment. 28. We now come to the analysis of Section 31(7), both clauses (a) and (b). For the time being we concentrate on clause (a) insofar it deals with the period for which interest may be awarded. A reading of clause (a) reveals that interest may be for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made. In real terms it means the period from the date on which the cause of action arose till filing of the claim petition by the 19 claimant and from the date of filing of the claim petition till the date of the award. Division Bench of the High Court relied upon _Sayeed Ahmed and Company_ (supra) wherein this Court analyzed Section 31(7) of the 1996 Act and opined that the difference between pre-reference period and _pendente lite_ period has disappeared insofar award of interest by the arbitrator is concerned. The said section now recognizes only two periods and makes the following provision: i) In regard to the period between the date on which the cause of action arose and the date on which the award is made (pre-reference period + _pendente lite_ ), the arbitral tribunal may award interest at such rate as it deems reasonable for the whole or any part of the period unless otherwise agreed by the party; ii) For the period from the date of award to the date of payment, interest at the rate of 18 percent per annum (this is in reference to the pre 23.10.2015 position) if no specific order is made in regard to interest; however, the arbitrator may award interest at a different rate for the period between the date of award and the date of payment. 29. Based on the aforesaid decision, the Division Bench held that it was not open for the arbitral tribunal to have carved out three periods for payment of interest: pre-reference, 20 _pendente lite_ and future when the statute provides for only two periods: first period being the period between the date on which the cause of action arose and the date on which the award is made and the second period is from the date of the award till the date of payment. 30. We are unable to agree with the view expressed by the Division Bench. Even in _Sayeed Ahmed and Company_ (supra) relied upon by the Division Bench, the Bench held that Section 31(7) had carved out two periods, the first period being from the date on which the cause of action arose till the date on which the award is made and the second period being from the date of award till the date of payment. As regards the first period, the Bench clarified that it includes the pre-reference period plus _pendente lite_ period. Though the arbitral tribunal had granted interest for three periods: pre-reference period, _pendente lite_ and post award period, the first two period basically comprises of the period contemplated under clause (a) of sub-section (7) of Section 31. It is another matter that the arbitral tribunal awarded varying degrees of interest for the two sub-periods: 18 21 percent per annum for the pre-reference period and 12 percent as _pendente lite,_ excluding from the said period, the period of eight years when the appellant was found to be remiss in pursuing its claims before the arbitral tribunal. This is also permissible as we shall explain. 31. Therefore, _Sayeed Ahmed and Company_ (supra) does not exclude or does not say that interest should not be granted for the pre-reference period. All that it explains is that Section 31(7)(a) has joined the two periods of interest: pre-reference and _pendente lite_ . 32. This position has been clarified by a recent decision of this Court in _Pam Developments Private Limited Vs. State of West Bengal[2]_ . After extracting Section 31(7) of the 1996 Act, this Court held that power of the arbitrator to grant pre-reference interest, _pendente lite_ interest and post award interest under Section 31(7) of the 1996 is now fairly well settled. The Bench, thereafter, culled out the following legal propositions in this > 2 (2024) 10 SCC 715 22 ## regard highlighting the difference in the position of law _qua_ the Arbitration Act, 1940 _vis-à-vis_ the 1996 Act: 23. The power of the arbitrator to grant prereference interest, _pendente lite_ interest, and postaward interest under Section 31(7) of the Act is fairly well-settled. The judicial determinations also highlight the difference in the position of law under the Arbitration Act, 1940. The following propositions can be summarised from a survey of these cases: 23.1. Under the Arbitration Act, 1940, there was no specific provision that empowered an arbitrator to grant interest. However, through judicial pronouncements, this Court has affirmed the power of the arbitrator to grant pre-reference, _pendente lite_ , and post-award interest on the rationale that a person who has been deprived of the use of money to which he is legitimately entitled has a right to be compensated for the same. When the agreement does not prohibit the grant of interest and a party claims interest, it is presumed that interest is an implied term of the agreement, and, therefore, the arbitrator has the power to decide the same. 23.2. Under the 1940 Act, this Court has adopted a strict construction of contractual clauses that prohibit the grant of interest and has held that the 23 arbitrator has the power to award interest unless there is an express, specific provision that excludes the jurisdiction of the arbitrator from awarding interest for the dispute in question. 23.3. Under the 1996 Act, the power of the arbitrator to grant interest is governed by the statutory provision in Section 31(7). This provision has two parts. Under clause ( _a_ ), the arbitrator can award interest for the period between the date of cause of action to the date of the award, _unless otherwise agreed by the parties_ . Clause ( _b_ ) provides that unless the award directs otherwise, the sum directed to be paid by an arbitral award shall carry interest @ 2% higher than the current rate of interest, from the date of the award to the date of payment (referring to the post 23.10.2015 position). 23.4. The wording of Section 31(7)( _a_ ) marks a departure from the Arbitration Act, 1940 in two ways : _first_ , it does not make an explicit distinction between pre-reference and _pendente lite_ interest as both of them are provided for under this subsection; _second_ , it sanctifies party autonomy and restricts the power to grant pre-reference and _pendente lite_ interest the moment the agreement bars payment of interest, even if it is not a specific bar against the arbitrator. 24 23.5. The power of the arbitrator to award prereference and _pendente lite_ interest is not restricted when the agreement is silent on whether interest can be awarded or does not contain a specific term that prohibits the same. 23.6. While _pendente lite_ interest is a matter of procedural law, pre-reference interest is governed by substantive law. Therefore, the grant of prereference interest cannot be sourced solely in Section 31(7)( _a_ ) (which is a procedural law), but must be based on an agreement between the parties (express or implied), statutory provision (such as Section 3 of the Interest Act, 1978), or proof of mercantile usage. 24. In view of the above, the High Court had no reason to interfere with the arbitral award with respect to grant of pre-reference interest, since the contract between the parties does not prohibit the same. 33. This position has been further explained by a recent decision of this Bench in _North Delhi Municipal Corporation Vs. S.A. Builders Ltd.[3] ._ After adverting to Section 31(7) of the 1996 Act, this Court explained as under: > 3 (2024) SCC Online SC 3768 25 **36.1.** From a minute reading of sub-section (7), it is seen that it has got two parts: the first part i.e. clause (a) deals with passing of award which would include interest up to the date on which the award is made. The second part i.e. clause (b) deals with grant of interest on the ‘sum’ awarded by the arbitral tribunal. 33.1. Thereafter the Bench observed that under Section 31(7) of the 1996 Act, an arbitral tribunal has the power to grant – (i) pre-award (ii) _pendente lite_ (iii) post-award interest. The Bench explained the reason for award of such interest in the following manner: **39.** Generally, going by the provisions contained in Section 31(7) of the 1996 Act, it is evident that an arbitral tribunal has the power to grant (i) pre-award (ii) _pendente lite_ (iii) post-award interest. Intention behind awarding pre-award interest is primarily to compensate the claimant for the pecuniary loss suffered from the time the cause of action arose till passing of the arbitral award. Further, this is also to ensure that the arbitral proceeding is concluded within a reasonable period to minimise the impact of the pre-award interest as well as interest _pendente lite_ ; thereby promoting efficiency in the arbitration process. Similarly, grant of post-award interest also serves a salutary purpose. It primarily acts 26 as a disincentive to the award debtor not to delay payment of the arbitral amount to the award holder. 34. Thus, what Section 31(7)(a) has done is that there is now a statutory recognition of the power of the arbitral tribunal to grant pre-reference interest from the date on which the cause of action arose till the date on which the award is made. There was a vacuum in the Arbitration Act, 1940 as there was no such provision for granting pre-reference interest. It was through judicial pronouncements that such power of the arbitrator to grant pre-reference interest was conferred. Now under Section 31(7)(a) of the 1996 Act, such power is statutorily recognized. 35. Let us revert back to clause (a) of sub-section (7) of Section 31 of the 1996 Act. A careful and minute reading of this provision will make it clear that the arbitral tribunal has the discretion to include in the sum awarded interest at such rate as it deems reasonable on the whole or any part of the money awarded for the whole or any part of the period from the date on which the cause of action arose till the date on which the award is made. We may exclude that part of the sentence ‘on 27 the whole or any part of the money’ from our analysis since this is not relevant to the controversy. If we exclude this portion, what then becomes discernible is that the arbitral tribunal has the discretion to include in the sum awarded : firstly, _interest at such rate as it deems reasonable;_ and secondly, _for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made._ This would mean that the arbitral tribunal can exclude a period from the date on which the cause of action arose till the date on which the award is made for the purpose of grant of interest, as has been done in the present case. It would also mean that the arbitral tribunal can grant interest for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made. It can be a composite period or the said period can be further sub-divided, as done in the present case i.e. from the date of cause of action to filing of the claim and from the date of filing of the claim till the date of the award excluding the period when the appellant was found to be remiss. It would also mean that there can be one rate of 28 interest for the whole period or one or more rates of interest for the sub-divided periods as has been done in the instant case. In our opinion, this would be the correct approach to interpret Section 31(7)(a), given the scheme of the 1996 Act. 36. That being the position, we are of the view that the Division Bench had fallen in error by holding that the arbitral tribunal had no jurisdiction to award interest for two periods i.e. pre-reference and _pendente lite_ when the statute provides for only one period viz. from the date when the cause of action arose till the date of the award. The view expressed by the High Court is not the correct interpretation of Section 37(1)(a) of the 1996 Act as explained by us supra as well as in _Pam Developments Private Limited_ (supra) and _S.A. Builders Ltd._ (supra). 37. This brings us to the second issue on which the High Court set aside the directions of the arbitral tribunal contained in paragraph 58(b) of the award. According to the Division Bench, the arbitral tribunal had committed an illegality in forging the principal amount with interest while computing the awarded amount on which future interest is to be paid. Interest 29 awarded for the past period could not have been subjected to further levy of interest during the _pendente lite_ or post award period on merger with the principal amount as this would amount to levy of compound interest. 38. This aspect of the matter is no longer _res integra._ 39. In _State of Haryana Vs. S.L. Arora[4]_ , a two-Judge Bench of this Court observed that as regards pre-award period, interest has to be awarded as specified in the contract and in the absence of any contract, as per the discretion of the arbitral tribunal. However, with regard to the post-award period, the interest is payable as per the discretion of the arbitral tribunal and in the absence of exercise of such discretion, at the mandatory statutory rate of 18 percent per annum. Award of interest like award of cost are ancillary matters. Therefore, the expressions _sum for which the award is made_ and _the sum directed to be paid by an arbitral award_ contextually refers to the award on the substantive claims and not ancillary or > 4 (2010) 3 SCC 690 30 consequential directions relating to interest or cost. It was held that arbitral tribunals did not have the power to award interest upon interest or compound interest either for the pre-award period or for the post-award period. 40. A three-Judge Bench of this Court in _Hyder Consulting (UK) Ltd. Vs. Governor, State of Orissa[5]_ , opined that it was not possible to agree with the conclusion in _S.L. Arora_ (supra) that Section 31(7) of the 1996 Act does not require that interest which accrues till the date of the award be included in the _sum_ from the date of the award for calculating the postaward interest. Justice Bobde (as His Lordship then was) authoring the majority opinion was of the view that the conclusion reached in _S.L. Arora_ (supra) did not seem to be in consonance with the clear language of Section 31(7) of the 1996 Act. _Hyder Consulting (UK) Ltd._ (supra) declared that _S.L. Arora_ (supra) was wrongly decided in that it held that a sum directed to be paid by an arbitral tribunal and the reference to the award on the substantive claim did not refer to > 5 (2015) 2 SCC 189 31 interest _pendente lite_ awarded on the _sum directed to be paid upon award_ and that in the absence of any provision of interest upon interest in the contract, the arbitral tribunal did not have the power to award interest upon interest or compound interest either for the pre-award period or for the post-award period. It has been clarified that the ‘sum’ includes the principal as adjudged together with the interest granted. 41. A three-Judge Bench of this Court in _UHL Power Company Ltd. Vs. State of Himachal Pradesh[6]_ declared that the judgment in _S.L. Arora_ (supra) has since been overruled by a three-Judge Bench of this Court in _Hyder Consulting (UK) Ltd._ (supra). The majority view in _Hyder Consulting (UK) Ltd._ (supra) is that post-award interest can be granted by an arbitrator on the interest amount awarded. 42. This view was reiterated by this Court in subsequent decisions (please see _Delhi Airport Metro Express Private Ltd. Vs._ > 6 (2022) 4 SCC 116 32 _Delhi Metro Rail Corporation[7]_ and _Morgan Securities and Credits Private Ltd. Vs. Videocon Industries Limited[8] )._ 43. Finally, in _S.A. Builders_ (supra), this Bench after a thorough analysis of Section 31(7)(a) and Section 31(7)(b) of the ## 1996 Act came to the following conclusion: **38.** Natural corollary to the above analysis would be that the ‘sum’ so awarded by the arbitral tribunal which may include interest from the date when the cause of action arose to the date of the award, would carry further interest of 18 percent from the date of the award to the date of payment unless the arbitral award otherwise directs (referring to the pre 23.10.2015 position). Thus, the legislative intent is that the awarded sum whether inclusive of interest or not, in case included, then from the date of cause of action to the date of award, would carry further interest from the date of the award to the date of payment. 44. It has been held that the sum awarded would mean the principal amount plus the interest awarded from the date of cause of action upto the date of the award. The sum awarded in Section 31(7)(a) would mean principal amount plus the interest > 7 (2022) 9 SCC 286 > 8 (2023) 1 SCC 602 33 awarded. Thereafter, as per Section 31(7)(b) of the 1996 Act, the sum (principal amount + interest) would carry further interest at the rate of 2 per cent higher than the current rate of interest prevalent on the date of the award to the date of payment. 45. Therefore, in view of the clear legal position delineated as above, impugned judgment of the Division Bench dated 01.08.2023 cannot be sustained. 46. Thus, having regard to the discussions made above, impugned judgment and order dated 01.08.2023 passed by the Division Bench of the High Court is hereby set aside. Civil appeal is accordingly allowed. However, there shall be no order as to cost. **………………………………J. [ABHAY S. OKA]** **.……………………………J. [UJJAL BHUYAN]** **NEW DELHI; MAY 15, 2025.** 34
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.