Supreme Court of IndiaSupreme Court · 2014Division BenchPartly allowed; no order as to costs.

M/S Harsha Constructions v. Union of India & Ors.

Case / Petition Number:
Civil Appeal No. 534 of 2007
Neutral Citation:[2014] 7 S.C.R. 668

Case Synopsis & Summary

Harsha Constructions, a road-construction contractor, challenged an arbitral award arising from a contract with the Union of India for constructing a road bridge at a level crossing. The contract contained detailed arbitration provisions: Clause 39 governs extra work and the method for fixing rates when such work is not listed in the accepted schedule, including a requirement for notice and an Engineer–Contractor negotiation, with a right to appeal to the Chief Engineer if the rate fixed by the Engineer is not acceptable. Clause 63 provides that disputes arising under the contract shall be referred to the Railways, with a mechanism for decisions that are final and binding on the contractor, and, critically, that certain matters enumerated (including Clause 39) are “Excepted matters” and stand excluded from arbitration. Disputes over the amount payable for extra work were partly resolved by payments made under protest, and an Arbitrator (appointed by a former Judge of the Andhra Pradesh High Court) decided all issues, including those the contractor contended were non-arbitrable. The appellant challenged the City Civil Court’s and the High Court’s upholding of the Arbitrator’s award, arguing that the Arbitrator had no authority to decide non-arbitrable issues. The Supreme Court held that arbitration arises from a contract and cannot be presumed absent a written contract; matters designated as “excepted” cannot be referred to arbitration. It quashed the non-arbitrable portion of the award and upheld the arbitrable portion, partly allowing the appeal with no costs, and left open the contractor’s right to pursue recovery for non-contract work.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Anil R. Dave
  • Vikramjit Sen
Judgment Date
2014-09-05
Court Decision / Holding
Partly allowed; the award was quashed to the extent it dealt with non-arbitrable disputes, while the arbitrable portion was upheld. No costs were awarded.
Final Disposition
Partly allowed; no order as to costs.

Parties to the Case

Appellants / Petitioners

  • M/s Harsha Constructions

Respondents

  • Union of India
  • Railways/authorities (as represented by Railway authorities)

Legal Representation & Advocates

Counsels for Petitioners

  • • Vemula Prasad Rao
  • • G. Ramakrishna Prasad
  • • Filza Moonis

Counsels for Respondents

  • • D.S Mahra

Provisions of Law Cited

Arbitration and Conciliation Act, 1996, Section 34Arbitration and Conciliation Act, 1996, Section 7(3)

Legal Doctrines & Maxims

  • Arbitration arises from a contract; there must be a written contract for arbitration.
  • There cannot be a presumption of arbitration where the contract does not provide for it (written contract required by Section 7(3)).
  • Non-arbitrable disputes cannot be referred to arbitration.
  • Excepted matters are excluded from the purview of the arbitration clause and are final and binding.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contended that Clause 39 requires the Engineer to determine rates for extra work through negotiations, and that any final decision on rates rests with the Engineer, with a right of appeal to the Chief Engineer. Since the Chief Engineer had not finalized the decision, there was no valid arbitrable dispute to be referred to arbitration for those items. The agreement also excluded certain matters from arbitration as ‘excepted’, per Clause 63. The Arbitrator’s jurisdiction to decide non-arbitrable disputes was thus impermissible; the award on such issues should be quashed, while the arbitrable portion could stand if properly decided within the contract framework.

Contentions of Respondents

The respondents urged that disputes arose under the contract and that the appropriate rates and disputes were within the scope of arbitration as per the contract clauses. They argued that the Engineer’s determinations, and the process culminating in the Chief Engineer’s final decision, formed the appropriate mechanism for settlement, with arbitration limited to the remaining matters not excluded as ‘excepted’. It was contended that the award should be binding where the contract prescribes a final decision by the Chief Engineer and that the arbitrable issues should be upheld if they fall within the contract’s framework.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
General Manager, Northern Railway and another v. Sarvesh Chopra[(2002) 4 SCC 45]Mentioned OnlyCited as background authority; used to contextualize arbitration principles but not expressly followed or distinguished in the operative decision.
Madnani Construction Corporation (P) Limited v. Union of India & ors.[(2010) 1 SCC 549]Mentioned OnlyCited in the argument section; not expressly adopted or overruled in the judgment's ratio.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,964 words•~14 min read

In The Court Record

M/S Harsha Constructions v. Union of India & Ors.

A ## [2014] 7 S.C.R. 668 ## M/S. HARSHA CONSTRUCTIONS _v._ UNION OF INDIA & ORS. (Civil Appeal No. 534 of 2007) B SEPTEMBER 05, 2014 **[ANIL R. DAVE AND VIKRAMAJIT SEN, JJ.]** - - _Arbitration and Conciliation Act, 1996 ss. 34, 7(3)_ - _Contract of arbitration Dispute pertaining to the amount_ C _payable to the contractor in relation to extra work done by the_ - _contractor Amount payable to the contractor not final since_ - _dispute not decided by the Chief Engineer Though some_ - _amount paid but accepted under protest by the contractor In terms of the contract clause, said dispute specifically not_ - D _arbitrable However, "excepted matter" referred to arbitrator_ - _Arbitrator deciding the issue holding that the same were not_ - _excepted matters but arbitrable Held: Arbitration arises from_ a _contract and unless there is_ a _specific written contract,_ a - _contract with regard to arbitration cannot be presumed As_ E _per the Contract clause, arbitrator could nof arbitrate upon the·_ - _excepted disputes If_ a _non-arbitrable dispute is referred to an Arbitrator and an issue is framed by the Arbitrator in relation thereto, there cannot be_ a _presumption or_ a _conclusion to the effect that the parties had agreed to refer_ - F _the issue to the Arbitrator Award regarding non-arbitrable_ - _dispute quashed and set aside Liberty granted to the contractor to take appropriate legal action for recovery_ ol _payment for work done not forming part of the contract._ ## **Partly allowing the appeal, the Court** G **H** **HELD: Arbitration arises from a contract and unless there is a specific written contract, a contract with regard to arbitration cannot be presumed.:Thus, so far as the disputes which have been referred to in Clause 39 of the** 668 HARSHA CONSTRUCTIONS _v._ UNION OF INDIA 669 contract are concerned, it was not open to the Arbitrator A to arbitrate upon the said disputes as there was a specific clause whereby the said disputes had been "excepted". Moreover, when the law specifically makes a provision · with regard to formation of a contract in a particular manner, there cannot be any presumption with regard to 8 a contract if the contract is not entered into by the mode prescribed under the Act.)f a non-arbitrable dispute is referred to an Arbitrator and even if an issue is framed ·by the Arbitrator in relation to such a dispute, there cannot be a presumption or a conclusion to the effect that C the parties had agreed to refer the issue to the Arbitrator. In the instant case, the respondent authorities had raised· an objection relating to the arbitrability-of the aforestated issue before the Arbitrator and yet the Arbitrator had rendered his decision on the said "excepted" dispute. It 0 was not open to the Arbitrator to decide the issues which were not arbitrable and the award, so far as it relates to disputes regarding non-arbitrable disputes-determination of the rate for extra work done by the contractor is concerned, is bad in law and is quashed. The portion of the award so far as it pertains to the disputes which were E arbitrable is upheld. [Para 20-23] [675-F-H; 676-A-F] _General Manager, Northern Railway and another v. Sarvesh Chopra_ 2002 (2) SCR 156:(2002) 4 SCC 45; _Madnani Construction Corporation (P) Limited v. Union of_ F _India_ & _ors._ 2009 (16) SCR 216: (2010) 1 sec 549 - referred· to. ## Case Law Reference: 2002 (2) SCR 156 Referred to Para 13 G 2009 (16) SCR 216 Referred to Para 13 CIVIL APPELLATE JURISDICTION : Civil Appeal No. 534 of 2007. H 670 SUPREME COURT REPORTS [2014] 7 S.C.R. A From the Judgment and Order dated 09.09.2005 of the High Court of Judicature, Andhra Pradesh at Hyderabad in. C.M.A. No. 476 of 2005. Vemula Prasad Rao, G. Ramakrishna Prasad, Filza 8[Moonis, ][Bharat ][J. ][Joshi ][for ][the ][Appellant. ] D.S Mahra for the Respondents. The Judgment of the Court was delivered by ANIL R. DAVE, J. 1. Aggrieved by the judgment dated 9th C September, 2005 delivered by the High Court of Judicature, Andhra Pradesh at Hyderabad, in CMA No.476 of 2005, this appeal has been filed by M/s Harsha Constructions, a contractor, against Union of India and its authorities. Hereinafter, the appellant has been described as a 'Contractor'. D 2. The Union of India had entered into a contract for construction of a road bridge at a level crossing and in the said contract there was a clause with regard to arbitration. The issue with which we are concerned in the instant case, in a nutshell, E is as under:- . "When in a contract of arbitration, certain disputes are expressly "excepted", whether the Arbitrator can arbitrate on such excepted issues and what are the consequences if the Arbitrator decides such issues?" ## , F - 3. For the purpose of considering the issue, in our opinion, certain clauses incorporated in the contract are relevant and those clauses are reproduced hereinbelow:- G H "Cl~use 39. Any item of work carried out by the Contractor on the· instructions of the Engineer which is not included in the accepted schedule of rates shall be executed at the rates set forth in the "Schedule of Rates, South Central Railway" modified by the tender percentage and where such items are not contained in the latter at the rates HARSHA CONSTRUCTIONS _v._ UNION OF INDIA 671 [ANIL R. DAVE, J.] agreed upon between the Engineer and the Contractor A before the execution of such items of work and the Contractor shall be bound to notify the Engineer at least seven days before the necessity arises for the execution of such items of work that the accepted schedule of rates does not include a rate or rates for the extra work involved. B The rates payable for such items shall be decided at the meeting to be held between the Engineer and the contractor in as short a period as possible after the need for the special item has come to the notice. In case the C contractor {ails to attend the meeting after being notified to do so or in the event of no settlement being arrived at the Railway shall be entitled to execute the extra works by other means and the contractor shall have no claim for loss or damage that may result from such procedure. Provided that if the Contractor commences work or incurs any D expenditure in regard thereto before the rates are determined and agreed upon as lastly mentioned, then and in such a case the Contractor shall only be entitled to be paid in respect of the work carried out or expenditure incurred by him prior to the date of the rates as aforesaid. E according to the rates as shall be fixed by the Engineer. However, if the contractor is not satisfied with the decision of the Engineer in this respect he may appeal to the Chief Engineer within 30 days of getting the decision of the Engineer supported by the analysis of the rates claimed. F The Chief Engineer's decision after hearing both the parties in the matter would be final and binding on the contractor and the Railway." F "Clause-63. All disputes and differences of any kind G whatsoever arising out of or in connection with the contract whether during the progress of the work or after its completion and whether before or after the determination of the contract shall be referred by the Contractor to the Railway and the Railway shall within a reasonable time H SUPREME COURT REPORTS [2014] 7 S.C.R. 672 A B c > after receipt of the contractor's presentation make and notify decisions on all matters referred to by the contractor in writing provided that matters for which provision has been made in Clause 18, 22(5), 39, 45(a), 55, 55-A(5), 6.1 (2) and 62(1 )(.xiii)(B)(e)(b) of the General Conditions of contract or in any Clause of the Special conditions of the contract shall be deemed as 'Excepted matters' and decisions thereon shall be final and binding on the contractor; provided further that excepted matters shall stand specifically excluded from the purview of the arbitration clause and shall not be referred to arbitration." 4. Upon perusal of Clause 63 of the aforestated contract, it is quite clear that the matters for which provision had been made in Clauses 18, 22(5), 39, 45(a), 55, 55-A(5), 61 (2) and 62(1 )(xiii)(B)(e)(b) of the ~eneral Conditions of Contract were D "excepted matters" and they were not to be referred to the arbitrator. E _5. In the instant case, we are concerned with a dispute which had arisen with regard to the amount payable to the contractor in relation to extra work done by the contractor .. • 6. Upon perusal of Clause 39, we find that in the event of extra or additional work entrusted to the contractor, if rates at which the said work was to be done was not specified in the contract, the amount payable for the additional work done was F · to be discussed by the contractor with the concerned Engineer and ultimately the rate was to be decided by the Engineer. If the rate fixed by the Engineer was not acceptable to the col'ltractor, the contractor had to file an appeal to the Chief Engineer within 30 days of getting the decision of the Engineer G and the Chief Engineer's decision about the amount payable was to be final. 7. It is not in dispute that some work, which was not covered under the contract had been entrusted to the contractor H· and for determining the amount payable for the said work, HARSHA CONSTRUCTIONS _v._ UNION OF INDIA 673 [ANIL R. DAVE, J.] certain meetings had been held by the contractor and the. A concerned Engineer but they could not agree to any rate. Ultimately, some amount was paid in respect of the additional work done, which was not acceptable to the contractor but the contractor accepted the same under protest. B 8. In addition to the aforestated dispute with regard to determination of the rate at which the contractor was to be paid for the extra work done by it, there were some other disputes also and in order to resolve all those disputes, Respondent No.5, a former Judge of the High Court of Andhra Pradesh, had been appointed as an Arbitrator. c 9. The learned Arbitrator decided all the disputes under his Award dated 21.9.2002 though the contractor had objected to arbitrability of the disputes which were not referable to the Arbitrator as per Clause 39 of the Contract. Being aggrieved by the Award, Union of India had preferred an appeal before the Chief Judge, City Civil Court, Hyderabad under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "the Act") and the said appeal was allowed, whereby the Award was set aside. D E 10. Before the City Civil Court, in the appeal filed under Section 34 of the Act, the following two issues had been framed:- - {a) Whether the dispute was in relation to an "excepted matter" and was not arbitrable? F - (b) Whether the claimant was entitled to the amounts awarded by the Arbitrator? 11. The Court decided the appeal in favour of the G respondent and against the contractor. Being aggrieved by the order dated 8.4.2005 passed by the XIVth Additional Chief Judge, City Civil Court, Hyderabad, CMA No.476 of 2005 was filed by the contractor before the High Court and the High Court H 674 SUPREME COURT REP08.TS [2014] 7 S.C.R. A was pleased to dismiss the same by virtue of the impugned judgment and therefore, the contractor has filed this appeal. 12. The learned counsel appearing for the appellantcontractor had mainly submitted that as per Clause 39 of the 8[contract, the Engineer of the respondent authorities was duty ] bound to decide the rate at which payment was to be made for the extra work done by the contractor, through negotiations between the parties. A final decision on the said subject was taken by the respondent authorities without the contractor's approval and therefore, there was a dispute between the parties. C He had further submitted that no specific decision was taken by the Engineer and therefore, there was no question of filing any appeal before the Chief Engineer and as the Chief Engineer did not take any decision, the aforestated clauses, viz. Clauses 39 and 64 would not apply because clause 64 would D referring to a decision of the Chief Engineer, but as the Chief Engineer had· not taken any decisiun, there was no question with regard to "excepti11g" clause 39. He had, therefore, submitted that the Award in toto was correct and the High Court had wrongly upheld the dismissal of the Award by the trial Court. E 13. The learned counsel had, thereafter, referred to the judgmen.ts delivered by this Court in _General Manager, Northern Railway and another v. Sarvesh Chopra_ [(2002) 4 SCC 45] and _Madnani Construction Corporation (P) Limited_ F _v. Union of India_ & ors.[(2010) 1 SCC 549] to substantiate his case. 14. The learned counsel had, thereafter, submitted that the appeal deserved to be allowed and the judgment delivered by the High Court confirming the order passed by the City Civil G Court deserved to be quashed and set aside. 15. There was no representation on behalf of the Union of India and therefore, we are constrained to consider the submissions made by learned counsel for the appellant only. H 16. Upon perusal of both the clauses included in the HARSHA CONSTRUCTIONS _v._ UNION OF INDIA 675 [ANIL R. DAVE, J.] contract, which have been referred to hereinabove, it is crystal A clear that all the disputes were not arbitrable. Some of the disputes which had been referred to in Clause 39 were specifically not arbitrable and in relation to the said disputes the co11tractor had to negotiate with the concerned Engineer of the respondent and if the contractor was not satisfied with the B rate determined by the Engineer, it was open to the contractor to file an appeal against the decision of the Engineer before the Chief Engineer within 30 days from the date of communication of the decision to the contractor. 17. In the instant case, there was no finality so far as the C amount payable to the contractor in relation to the extra work done by it is concerned, because the said dispute was never decided by the Chief Engineer. In the aforestated circumstances, when the disputes had been referred to the Arbitrator, the disputes which had been among "excepted D matters" had also been referred to the learned Arbitrator. · 18. Upon perusal of the case papers we find that before the learned Arbitrator, the contractor did object to the arbitrability of the disputes covered under Clause 39, but the E Arbitrator had decided the said issues by holding that !he same were not "excepted matters" but arbitrable. 19. The question before this Court is whether the Arbitrator could have decided the issues which were not arbitrable. F 20. Arbitration arises from a contract and unless there is a specific written contract, a contract with regard to arbitration cannot be presumed. Section 7(3) of the Act clearly specifies that the contract with regard to arbitration must be in writing. Thus, so far as the disputes which have been referred to in G Clause 39 of the contract are concerned, it was not open to the Arbitrator to arbitrate upon the said disputes as there was a specific clause whereby the said disputes had been "excepted". Moreover, when the law specifically makes a provision with regard to formation of a contract in a particular H 676 SUPREME COURT REPORTS [2014] 7 S.C.R. - A manner, there cannot be any presumption with regard to a contract if the contract is not entered into by the mode prescribed under the Act. 21. If a non-arbitrable dispute is referred to an Arbitrator and even if an issue is framed by the Arbitrator in relation to 8 such a dispute, in our opinion, there cannot be a presumption or a conclusion to the effect that the parties had agreed to refer the issue to the Arbitrator. In the instant case, the respondent authorities had raised an objection relatinQ to the arbitrability of the aforestated issue before the Arbitrator and yet the C Arbitrator had rendered his decision on the said "excepted" dispute. In our opinion, the Arbitrator could not have decided the said "excepted" dispute. 22. We, therefore, hold that it was not open to the Arbitrator D to decide the issues which were not arbitrable and the award, so far as it relates to disputes regarding non-arbitrable disputes is concerned, is bad in law and is hereby quashed. 23. We also take note of the fact that the contract had been E entered into by the parties on 24.4.1995 and the contractual work had been finalised on 31.3.1997. The Award was made on 21.9.2002 and therefore, we uphold the portion of the award so far as it pertains to the disputes which were arbitrable, but so far as the portion of the arbitral award which determines the rate for extra work done by the contractor is concerned, we F quash and set aside the same. 24. Needless to say that it would be open to the contractor to take appropriate legal action for recovery of payment for work done, which was not forming part of the contract because G the said issue decided by the Arbitrator is now set aside. 25. For_the reasons recorde~ hereirrabove, the appeal is partly allowed with no order as to costs. Nidhi Jain Appeal partly allowed. H
End of Judgment Record
Browse All Supreme Court of India (2014) Decisions
2014-07-01

Duryodhan Rout v. State of Orissa

These appeals challenge a common judgment convicting Duryodhan Rout of rape and murder of a 10-year-old girl, Subhasini Bhoi. The trial court convicted him under IPC sections 376(f), 302, and 201 and sentenced him to death; on reference, the High Court remitted the death sentence for the 302 offence to life imprisonment while keeping the other sentences unchanged. The prosecution's case rested solely on circumstantial evidence. PW-1 and PW-2 saw the accused with the victim on a bicycle around 4 p.m. and returning alone about an hour later; PW-5 (father) and PW-6 (mother) testified that the child was taken on the pretext of talking on the phone. In custody, the accused confessed before PW-3 and PW-4, and under Section 27 of the Evidence Act the recovery of the body and the underwear was recorded; the autopsy by PW-9 indicated throttling and injuries consistent with rape. The chain of circumstances — last-seen with the victim, recovery of the corpse in the jungle, and the forensic findings — formed a robust basis for conviction. The central legal issue was whether sentences for multiple offences should run consecutively. The Court held that life imprisonment is the remainder of a convict's natural life, and the proviso to Section 31(2) Cr.P.C. prevents aggregation beyond fourteen years, thus consecutive sentences cannot be imposed where life imprisonment is one of the terms. Consequently, all IPC sentences should run concurrently; the death sentence for the 302 offence was replaced by life imprisonment, and the appeal was allowed in part.

2014-12-16

Nand Kishore v. State of Madhya Pradesh

This is a criminal original jurisdiction writ petition under Article 32 challenging the continued incarceration of a convict under Section 302 IPC, with the petitioner contending entitlement to the Juvenile Justice (Care and Protection of Children) Act, 2000 (JJC Act) protections on the ground that he was a juvenile at the time of the offence (born 14 April 1980; incident on 18 June 1997). The Court scrutinized documentary and oral evidence from the Juvenile Justice Board indicating the petitioner’s true date of birth and concluded that on the date of occurrence he was 17 years 2 months 4 days old, thereby satisfying the juvenile criteria. The judgment clarifies a central legal question: whether the protections and benefits under the JJC Act, enacted in 2000, can be extended to those convicted before its coming into force if they were juveniles at the time of the offence. Relying on earlier decisions such as Hariram v. State of Rajasthan and Ajay Kumar v. State of Madhya Pradesh (and others), the Court held that a person who had not completed 18 years on the date of offence is entitled to the Act’s benefits as if the provisions had always existed, effectively retroactively applying the protective regime. The petition was allowed; the petitioner is to be released forthwith, with bail bonds and sureties discharged, reflecting the Court’s protective stance for juveniles in criminal proceedings.

2014-04-24

Vishal Goyal & Ors. v. State of Karnataka & Ors.

This batch of writ petitions under Article 32 concerns admissions to Post Graduate Medical and Dental courses in government medical/dental colleges and the state quota in private colleges in Karnataka for the 2014-2015 academic year. The petitioners, who completed MBBS/BDS in Karnataka, challenged sub-clause (a) of clause 2.1 of two National Board of Examinations Information Bulletins (PGET-2014) which defined “Karnataka Origin” to permit admission only to those who satisfy certain criteria, effectively excluding many who studied in Karnataka institutions. They argued this violates Article 14 (equality before law and equal protection of laws) and undermines merit-based selection for postgraduate courses. They invoked Dr. Pradeep Jain & Others v. Union of India (1984) to contend that institutional preference may be permissible but must conform to equality; Magan Mehrotra v. Union of India (2003), Saurabh Chaudhri v. Union of India (2003), and Nikhil Himthani v. State of Uttarakhand (2013) were cited to support the continuing emphasis on merit and equality. The State countered that Article 371J allows reservation for the Hyderabad-Karnataka region and argued that the Pradeep Jain framework applies only to government or state-instrumentality institutions and not to private colleges. The Court held sub-clause (a) ultra vires Article 14, directed fresh Information Bulletins, and ordered admissions in accordance with the law on the basis of existing entrance test results, with the general counselling schedule from Dr. Fraz Naseem & Ors. not applying for 2014-2015 Karnataka admissions.

2014-08-21

SINGH RAM (D) THR. L.Rs. v. SHEO RAM & ORS.

This is a Supreme Court of India decision on the limit of time within which a usufructuary mortgagee can seek relief, and the corresponding equity of redemption for the mortgagor. The appellants challenged the Punjab and Haryana High Court Full Bench’s view that there is no fixed time for redemption in a usufructuary mortgage and that the right to seek redemption arises on payment/deposit of mortgage money, irrespective of the mortgage date. The HP High Court’s decision was later reversed by a larger bench of this Court in the context of reconciling conflicting precedents such as Sampuran Singh, Prabhakaran and Jayasingh Dhyanu Mhoprekar, Parichhan Mistry and Harbans etc., emphasizing that Section 62 of the Transfer of Property Act confers a special right on the usufructuary mortgagor to recover possession, which begins only when the mortgage money is paid out of rents and profits or when paid/deposited by the mortgagor. Article 61 of the Limitation Act governs the period for redeeming or recovering possession (30 years from accrual of the right, unless restricted). The Court reaffirms the principle ‘once a mortgage, always redeemable’ and rejects a blanket 30-year extinguishment rule for usufructuary mortgages, upholding the Full Bench view of the Punjab and Haryana High Court and dismissing the appeals. The decision emphasizes equity, statutory recognition under Section 62, and the distinctive treatment of usufructuary mortgages.