M/S Harsha Constructions v. Union of India & Ors.
Case Synopsis & Summary
Harsha Constructions, a road-construction contractor, challenged an arbitral award arising from a contract with the Union of India for constructing a road bridge at a level crossing. The contract contained detailed arbitration provisions: Clause 39 governs extra work and the method for fixing rates when such work is not listed in the accepted schedule, including a requirement for notice and an Engineer–Contractor negotiation, with a right to appeal to the Chief Engineer if the rate fixed by the Engineer is not acceptable. Clause 63 provides that disputes arising under the contract shall be referred to the Railways, with a mechanism for decisions that are final and binding on the contractor, and, critically, that certain matters enumerated (including Clause 39) are “Excepted matters” and stand excluded from arbitration. Disputes over the amount payable for extra work were partly resolved by payments made under protest, and an Arbitrator (appointed by a former Judge of the Andhra Pradesh High Court) decided all issues, including those the contractor contended were non-arbitrable. The appellant challenged the City Civil Court’s and the High Court’s upholding of the Arbitrator’s award, arguing that the Arbitrator had no authority to decide non-arbitrable issues. The Supreme Court held that arbitration arises from a contract and cannot be presumed absent a written contract; matters designated as “excepted” cannot be referred to arbitration. It quashed the non-arbitrable portion of the award and upheld the arbitrable portion, partly allowing the appeal with no costs, and left open the contractor’s right to pursue recovery for non-contract work.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Anil R. Dave
- Vikramjit Sen
- Judgment Date
- 2014-09-05
- Court Decision / Holding
- Partly allowed; the award was quashed to the extent it dealt with non-arbitrable disputes, while the arbitrable portion was upheld. No costs were awarded.
- Final Disposition
- Partly allowed; no order as to costs.
Parties to the Case
Appellants / Petitioners
- M/s Harsha Constructions
Respondents
- Union of India
- Railways/authorities (as represented by Railway authorities)
Legal Representation & Advocates
Counsels for Petitioners
- • Vemula Prasad Rao
- • G. Ramakrishna Prasad
- • Filza Moonis
Counsels for Respondents
- • D.S Mahra
Provisions of Law Cited
Legal Doctrines & Maxims
- Arbitration arises from a contract; there must be a written contract for arbitration.
- There cannot be a presumption of arbitration where the contract does not provide for it (written contract required by Section 7(3)).
- Non-arbitrable disputes cannot be referred to arbitration.
- Excepted matters are excluded from the purview of the arbitration clause and are final and binding.
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contended that Clause 39 requires the Engineer to determine rates for extra work through negotiations, and that any final decision on rates rests with the Engineer, with a right of appeal to the Chief Engineer. Since the Chief Engineer had not finalized the decision, there was no valid arbitrable dispute to be referred to arbitration for those items. The agreement also excluded certain matters from arbitration as ‘excepted’, per Clause 63. The Arbitrator’s jurisdiction to decide non-arbitrable disputes was thus impermissible; the award on such issues should be quashed, while the arbitrable portion could stand if properly decided within the contract framework.
Contentions of Respondents
The respondents urged that disputes arose under the contract and that the appropriate rates and disputes were within the scope of arbitration as per the contract clauses. They argued that the Engineer’s determinations, and the process culminating in the Chief Engineer’s final decision, formed the appropriate mechanism for settlement, with arbitration limited to the remaining matters not excluded as ‘excepted’. It was contended that the award should be binding where the contract prescribes a final decision by the Chief Engineer and that the arbitrable issues should be upheld if they fall within the contract’s framework.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| General Manager, Northern Railway and another v. Sarvesh Chopra | [(2002) 4 SCC 45] | Mentioned Only | Cited as background authority; used to contextualize arbitration principles but not expressly followed or distinguished in the operative decision. |
| Madnani Construction Corporation (P) Limited v. Union of India & ors. | [(2010) 1 SCC 549] | Mentioned Only | Cited in the argument section; not expressly adopted or overruled in the judgment's ratio. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/S Harsha Constructions v. Union of India & Ors.
Related Decisions & Precedents from Supreme Court of India (2014)
Duryodhan Rout v. State of Orissa
These appeals challenge a common judgment convicting Duryodhan Rout of rape and murder of a 10-year-old girl, Subhasini Bhoi. The trial court convicted him under IPC sections 376(f), 302, and 201 and sentenced him to death; on reference, the High Court remitted the death sentence for the 302 offence to life imprisonment while keeping the other sentences unchanged. The prosecution's case rested solely on circumstantial evidence. PW-1 and PW-2 saw the accused with the victim on a bicycle around 4 p.m. and returning alone about an hour later; PW-5 (father) and PW-6 (mother) testified that the child was taken on the pretext of talking on the phone. In custody, the accused confessed before PW-3 and PW-4, and under Section 27 of the Evidence Act the recovery of the body and the underwear was recorded; the autopsy by PW-9 indicated throttling and injuries consistent with rape. The chain of circumstances — last-seen with the victim, recovery of the corpse in the jungle, and the forensic findings — formed a robust basis for conviction. The central legal issue was whether sentences for multiple offences should run consecutively. The Court held that life imprisonment is the remainder of a convict's natural life, and the proviso to Section 31(2) Cr.P.C. prevents aggregation beyond fourteen years, thus consecutive sentences cannot be imposed where life imprisonment is one of the terms. Consequently, all IPC sentences should run concurrently; the death sentence for the 302 offence was replaced by life imprisonment, and the appeal was allowed in part.
Nand Kishore v. State of Madhya Pradesh
This is a criminal original jurisdiction writ petition under Article 32 challenging the continued incarceration of a convict under Section 302 IPC, with the petitioner contending entitlement to the Juvenile Justice (Care and Protection of Children) Act, 2000 (JJC Act) protections on the ground that he was a juvenile at the time of the offence (born 14 April 1980; incident on 18 June 1997). The Court scrutinized documentary and oral evidence from the Juvenile Justice Board indicating the petitioner’s true date of birth and concluded that on the date of occurrence he was 17 years 2 months 4 days old, thereby satisfying the juvenile criteria. The judgment clarifies a central legal question: whether the protections and benefits under the JJC Act, enacted in 2000, can be extended to those convicted before its coming into force if they were juveniles at the time of the offence. Relying on earlier decisions such as Hariram v. State of Rajasthan and Ajay Kumar v. State of Madhya Pradesh (and others), the Court held that a person who had not completed 18 years on the date of offence is entitled to the Act’s benefits as if the provisions had always existed, effectively retroactively applying the protective regime. The petition was allowed; the petitioner is to be released forthwith, with bail bonds and sureties discharged, reflecting the Court’s protective stance for juveniles in criminal proceedings.
Vishal Goyal & Ors. v. State of Karnataka & Ors.
This batch of writ petitions under Article 32 concerns admissions to Post Graduate Medical and Dental courses in government medical/dental colleges and the state quota in private colleges in Karnataka for the 2014-2015 academic year. The petitioners, who completed MBBS/BDS in Karnataka, challenged sub-clause (a) of clause 2.1 of two National Board of Examinations Information Bulletins (PGET-2014) which defined “Karnataka Origin” to permit admission only to those who satisfy certain criteria, effectively excluding many who studied in Karnataka institutions. They argued this violates Article 14 (equality before law and equal protection of laws) and undermines merit-based selection for postgraduate courses. They invoked Dr. Pradeep Jain & Others v. Union of India (1984) to contend that institutional preference may be permissible but must conform to equality; Magan Mehrotra v. Union of India (2003), Saurabh Chaudhri v. Union of India (2003), and Nikhil Himthani v. State of Uttarakhand (2013) were cited to support the continuing emphasis on merit and equality. The State countered that Article 371J allows reservation for the Hyderabad-Karnataka region and argued that the Pradeep Jain framework applies only to government or state-instrumentality institutions and not to private colleges. The Court held sub-clause (a) ultra vires Article 14, directed fresh Information Bulletins, and ordered admissions in accordance with the law on the basis of existing entrance test results, with the general counselling schedule from Dr. Fraz Naseem & Ors. not applying for 2014-2015 Karnataka admissions.
SINGH RAM (D) THR. L.Rs. v. SHEO RAM & ORS.
This is a Supreme Court of India decision on the limit of time within which a usufructuary mortgagee can seek relief, and the corresponding equity of redemption for the mortgagor. The appellants challenged the Punjab and Haryana High Court Full Bench’s view that there is no fixed time for redemption in a usufructuary mortgage and that the right to seek redemption arises on payment/deposit of mortgage money, irrespective of the mortgage date. The HP High Court’s decision was later reversed by a larger bench of this Court in the context of reconciling conflicting precedents such as Sampuran Singh, Prabhakaran and Jayasingh Dhyanu Mhoprekar, Parichhan Mistry and Harbans etc., emphasizing that Section 62 of the Transfer of Property Act confers a special right on the usufructuary mortgagor to recover possession, which begins only when the mortgage money is paid out of rents and profits or when paid/deposited by the mortgagor. Article 61 of the Limitation Act governs the period for redeeming or recovering possession (30 years from accrual of the right, unless restricted). The Court reaffirms the principle ‘once a mortgage, always redeemable’ and rejects a blanket 30-year extinguishment rule for usufructuary mortgages, upholding the Full Bench view of the Punjab and Haryana High Court and dismissing the appeals. The decision emphasizes equity, statutory recognition under Section 62, and the distinctive treatment of usufructuary mortgages.