M/S Grand Construction Company (Firm) v. Union of India

Case / Petition Number:
A.S. No. 265 of 1998 (OS. 451/1996, Sub Court, Nedumangad)
Neutral Citation:/null

Case Synopsis & Summary

This High Court of Kerala, Ernakulam, heard A.S. No. 265 of 1998 challenging an order in O.S. 451/1996, Nedumangad Sub Court. The dispute centers on arbitration invoked under clause 25 of a contract with the Department of Space, ISRO, Bangalore, where the contractor seeks appointment of arbitrators if the bill is yet to be settled. The trial court held that the request for arbitration was time-barred, deeming the claim waived since the final bill had been issued and no timely arbitration demand was made within 90 days of the government’s intimation that the bill was ready for payment. The appellant contends Ext. B2 is not a final bill and that the 90-day limit should not apply, since disputes about the finality of the bill and the correctness of amounts require resolution before arbitration. The respondents rely on the 90-day clause to argue waiver and discharge of liability. The judgment discusses Delhi High Court precedents: Jai Chand Bhasin v. Union of India (AIR 1983 Delhi 508) supports arbitration by arbitrator rather than court for finality questions; Ram Nath Mehra & Sons v. Union of India (AIR 1982 Delhi 164) was overruled by AIR 1983 Delhi 508. The court ultimately holds that the arbitrator must decide whether the 90-day demand was made and whether waiver applies, directing referral to arbitration.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • M.N. Krishnan
Judgment Date
2010-07-26
Court Decision / Holding
Appeal allowed; the lower court’s judgment is set aside; the matter is referred to arbitration in terms of the arbitration agreement. The trial court is directed to file the agreement before it if not already filed, and to appoint arbitrators as per the contract; a panel from both parties should be consulted; the authorized appointer is the Director, Vikram Sarabhai Space Centre (VSPSC), Trivandrum, and directions are issued for the same. Parties are to appear for further directions on 7.9.10.
Final Disposition
Appeal allowed; lower court’s order set aside; matter referred to arbitration; appointment of arbitrator to be in accordance with the contract, directed to appoint by Director, VSPSC; parties to appear for further directions on 7.9.10.,

Parties to the Case

Appellants / Petitioners

  • M/S Grand Construction Company (Firm), Sitara, Asramam Residency Road, Kollam

Respondents

  • Union of India, rep. by Chairman & Secretary, Department of Space, ISRO, Bangalore; Engineer-in-Charge, Department of Space, PSLV Project, Nedumangad; Chief Engineer, Department of Space, ISRO, Bangalore

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri B. Krishna Mani
  • • Sri V. Prem Chand
  • • Sri K. Subash Chandra Bose

Counsels for Respondents

  • • Sri Mohan Idiculla Abraham
  • • Sri K. Ramakumar, Senior Advocate for Sri T.P.M. Ibrahim Khan, ASG for India (for Respondents)

Provisions of Law Cited

Clause 25 of the contractSection 20 of the Arbitration Act

Legal Doctrines & Maxims

  • Waiver of rights where final bill is accepted or where contractor does not timely demand arbitration

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that Ext. B2 has not been admitted as the final bill and that the 90-day limitation for requesting arbitration should not apply until a final bill is established. It relies on communications and conduct suggesting ongoing dispute over the amount and correctness, which negate a finality finding. The appellant cites Jai Chand Bhasin v. Union of India (AIR 1983 Delhi 508) to argue that a question about finality or waiver is arbitrable and should be decided by the arbitrator rather than the court under Section 20 of the Arbitration Act.

Contentions of Respondents

The respondents argue that a final bill had been prepared and served, making the 90-day window for arbitration demand binding; thus the contractor’s claim is waived and barred by clause 25, discharging the Government of liability. They rely on the statutory clause to support non-arbitration and stress the need for adherence to the contractual waiver provision. They reference Delhi decisions including Ram Nath Mehra & Sons v. Union of India (AIR 1982 Delhi 164) and its subsequent overruling by AIR 1983 Delhi 508 to support their position.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Jai Chand Bhasin v. Union of India and anotherAIR 1983 Delhi 508PositiveExplicitly held that disputes about whether a bill has become final and related waiver issues are for arbitration/arbitrator under section 20; supports referring to arbitration in the present case.
Ram Nath Mehra & Sons v. Union of IndiaAIR 1982 Delhi 164OverruledOverruled by AIR 1983 Delhi 508, which reversed the view that the time elapse question is a Court matter, not arbitrator.
Wild Life Institute of India, Dehradun v. Vijay Kumar Garg1997 (10) Supreme Court Cases 528Mentioned OnlyReferenced as a related precedent discussing waiver when a final bill is accepted; not directly adopted as a binding rule in the present decision.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,501 words•~7 min read

In The Court Record

M/S Grand Construction Company (Firm) v. Union of India

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE M.N.KRISHNAN** **MONDAY, THE 26TH JULY 2010 / 4TH SRAVANA 1932** ## **AS.No. 265 of 1998(A)** **--------------------------------** **OS.451/1996 of SUB COURT, NEDUMANGAD** **....................** ## **APPELLANT(S): PLAINTIFF** **--------------------------------------** ## **M/S. GRAND CONSTRUCTION COMPANY (FIRM), HEAD OFFICE, SITARA, ASRAMAM RESIDENCY ROAD, KOLLAM 2.** - **BY ADVS. SRI.B.KRISHNA MANI SRI.V.PREMCHAND SRI.K.SUBASH CHANDRA BOSE** ## **RESPONDENT(S): DEFENDANTS** **------------------------------------------------** **1. UNION OF INDIA, REP.BY THE CHAIRMAN & SECRETARY, DEPARTMENT OF SPACE, I.S.R.O., ANDAREEKSHA BHAVAN, NEW BEL , BANGALORE 54.** **2. THE ENGINEER-IN – CHARGE, DEPARTMENT OF SPACE ,CIVIL ENGINEERING DIVISION, P.S.L.V. PROJECT, VALIYAMALA, NEDUMANGAD, THIRUVANANTHAPURAM.** **3. THE CHIEF ENGINEER, DEPARTMNET OF SPACE, I.S.R.O. ANDAREEKSHA BHAVAN, NEW BEL ROAD, BANGALORE 54.** - **ADV. SRI.MOHAN IDICULLA ABRAHAM** - **SRI.K.RAMAKUMAR, SENIOR ADVOCATE FOR SRI.T.P.M.IBRAHIM KHAN,ASST.S.G OF INDI FOR R** **THIS APPEAL SUITS HAVING BEEN FINALLY HEARD ON 26/07/2010, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **tss** ## **M.N. KRISHNAN, J. = = = = = = = = = = = = = = = A.S. NO. 265 OF 1998 = = = = = = = = = = = = = = = Dated this the 26[th] day of July, 2010.** ## **J U D G M E N T** This appeal is preferred against the judgment and decree passed by the Subordinate Judge, Nedumangad in O.S.451/96. The said suit was filed with a prayer to file agreement and to direct the 3[rd] defendant to appoint an arbitrator within a specified time and in case of failure to do so, request the Court to appoint arbitrators consisting of two members one by either side. The trial Court by referring to clause 25 held that request for arbitration is made beyond the period of 90 days and therefore after the issuance of the final bill and therefore under the clause arbitration cannot be done. It is challenging that decision the present appeal is filed. **A.S. 265 OF 1998** -2- 2. Heard the learned counsel appearing for both the sides. Clause 25 of the agreement is extracted as follows. “Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, designs, drawings and instructions herein before mentioned and as to the quality of workmanship, or materials used on the work, or as to any other question, claim, right, matter or thing whatso-ever, in any way arising out of or relating to the contract design drawings specifications estimates instructions orders or these conditions or otherwise concerning the works or the execution or failure to execute the same, whether arising during progress of the work or after the completion or abandonment thereof shall be referred to the sole ## **A.S. 265 OF 1998** -3- arbitration of the person appointed by the Chief Engineer, Department of Space, Bangalore............ It is also the terms of the contract that if the contractor do not make any demand for arbitration in respect of any claim in writing within 90 days of receiving the intimation from the Department that the bill is ready for payment, the claim of the contractor will be deemed to have been waived and absolutely barred and the Government shall be discharged and released of all liabilities under the contract in respect of those claims.” 3. Now the contention raised by the defendants in this case is that a final bill has been prepared and sent and since the arbitration request has not come within 90 days from 2.2.87 (the date of final bill according to the defendants) by virtue of clause 25 it cannot be ## **A.S. 265 OF 1998** -4- referred to arbitration and the right of the contractor should be deemed to have been waived by the contractor and therefore he is not entitled to any relief. The learned counsel for the appellant would submit on the contrary that Ext.B2 is not a final bill. He does not admit it as a final bill and in support of the same he would submit that there are many communications between the plaintiff and the defendants regarding the correctness of the amount etc. and regarding the transaction. So here is a case where the plaintiff does not admit about the fact that Ext.B2 is a final bill. As per the provisions of the agreement unless it has become a final bill the question of 90 days limitation for preferring a request for arbitration may not arise at all. It is in this background we have to analyze the case. The matter has come up ## **A.S. 265 OF 1998** -5- before a Division Bench of the Delhi High Court in the decision reported in **Jai Chand Bhasin v. Union of India and another(AIR 1983 Delhi 508)** . The Court held that when there is a dispute that the bill has not become final and that itself is a dispute it is for the arbitrator to decide that question and therefore that point also is a question that arises for determination by the arbitrator. The Delhi High Court in the decision reported in **Ram Nath Mehra & sons v. Union of India(AIR 1982 Delhi 164)** had taken a decision that the question whether the time has elapsed or not is a question to be decided by the Court and not by the arbitrator. But the Division Bench of the Delhi high Court in the decision reported in **AIR 1983 Delhi 508** held that the said view expressed in **AIR 1982 Delhi 164** is not correct and has overruled the same. **A.S. 265 OF 1998** -6- The Division Bench held that, “We would, therefore, answer the question by holding that it is for the arbitrator to decide whether in fact the applicant had or had not made a demand for arbitration within 90 days of receiving the intimation from the government that the bill is ready for payment, and in the circumstances whether the claim should be deemed to have been waived and the government is discharged and released from its liability. These are not matters which are within the purview of the Court when dealing with the application like the present under section 20 of the Act.” Therefore the Court set aside the order directing the agreement to file in Court and the matter was directed to be referred to the ## **A.S. 265 OF 1998** -7- arbitration in terms of the arbitration agreement. Now one of the decisions that may be cited will be **Wild Life Institute of India, Dehradun v. Vijay Kumar Garg (1997 (10) Supreme Court Cases 528** . It was a case where the contractor accepted it as a final bill and received the payment regarding the complete satisfaction. Under those circumstances the Hon'ble Supreme Court held that the term as per the clause had come into force and there should be a waiver by the contractor and therefore not entitled to any relief. 4. So far as this case is concerned there is no such admission and it is the specific contention that the bill is not final and it is attempted to be established by producing the subsequent communications between the defendant and the contractor. Therefore the said decision ## **A.S. 265 OF 1998** -8- will not come to the rescue. So according to me now whether there is any waiver as contended by the department is also a matter which has to be considered by the arbitrator for the reason that it is also arbitrable. If the answer to that question is against the contractor it will go against the contractor. Therefore the judgment and decree of the lower Court are set aside and the appeal is allowed and a direction is given to file the agreement before the Court, if not already filed and the matter be referred to the arbitration in terms of the arbitration agreement. The trial court is directed to act accordingly in accordance with law. I make it very clear the appointment shall be as per the terms of the agreement and only on failure to do so the Court shall appoint persons after collecting the panel from both the parties. It ## **A.S. 265 OF 1998** -9- has also to be made further clear when the matter goes to the arbitrator the parties can raise the contentions which they are entitled to raise under the terms of the agreement. As per the memo filed by the respondent, at present the authority authorised to appoint the arbitrator is Director, Vikram Sarabhai Space Centre (V.S.S.C), Trivandrum-695022. So the Court below has to direct him to appoint the arbitrator. Parties are directed to appear before the trial court for further directions on 7.9.10. ## **Sd/M.N. KRISHNAN, JUDGE.** ul/- _[true copy]_ _P.A. To Judge._ ## **A.S. 265 OF 1998** -10- **M.N. KRISHNAN, J. = = = = = = = = = = A.S. No. 265 OF 1998 = = = = = = = = = = =** **J U D G M E N T 26[th] July, 2010.**
End of Judgment Record
Browse All High Court of Kerala (2010) Decisions
2010-09-09

T.K. Biju and Gangaprasad S. v. State of Kerala and The Director, Institute of Human Resources Development (IHRD)

This batch of writ petitions challenges the Institute of Human Resources Development’s (IHRD) recruitment process for the Last Grade Service under notification RECT/03/09/HRD (dated 21.1.2009). The core questions concern the validity of the 23.8.2009 written test, the 23.10.2009 short list (main and supplementary) drawn therefrom, and the 19.3.2010 rank list published after interviews. Petitioners—mostly former daily wage/ad hoc employees—also pursue regularisation, arguing that the selection framework and weightage for past service were either discriminatory or inadequately applied. Ext.P4 had disposed of earlier petitions by directing IHRD to finalise recruitment under a resolution dated 9.7.2007, and Ext.P5 laid down the recruitment rules: an objective written test (70 marks) and an interview (30 marks) with category-wise cut-offs (Rule 5.3) and a rank list valid for three years (Rule 5.4). The court holds that deviations such as clause 8 in the hall ticket do not render the process void in the absence of prejudice, and upholds the short-list’s legality to a large extent. However, drawing on Umadevi (3) and Satya Prakash, the court ultimately directs a limited revisiting of the rank list to grant weightage under Rule 5.2 to those petitioners who would have been included, while denying general regularisation. All petitions are disposed with these directions.

2010-01-21

State of Kerala and District Collector, Kollam v. K. Raghavan

This is a review petition filed by the State of Kerala and the District Collector, Kollam, challenging the High Court’s 23 March 2009 judgment in W.P.(C).29695 of 2005, which directed the Government to consider a freedom fighter’s pension claim and to grant pension from the date of application. The petition traces a long history: the applicant, aged about 75 at the time of filing on 29.12.1995, faced earlier adverse orders in 1987 and 1989; after litigation, the 2005 judgment directed reconsideration and culminated in a 2009 order granting pension in December 2009 but from the date of sanction rather than from the date of application. The review petition contends that the Supreme Court’s decision in State of M.P. and Another v. Devkinandan Maheshwari (2003) and a Division Bench decision followed in W.A. Nos.1419/2006 & 1818/2006 require pension from the date of sanction, not the application date, and thus the judgment should be recalled. It also relies on Dokka Samuel v. Dr. Jacob Lazarus Chelly (1997) to assert that omitting authorities is not a ground for review. The Court, however, finds that omission to cite authorities cannot ground a review and that the government’s delay in compliance violates the Court’s directions, warranting dismissal of the review petition with costs.

2010-02-23

Anitha Rajan v. Revenue Divisional Officer, Thrissur; Thasildar, Chavakkad; Village Officer, Nattika; Sub Registrar, Thriprayar

Anitha Rajan, the petitioner, purchased 50 cents of land in Re-Survey No.166/1, Nattika village, Thrissur district, from the legal heirs of late Gangadharan via Ext.P3 sale deed registered at Triprayar. The conveyance, through power of attorney documents Ext.P1 (executed by Ajayan in Dubai in favor of his mother Rathnabhai) and Ext.P2 (executed by Usha in India), prompted mutation proceedings before the Revenue Divisional Officer (RDO). The RDO refused to effect mutation unless the original Ext.P1 POA was produced for adjudication of stamp duty under the Kerala Stamp Act, 1959, claiming non-compliance with stamping and the need to determine stamp duty under sections 31 and 32. The petitioner contends that it is not mandatory to submit every PoA executed outside India for adjudication; only instruments chargeable with duty which cannot be stamped by private persons must be taken to the Collector under section 18(2). Ext.P1, though executed abroad, is on Indian stamp paper and was presented at registration, having been stamped Rs.150 under Article 44(f). The court analyzed sections 18(1), 18(2), 31 and 32 and held that section 18 applies to instruments executed outside India; since Ext.P1 is duly stamped, Section 18 has no application and Sections 31-32 cannot be invoked to compel production. Relying on Madras High Court decisions Manoharan v. Velu and R.B.K. Rajeswari Nachiar, the court held the Village Officer erred in requiring Ext.P1 before the RDO, quashed Exts.P4 and P6, and directed mutation actions to be completed within two months of certified judgment copy.

2010-03-23

V. Mohanan Nair v. Babu Pillai and others

This writ petition arises from a complex land dispute in Nedumangad where the petitioner, V. Mohanan Nair, challenged a trial court order that set aside a commissioner's report and remitted for a fresh report. In O.S. 380/2005 the plaintiff sought a permanent injunction; in O.S. 542/2005 the second respondent sought declaration of title and possession based on deeds executed in 2005. To resolve the location of the plaint schedule property, a commission was appointed, and Ext. P2 report and plan were filed. Subsequently, I.A. 4808/2009 was filed by the second respondent seeking to set aside the commission report and plan and remit for a fresh report. The trial court remitted the matter; Ext.P8 records the order, which the petitioner challenged in this Writ Petition. The respondents relied on a decision in Sarojini v. Karthiyani Amma to contend that Article 227 petitions against commission reports are not maintainable, while the petitioner argued lack of justification for remitting and the undue delay in filing the petition. The Kerala High Court, while recognizing the normal reluctance to exercise visitorial jurisdiction, held that exceptional circumstances permit interference under Article 227 and remanded the matter for fresh consideration, directing that the trial court assess sufficiency of Exts. C1, C1(a), C1(b) and allow further inspection if needed. The result is a remand to ensure a fair adjudication on the commission report."