M/s Eureka Builders & Ors. v. Gulabchand s/o Veljee Dand (Deceased) Through LRs & Others
Case Synopsis & Summary
These appeals arise from a common final judgment of the Karnataka High Court, Circuit Bench at Dharwad, in four connected appeals arising from civil suits relating to land in Hubli. The suit concerns two parcels of land, CTS Nos. 361 and 366 on Kusugal Road, described as watan property under the MHO Act and later governed by the KVA Act. The original owners, three Patils, leased and later transferred rights in the mid-20th century; Shah Veljee Kanjee acquired CTS 361 in 1942 and CTS 366 in 1943, with his heirs subsequently in title. In 1957, the widow and two major daughters of Shah Veljee Kanjee sold the land to Gadag Co-operative Cotton Sales Society. The plaintiff, Shah Veljee Kanjee’s son (now represented by his legal heirs) sought a declaration of title and partition of 1/5 of the suit land, alleging subsisting title recognized in a 1977 Civil Court decree (O.S. No. 9/1969). The Trial Court decreed partition in the plaintiff’s favor; the High Court modified the findings, holding the plaintiff owner of the suit land and entitled to 1/5 share along with other legal representatives of Shah Veljee Kanjee. The appellants, buyers through the Patils, challenged this. The Supreme Court held that the appellants could not establish subsisting title through the original holders, whose rights were extinguished by prior transfers and by the lapse of time. Upholding the High Court, the Court dismissed the appeals as lacking merit.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Abhay Manohar Sapre
- Judgment Date
- 2018-05-03
- Court Decision / Holding
- Appeals dismissed; High Court’s judgment affirming plaintiff’s ownership and 1/5 share stands. The Supreme Court upheld the High Court’s reasoning that the appellants could not establish subsisting title and that the plaintiff had title by operation of law.
- Final Disposition
- Dismissed
Parties to the Case
Appellants / Petitioners
- M/s Eureka Builders & Ors.
Respondents
- Gulabchand s/o Veljee Dand (Deceased) through LRs and others
Legal Representation & Advocates
Counsels for Petitioners
- • Mr. Shekhar Naphade
Counsels for Respondents
- • Mr. Basava Prabhu S. Patil
- • Mr. G.V. Chandrashekhar
- • Mr. Ranbir Singh Yadav
- • Mr. Raghavendra S. Srivastava
Provisions of Law Cited
Legal Doctrines & Maxims
- A fortiori
- A person can transfer only the rights he possesses
- Inter se rights
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants contended that they entered into an agreement with the original owners (three Patils) for purchase in 2001 and claimed that the two State re-grant orders (1973) created subsisting rights in the original holders that could be transferred; therefore, if the original holders had any rights, the appellants could claim through them. They argued that the plaintiff’s title should be defeated by the re-grant orders and that the plaintiff could not claim a 1/5 share against the sellers and their successors.
Contentions of Respondents
The respondents asserted that the plaintiff had already established subsisting title in 1942/1943 through Shah Veljee Kanjee and that the re-grant orders did not revive rights after extinguishment. They emphasized that the original holders failed to maintain or press their claim within the limitation period and that the plaintiff’s possession since 1942/1943 was continuous and adverse to the claims of the original holders and their successors.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/s Eureka Builders & Ors. v. Gulabchand s/o Veljee Dand (Deceased) Through LRs & Others
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.