M/s EMAAR INDIA LTD. v. Tarun Agarwal Projects LLP & Anr.
Case Synopsis & Summary
This is a Civil Appeal under the Arbitration and Conciliation Act challenging a Delhi High Court order appointing arbitrators in Arbitration Petition No. 637 of 2021. The dispute stems from a Collaboration Agreement dated 07.05.2009 for developing a residential colony in Sector 62 and 65, Gurgaon, and an Addendum dated 19.04.2011. The respondents (original petitioners) claimed non-performance under the Addendum, issued a notice seeking possession of five plots and damages of Rs 10 crores, and invoked Section 11(5) & (6) to obtain court appointment of arbitrators. The appellant contended that Clauses 36 and 37 of the Addendum create a bifurcated regime: Clause 36 allows enforcement through a court for disputes arising under Clauses 3, 6 and 9, while Clause 37 provides for arbitration for “all or any dispute arising out of or touching upon or in relation to the terms of this Agreement.” The High Court, after noting Clauses 36 & 37, appointed arbitrators under Clause 37, holding that arbitration need not be barred. The appellant argued that the matter requires a preliminary inquiry into arbitrability and whether the dispute falls within Clause 36, citing Vidya Drolia, Booz Allen, Indian Oil and other decisions that emphasize limited judicial review at the Section 11 stage. The Supreme Court ultimately held that the High Court erred by not conducting a preliminary inquiry and remitted the matter for fresh consideration after such inquiry, quashing the arbitral appointment.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- M.R. Shah
- Judgment Date
- 2022-09-30
- Court Decision / Holding
- The impugned judgment and order passed by the High Court appointing the arbitrators in terms of Clause 37 of the Addendum Agreement dated 19.04.2011 is quashed and set aside. The matter is remitted to the High Court to decide the application under Section 11(5) and (6) afresh and to pass an appropriate order after holding a preliminary inquiry/review on whether the dispute is arbitrable or not and/or whether the dispute falls within Clause 36 of the Addendum Agreement or not.
- Final Disposition
- Appeal allowed. The High Court’s order appointing arbitrators is quashed and set aside. The matter is remitted to the High Court to decide the Section 11(5) & (6) application afresh after holding a preliminary inquiry on arbitrability and on whether the dispute falls within Clause 36 or Clause 37 of the Addendum Agreement, with appropriate orders passed thereafter, including potential reappointment of arbitrators if warranted by the inquiry. This is without costs to either side.
Parties to the Case
Appellants / Petitioners
- M/s EMAAR India Ltd.
Respondents
- Tarun Agarwal Projects LLP
- Anr.
Legal Representation & Advocates
Counsels for Petitioners
- • Shri Dhanesh Relan
Counsels for Respondents
- • Shri Siddharth Bhatnagar
Provisions of Law Cited
Legal Doctrines & Maxims
- Competence-competence
- Severability
- Restricted and limited judicial review at Section 8/11 stage
- Four-fold non-arbitrability test (paras 76.1–76.6)
- Arbitration clause must be strictly construed
- Arbitral tribunal as primary determiner of non-arbitrability (competence-competence)
- Prima facie test at reference stage for non-arbitrability (Vidya Drolia)
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant submits that Clause 36 of the Addendum Collaboration Agreement allows the other party to obtain enforcement through the appropriate court of law in cases of disputes arising under Clauses 3, 6 and 9. Clause 37 provides for arbitration for all or any dispute arising from the terms of the agreement. The High Court’s appointment of arbitrators under Clause 37 (despite Clause 36) bypassed the need to determine arbitrability. Citing Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd., Vidya Drolia, Indian Oil, and Booz Allen & Hamilton, the appellant argues that at the Section 11 stage, the court must conduct a preliminary inquiry to decide whether the dispute is arbitrable or falls under Clause 36; if non-arbitrable, arbitration should be refused. The reliance is on the restricted scope of judicial review post-amendments (Act 3 of 2016 and Act 33 of 2019) and the primacy of arbitral decision on arbitrability.
Contentions of Respondents
The respondents contend that Clauses 36 and 37 should be read together, showing the parties’ intent to arbitrate disputes under the Addendum. They argue the High Court correctly held that the dispute could be settled under arbitration and that the court’s intervention should not substitute the arbitral process. They rely on Vidya Drolia to emphasize a limited court review at Section 11, but contend that no manifest non-arbitrability exists on the facts, and the conjoint reading of Clauses 36 and 37 supports arbitration. They suggest the arbitrator’s appointment should stand and the issue of arbitrability can be decided by the arbitrator at a later stage under Section 16.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (13)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Uttarakhand Purv Sainik Kalyan Nigam Limited v. Northern Coal Field Limited | (2020) 2 SCC 455 | Positive | Cited to support the proposition that appointment of an arbitrator may be refused if the arbitration agreement is not in writing or if the dispute is beyond the arbitration agreement. |
| Vidya Drolia and Ors. v. Durga Trading Corporation | (2021) 2 SCC 1 | Positive | Cited for the principle of limited/restricted judicial review at Section 8/11 and the primacy of arbitrability determination by the arbitral tribunal, with a need for a preliminary inquiry in certain circumstances. |
| Indian Oil Corporation Limited v. NCC Limited | 2022 SCC OnLine SC 896 | Positive | Cited to support that at Section 11 stage a preliminary inquiry is permissible on arbitrability. |
| Oriental Insurance Co Ltd. v. Narbheram Power and Steel (P) Ltd. | (2018) 6 SCC 534 | Positive | Cited to emphasize strict construction of arbitration clauses and the non-arbitrability where explicit exclusions exist. |
| Rajasthan State Industrial Development and Investment Corporation v. Diamond and Gem Development Corporation Ltd. | (2013) 5 SCC 470 | Positive | Cited for strict interpretation of contract terms and avoiding revision of contract terms by the court. |
| Harsha Construction v. Union of India | (2014) 9 SCC 246 | Positive | Cited regarding the requirement that arbitration agreements be in writing and not to infer arbitrability where not provided. |
| Booz Allen & Hamilton Inc. v. SBI Home Finance Ltd. | (2011) 5 SCC 532 | Positive | Cited for the four-fold test of non-arbitrability and related criteria. |
| Garware Wall Ropes Ltd. v. Coastal Marine Constructions & Engg. | (2019) 9 SCC 209 | Positive | Cited on who should decide non-arbitrability and competence-competence. |
| United India Insurance Co. Ltd. v. Hyundai Engg. & Construction Co. Ltd. | (2018) 17 SCC 607 | Positive | Cited on matters related to non-arbitrability and arbitration agreements. |
| Narbheram Power & Steel (P) Ltd. | supra | Positive | Cited as part of the body of decisions addressing non-arbitrability and enforceability. |
| Olympus Superstructures (P) Ltd. v. Meena Vijay Khetan and Ors. | (1999) 5 SCC 651 | Positive | Cited for discussion on disputes that cannot be referred to arbitration and the boundaries of arbitration. |
| Patel Engineering Ltd. | null | Positive | Cited for the scope of judicial review in the context of arbitration matters post amendments. |
| Vidya Drolia and Ors. v. Durga Trading Corporation | (2021) 2 SCC 1 | Mentioned Only | Repeated reference to Vidya Drolia to emphasize the limited review framework. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/s EMAAR INDIA LTD. v. Tarun Agarwal Projects LLP & Anr.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.