High Court of KeralaDivision BenchAppeal allowed; set aside lower Court order; se...

M/S. DEVCHAND CONSTRUCTION v. UNION OF INDIA

Case / Petition Number:ARB.A NO. 29 OF 2018

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • P. B. Suresh Kumar
  • C. S. Sudha
Judgment Date
2022-02-16
Court Decision / Holding
The appeal is allowed. The impugned order in O.P.(Arb.) No.105/2015 is set aside. The Award to the extent it disallowed Claim No.1 for the release of security deposit of ₹3,00,000 towards risk liability is set aside and the said claim shall stand allowed. The amount of ₹3,00,000 shall be returned to the claimant with interest at 6% per annum from the date of moving the claim until realisation, along with costs.
Final Disposition
Appeal allowed; set aside lower Court order; security deposit to be released with interest and costs.

Parties to the Case

Appellants / Petitioners

  • M/S. DEVCHAND CONSTRUCTION, Thokkottu-PERUMANNUR POST, MANGALORE - 575017, represented by its Proprietor, Mr. Dinakar Ullal

Respondents

  • Union of India represented by Deputy Chief Engineer (Construction), Southern Railway, Kannur-670001

Legal Representation & Advocates

Counsels for Petitioners

  • • SMT. SANTHA VARGHESE
  • • SRI. RANJITH VARGHESE
  • • SRI. RAHUL VARGHESE

Counsels for Respondents

  • • SRI. S.ANANTHAKRISHNAN, SC, RAILWAYS

Case Synopsis & Summary

Devchand Construction v. Union of India is an arbitration appeal under Section 37 challenging an Arbitral Tribunal award of 24.04.2015 in O.P.(Arb.) No.105/2015. The dispute relates to the doubling of the Shornur–Mangalore track and related ballast work, with the contract terminated for alleged breach before completion. The Tribunal partly allowed the claimant’s prayer, permitting release of only ₹46,959 from the final bill, after deducting ₹3,00,000 as risk liability and forfeiture of the Earnest Money/Security Deposit; it found no demonstrable loss to the respondent. The appellant contends that the security deposit was forfeited without lawful basis, arguing that there was no pre-estimate of damages and no proven loss, so Sections 73–75 of the Indian Contract Act cannot justify forfeiture. It relies on case law including Fateh Chand, Rampur Distillery, and Kerala authorities, and on Kailash Nath Associates for the nature of damages and the difference between liquidated damages and penalties. The Railways defend the forfeiture as a risk liability under the contract’s terms. The High Court, noting that the Award did not identify a pre-stated sum for breach and that no loss was shown, holds that Sections 73–75 cannot govern the case; it reiterates the fundamental policy of Indian law under Section 34(2)(b)(ii) of the Arbitration Act. It further requires that forfeiture must be supported by loss or an authorized pre-estimate; the security deposit should be refunded with interest. The appeal is allowed, and the impugned order set aside.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 37Arbitration and Conciliation Act, 1996 - Section 34Arbitration and Conciliation Act, 1996 - Section 34(2)(b)(ii)Indian Contract Act, 1872 - Section 73Indian Contract Act, 1872 - Section 74General Conditions of Contract - Clause 62

Legal Doctrines & Maxims

  • IpsO facto
  • Reasonable compensation not exceeding the amount named or penalty under Section 74 of Indian Contract Act, 1872
  • No loss no damage principle under Sections 73-75 of the Indian Contract Act, 1872
  • Fundamental policy of Indian law under Section 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996
  • Forfeiture of security deposit requires loss or a pre-estimate to be valid

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the Arbitral Tribunal erred in holding the security deposit of ₹3,00,000 as forfeitable for breach where no loss or damage was caused; since no liquidated damages clause existed, Section 74 could not apply; under Section 73, compensation requires proven loss; reliance on Fateh Chand, Rampur Distillery, and Kerala authorities, and on Kailash Nath Associates for the nature of damages and the difference between liquidated damages and penalties; seeks release of the security deposit with interest.

Contentions of Respondents

The Railways contend the security deposit was forfeitable as risk liability due to breach; the award reflected the contract terms; the EMD had been forfeited; arguments emphasize that the breach justified deduction; reliance on GCC Clause 62 and applicable law.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Fateh Chand v. Balkishan Dass[1963] SC 1405PositiveCited to discuss that Section 74 contemplates compensation even without proof of loss, though not applicable here due to lack of a penalty clause.
State of Kerala v. United Shippers and Dredgers Ltd.AIR 1982 Ker 281Mentioned OnlyCited in context of forfeiture/loss principles; not directly relied upon for the present decision.
Abdulla v. State of Kerala2001 KHC 822Mentioned OnlyCited as authority in relation to loss/damage concepts; not central to the decision.
Kailash Nath Associates v. Delhi Development Authority(2015) 4 SCC 136PositiveCited to support the principle that forfeiture of security deposits is not automatic and depends on pre-estimated damages.
Union of India v. Rampur Distillery and Chemical Co. Ltd.AIR 1973 SC 1098PositiveHeld that forfeiture of security deposit for breach requires showing loss; supports the appellant's argument.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against M/S. DEVCHAND CONSTRUCTION v. UNION OF INDIA and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT** **THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR** **&** **THE HONOURABLE MRS. JUSTICE C.S. SUDHA** **WEDNESDAY, THE 16[TH] DAY OF FEBRUARY 2022 / 27TH MAGHA, 1943 ARB.A NO. 29 OF 2018** **AGAINST THE ORDER/JUDGMENT IN OP(ARB.) 105/2015 OF DISTRICT COURT, KASARAGOD** ## **APPELLANT/S:** **M/S. DEVCHAND CONSTRUCTION, THOKKOTTU-PERUMANNUR POST, MANGALORE - 575017, REPRESENTED BY ITS PROPRIETOR, MR.DINAKAR ULLAL.** **BY ADVS. SMT.SANTHA VARGHESE SRI.RANJITH VARGHESE SRI.RAHUL VARGHESE** ## **RESPONDENT/S:** **UNION OF INDIA, REPRESENTED BY THE DEPUTY CHIEF ENGINEER (CONSTRUCTION), SOUTHERN RAILWAY, KANNUR-670001.** **BY ADV SRI.S.ANANTHAKRISHNAN, SC, RAILWAYS** **THIS ARBITRATION APPEALS HAVING COME UP FOR ADMISSION ON 16.02.2022, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** ## **Arb. Appeal No.29 of 2018** -2- **“C.R.”** ## **P.B. SURESH KUMAR & C.S. SUDHA, JJ. ----------------------------------------------Arb. Appeal No.29 of 2018 ----------------------------------------------Dated this the 16[th] day of February, 2022** ## **JUDGMENT** ## **C.S.Sudha, J.** This appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 (the Act), is against the order dated 04.12.2017 in O.P.(Arb.) No.105/2015 of the District Court, Kasaragod. 2. The appellant herein is the petitioner before the court below and the claimant before the Arbitral Tribunal (AT). The respondent herein is the respondent before the court below and the respondent before the AT. The parties in this appeal will be referred to as described in the arbitral proceedings. 3. The respondent awarded the work of ‘doubling of track between Shornur and Mangalore, Cannanore-Uppala section: collection and stacking of 50mm size machine crushed hard stone ballast alongside the alignment/station yards/ on top of the new formation between Kottikulam ## **Arb. Appeal No.29 of 2018** -3- and Kasaragod stations (Balance works)’ to the claimant on 19.09.2000 for a value of ₹ 1,19,39,274/-. Letter of Acceptance (LoA) was issued on 19.09.2000. The work was to be completed within a period of nine months, that is, by 18.06.2001. Alleging breach on the part of the claimant, the contract was terminated by the respondent before the expiry of the completion period. Disputes arose between the parties. Arbitration proceedings was initiated. The AT consisting of three Arbitrators passed an award on 24.04.2015. The AT disallowed all the claims of the claimant except claim no. 1 for release of an amount of ₹ 3,46,959/-, which amount had been forfeited by the respondent towards risk liability amount. This claim was partly allowed to the tune of ₹ 46,959/-. All the other claims including the prayer for return of the Earnest Money Deposit (EMD) was rejected. Aggrieved, the claimant/contractor took up the matter before the District Court. The said Original Application filed under s.34 of the Act was dismissed by the impugned order. 4. Heard Shri.Rahul Varghese, the learned counsel for the appellant and Shri.Ananthakrishnan, the learned Standing Counsel for the Railways. 5. In the appeal memorandum it is stated that during the pendency ## **Arb. Appeal No.29 of 2018** -4- of the proceeding before the court below, the respondent released the EMD amounting to ₹50,000/-. This according to the claimant has been done when the respondent realized that it was illegal for them to have withheld the same, especially when they had not suffered any loss or damage. Therefore, the only point to be decided in this appeal is whether there is any infirmity in the finding of the AT that the respondent is entitled to forfeit the security deposit of ₹ 3 lakhs towards risk liability in the absence of any loss or damage. According to the AT, the claimant had failed to execute the work and hence the contract had been terminated at his risk and cost in terms of Clause 62 of the General Conditions of Contract. An amount of ₹ 3 lakhs deposited as security deposit and an amount of ₹ 46,959/- towards advertisement charges had been deducted by the respondent from the final bill as the amount towards risk liability. The AT concluded that since the breach of the contract had been committed by the claimant/contractor, the security deposit of ₹ 3 lakhs is liable to be forfeited and therefore out of the total amount of ₹3,46,959/- claimed by the claimant, only an amount of ₹ 46,959/- was allowed. However, in the award itself it is stated that no loss/damage had been caused to the respondent. Therefore, it is submitted by the learned counsel for the claimant/contractor that in such circumstances ## **Arb. Appeal No.29 of 2018** -5- the forfeiture of ₹3 lakhs deposited as security deposit is patently wrong, illegal and perverse. Reference was made to the decisions in **Fateh Chand vs. Balkishan Dass [1963 SC 1405]; State of Kerala vs. United Shippers and Dredgers Ltd. [AIR 1982 Ker 281]; Abdulla vs. State of Kerala [2001 KHC 822]** and **Kailash Nath Associates vs. Delhi Development Authority [(2015)4 SCC 136]** in support of this argument. 6. Here we need to refer to Sections 73 and 74 of the Indian Contract Act, 1872. Section 74 of reads thus - _“74_ _**Compensation for breach of contract where penalty stipulated for** :-[When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.”_ 7. As laid down in the aforesaid decisions, in a case coming under Section 74, it is not necessary for the party claiming compensation under this Section to prove that actual damage or loss has been caused. Then the question is whether even in the absence of legal injury, compensation is liable to be paid for breach simplicitor. Under Section 74, whether it is a ## **Arb. Appeal No.29 of 2018** -6- case of liquidated damages or penalty, what the party faced with the breach gets is only reasonable compensation, subject to the limit of the amount stipulated in the contract itself. Section 74 dispenses with proof of the extent of real or actual or factual loss or damage, but provides for grant of reasonable compensation, subject to the condition that it shall not exceed the sum stipulated as penalty in the contract. The proof of the extent of loss or damage suffered in fact, i.e., proof of the extent of actual damage or loss suffered is dispensed with in Section 74. This would not mean that there need not be any loss or damage. What is meant is only that proof of actual damage or loss is not necessary. 8. In the case on hand, it cannot be Section 74 that could have been invoked, because the Award does not say that any sum has been named in the contract as the amount to be paid in case of breach. In other words, the parties had never made a genuine pre-estimate of the amount to be paid in the event of any damage or loss likely to be caused by the breach or that there is any clause relating to liquidated damages in the contract. 9. Section 73 reads- _“When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the_ ## **Arb. Appeal No.29 of 2018** -7- _contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it._ _Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach.”_ 10. The words 'loss or damage' in the aforesaid sections would necessarily indicate that the party who complains of breach must have really suffered some loss or damage apart from being faced with the mere act of breach of contract. That is because every breach of every contract need not necessarily result in actual loss or damage. Compensation payable under Section 73, 74 as also under Section 75 is only for loss or damage caused by the breach and not account of the mere act of breach. If in any case the breach has not resulted in or caused any loss or damage to a party, he cannot claim compensation. 11. Further, in **Union of India v. Rampur Distillery and Chemical Co. Ltd. (AIR 1973 SC 1098) the Apex Court** held that a party to a contract taking security deposit from the other party to ensure due performance of the contract, is not entitled to forfeit the deposit on ground of default when no loss is caused to him in consequence of such default. When the question is one of forfeiture of security deposit in case of breach of ## **Arb. Appeal No.29 of 2018** -8- contract, such sum does not _ipso facto_ go to the respondents. If the party complaining is in a position to adduce evidence whereby the court can assess reasonable compensation, then without proof of actual loss, damages will not be awarded and amount mentioned by the contract will be penalty. In such circumstances, it has been held that the security amount is liable to be forfeited. 12. As noticed earlier, the Award in this case clearly says that no loss or damage has been caused to the respondent. That being the position, neither the provisions of Sections 73, 74 or 75 could have been invoked nor are they applicable in this case. That being the position, the AT was certainly wrong in rejecting the claim of the claimant for release of the amount of security deposit of ₹ 3 lakhs. This finding in violation of the provisions of Sections 73 to 75 of the Contract Act, is certainly in contravention of the fundamental policy of Indian Law as contemplated in Section 34(2)(b)(ii) of the Act. In the result, the appeal is allowed. The impugned order dated 4.12.2017 in O.P.(Arb.) No.105/2015 is set aside. The Award to the extent it disallows Claim No.1 for the release of security deposit of ₹ 3 lakhs towards risk liability amount, is set aside and the said claim shall stand allowed. The ## **Arb. Appeal No.29 of 2018** -9- amount has been withheld without any justification and therefore the amount of ₹ 3 lakhs will be returned by the respondent to the claimant with interest @ 6% p.a. from the date of moving the claim before the AT till realisation and costs. sd/- **P.B.SURESH KUMAR, JUDGE.** sd/- **C.S.SUDHA, JUDGE.** STK