High Court of KeralaSingle JudgeWrit petition dismissed; Exhibit P26 terminatio...

M/S. Deens Constructions v. State of Kerala and others

Case / Petition Number:W.P.(C) No. 12643 of 2023

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Shaji P. Chaly, J.
Judgment Date
2023-04-25
Court Decision / Holding
Needless to say, the writ petition fails and accordingly it is dismissed.
Final Disposition
Writ petition dismissed; Exhibit P26 termination upheld; contract binding and termination justified.

Parties to the Case

Appellants / Petitioners

  • M/S. Deens Constructions

Respondents

  • State of Kerala represented by the Secretary to the Government Public Works Department, Government Secretariat, Thiruvananthapuram, Kerala – 695001
  • Chief Engineer PWD Roads Division, Thiruvananthapuram, PIN – 695033
  • Superintending Engineer PWD Roads Division, Central Circle, Aluva, Ernakulam, Kerala – 683101
  • Executive Engineer PWD Roads Division Ernakulam – 682 024
  • Assistant Executive Engineer PWD, Roads Sub-Division, North Paravur – 683 513
  • Assistant Engineer, PWD, Roads Section, Njarakkal – 682 503

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. Santosh Mathew
  • • Smt. Karthika Maria
  • • Sri. Anil Sebastian Pulickel
  • • Sri. Abi Benny Areeckal
  • • Sri. Mathew Nevin Thomas
  • • Sri. Kurian Antony Mathew

Counsels for Respondents

  • • Sri. K.V. Manoj Kumar, SPL. Government Pleader

Case Synopsis & Summary

The petitioner, a contractor engaged by the State Public Works Department for the Special Package Non Plan works 2020-21—Improvements (BM & BC) to Vypin-Pallipuram Parallel Road, Ch. 11/000 to 17/000, challenges Exhibit P26, the termination order dated 15.03.2023 issued by the Superintending Engineer, PWD Roads Division, Central Circle, Aluva. The core dispute centers on termination at the petitioner’s risk and cost after a prolonged sequence of delays attributed to public obstruction, Covid-19, shortages of materials, monsoon and floods, and a shift in instructions requiring reporting of intermediate levels after laying the GSB layer. The petitioner contends that intermediate levels were not approved timely due to non-cooperation, and that pandemic-related constraints and material unavailability hindered progress; the petitioner relies on Sections 56 and 55 of the Indian Contract Act, 1872 and on Supreme Court judgments to argue that the State and its instrumentalities must observe constitutional guarantees, especially Article 14. The respondents contend that despite extensions the project did not progress; termination was legal under the contract terms. The court reviews whether there is arbitrariness in Exhibit P26, finds that despite opportunities, progress remained lacking and that extensions were granted; thus, the writ petition is dismissed and the termination stands. The decision underscores that contract terms bind the parties and writ court interference is unwarranted where there is no demonstrated illegality in termination.

Provisions of Law Cited

Section 56 Indian Contract Act, 1872Section 55 Indian Contract Act, 1872Article 14, Constitution of IndiaArticle 226, Constitution of IndiaPart III, Constitution of India

Legal Doctrines & Maxims

  • Force majeure (concept in contractual matters)
  • Equality before law under Article 14 of the Constitution
  • Contract binds the parties; termination under contract terms permissible

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends delays were caused by (i) public obstruction and interference by local representatives; (ii) Covid-19 pandemic causing labour and material shortages; (iii) late approval of initial levels and shifting of measurement requirements after GSB layer; (iv) material unavailability; (v) multiple extensions and communications. The petitioner relies on Sections 56 and 55 of the Indian Contract Act, 1872 and on Supreme Court judgments to argue State liability under Part III, particularly Article 14, and seeks quashing of Exhibit P26 termination and restoration of work progress.

Contentions of Respondents

The respondents contend that despite extensions the project did not progress; the contract permitted termination for breach; external factors were considered but not proven as force majeure; the petitioner was given multiple opportunities and extensions; the writ petition should be dismissed; the termination was proper under the agreement and the state instrumentality cannot be compelled to perform where performance is blocked by the contractor’s failure to progress as required.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
J.G. Engineers Private Limited v. Union of India(2011) 5 SCC 758DistinguishedCited to discuss constitutional obligations; court distinguished as not directly applicable to the contract termination context here.
Food Corporation of India v. Kamadhenu Cattle Feed Industries[(1993) 1 SCC 71]DistinguishedCited in constitutional rights discussion but found inapplicable to the present contractual termination analysis.
State of Karnataka v. Shree Rameshwara Rice Mills[(1987) 2 SCC 160]DistinguishedCited for broad constitutional principles but distinguished on facts for the current case.
Tulsi Narayan Garg v. M.P. Road Development Authority, Bhopal[(2019 SCC Online SC 1158)]DistinguishedCited to support rights arguments but distinguished in the specific contractual termination context.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against M/S. Deens Constructions v. State of Kerala and others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

W.P.(C) No. 12643/2023 : 1 : IN THE HIGH COURT OF KERALA AT ERNAKULAM ## PRESENT THE HONOURABLE MR. JUSTICE SHAJI P.CHALY TUESDAY, THE 25[TH] DAY OF APRIL 2023 / 5TH VAISAKHA, 1945 ## WP(C) NO. 12643 OF 2023 ## PETITIONER/S: M/S. DEENS CONSTRUCTIONS FIRST FLOOR, DEENS BUILDING, PERINGALA P.O., ERNAKULAM, REPRESENTED BY ITS MANAGING PARTNER, SHRI. SHAHUL HAMEED., PIN – 684 565. BY ADVS. SRI. SANTHOSH MATHEW SMT. KARTHIKA MARIA SRI. ANIL SEBASTIAN PULICKEL SRI. ABI BENNY AREECKAL SRI. MATHEW NEVIN THOMAS SRI. KURIAN ANTONY MATHEW ## RESPONDENT/S: - 1 STATE OF KERALA REPRESENTED BY THE SECRETARY TO THE GOVERNMENT PUBLIC WORKS DEPARTMENT, GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM, KERALA – 695 001. - 2 CHIEF ENGINEER PWD ROADS DIVISION, THIRUVANANTHAPURAM, PIN – 695 033. - 3 SUPERINTENDING ENGINEER PWD ROADS DIVISION, CENTRAL CIRCLE, ALUVA ERNAKULAM, KERALA, PIN – 683 101. - 4 EXECUTIVE ENGINEER PWD ROADS DIVISION ERNAKULAM – 682 024. - 5 ASSISTANT EXECUTIVE ENGINEER PWD, ROADS SUB-DIVISION, NORTH PARAVUR, PIN – 683 513. - 6 ASSISTANT ENGINEER, PWD, ROADS SECTION, NJARAKKAL., PIN – 682 503. SRI. K.V. MANOJ KUMAR, SPL. GOVERNMENT PLEADER THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 11.04.2023, THE COURT ON 25.04.2023 DELIVERED THE FOLLOWING: W.P.(C) No. 12643/2023 ## : 2 : ## **SHAJI P. CHALY, J.** --------------------------------------------------------W.P.(C). No. 12643 of 2023 --------------------------------------------------------Dated this the 25[th] day of April, 2023. ## **JUDGMENT** The petitioner, a contractor engaged by the State Public Works Department for the work “Special Package Non Plan works 2020-21-Improvements (BM & BC) to Vypin-Pallipuram Parallel road Ch. 11/000 to 17/000”, has filed this writ petition challenging Exhibit P26 order dated 15.03.2023 passed by the Superintending Engineer, PWD Roads Division, Central Circle, Aluva Ernakulam District-- respondent No.3; whereby the contract was terminated at the risk and cost of the petitioner. 2. The basic facts for the disposal of the writ petition are as follows: On the basis of Exhibit P1 Notice Inviting Tender dated 15.02.2021, the petitioner participated in the tender and was awarded the work as per Exhibit P2 letter of acceptance; consequent to which Exhibit P3 agreement dated 08.09.2021 was executed by and between the parties. 3. As per the terms and conditions of the tender, the petitioner has provided a bank guarantee of Rs.8,83,750/-, which is valid upto 14.01.2027. The petitioner had submitted initial levels to the W.P.(C) No. 12643/2023 : 3 : Assistant Engineer, PWD Roads Section, Njarakkal, respondent No.6, evident from Exhibit P4 communication dated 18.08.2021. 4. According to the petitioner, the said levels were not approved for an inordinate amount of time. It is further submitted that the work involves scarifying the existing surface of the site. According to the petitioner, it was part of the petitioner’s scope of work and necessary for the execution of the work as a whole. It is also submitted that the Chief Technical Examiner of the State Government, respondent No.1, vide Exhibit P5 Observation memo dated 11.11.2021, had directed the Executive Engineer, PWD Roads Division, Ernakulam, respondent No.4, to report the intermediate levels after scarifying the existing carriageway and rolling the scarified materials before laying the GSB layer. 5. Apparently, the said instruction was passed on to the petitioner by the Assistant Engineer, PWD Roads Section, Njarakkal, respondent No.6, as per Exhibit P6 letter dated 07.12.2021. The case of the petitioner is that the petitioner was obstructed from carrying out scarification by members of the local public, including the elected representatives of the local Panchayat, which according to the petitioner, is recorded in Exhibit P7 letter dated 07.12.2021 submitted by the petitioner to the Superintending Engineer, respondent No.3. W.P.(C) No. 12643/2023 : 4 : 6. Therefore, according to the petitioner, the intermediate levels could not be reported, since as per the instructions contained in Exhibits P5 and P6, the same was possible only after the scarification was done and before the GSB layer was laid. Anyhow, it is admitted that the petitioner was subsequently instructed orally by the Assistant Executive Engineer, PWD Roads Sub division, North Paravur, 5[th] respondent, to take levels after GSB layer was laid. It seems, as per Exhibit P8 letter dated 03.03.2022, the petitioner sought written confirmation of the same, since it deviated from the earlier instructions. 7. It is further submitted that the above stated work was severely affected by the consequences of pandemic Covid-19, such as shortage of men and materials, and that the shortage of material, in particular, persisted throughout the course of the work and contributed immensely to slow the progress of the work. It is also submitted that the materials as per Exhibit P3 agreement were not available in the market, which also contributed to the slow progress of the work. That apart, it is submitted that there were only limited number of crusher units operational in Ernakulam District, which according to the petitioner, is recorded in Exhibit P9 minutes of the hearing conducted by the Superintending Engineer, PWD Roads Division, Central Circle, Aluva, respondent No.3, dated W.P.(C) No. 12643/2023 : 5 : 19.05.2022. It seems, the petitioner, in that regard, had issued Exhibit P10 letter dated 28.05.2022 to the Superintending Engineer. 8. It is further contended that the onset of monsoon and heavy rains and flooding in the area also led to the delay in work. The sum and substance of the contention advanced by the petitioner is that various factors beyond the control of the petitioner delayed the progress of the work and the petitioner cannot be blamed for the same. Further, due to heavy rains, turbulent sea water and the nature of the soil and site, the petitioner had to execute excess quantities and the petitioner has issued Exhibit P11 letter dated 26.08.202 to the Superintending Engineer, respondent No. 3, which according to the petitioner, was supported by the Assistant Engineer, 6[th] respondent, vide Exhibit P12 report dated 27.08.2022. The said aspect was supported by the report of the Assistant Executive Engineer, 5[th] respondent, vide Exhibit P13 report dated 02.09.2022. 9. Therefore, it is submitted that in spite of earnest efforts made by the petitioner, no action was initiated in respect of the excess quantity claimed by the petitioner. Anyhow, it is admitted that the petitioner, as per Exhibit P14 letter dated 16.09.2022, has requested for extension of time of completion. It seems, Exhibit P15 letter dated 16.09.2022 is issued by the Assistant Engineer, W.P.(C) No. 12643/2023 : 6 : respondent No.6, to the Assistant Executive Engineer, respondent No. 5, supporting the time extension sought for by the petitioner. Even though the petitioner has sought for extension of time upto 31.03.2023, it was granted only upto 17.12.2022, despite the recommendation made by the Assistant Executive Engineer upto 31.03.2023, without fine. 10. Anyhow, it is submitted that in spite of the extension of time, the initial levels of the work were not yet approved by the respondents. It seems, as per Exhibit P16 communication dated 23.11.2022, the Superintending Engineer, respondent No.3, issued a communication to the Executive Engineer, 4[th] respondent, seeking a detailed level proposal report and an explanation for delay in the submission of initial levels 11. According to the petitioner, a hearing was held on 09.12.2022 by the Superintending Engineer, respondent No.3, to take stock of the work. It is the case of the petitioner that the petitioner's submission that the slow progress of the work at that stage was due to the financial crisis brought about due to the delay in payment of the petitioner’s bills, has been recorded in Exhibit P17 minutes of hearing dated 09.12.2022. While so, on 03.01.2023, the petitioner, as per Exhibit P18, again sought for extension of time of completion till 31.03.2023. W.P.(C) No. 12643/2023 : 7 : 12. In the meanwhile, on 05.01.2023, the Assistant Executive Engineer, 5[th] respondent, submitted Exhibit P20 corrected initial level proposal to the Executive Engineer, respondent No.4. According to the petitioner, the Superintending Engineer, PWD (Buildings), Central Circle, Thrissur, at that point of time, arbitrarily and illegally cancelled the petitioner’s Class A Contractors licence vide Exhibit P21 letter dated 09.01.2023. Admittedly, Exhibit P21 order dated 09.01.2023 arises out of the termination of another work undertaken by the petitioner and the same is under challenge in W.P.(C) No. 328 of 2023. Therefore, it is submitted that consequent to Exhibit P21 order cancelling the petitioner‘s contractors licence, the bank imposed a debit freeze on the petitioner’s account effectively rendering it impossible for the petitioner to carry out any further work. 13. However, on 12.01.2023, Exhibit P22 supplemental agreement was entered into by and between the petitioner and the Superintending Engineer, respondent No. 3, giving effect to Exhibit P18 order. According to the petitioner, the petitioner, vide Exhibit P23 dated 31.01.2023, reported that the work could not progress due to tipper, quarry and crusher strikes. It is further submitted that initial levels were finally approved only on 06.02.2023 i.e., after the petitioner’s licence had been suspended as per Exhibit P21 W.P.(C) No. 12643/2023 : 8 : order dated 09.01.2023. 14. While so, on 27.02.2023, the Superintending Engineer, respondent No.3, issued Exhibit P24 notice dated 27.02.2023 to the petitioner stating that the work would be terminated at the petitioner’s risk and cost, if the petitioner did not re-commence the work, completely ignoring the issues that had led him not being able to execute the work any longer. Narrating the said alleged incident, the petitioner has submitted Exhibit P25 representation dated 28.02.2023, pointing out that an amount of Rs.1,20,12,245.95 is due to the petitioner and that the same is withheld due to the failure on the part of the respondents itself in approving the initial levels. Anyhow, on 15.03.2023, the impugned Exhibit P26 order was issued terminating the work of the petitioner. According to the petitioner, Exhibit P26 is arbitrary and illegal; that Exhibit P26 order perversely interprets the petitioner’s submissions in Exhibit P25 representation to find fault with the petitioner for facing the consequences of the illegal actions of the respondents surrounding Exhibit P26 order. 15. That apart, it is contended that Exhibit P26 order does not address any of the actual issues regarding the work that were raised by the petitioner in Exhibit P25. It is also argued that the petitioner has made earnest efforts to carry out the work to the W.P.(C) No. 12643/2023 : 9 : extent possible and the delay had occurred due to the reasons that are not attributable to the petitioner. It is further contended that the respondents had not even approved the initial levels for the work till 06.02.2023, which was supposed to be done before the commencement of the work by the petitioner. 16. Therefore, the sum and substance of the contention advanced by the petitioner is that the petitioner cannot be compelled to carry out the work when the petitioner is not being paid for the work already done and when the initial levels for the work were not approved more than one year after Exhibit P3 was entered into. Therefore, it is contended that the petitioner is unable to maintain the liquidity required for executing the work due to the acts and omission of the respondents, consequent to which the petitioner cannot be compelled to execute the work that would lead to its financial ruin. The learned counsel has relied upon Section 56 of the Indian Contract Act, 1872 to establish the same. 17. The petitioner has also relied upon Section 55 of the Act, 1872 to state that since the respondents have failed to execute their part of contract, time is not the essence of the contract. The petitioner has also placed reliance upon the judgments of the Apex Court in J. _**G. Engineers Private Limited v. Union of India**_ [(2011) 5 SCC 758]; _**Food Corporation of India v. Kamadhenu**_ W.P.(C) No. 12643/2023 : 10 : _**Cattle Feed Industries**_ [(1993) 1 SCC 71]; _**State of Karnataka v. Shree Rameshwara Rice Mills**_ [(1987) 2 SCC 160]; _**Tulsi Narayan Garg v. M.P. Road Development Authority, Bhopal**_ [(2019 SCC Online SC 1158], and various other judgments of the Honourable Supreme Court to canvass the proposition that the State and its instrumentalities, even in contractual matters, are liable to adhere to the fundamental rights guaranteed under Part III of the Constitution of India, especially the rights emanating from Article 14 of the Constitution of India. 18. I have heard the learned counsel for the petitioner Sri. Santhosh Mathew and the learned Special Government Pleader Sri. K.V. Manoj Kumar, and perused the pleadings and materials on record. 19. The deliberation of facts made above would make it clear that the sole question to be considered is whether any manner of interference is required to Exhibit P26 order of termination passed by the Superintending Engineer. It is quite clear and evident that the petitioner has not started the work after submitting the initial level alleging that the initial level was not approved by the respondents. But, fact remains, even according to the petitioner, even though as per Exhibits P5 and P6 observation Memos, directions were issued to the Executive Engineer to report the W.P.(C) No. 12643/2023 : 11 : intermediate levels after scarifying the existing carriageway and rolling the scarified materials before laying the GSB layer, the petitioner was subsequently instructed orally by the 5[th] respondent to take measures after GSB layer was laid. 20. The case projected by the petitioner is that even though the petitioner has sought for a written confirmation as per Exhibit P8 letter, it was not given. Admittedly, the petitioner does not have an established case that the petitioner was, in any way, prevented from proceeding with the work. However, the contention of the petitioner therein is that various factors beyond its control, including shortage of materials for executing the work, precluded it from starting the work. I am of the view that the petitioner, being an experienced contractor, especially in road work, should be well aware of the availability or shortage of any materials within a reasonable area. After undertaking the work and executing the agreement to complete the work within a time period, the petitioner is not expected to violate the terms and conditions of the contract entered into by and between the parties stating that due to the factors beyond its control, the work could not be completed. 21. It is an admitted fact that the petitioner has sought for extension of time which was granted initially for a period of three months from 17.09.2022 upto 17.12.2022 by executing Exhibit P22 W.P.(C) No. 12643/2023 : 12 : supplemental agreement. The petitioner has again sought for extension of time which was granted upto 31.01.2023 imposing a fine of Rs.1,15,556/-. Having executed the supplemental agreements, the petitioner cannot turn around and say that it could not complete the work due to reasons beyond its control and other force majeure factors. It is also equally important to note that the circumstances leading to the execution of supplemental agreements is not under challenge. Which means, on the basis of the request made by the petitioner, time of completion was extended, which, in turn, is a clear indicator to show that the petitioner was responsible for the delay in executing the work. 22. On a perusal of the documents available on record and Exhibit P26 impugned order, it is clear that various communications were issued to the petitioner to complete the work at the earliest possible. It seems various conferences were held in the presence of the Member of the Legislative Assembly concerned and the District Collector. It is evident that since the work in question is a road work, the public has also protested the slow progress of the work. Anyhow, in spite of the two extensions given, the petitioner has not achieved any progress. However, the petitioner has a case that since it was not paid the amounts for the work done, the contract has become impossible to be performed and by virtue of Section 56 W.P.(C) No. 12643/2023 : 13 : of the Contract Act, 1872, the petitioner cannot be compelled to perform the agreement executed by and between the parties. 23. In my considered opinion, even though force majeure factors are put forth by the petitioner, it could not establish the same by producing convincing materials before this Court. It may be true, in contractual matters also, the writ court may be justified in interfering even with the factual findings rendered by the State or its instrumentalities. But, in order to arrive at such a conclusion, there should be adequate materials to justify such an action. 24. It may be true, the Assistant Engineer and the Assistant Executive Engineer might have made recommendations on the basis of the request made by the petitioner. But, ultimately, the agreement authority has to take a decision. In fact, as pointed out above, extensions were granted as sought for by the petitioner and despite the same, it could not achieve sufficient progress in the work. It is quite clear and evident from Exhibit P2 letter of acceptance issued by the Superintending Engineer that the work had to be completed within 12 months and as per the bar chart submitted. The letter of acceptance is dated 01.07.2021. However, the petitioner could not make any required progress, despite the communications issued by the agreement authority and other officials, and in spite of extending the time of completion of the W.P.(C) No. 12643/2023 : 14 : work twice. 25. Considering the facts and figures, I am of the view that the petitioner has not made out a case of arbitrariness, illegality or unfairness in Exhibit P26 order, especially due to the fact that enough and more opportunities were provided to the petitioner; that the petitioner was heard, and that even the petitioner made an assurance that the work would be started immediately after the strike of the tipper lorries were over. It is also clear that despite the extended time, and beyond the period the petitioner hesitated to re-start the work 26. That apart, it is categoric and clear from the submissions made by the petitioner in the writ petition itself that he is unable to perform the work, even though he has a contention that the work is now impossible to be performed, consequent to the action on the part of the respondents. I am of the view that payment is to be effected on the basis of the agreement executed by and between the parties. It is also not in dispute that as per the agreement executed by and between the parties and the General Terms and Conditions of the contract, if the terms and conditions are violated, the agreement authority is vested with ample powers to terminate the contract. 27. The contention advanced by the petitioner, relying upon W.P.(C) No. 12643/2023 : 15 : various judgments of the Apex Court that the agreement authority is not vested with powers to terminate the contract and for that purpose the agreement authority has to approach the civil court, in my considered opinion, is not having any foundation or basis. 28. Considering the facts and figures, I am of the view that reliance placed by the petitioner on the proposition of law laid down by the Apex Court in the judgments specifically mentioned in the grounds of the writ petition, would not come to the rescue of the petitioner, since action was initiated by the respondents on the basis of the clear terms and conditions contained under the agreement executed by and between the parties and the tender documents. The petitioner has no case that the terms and conditions of the agreement is forbidden by law, illegal, void, opposed to public policy, or unconscionable, to make it nugatory or impossible to be performed or acted upon. 29. Therefore, needless to say, the agreement binds the parties to it; and in this case having not acted upon in terms of the agreement by the petitioner, the agreement authority was legally correct and justified in terminating the contract. In that view of the matter it cannot be said that the petitioner was able to establish any case of illegality, maladies, irrationality, arbitrariness or any such legal infirmities justifying to exercise the powers conferred on W.P.(C) No. 12643/2023 : 16 : this court under article 226 of the Constitution of India. Needless to say, the writ petition fails and accordingly it is dismissed. sd/- **SHAJI P. CHALY, JUDGE.** Rv W.P.(C) No. 12643/2023 : 17 : ## **APPENDIX OF WP(C) 12643/2023** ## PETITIONER’S EXHIBITS: |Exhibit P1|A TRUE COPY OF THE NIT DATED 15.02.2021 FLOATED| |---|---| ||BY THE 3RD RESPONDENT FORTHE WORK "SPECIAL| ||PACKAGE NON PLAN WORKS 2020-21 -| ||IMPROVEMENTS (BM &BC) TO VYPIN -PALLIPURAM| ||PARALLEL ROAD CH. 11/000 TO 17/000".| |Exhibit P2|A TRUE COPY OF THE LOA DATED 01.07.2021 ISSUED| ||IN FAVOUR OF THE PETITIONER.| |Exhibit P3|A TRUE COPY OF THE RELEVANT EXTRACTS OF THE| ||AGREEMENT DATED 08.09.2021 EXECUTED BETWEEN| ||THE PETITIONER AND THE 3RD RESPONDENT.| |Exhibit P4|A TRUE COPY OF THE PETITIONER'S LETTER DATED| ||18.08.2021 TO THE 6TH RESPONDENT.| |Exhibit P5|A TRUE COPY OF THE OBSERVATION MEMO DATED| ||11.11.2021 OF THE CHIEF TECHNICAL EXAMINER OF| ||THE 1ST RESPONDENT TO THE 4TH RESPONDENT.| |Exhibit P6|A TRUE COPY OF THE 6TH RESPONDENT'S LETTER| ||DATED 07.12.2021 TO THE PETITIONER.| |Exhibit P7|A TRUE COPY OF THE PETITIONER'S LETTER TO THE| ||3RD RESPONDENT DATED 26.02.2022.| |Exhibit P8|A TRUE COPY OF THE PETITIONER'S LETTER DATED| ||03.03.2022 TO THE 4TH RESPONDENT.| |Exhibit P9|A TRUE COPY OF THE MINUTES OF THE HEARING| ||CONDUCTED BY THE 3RD RESPONDENT DATED| ||19.05.2022.| |Exhibit P10|A TRUE COPY OF THE PETITIONER'S LETTER TO THE| ||3RD RESPONDENT DT 28.05.2022| |Exhibit P11|A TRUE COPY OF THE PETITIONER'S LETTER DATED| ||26.08.2022 TO THE 3RD RESPONDENT.| |Exhibit P12|A TRUE COPY OF THE REPORT OF THE 6TH| ||RESPONDENT DATED 27.08.2022.| |Exhibit P13|A TRUE COPY OF THE REPORT SUBMITTED BY THE 5TH| ||RESPONDENT DATED 02.09.2022 TO THE 4TH| ||RESPONDENT.| |Exhibit P14|A TRUE COPY OF THE PETITIONER'S REQUEST FOR| ||EXTENSION IN TOC DATED 16.09.2022.| |Exhibit P15|A TRUE COPY OF THE LETTER OF THE 6TH| ||RESPONDENT DATED 16.09.2022 TO THE 5TH| ||RESPONDENT.| |Exhibit P16|A TRUE COPY OF THE 3RD RESPONDENT'S| ||COMMUNICATION TO THE 4TH RESPONDENT DATED| ||23.11.2022.| |Exhibit P17|A TRUE COPY OF THE MINUTES OF THE HEARING| ||DATED 09.12.2022 HELD BY THE 3RD RESPONDENT.| |Exhibit P18|A TRUE COPY OF THE 3RD RESPONDENT'S ORDER| ## W.P.(C) No. 12643/2023 : 18 : DATED 19.12.2022 Exhibit P19 A TRUE COPY OF THE PETITION'S EXTENSION REQUEST DATED 03.01.2023 Exhibit P20 A TRUE COPY OF THE 5TH RESPONDENT'S LETTER TO THE 4TH RESPONDENT DATED 05.01.2023. Exhibit P21 A TRUE COPY OF THE ORDER OF THE SUPERINTENDING ENGINEER, PWD (BUILDINGS) CENTRAL CIRCLE, THRISSUR DATED 09.01.2023 Exhibit P22 A TRUE COPY OF THE SUPPLEMENTAL AGREEMENT DATED 12.01.2023 EXECUTED BETWEEN THE PETITIONER AND THE 3RD RESPONDENT.. Exhibit P23 A TRUE COPY OF THE PETITIONER'S LETTER DATED 31.01.2023 TO THE 6TH RESPONDENT. Exhibit P24 A TRUE COPY OF THE 3RD RESPONDENT'S NOTICE DATED 27.02.2023 TO THE PETITIONER. Exhibit P25 A TRUE COPY OF THE PETITIONER'S REPRESENTATION DATED 28.02.2023 TO THE 3RD RESPONDENT. Exhibit26 A TRUE COPY OF THE 3RD RESPONDENT'S ORDER DATED 15.03.2023. ## RESPONDENTS’ EXHIBITS: NIL True Copy rv PS To Judge.