High CourtDivision BenchAppeal dismissed, with no order as to costs

M/S Channy Enterprises v. Commissioner of Central Excise, Chandigarh

Case / Petition Number:Civil Appeal No. 2415 of 2005
Neutral Citation:[2005] 3 S.C.R. 252

Case Details & Bench

Court
High Court
Hon'ble Judges
  • Ruma Pal
  • C.K. Thakker
Judgment Date
2005-04-05
Court Decision / Holding
Appeal dismissed.
Final Disposition
Appeal dismissed, with no order as to costs

Parties to the Case

Appellants / Petitioners

  • M/S Channy Enterprises

Respondents

  • Commissioner of Central Excise, Chandigarh

Legal Representation & Advocates

Counsels for Petitioners

  • • P. C. Jain
  • • Sandeep Jain
  • • Rajesh Kumar

Counsels for Respondents

  • • R. Venkataramani
  • • V. G. Pragasam
  • • P. Parmeswaran

Case Synopsis & Summary

With effect from 1 September 1997, the Government notified ingots and billets under Section 3A of the Central Excise Act, 1944 for levy of excise duty on the basis of the annual capacity of production (ACP) of a factory. To determine ACP, the Induction Furnace Annual Capacity Determination Rules, 1997 were framed; Rule 3 and 4 operate with the Central Excise Rules, 1944, Rule 96(ZP). Circular dated 26 February 1998 clarified ACP where a unit has more than one rolling mill. It states that if a unit has one reheating furnace with two rolling mills, the higher capacity of the two mills should be taken as ACP; however, if each rolling mill has a separate reheating furnace, the ACP would be the sum total of the capacities of each rolling mill in the unit, irrespective of simultaneous operation. The appellant, having two mills, had previously operated with one furnace and later installed a second furnace but with a single motor, arguing ACP should reflect the higher mill’s capacity. The Commissioner clubbed the capacities on the basis of the 1998 circular, a decision upheld by the CE GAT and the High Court. The Supreme Court held that the 1998 circular applies only when a unit has a single heating furnace; when each mill has its own furnace, ACP is the sum of the capacities. The court emphasized that ACP is based on capacity to produce, not actual production, and rejected the appellent’s technical contentions.

Provisions of Law Cited

Central Excise Act, 1944, Section 3AInduction Furnace Annual Capacity Determination Rules, 1997, Rules 3 and 4Central Excise Rules, 1944, Rule 96(ZP)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contended that ACP is determined on the basis of one motor per unit; since there are two furnaces but only one motor, the ACP should be determined by the higher capacity of the two mills. They urged that the second furnace’s setting was approved, that the expert certificate supporting non-simultaneous operation should not be discarded, and that the approval should inform the ACP; they relied on the formula in Rule 3 for ACP as incorporating the motor drive. The appellant also submitted that the second furnace was installed with the Commissioner's knowledge.

Contentions of Respondents

The respondents argued that the 1998 circular correctly prescribes ACP calculation: take the higher capacity only if a unit has a single reheating furnace; with two furnaces, each mill’s capacity should be aggregated. They contended that the question of running furnaces separately had been admitted and that the Commissioner's order was based on the circulars and the admitted facts; the expert certificate was disregarded as it was issued after a nine-month delay. They rejected the expert opinion in favor of a plain-language interpretation of the circular and rules.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Hindustan Ferodo Ltd. v. Collector of Central Excise(1997) 89 ELT 16(SC)DistinguishedThe Court distinguished this case, noting that in Hindustan Ferodo the Tribunal’s involvement and evidentiary role differed; here the court relied on the circular and admitted facts, treating the issue as one of statutory interpretation rather than adduced evidence.
Aditya Steel Industries Ltd. v. CCE & C, Bhubaneswar(2002) 53 RL T 1068DistinguishedThe Kolkata Bench decision relied on circulars; the Supreme Court distinguished it, clarifying that ACP determination hinges on whether separate furnaces exist and how capacity is aggregated.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against M/S Channy Enterprises v. Commissioner of Central Excise, Chandigarh and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

A B # M/S CHANNY ENTERPRISES _v._ COMMISSIONER OF CENTRAL EXCISE, CHANDIGARH APRIL 5, 2005 [RUMA PAL AND C.K. THAKKER, JJ.] _Excise:_ > _Central Excise Act, 1944-Section 3A-lnduction Furnace Annual_ C _Capacity Determination Rules, 1997-Rules 3 and 4-Circular dated 26-21998-Central Excise Rules, 1944-Rule 96(ZP)-Hot rolled steel productsLevy of duty on the basis of Annual Capacity of Production(ACP)-Assessee having two rolling mills, each mill with a separate heating furnaceCommissioner relying upon the 1998 Circular determining the ACP by clubbing_ D _the capacity of both the mills-Correctness of-Held: Correct-The 1998 Circular clearly says that the capacity of the higher of the two mills would be taken for assessing the ACP only if each rolling mill did not have a separate heating furnace-If each rolling mill had a separate heating furnace, then the capacity of the unit would be the sum total of the capacity of each rolling mill_ > _in the unit irrespective of the fact that only one mill operated at a time._ E E With effect from 1st September 1997, steel ingots and billets were notified under Section 3-A of the Central Excise Act, 1944 for levy of excise duty on the basis of Annual Capacity of Production (ACP) of the factory producing such goods. For determination of the ACP, the Induction Furnace Annual Capacity Determination Rules, 1997 were framed. In F answer to a query raised as to how would the ACP be determined if a unit has more than one rolling mill in the same premises but operates only one rolling mill at a time, it was clarified by Circular dated 26th February 1998 issued by the Board that if a unit has one re-heating furnace with two rolling mills, then the higher capacity of the two mills should be taken G as the assessed annual capacity for the unit. However, if each rolling mill has a reheating furnace, the cap~city of the unit would be the sum total of the capacity of each rolling mill in the unit. Appellant has two mills in which it manufactures hot rolled steel 251 [2005] 3 S.C.R. 252 ## SUPREME COURT REPORTS A products. Prior to 1st September 1999, it had one heating furnace and its ACP was fixed on "that basis. The appellant subsequently installed a second furnace but, according to the appellant, there was only one electric motor which meant that both the furnaces could not be operated simultaneously. Pursuant to the said change, the Commissioner on the basis of the 1~8 B Circular determined the ACP of Appellant by clubbing the capacity of both the rolling mills. Appeal against the Commissioner's order being dismissed by CEGAT, Appellant filed Reference Petition under Section 35-H (I) of the Act as wet! as a writ petition before High Court, which were dismissed. C In appeal before this Court the appellant contended that the formula for determination of the ACP was on the basis of one motor per unit; that therefore despite having two furnaces since there was only one motor which was common to both, in terms of the said Circular the capacity of the higher of the mills should have been taken as the ACP. Respondents however contended that the question of taking the higher capacity of the D two mills would only arise if there was one re-heating furnace. ## Dismissing the appeal, the Court HELD : 1. It is not the appellant's case that the 1998 Circular was incorrect. On the contrary it has been relied on to claim that the ACP E should have been determined with reference to the mill which had the higher capacity. The Circular in answer to a query which exactly reflects the issue in this case, clearly says that the capacity of the higher of the two .mills would be taken for assessing the ACP only if each rolling mill did not have a separate re-heating furnace. If each rolling mill had a F separate. heating furnace, as the appellant admittedly does, then the capacity of the unit would be the sum total of the capacity of each rolling mill in the unit irrespective of the fact that only one mill operated at a time. The language could not be plainer. What the appellant's argument overlooks is that the scheme did not operate on the basis of the actual production but on the capacity of the rolling mills to produce. There is G therefore no reason to differ.with the ~iew expressed by the Commissioner, CEGAT and the High Court. [255-E-H] _Hindustan Ferodo Ltd._ v. _Collector of Central Excise,_ (1997) 89 ELT 16(SC) and _Aditya Steel Industries Ltd._ v. _CCE_ & _C, Bhubaneswar,_ (2002) H 53 RL T 1068, distinguished. 253 CHANNY ENTERPRISES v. C.C.E. [RUMA PAL, J.] 2. The appellant's contention that the second mill was set up after A the approval of the Commissioner is of no consequence. The approval granted by the Commissioner did not in any way affect the assessment required to be made in accordance with the Rules. 1257-B) CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2415 of2005. B Form the Judgment and Order dated 27 .11.2002 of the Punjab and Haryana High Court in C.E.C.No. 102 of 2002. P.C. Jain, Sandeep Jain and Rajesh Kumar for the Appellant. c R. Venkataramani, V.G. Pragasam and P. Parmeswaran with for the Respondent. > The Judgment of the Court was delivered by RUMA PAL, J. Leave granted. The appellant has two mills in which it manufactures hot rolled steel products. With effect from lst September 1997, the Government of India notified -ingots and billets under Section 3-A of the Central Excise Act, 1944 for levy of excise duty on the basis of the annual capacity of production (ACP) of the factory. To give effect to the scheme, Rules were framed for E determination of the annual capacity of production of a factory producing such notified goods known as the Induction Furnace Annual Capacity Determination Rules 1997. By the Rules, the ACP of a factory was taken to be a fixed multiple of the total capacity of the furnaces installed in the factory. The manner of levy and collection of duty was governed by Rule F 96(ZP) of the Central Excise Rules, 1944 also issued under Section 3A of the Act. Circular dated 26th February 1998 had been issued by way of a clarification in answer to questions raised in connection with the operation of the Rules. One of the questions so raised Was: "How would the annual capacity of production be determined if a G unit has more than one rolling mill in the same premises but operates only one rolling mill at a time." In answer to this, it was clarified that : H 254 [2005) 3 S.C.R. SUPREME COURT REPORTS A "If a unit has one re-heating furnace with two rolling mills, then the · capacity of the higher of the two mills should be taken as the assessed annual capacity for the unit. However, if each rolling mill has a reheating furnace, the capacity of the unit would be the sum total of the capacity of each rolling milf in the unit". B Prior to lst September 1999, the appellant had one heating furnace and the appellant's ACP was fixed on that basis. The appellant then installed a second furnace but, according to the appellant, there was only one electric motor which meant that the both furnaces could not be operated simultaneously. The appellant notified the change to the Commissioner under C Rule 4. of the Rules. According to the appellant, the approval was communicated to the appellant by the Commissioner's letter dated 25th August 1999 after which the appellant filed a revised declaration on lst September 1999. Response was given to this on 17th October 2000 by the Commissioner's office which sought to club the capacity of both the rolling mills since the D second heating furnace h'ad been installed on the basi~ of the circular dated 26th February 1998. The appellant's submission that the circular did not have any application to the appellant's case because both the furnaces could not be operated simultaneously was rejected by the Commissioner who then proceeded to fix the ACP by clubbing the capacity of both the rolling mills. An appeal was preferred by the appellant to the Customs Excise and Gold E Control Appellate Tribunal (CEGA T) which rejected the appellant's appeal and affirmed the Commissioner's order. The appellant filed a Reference Petition under Section 35-H (I) of the Act as well as a writ petition contending that the respondents were not justified in determining the ACP of the appellant by taking the capacity of both the mills together. The High Court dismissed F the Reference Application and the Writ Petition holding that no question of law arose from the order of the Tribunal. It was also found that the CEGA T had considered all aspects of the matter and had correctly determined the question raised. The appellant has contended that all the fora had erred in overlooking G the formula provided under Rule 3 for determination of the ACP which showed that a vital element of the formula included the revolutions per minute.· of the drive. This, according to the appellant, showed that the formula for calculating the ACP was on the basis of one motor per unit. It is therefore submitted that despite having two electric furnaces since there was only one H motor which was common to both, then in terms of the circular issued by the CHANNY ENTERPRISES _v._ C.C.E. [RUMA PAL, J.] 255 Board itself the higher capacity of the mills should have been taken as the A ACP. The second submission is that the appellant had submitted a certificate from the National Institute of Secondary Steel Technology, a Government Institute, which certified that the two mills could not be run simultaneously with the same motor and common flywheel. It is contended that the Commissioner could not discard the opinion of an expert and determine the B technical issue on the basis of his own opinion. it was finally submitted that the Commissioner had himself approved the setting up of the second furnace within the ACP of the units. Learned counsel appearing· for the respondents has submitted that the circular dated 26th February 1998 relied upon by both the parties had been C misconstrued by the appellant. It is submitted that the question of taking the. higher capacity of the two mills would onfy arise if there was one re-heating furnace. According to the . respondents, the installation of the two rolling mills and two heating furnaces had not been disputed by the apl'ellant before the Commissioner. It is said that the Commissioner had applied his mind to D the expert's certificate but had rejected it because it was issued after a lapse of nine months from the date of the withdrawal of the capacity based assessment scheme on 31st March 2000. The Commissioner in fact determined the issue on the basis of the admitted facts and on an interpretation of the 1998 circular. E The respondent's contentions are correct. It is not the appellant's case that the 1998 circular was incorrect. On the contrary it has been relied on to claim that the ACP should have been determined with reference to the mill which had the higher capacity alone. The circular in answer to a query which exactly reflects the issue in this case, clearly says that the capacity of the F higher of the two mills would be taken for assessing the ACP only if each rolling mill did riot have a separate re-heating furnace. If each rolling mill had a separate heating furnace, as the appellant admittedly does, then the capacity of the unit would be the sum total of the capacity of each rolling mill in the unit irrespective of the fact that only one mill operated at a time. The language could not be plainer. What the appellant's argument overlooks G is that the scheme did not operate on the basis of the actual production but on the capacity of the rolling mills to produce. We, therefore, see no reason to differ with the view expressed by the Commissioner, CEGA T and the High Court. H 256 {2005) 3 S.C.R. SUPREME COURT REPORTS A The criticism of the action of the Tribunal in _Hindustan F erodo Ltd._ v. _Collector of Cef!tral Excise,_ ( 1997) 89 EL T 16 SC where the Tribunal· had entered into the arena of dispute and in effect given evidence on behalf of the Revenue before itself, would not apply here. The. Revenue in that· case had led no evidence in support of its case . .The assessee had. In the present B case CEGA T proceeded on the basis of the admitted facts and relied on the language of the circular to reject the appellant's·. appeal. > The appellant has also sought support from a decision of the. Kolkata Bench of CEGAT in _Aditya Steel Industries Ltd._ v. _CCE &_ C, _Bhubaneswar,_ (2002) 53 RL T I 068. The Tribunal relied upon the Board's circulars No.325/ C 41/97-CX dated 25.7.1997 and 326/42/97-CX to hold that where it was not > technically possible to run two mills simultaneously because of a common power supply, the capacity of the stand by mill was not to be taken into consideration for determining the. ACP. D E F We do not agree. Separate schemes were formulated under Section 3A (}f the Ac_t,in re.latioJ? tp in~llction(urnaces and hot rMolling mills. Circular 325 dated 25.7.1997 dealt with induction furnaces and specifically provided: "In this context, it is understood that some induction furnace units have, what they call "idle" crucible. It is reported that at any point of time only one crucible is used and the other remains idle. h1 such cases, it is claimed, the induction furnace unit has one transforM~t and one electrical panel..As .such the capacity of the induction furnace is relatable to crucible(s), excluding the "idle (separate or stand by)" crucible. This aspect may kindly be examined on basis of facts of each such case and the furnace capacity may be ascertained accordingly". Circular No. 326 also dated 25. 7 .1997 dealt with the capacity of production of hot re-rolling mills. There is no paragraph in this circular similar to the quoted paragraph relating to the ACP of induction furnaces. G Paragraph I 8 of Circular No. 326 ·.says that the paragraphs in the circular explain the salient features of Section 3A scheine as applicable to re-rolling mills. It also says that the scheme, in general terms, is on the same lines as that for the Induction Furnace units and that th~refore the explanation on some of the common features are the same as those containe~ i.n circular No. H 325. This does not tantamount to saying that all the features of the induction ' 257 CHANNY ENTERPRISES _v._ C.C.E. [RUMA PAL, .I.) furnace scheme were to be incorporated into the hot rolling mill scheme. The appellant's contention that the second mill was set up after the approval of the Commissioner is ofno consequence. The approval granted by the Commissioner did not in any way affect the assessment required to be made in accordance with the Rules. B In the circumstances, the appe;ll is dismissed but without any order to costs. B.B.B. Appeal dismissed. ,.