High Court of KeralaSingle JudgeWrit petition disposed of with directions to re...

M.S. Abdul Hakeem v. State of Kerala and Others

Case / Petition Number:WP(C) 24356 of 2021
Neutral Citation:/

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • V.G. Arun
Judgment Date
2022-11-30
Court Decision / Holding
Writ petition disposed of directing the second respondent to reconsider the liability imposed by Ext.P13 insofar as it imposes liability on the petitioner. The decision to be taken after affording an opportunity of hearing, with consideration of the discussion in the judgment. Till a fresh decision is taken, further proceedings based on Ext.P14 shall be kept in abeyance.
Final Disposition
Writ petition disposed of with directions to reconsider Ext.P13 liability order with an opportunity of hearing; keep Ext.P14 in abeyance until a fresh decision is taken.

Parties to the Case

Appellants / Petitioners

  • M.S. Abdul Hakeem

Respondents

  • State of Kerala represented by Secretary to Government, Public Works Department, Government Secretariat, Thiruvananthapuram
  • Superintending Engineer, Harbour Engineering (North Circle), Kozhikode
  • Executive Engineer, Harbour Engineering Division, Puthiyani­rathu, Elathoor, Kozhikode
  • Assistant Executive Engineer, Harbour Engineering Department, Fishery Harbour Sub Division, Puthiyanda P.O., Kozhikode

Legal Representation & Advocates

Counsels for Petitioners

  • • Jomy George
  • • R. PadmaraJ
  • • M.J. Benny
  • • Deepak Mohan
  • • R. Ajith Kumar (V.K. Edom)
  • • Chitra N. Das
  • • Rishab S.

Counsels for Respondents

  • • P.S. Appu, Government Pleader

Case Synopsis & Summary

Petitioner M.S. Abdul Hakeem, a Class A PWD contractor, was awarded the contract for construction of a compound wall around the Puthiyappa Fishery Harbour and the locker rooms. The project was plagued from the outset by obstruction from residents who claimed the site as their playground and that the wall would obstruct harbour access. Despite the impediments, the petitioner completed 21% of the work by February 2019, after which locals threatened workers and officials, causing work to halt. The contract period of 10 months lapsed, prompting requests for an extension; Ext.P7 extended the period only up to 31.12.2019. The petitioner's subsequent attempts to resume were frustrated by continued hindrance, and, finding the project untenable, he sought relief to be relieved from the contract without penalties. The respondents purportedly rearranged the work and issued a demand of Rs. 43,91,444 as liability and risk-cost, despite representations made by the petitioner. The petitioner contended that the delay was caused by obstruction and should be treated as impossibility of performance, invoking Section 67 of the Indian Contract Act, 1872, and relying on Shripati Lakhu Mane v. Maharashtra Water Supply and Sewerage Board to argue that abandonment cannot be deemed in the absence of reciprocal performance. The High Court ultimately found merit in the petitioner’s claim of obstruction and improper liability assessment, directing the second respondent to reconsider Ext.P13 after a hearing and keeping Ext.P14 in abeyance, thereby sending the matter for fresh decision.

Provisions of Law Cited

Indian Contract Act, 1872, Section 67PWD Manual, Clause 2116.2.1Constitution of India, Article 226

Legal Doctrines & Maxims

  • Abandonment cannot be inferred without performance of reciprocal promises (Shripati Lakhu Mane principle)
  • Reciprocal promises must be performed for abandonment to be established
  • Damages cannot be unilaterally assessed without proving legal injury

Submissions & Arguments

Contentions of Appellants / Petitioners

Advocates for the petitioner contended that the delay in completion was not attributable to the petitioner; obstruction at the site made completion impossible, and therefore the respondents could not unilaterally impose liability or damages under Ext.P13. They argued that the respondents had admitted the delay due to obstruction; the sudden change in posture and the blame placed on the petitioner were unjustified. The petition sought relief from penalties and cancellation of liability, underscored by the principle that abandonment cannot be declared unless reciprocal promises are performed, a proposition supported by Shripati Lakhu Mane. It was urged that the authorities failed to consider the petitioner's representations and that the dispute could not be resolved in a writ petition under Article 226, calling for a fresh decision after hearing with respect to the alleged damages and risk-cost.

Contentions of Respondents

Advocate for the respondents maintained that the contract period was initially extended because the petitioner was prevented from performing due to obstruction, and that even after the dispute subsided the petitioner was unwilling to continue without a revised estimate. They highlighted a meeting held on 20.03.2020 and the subsequent restart on 23.03.2020, noting Covid-19 disruptions and limited obstruction (about 200 of 1530 metres). They argued that the petitioner’s refusal to proceed under revised terms led to termination and re-arrangement, resulting in a liability of Rs. 43,91,444 under Clause 2116.2.1 of the PWD Manual, plus 30% of the balance work. They submitted that monetary disputes are not suitable for resolution under Article 226 and requested dismissal of the petition or upholding the recounting of damages after proper due process.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Shripati Lakhu Mane v. Maharashtra Water Supply and Sewerage Board2022 (2) KLT 772(SC)PositiveThe court adopts the principle from the cited Supreme Court case that abandonment cannot be inferred without reciprocal promises being performed, especially where hindrances prevent performance.
Joseph v. Executive Engineer, Irrigation Division, Thrissur and others2014 (2) KHC 143Mentioned OnlyCited by the petitioner in support of general principles on damages and liability but not central to the court’s decision.
State of Kerala v. United Shippers and Dredgers1982 KLT 738Mentioned OnlyCited as authority by the petitioner; not a decisive factor in the judgment.
Varkey Thomas v. G.Vijayendra Kurup and others2017 (1) KHC 452Mentioned OnlyCited by the petitioner to support related propositions; not central to the outcome.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against M.S. Abdul Hakeem v. State of Kerala and Others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT** ## **THE HONOURABLE MR.JUSTICE V.G.ARUN** **WEDNESDAY, THE 30[TH] DAY OF NOVEMBER 2022 / 9TH AGRAHAYANA,** ## **1944** ## **WP(C) NO. 24356 OF 2021** ## **PETITIONER:** M.S.ABDUL HAKEEM, AGED 35 YEARS PWD CONTRACTOR, QUADRIYA MANZIL, MARA, CHENGALA P.O. KASARAGOD 671 541. BY ADVS. JOMY GEORGE R.PADMARAJ M.J.BENNY DEEPAK MOHAN R.AJITH KUMAR [V.K.EDOM] CHITRA N. DAS RISHAB S. ## **RESPONDENTS:** 1 STATE OF KERALA REPRESENTED BY SECRETARY TO GOVERNMENT, PUBLIC WORKS DEPARTMENTS, GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM 695 001. 2 SUPERINTENDING ENGINEER, HARBOUR ENGINEERING (NORTH CIRCLE), KOZHIKODE 673 303. 3 EXECUTIVE ENGINEER, HARBOUR ENGINEERING DIVISION, PUTHIYANIRATHU P.O., ELATHOOR, KOZHIKODE 673 303. 4 ASSISTANT EXECUTIVE ENGINEER, HARBOUR ENGINEERING DEPARTMENT, FISHERY HARBOUR SUB DIVISION, PUTHIYANDAI P.O. KOZHIKODE 673 021. BY GP P S APPU ## **THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION** **ON 06.07.2022, THE COURT ON 30.11.2022 DELIVERED THE FOLLOWING:** W.P.(C) No.24356 of 2021 -2- ## **JUDGMENT** Dated this the 30[th] day of November, 2022 The petitioner, an A Class PWD contractor, was awarded the work “Construction of compound wall around the Puthiyappa Fishery Harbour and construction of Locker Rooms”. The selection notice is dated 30.07.2018, the agreement was executed on 14.08.2018 and the site handed over on 22.08.2018. From the initial stages itself, the residents of a nearby colony obstructed the work, claiming that the work site is their playground and construction of compound wall will obstruct their access to the harbour. Despite the hindrance, the petitioner completed 21% of the work by February, 2019. At that stage, the local residents obstructed and threatened the workers and PWD officials. Faced with a potentially W.P.(C) No.24356 of 2021 -3- dangerous situation, the work was stopped. The third respondent informed the second respondent about the situation as per Ext.P3 letter dated 15.03.2019. As the contract period of 10 months expired in the meanwhile, the petitioner sought extension of time of the contract period up to 31.03.2020. By Ext.P6 letter dated 09.08.2019 the fourth respondent also recommended to extend the contract period, without imposing penalty. Accordingly, Ext.P7 order was issued by the second respondent extending the time limit, but only up to 31.12.2019. The petitioner commenced the work immediately thereafter, but the local residents again obstructed. As it became evident that he will not be able to proceed with the work, the petitioner submitted Ext.P8 representation, requesting to relieve him of the contract, without risk and cost. To the petitioner's dismay, without even considering his representation and in complete deviation of the ## W.P.(C) No.24356 of 2021 -4- earlier stand, the third respondent issued Ext.P9 communication blaming the petitioner for the delay in completing the work. Thereupon, the petitioner submitted Ext.P10 representation, requesting to take immediate action to resolve the issues at the site and to revise the estimate. Although, fourth respondent issued Ext.P11 letter to the third respondent stating that the contract period can be extended up to 31.03.2021 by imposing a fine of Rs.50,000/-, by Ext.P13 order the second respondent directed to rearrange the work at the petitioner's risk and cost. The work was accordingly rearranged and Ext.P14 notice issued to the petitioner, demanding an amount of Rs.43,91,444/- towards risk and cost. Thereupon, the petitioner submitted Ext.P16 representation highlighting the reasons for the delay in completing the work and requesting to exempt him from risk and cost. The second respondent having failed to act upon W.P.(C) No.24356 of 2021 -5- Ext.P16 representation, this writ petition is filed seeking the following reliefs; _“(a) issue a writ of certiorari or any other appropriate writ, order or direction quashing Exhibit P-13 order and P-14 demand notice of the 2[nd] respondent._ _(b) issue a writ of mandamus or any other appropriate writ order or direction, directing the respondents to relive the petitioner from the contractual obligations without imposing any penalty._ _(c) to declare that the petitioner has not committed any breach of contract so as to enable the respondents to impose any penalty on the petitioner for noncompletion of the work._ _or in the alternative_ _(d) issue a writ of mandamus or any_ _other appropriate writ, order or direction, directing the respondents to quantify the damages if any suffered by the respondents before demanding any amount from the petitioner, after_ _affording an opportunity of hearing to the petitioner.”_ 2. Adv.Jomy George, learned Counsel for the petitioner, assailed Exts.P13 order and P15 -6- ## W.P.(C) No.24356 of 2021 notice on the following grounds; The respondents themselves have admitted that the delay in completing the construction is not attributable to the petitioner. There is no justification in the sudden _volte face_ on the part of the respondents, by putting the entire blame on the petitioner. The obstruction at the site had made further construction impossible and thereby the contract stood frustrated. The respondents committed gross illegality in mulcting the petitioner with risk and cost, terming the disability to continue the work as abandonment. The said approach is against Section 67 of the Contract Act, 1872. This question was considered by the Apex Court in _**Shripati Lakhu Mane v. Maharashtra Water Supply and Sewerage**_ _**Board**_ **[** _**2022 (2) KLT 772(SC)]** and it was_ held that, refusal of the contractor to continue to execute the work cannot be termed as abandonment -7- ## W.P.(C) No.24356 of 2021 of contract unless the reciprocal promises are performed by the other party. In the instant case, the respondents had failed to perform their reciprocal duty of providing hindrance free site. The respondents are not entitled to unilaterally assess the damages, that too, without proving the legal injury sustained. In support of this proposition, reliance is placed on the decisions in _**Joseph v. Executive Engineer, Irrigation Division, Thrissur and others [2014 (2) KHC 143]**_ , _**State of Kerala v. United Shippers and Dredgers [1982 KLT 738]**_ and _**Varkey Thomas v. G.Vijayendra**_ _**Kurup and others [2017 (1) KHC 452]**_ . Even otherwise, as the loss sustained by rearranging the work is only Rs.3,77,618.31, there is no justification in demanding an amount of Rs.43,91,944/-. 3. Adv.P.S.Appu, the learned Government Pleader, contended that the period of contract ## W.P.(C) No.24356 of 2021 -8- was initially extended on being convinced that the petitioner had been disabled from executing the work due to obstruction at the site. Later, even after the dispute was resolved, but, the petitioner was not willing to continue the work unless the rates are revised. A meeting was hence conducted on 20.03.2020 and the petitioner agreed to restart the work on 23.03.2020. Even though lockdown was imposed in the meanwhile, all arrangements for restarting the work, complying with Covid-19 protocol was made. Of the total length of 1530 metres of the compound wall, the obstruction was only over a portion of 200 metres. The adamant stand of the petitioner that he will not continue the work without a revised estimate had resulted in termination and re-arrangement of the contract. It is true that the difference in the amount quoted by the new bidder and the petitioner is Rs.3,77,618.31. Over and above this difference, the petitioner W.P.(C) No.24356 of 2021 -9- is also liable to pay 30% of the balance work amount as per Clause 2116.2.1 of the PWD Manual. Thus, the total amount due from the petitioner comes to is Rs.43,91,444/-. At any rate, this monetary dispute cannot be resolved in a writ petition under Article 226. 4. I find substantial merit in the petitioner's contention that he was disabled from continuing the work at the initial stages due to obstruction from the local residents. This fact is accepted by the respondents also. The only question is whether the petitioner could have completed the work pursuant to the discussion held on 20.03.2020. While the petitioner contends that it was not feasible to continue the work, the respondents argue that all arrangements for executing the work was done at the site. The above factual dispute cannot be resolved in a writ petition under Article 226. At the same time, I find substantial merit in the -10- ## W.P.(C) No.24356 of 2021 petitioner's contention that Ext.P13 order and Ext.P14 notice are issued without considering the issues raised in his representations. Before terminating the contract and imposing liability, the second respondent ought to have considered whether the contract was impossible of performance. If so, the petitioner's refusal to continue to execute the work cannot be termed as abandonment and should not result in the petitioner being imposed with liability. The legal position is clearly laid down in _**Shripati Lakhu Mane** (supra)_ . There is also merit in the contention that before imposing the liability, the question as to whether the respondents had suffered any legal injury ought to be addressed. Even in such a case, there cannot be a unilateral assessment of damages. No such exercise having been undertaken by the second respondent before passing Ext.P13 order, the second respondent is W.P.(C) No.24356 of 2021 -11- bound to take a fresh decision after affording an opportunity of hearing to the petitioner. The petitioner having filed Ext.P16 seeking reconsideration of Ext.P13, the writ petition is disposed of directing the second respondent to reconsider the decision at Ext.P13, insofar as it imposes liability on the petitioner. The decision shall be taken after affording an opportunity of hearing and by adverting to the discussion in this judgment. Till a decision is taken in the manner directed above, further proceedings based on Ext.P14 shall be kept in abeyance. Sd/- **V.G.ARUN** ## **JUDGE** Scl/ W.P.(C) No.24356 of 2021 -12- ## **APPENDIX OF WP(C) 24356/2021** PETITIONER EXHIBITS |Exhibit P1|TRUE COPY OF THE SELECTION NOTICE| |---|---| ||DATED 30.7.2018 ISSUED BY THE 2ND| ||RESPONDENT TO THE PETITIONER.| |Exhibit P2|TRUE COPY OF THE ORDER DATED| ||04.09.2018 OF THE 2ND RESPONDENT.| |Exhibit P3|TRUE COPY OF THE LETTER DATED| ||15.03.2019 ISSUED BY THE 3RD| ||RESPONDENT TO THE 2ND RESPONDENT.| |Exhibit P4|TRUE COPY OF THE LETTER DATED| ||11.04.2019 ISSUED BY THE 4TH| ||RESPONDENT TO THE 3RD RESPONDENT.| |Exhibit P5|TRUE COPY OF THE LETTER DATED| ||17.07.2019 ISSUED BY THE 4TH| ||RESPONDENT TO THE 3RD RESPONDENT.| |Exhibit P5 (A)|TRUE COPY OF THE MINUTES OF THE| ||MEETING DATED 15.07.2019 OF THE 4TH| ||RESPONDENT.| |Exhibit P6|TRUE COPY OF THE LETTER DATED| ||09.08.2019 ISSUED BY THE 4TH| ||RESPONDENT TO THE 3RD RESPONDENT.| |Exhibit P7|TRUE COPY OF THE ORDER DATED| ||29.11.2019 OF THE 2ND RESPONDENT.| |Exhibit P8|TRUE COPY OF THE REPRESENTATION DATED| ||31.12.2019 SUBMITTED BY THE PETITIONER| ||BEFORE THE 2ND RESPONDENT.| |Exhibit P9|TRUE COPY OF THE NOTICE DATED| ||12.05.2020 ISSUED BY THE 3RD| ||RESPONDENT TO THE PETITIONER.| |Exhibit P10|TRUE COPY OF THE REPRESENTATION DATED| ||25.05.2020 SUBMITTED BY THE PETITIONER| ||BEFORE THE 2ND RESPONDENT.| |Exhibit P11|TRUE COPY OF THE LETTER DATED| ||24.08.2020 ISSUED BY THE 4TH| ||RESPONDENT TO THE 3RD RESPONDENT.| |Exhibit P12|TRUE COPY OF THE NOTICE DATED| ||24.12.2020 ISSUED BY THE 2ND| ||RESPONDENT TO THE PETITIONER.| |Exhibit P13|TRUE COPY OF THE ORDER DATED| W.P.(C) No.24356 of 2021 ## -13- 09.02.2021 OF THE 2ND RESPONDENT. Exhibit P14 TRUE COPY OF THE NOTICE DATED 17.09.2021 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER. Exhibit P15 TRUE COPY OF THE LETTER DATED 08.10.2021 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER. Exhibit P16 TRUE COPY OF THE REPRESENTATION DATED 06.08.2021 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.